You are on page 1of 6

Empresas Públicas Planta de Tratamiento de Aguas Residuales Bello Section 15490

de Medellín Technical Specifications Sump Pumps

SECTION 15490

SUMP PUMPS

PART 1 GENERAL

1.1 SUMMARY
1.1.1 Section Includes: The work in this section includes the design, fabrication, furnishing,
assembly, testing, packaging, delivery, supervision of installation, installation and
start up of forty eight (48) submersible sump pumps with capacities and details as
scheduled, and installed as shown in drawings.1
1.1.2 The pumps shall be furnished singles or duplex in the following way:
1 Each location hereinafter indicated shall have two sump pumps
permanently installed, so for this nineteen (19) cases shall be thirty
eight (38) single sump pumps or nineteen (19) duplex sump pumps.
2 Portable sump pumps shall be single: six (6) pumps.2
3 For by-pass east side grit removal tanks: four (4) pumps 3

1.1.3 The scope of section also includes submersible electric motors, wire service,
submersible cable, PCL “Panel de Control Local” panels (one for two pump), cables
and local conduit for instrumentation, control and power, all power and control wiring
between machine and control panels, all wiring from the PCLs to the associated
process instrumentation, control level devices, chain or stainless steel cable for
lifting, and all necessary appurtenances required for a complete installation and
satisfactory operation.
1.1.4 Related work specified in 0ther sections includes:
1 General Requirements for Mechanical Equipments
2 Section 09900 – Painting
3 Section 13300 – Plant Control Systems
4 Section 13310 – Instrumentación y buses de campo
5 Section 13320 – Instrumentation - Control Panels and Panel Instruments
6 Section 13340 – DCS Distributed Control System
7 Section 15080 - Miscellaneous Pipe and Fittings
8 Section 16150 - Electric Motors
9 Document HTA-4-SP-16-009 – Pliego de Especificaciones Técnicas,
Diseño, Suministro, Montaje, Instalación, Pruebas y Puesta en Servicio
de Equipos de Sistema Eléctrico.

1
Adenda 19 / Capítulo 3 / Numeral 9
2
Adenda 19 / Capítulo 3 / Numeral 9
3
Adenda 19 / Capítulo 3 / Numeral 9

Design, Fabrication and Furnishing of Major Equipment Page 1 of 6


Empresas Públicas Planta de Tratamiento de Aguas Residuales Bello Section 15490
de Medellín Technical Specifications Sump Pumps

1.2 REFERENCES
1 ASME B16.1 - Cast Iron Pipe Flanges and Flanged Fittings, Class 25,
125, 250.
2 AFBMA 9 - Load Ratings and Fatigue Life for Ball Bearings.
3 AFBMA 11 - Load Ratings and Fatigue Life for, Roller Bearings
4 ASTM A 48 - Specification for Grey lron Castings.
5 Hydraulic Institute Standards

1.3 SUMP PUMPING EQUIPMENT SCHEDULE


1.3.1 Furnish equipment in accordance with the following schedule:

DESING
HIGH WATER LOW WATER
NUMBER OF RATING DYNAMIC MINIMUM
SERVED AREA UNITS POINT HEAD (m) EFFIC (%)
LEVEL LEVEL
(MASL) (MASL)
(L/S)
Three (3) Grit Sump
Pumps to Grit 2/Grit
5,6 5,1 40 1.405,6 1.405,2
Washers Sump
Inlet Pumping
Station 2 13,9 5,1 40 1.400 1.399
Two (2) Grease
Sump Pumps to 2/Grease
5,6 5,1 40 1.402,6 1.402,2
Digesters Sump

Screen House 2 20 7,3 40 1.405,0 1.404,0

Two (2) Primary


Sludge Pumping 2/Station 5,6 10,2 40 1.408,3 1.407,9
Station
Two (2) Return
Sludge Pumping 2/Station 5,6 10,2 40 1.407,42 1.407,02
Station
Four (4) Primary
Sediment. Scum 2/Station 5,6 10,2 40 1.411,17 1.410,87
Pumping Station
Two (2)
Secondary
Sediment. Scum 2/Station 5,6 10,2 40 1.411,28 1.410,98
Pumping Station
Service water
2 5,6 10,2 40 1.406,9 1.406.5
pumping station
By pass - east
4 5,6 10,2 40 1.399,2 1.398,50
side grit removal
tanks
Tunnel between
Digester Area and
Thickening 2 5,6 5,1 40 1.410,98 1.410,58
Building

Design, Fabrication and Furnishing of Major Equipment Page 2 of 6


Empresas Públicas Planta de Tratamiento de Aguas Residuales Bello Section 15490
de Medellín Technical Specifications Sump Pumps

Portable pumps
for joint works
with the inlet 1 13,9 10 40 N/A N/A
channel 4
Portable pumps
5 5,6 10,2 40 N/A N/A
where required

Total sump pumps units are:


Thirty one (31) sump pumps, 5,6 l/s; 10,2 m
Twelve (12) sump pumps, 5,6 l/s; 5,1 m
Two (2) sump pumps, 13,9 l/s; 5,1 m
One (1) sump pump, 13,9l/s; 10,0 m 5
Two (2) sump pumps, 20 l/s; 7,3 m

1.4 ELECTRICAL REQUIREMENTS


1.4.1 Design the sump pump equipment for use on a nominal 460 volts, 3 phase, 60 hertz
electrical service.
For all electrical requirements, refers to Section 16150: Electric Motors.

1.5 SUBMITTALS
1.5.1 General: Provide all submittals, including the following, as specified in the General
Requirements for Mechanical Equipments.
1.5.2 Shop Drawings: Submit shop drawings, including arrangement, installation, and
erection drawings of the equipment and equipment operating characteristics. Include
the following:
1 Pump performance curves. Draw curves for the specified conditions.
Include head, brake horsepower, and efficiency, all plotted as a function
of capacity, from zero to maximum capacity.
2 General arrangement drawing. Include materials of construction.
3 Cross section drawing of pumping unit.
4 Parts list with materials of construction identified.
5 Certifies for the main construction materials of the equipment.
6 Motor drawing and performance characteristics.
7 Recommended spare parts list.
8 Operating descriptions, component descriptions, control and protection
schematics, electrical connection diagrams and general arrangement
drawings, including panel front elevations, dimensions and fabrication
details, for control equipment.
9 Calculations in accordance with the General Requirements for
Mechanical Equipments.

4
Adenda 19 / Capítulo 3 / Numeral 9
5
Adenda 19 / Capítulo 3 / Numeral 9

Design, Fabrication and Furnishing of Major Equipment Page 3 of 6


Empresas Públicas Planta de Tratamiento de Aguas Residuales Bello Section 15490
de Medellín Technical Specifications Sump Pumps

1.5.3 Operation and Maintenance: Submit the operation and maintenance manuals for the
pumping equipment.
1.5.4 Installation Information: Provide all information required for installation of the
equipment including all erection drawings and written installation instructions.
1.5.5 Storage Instructions: Submit storage instructions for the equipment for use by the
contractor and by the Owner.

1.6 QUALITY ASSURANCE


1.6.1 Manufacturer: The equipment furnished under this section shall be designed and
manufactured by a company who shall demonstrate to the Owner satisfaction that
complies with the experience criteria as specified in the bid documents.
1.6.2 Single Source Responsibility: Furnish all pump components from a single
manufacturer if available.

1.7 DELlVERY, STORAGE AND HANDLING


1.7.1 Deliver and storage in accordance with the General Requirements and as directed
by the Owner, all products and materials to the site designated by the Owner. Off-
load the equipment.
1.7.2 Care: Use every precaution to prevent damage to the equipments during
transportation and delivery to the site. Take extreme care in loading and unloading to
the main equipment and accessories. Do such work slowly with skids and suitable
power equipment and keep the equipments under control at all times.

1.8 SPARE PARTS


1.8.1 General: Provide following spare parts for each pump delivered and securely
wrapped or boxed, indexed and tagged with complete information for use and
recording.
1 One (1) set double mechanical seals.
2 One (1) set lock-washer, Q-rings and gaskets.

PART 2 PRODUCTS

2.1 MATERIALS
2.1.1 Single or duplex submersible pumps: Furnish submersible centrifugal pumps with
stainless steel shaft, double mechanical seals cartridge type, factory-lubricated ball
bearings, and extra heavy-duty waterproof casing of close-grained cast iron with
integrally cast legs for supporting pump on bottom of sump. Provide cast-iron, non-
clog impeller capable of passing 50-millimeter (2- inch) solids.
1 Provide flat faced flanged discharge nozzle with drilling and dimensions
meeting the requirements of ASME B16.1, Class 125.
2 Provide motors as specified in Section 16150, Electric Motors.
3 Furnish liquid level switches consisting of NEMA 6 sealed float
switches for pump start and pump stop for each pump and high level
water alarm, (2-pole DPDT type for local and remote alarm circuit), with
height adjustable on 25-millimeter (1-inch) stainless steel support rod.
Design, Fabrication and Furnishing of Major Equipment Page 4 of 6
Empresas Públicas Planta de Tratamiento de Aguas Residuales Bello Section 15490
de Medellín Technical Specifications Sump Pumps

Position float switches for liquid level controls and alarm as follows and
at levels as indicated on the drawings and table hereinafter.
4 Don’t use mercury based switches.
5 Terminate the wiring of the switches in a dedicated junction box
furnished with terminal strips. Install the box near the sump. Wiring
from the float switches shall be connected to the terminals that shall be
marked according to the switches tags. Complete the wiring from the
box to the station CCM.
6 Furnish heavy-duty waterproof power cables rated at 600 volts and
control cables rated at 600 volts, with sufficient slack to permit pump
removal from sump for servicing without disconnecting the cables.
7 Furnish PCL for local hand operation. Includes all elements required for
control and visualization of the pump.
2.1.2 Magnetic Starters: Furnish magnetic starters that meet the requirements of
Document HTA-4-SP-16-009 Rev. 1 – Pliego de Especificaciones Técnicas, Diseño,
Suministro, Montaje, Instalación, Pruebas y Puesta en Servicio de Equipos de
Sistema Eléctrico.
2.1.3 Lubrication of Equipment: Furnish equipment with internal or concealed bearings
lubrication fittings extended to accessible location outside casing, excepting
hermetically sealed units with lifetime lubrication. Lubricate prior to start-up, and at
recommended intervals before turning equipment over to the Owner. Provide linen
tag or heavy duty shipping tag attached to each piece of equipment showing date of
lubrication and name and number of lubricant used. Provide typewritten list, in
triplicate, of each item lubricated and type of lubricant used.

2.2 OPERATION, MONITORING AND CONTROL


2.2.1 Refers to section 13300 – Sistemas de control de planta. The pumps shall be
controlled by CCM UCIs. The UCI shall execute the operation and protection for the
pumps and for the sump according to the information from the level switches.
2.2.2 The operation shall alternate the function Duty and Reserve of each pump.
Following level switch actions shall be programmed:
 LSH starts the duty pump.
 LSL stops the pump.
 LSHH starts the reserve pump.
 LSHH sends alarm signal.
2.2.3 The CCM UCIs shall communicate with the DCS that shall supervise the sump
activity.

PART 3 EXECUTION

3.1 INSTALLATION
3.1.1 Installation and assembly of the equipment shall be in accordance with the drawings
and with the manufacturer’s installation instruction manual. The contractor shall
furnish all bolts, tools and other devices necessary for installing the pumping

Design, Fabrication and Furnishing of Major Equipment Page 5 of 6


Empresas Públicas Planta de Tratamiento de Aguas Residuales Bello Section 15490
de Medellín Technical Specifications Sump Pumps

equipment. The manufacturer’s representative shall supervise the handling,


installation, start-up and testing of the equipment.
3.1.2 After the be installed and prior to first star-up, complete clean up inside the discharge
pipes or hoses connected to the pumps shall be done to remove any accumulated
construction debris. Any damage to the pumps or related equipment during initial
start-up due to foreign objects left in the connected pipes shall be corrected at the
contractor´s expense

3.2 FIELD TESTS


3.2.1 Tests: After installation of the pumping units, control equipment and all
appurtenances, perform and supervise a field running test, under actual operating
conditions as specified in the General Requirements. Tests will be of sufficient
duration to show that the equipment operate at the specified conditions, without
overheating of any parts and in all other respects meets all requirements of the
specifications.

The field tests procedures shall be approved by the Owner prior to testing;
accomplish testing with the equipment in operation.

Furnish all labor, materials and appurtenances necessary for supervising the field
tests.

Correct any defects in the equipment or failure to meet the requirements of the
specifications properly.
3.2.2 Test at rated speed to determine the curves of head brake horsepower, and
efficiency as a function of capacity. Take a minimum of six points including shutoff.
Take at least one point as near as possible to each specified condition of head and
capacity. Express capacity in liters per second and express head in meters of water.
Furnish copies of the curves, raw test data, calculated results and sufficient
information for computation and plotting of the curves.
3.2.3 Controls: Ensure that the tests also demonstrate that the equipment operates as
specified with its PCL control system and that it responds to the instrumentation
signals connected to the CCM. Ensure that the communication to the DCS works as
specified and that all listed variables to be transmitted to and from the DCS are
properly sent and received.
3.2.4 Field testing shall be conducted by an experienced field test engineer and will be
witnessed by the owner. Before initially energizing the motors, the contractor shall
have successfully tested all the control, monitoring, and protective circuits. This
through electrical checkout procedures shall have followed a detailed step-by-step
approved test plan. The motor units undergoing tests should also be checked at this
time.
3.2.5 Supervise field testing of each pumping unit in accordance with the test code of the
Hydraulic Institute, except as specified herein. Drive each pump by its own drive unit
during the test. Supervise field testing to include checking the operation of the
warning and drive shut-down circuitry. The test will include increasing the loading to
test the mechanical overload protection system.

END SECTION
Design, Fabrication and Furnishing of Major Equipment Page 6 of 6

You might also like