Calemard Plan
Calemard Plan
Date of
S.no. Steps Activities Requirements Responsibility
completion
Status
Communication to
I Chennai plant
•Communication to Chennai plant to get the schedule and plan for trials. •Need to send the mail regarding the requirements and permission
• Discussion with the projects about taking the trials • Input material from the same lot need to be taken from chennai
• Trials to be run with the floating knife • Projects have to set the parameters in the centering system, in case required,
III Trials in A.P. • Conducting the trial with the verified material. to optimize its working, taking chennai machine as a reference
• Width and cord distribution study to be done
Process proving with • During the supplier visit all the issues to be raised, corrected and closed.
IV the floating knives
• Verified material to be kept ready right before the visit of the supplier