REPORTER: Merluza, Shaira M.

provides the definitions of the terms used and the


What is CIAP Document 102? execution, correlation, and intent of contract documents, as
CIAP Document 102 or the “Uniform General Conditions of well as the rules to be followed in case of conflict or
Contract for Private Construction” contains terms and discrepancy.
conditions ordinarily established in construction contracts. It is Section II. Laws, Regulations, Site Conditions, Permits &
intended for use in contracts for private construction in the Taxes
Philippines. The Owner, with the Contractor’s assistance, shall
What is the intent of CIAP Document 102? secure and pay all construction permits and licenses
CIAP Document 102 was formulated to provide the necessary for the execution of the Work
procedures, guidelines, and criteria to be used by parties in a Section III. Equipment and Materials
construction Contract, or reference to the Contract to address provides that all materials and equipment must
deficiencies and/or any ambiguity. conform to all Laws that are in force and applicable during the
The CIAP Document 102 will contribute to the enhancement of period of construction, and that the Contractor shall bear all
fair contractual relationships in the construction industry. damages by reason of any delay in the Work arising from
What is a Construction Contract? failure to comply with such Laws.
A typical Construction Contract consists of an Agreement, Section IV. Premises and Temporary Structures
General Conditions, Drawings, Specifications, and other the Contractor is in charge of the safety and
documents. sanitation at the work site during and upon completion of
work.
Contract is used to describe the combination of two (2) sets of Section V. Protection of Work and Property
documents: the Agreement and the Contract Documents. Obligation to protect the Work and the Owner’s
property from damage
Agreement is used to describe the agreement signed by the provides that it is the obligation of the Contractor to
Owner and the Contractor, excluding the Contract Documents. protect the work and the Owner’s property from damage.
Section VI. Labor, Work and Payments
Contract Documents are attached to the Agreement identified provides that the Owner shall at all times have access
therein as Contract Documents, including all additions, to the Work and shall provide sufficient number of inspectors
deletions and modifications which generally include the while Work is in progress to ensure quality. In charge of the
following: Special Provisions or Conditions; General safety and sanitation in the work premises.
Conditions; Specifications; Drawings; and other Bid Section VII. Contractor-Separate Contractor-Subcontractors
Documents. Relationship
The Owner shall provide for the coordination of the
Special Provisions or Conditions are instructions which are work performed by the Separate Contractor with the Work
issued prior to bidding to supplement and/or modify the of the Contractor.
Drawings, Specifications and/or General Conditions of the The Contractor is fully responsible to the Owner for
Contract. the acts and omissions of his Subcontractors.
Section VIII. Suspension of Work and Termination of
Specifications are the written or printed description of the work Contract
to be done describing qualities of the material to be used, the Contractor’s Rights to Suspend Work or Terminate
equipment to be installed and the mode of construction. Contract;
Section IX. Responsibilities and Liabilities of
Drawings are graphical presentations of the Work, including Contractor and of Owner
supplementary details and shop drawings. (Contractor’s Responsibility for Accidents and
Damages) states that the Contractor shall be primarily
General Conditions of Contract pertain to the roles, rights and responsible for all safety measures in executing the Work
obligations of the contracting parties, and the rules and Bonds and Guarantees required of the Contractor
procedures by which the parties and everyone concerned will 1. Contractor’s Liability Insurance (Contractor,
be able to meet their obligations and perform the Works Subcontractors and Owner)
covered under the Contract. 2. Accident Insurance for Workers
3. Contractor’s Fire Insurance
REPORTER: MOROLA, RENATO L. 4. Contractor’s Performance and Payment Bonds
Construction Industry Authority of the Philippines (CIAP) 5. Contractor’s Guarantee Bond
Document 102 contains these conditions which are generally 6. Contractor’s Guarantee-Warranty
applicable for all types of construction contracts: REPORTER: AUTOR, JOY LAURIA MAE B

Section I. Definitions and Documents What is Progress Payment?


The Contractor may submit periodically but not more than What is a punch list?
once each month a Request for Payment for work done. Each
request for progress payment shall be computed from the work Punch list, as defined under Article 20.11 C (a), is the list
completed on all items listed in the Breakdown of Work and of defects found or discovered on the completed work and
Corresponding Value, less a retention of 10% of the progress which should be received by the Contractor not later than 30
payment to the Contractor. days from date of substantial completion.

What is Retention Money? What circumstances necessitate an extension of time?

Progress payments are subject to retention of ten percent Article 21.04 (Extension of Time) provides that the
(10%). The purpose of retention is to cover uncorrected Contractor shall be entitled to an equitable adjustment of
discovered defects and third party liabilities. (Not in CIAP Doc. completion time subject to certain conditions.
102) What is the penalty for delay?
What are the documents to be submitted by the Contractor to Article 21.05 provides that upon failure of the Contractor
the Owner before to complete the Work within the Completion Time, the
final payment? Contractor shall pay the Owner liquidated damages in the
amount stipulated in the Contract as indemnity, but shall not
1. Certificate of Final Building Occupancy; exceed ten percent (10%) of the total contract price [Art. 29.06
(3)].
2. Certificate of Final Inspection of electrical, telephone,
sanitary, What are the issues that can be submitted for mediation or
arbitration?
mechanical, water, gas, safety and other utilities;
The jurisdiction of the (Construction Industry Arbitration
3. Original and three (3) sets of prints of “As-Built Drawings” of
electrical, Commission)CIAC may include, but is not limited to, the
following:
sanitary, gas, telephone, and mechanical works;
- violation of specifications for materials and workmanship;
4. Three (3) copies of Directory of Panel Boards and list of
circuits; - violation of the terms of agreement;
5. Three (3) copies of Instructions and Manual for operating - interpretation and/or application of contractual provisions;
and
- commencement time and delays;
maintaining of fixtures and equipment;
- maintenance and defects;
6. Three (3) copies of Keying Schedule; and
- changes in contract cost
7. Release of liens arising under the Contract (Sworn
Statement or - payment default of employer or contractor; and

Indemnity Bond). - amount of damages and penalties.

When shall the Owner release the retention money?


The amount retained by the Owner under the provision of
the Contract shall be released not later than the expiration of
the “Period of Making Good of Known Defects”.
What does “Period of Making Good of Known Defects” mean?
REPORTER: Daquigan, Mary Joza
The expression “Period of Making Good of Known
Defects” shall mean a period of not more than thirty (30) CHAPTER 1 - OBLIGATIONS
calendar days, calculated from the date of receipt by the
An obligation is a juridical necessity to give, to do or not to do.
Contractor of the last item in the punch list.
Art. 1157. Obligations arise from:
What is substantial completion?
(1) Law;
Section VI, Article 20.11 (Substantial Completion and its
Effect) provides that there is substantial completion when the (2) Contracts;
Contractor completes ninety five percent (95%) of the Work.
(3) Quasi-contracts;  Subrogating a third person in the rights of the creditor.
(4) Acts or omissions punished by law; and Other causes of extinguishment of obligations, such as
annulment, rescission, fulfillment of a resolutory condition, and
(5) Quasi-delicts.
prescription, are governed elsewhere in this Code. (1156a)
CHAPTER 2 - NATURE AND EFFECT OF OBLIGATIONS
REPORTER: ZUNIGA, JEAN MAY B.
- Every person obliged to give something is also
CHAPTER 1
obliged to take care of it with the proper diligence of a
good father of a family, unless the law or the GENERAL PROVISIONS
stipulation of the parties requires another standard of
care. Art. 1305. A contract is a meeting of minds between two
persons whereby one binds himself, with respect to the other,
- If person obliged to do something fails to do it, the to give something or to render some service.
same shall be executed at his cost.
Art. 1306. The contracting parties may establish such
- Those who in the performance of their obligations are stipulations, clauses, terms and conditions as they may deem
guilty of fraud, negligence, or delay, and those who in convenient, provided they are not contrary to law, morals, good
any manner contravene the tenor thereof, are liable customs, public order, or public policy.
for damages. Art. 1308. The contract must bind both contracting parties; its
validity or compliance cannot be left to the will of one of them.
- Usurious transactions shall be governed by special
laws. Art. 1311. Contracts take effect only between the parties, their
assigns and heirs, except in case where the rights and
CHAPTER 3 - DIFFERENT KINDS OF OBLIGATIONS obligations arising from the contract are not transmissible by
1. Pure and Conditional Obligation their nature, or by stipulation or by provision of law. The heir is
not liable beyond the value of the property he received from
2. Obligations with a Period the decedent.
3. Alternative Obligations If a contract should contain some stipulation in favor of a third
person, he may demand its fulfillment provided he
4. Joint and Solidary Obligations communicated his acceptance to the obligor before its
5. Divisible and Indivisible Obligations revocation. A mere incidental benefit or interest of a person is
not sufficient. The contracting parties must have clearly and
6. Obligations with a Penal Clause deliberately conferred a favor upon a third person.
CHAPTER 4 - EXTINGUISHMENT OF OBLIGATIONS Art. 1313. Creditors are protected in cases of contracts
intended to defraud them.
Obligations are extinguished:
Art. 1314. Any third person who induces another to violate his
(1) By payment or performance:
contract shall be liable for damages to the other contracting
 Application of Payments party.
Art. 1315. Contracts are perfected by mere consent, and from
 Payment by Cession
that moment the parties are bound not only to the fulfillment of
 Tender of Payment and Consignation what has been expressly stipulated but also to all the
consequences which, according to their nature, may be in
(2) By the loss of the thing due: keeping with good faith, usage and law.
(3) By the condonation or remission of the debt; Art. 1317. No one may contract in the name of another without
being authorized by the latter, or unless he has by law a right
(4) By the confusion or merger of the rights of creditor and to represent him.
debtor;
A contract entered into in the name of another by one who has
(5) By compensation; no authority or legal representation, or who has acted beyond
(6) By novation. his powers, shall be unenforceable, unless it is ratified,
expressly or impliedly, by the person on whose behalf it has
 Changing their object or principal conditions; been executed, before it is revoked by the other contracting
party.
 Substituting the person of the debtor;
 CHAPTER 2 to its kind. The fact that the quantity is not determinate shall
not be an obstacle to the existence of the contract, provided it
ESSENTIAL REQUISITES OF CONTRACTS is possible to determine the same, without the need of a new
GENERAL PROVISIONS contract between the parties.  
SECTION 3. - Cause of Contracts
Art. 1318. There is no contract unless the following requisites Art. 1350. In onerous contracts the cause is understood to be,
concur: for each contracting party, the prestation or promise of a thing
(1) Consent of the contracting parties; or service by the other; in remuneratory ones, the service or
benefit which is remunerated; and in contracts of pure
(2) Object certain which is the subject matter of the contract; beneficence, the mere liberality of the benefactor.
(3) Cause of the obligation which is established. (1261) Art. 1351. The particular motives of the parties in entering into
a contract are different from the cause thereof.
SECTION 1. - Consent
Art. 1352. Contracts without cause, or with unlawful cause,
produce no effect whatever. The cause is unlawful if it is
Art. 1319. Consent is manifested by the meeting of the offer
contrary to law, morals, good customs, public order or public
and the acceptance upon the thing and the cause which are to
policy.
constitute the contract. The offer must be certain and the
acceptance absolute. A qualified acceptance constitutes a Art. 1353. The statement of a false cause in contracts shall
counter-offer. render them void, if it should not be proved that they were
founded upon another cause which is true and lawful.
Acceptance made by letter or telegram does not bind the
offerer except from the time it came to his knowledge. The Art. 1354. Although the cause is not stated in the contract, it is
contract, in such a case, is presumed to have been entered presumed that it exists and is lawful, unless the debtor proves
into in the place where the offer was made. the contrary.
Art. 1327. The following cannot give consent to a contract: Art. 1355. Except in cases specified by law, lesion or
inadequacy of cause shall not invalidate a contract, unless
(1) Unemancipated minors;
there has been fraud, mistake or undue influence.
(2) Insane or demented persons, and deaf-mutes who do not CHAPTER 3
know how to write.
FORM OF CONTRACTS
Art. 1328. Contracts entered into during a lucid interval are
Art. 1356. Contracts shall be obligatory, in whatever form they
valid. Contracts agreed to in a state of drunkenness or during a
may have been entered into, provided all the essential
hypnotic spell are voidable.
requisites for their validity are present. However, when the law
Art. 1329. The incapacity declared in Article 1327 is subject to requires that a contract be in some form in order that it may be
the modifications determined by law, and is understood to be valid or enforceable, or that a contract be proved in a certain
without prejudice to special disqualifications established in the way, that requirement is absolute and indispensable. In such
laws. cases, the right of the parties stated in the following article
cannot be exercised.
SECTION 2. - Object of Contracts
Art. 1357. If the law requires a document or other special form,
Art. 1347. All things which are not outside the commerce of as in the acts and contracts enumerated in the following article,
men, including future things, may be the object of a contract. the contracting parties may compel each other to observe that
All rights which are not intransmissible may also be the object form, once the contract has been perfected. This right may be
of contracts. exercised simultaneously with the action upon the contract.
No contract may be entered into upon future inheritance (1279a)
except in cases expressly authorized by law. Art. 1358. The following must appear in a public document:
All services which are not contrary to law, morals, good (1) Acts and contracts which have for their object the creation,
customs, public order or public policy may likewise be the transmission, modification or extinguishment of real rights over
object of a contract. immovable property; sales of real property or of an interest
Art. 1348. Impossible things or services cannot be the object of therein a governed by Articles 1403, No. 2, and 1405;
contracts. (2) The cession, repudiation or renunciation of hereditary rights
Art. 1349. The object of every contract must be determinate as or of those of the conjugal partnership of gains;
(3) The power to administer property, or any other power which action to enforce the instrument, he cannot
has for its object an act appearing or which should appear in a subsequently ask for its reformation. 
public document, or should prejudice a third person;  Article 1368. Reformation may be ordered at the
instance of either party or his successors in interest, if
(4) The cession of actions or rights proceeding from an act the mistake was mutual; otherwise, upon petition of
appearing in a public document. the injured party, or his heirs and assigns.
All other contracts where the amount involved exceeds five  Article 1369. The procedure for the reformation of
hundred pesos must appear in writing, even a private one. But instrument shall be governed by rules of court to be
sales of goods, chattels or things in action are governed by promulgated by the Supreme Court.
Articles, 1403, No. 2 and 1405.
CHAPTER 5 Interpretation of Contracts
REPORTER: Luna, Jerome  Article 1370. If the terms of a contract are clear and
leave no doubt upon the intention of the contracting
CHAPTER 4 REFORMATION OF INSTRUNMENTS
parties, the literal meaning of its stipulations shall
 Article 1359. When, there having been a meeting of
control.
the minds of the parties to a contract, their true
 Article 1371. In order to judge the intention of the
intention is not expressed in the instrument purporting
contracting parties, their contemporaneous and
to embody the agreement, by reason of mistake,
subsequent acts shall be principally considered.
fraud, inequitable conduct or accident, one of the
 Article 1372. However general the terms of a contract
parties may ask for the reformation of the instrument
may be, they shall not be understood to comprehend
to the end that such true intention may be expressed.
things that are distinct and cases that are different
 If mistake, fraud, inequitable conduct, or accident has
from those upon which the parties intended to agree.  
prevented a meeting of the minds of the parties, the
 Article 1373. If some stipulation of any contract
proper remedy is not reformation of the instrument but
should admit of several meanings, it shall be
annulment of the contract.
understood as bearing that import which is most
 Article 1360. The principles of the general law on the
adequate to render it effectual
reformation of instruments are hereby adopted insofar
 Article 1374. The various stipulations of a contract
as they are not in conflict with the provisions of this
shall be interpreted together, attributing to the
Code.
doubtful ones that sense which may result from all of
 Article 1361. When a mutual mistake of the parties
them taken jointly.
causes the failure of the instrument to disclose their
 Article 1375. Words which may have different
real agreement, said instrument may be reformed.
significations shall be understood in that which is
 Article 1362. If one party was mistaken and the other
most in keeping with the nature and object of the
acted fraudulently or inequitably in such a way that
contract.
the instrument does not show their true intention, the
 Article 1376. The usage or custom of the place shall
former may ask for the reformation of the instrument.
be borne in mind in the interpretation of the
 Article 1363. When one party was mistaken and the
ambiguities of a contract, and shall fill the omission of
other knew or believed that the instrument did not
stipulations which are ordinarily established.  
state their real agreement, but concealed that fact
 Article 1377. The interpretation of obscure words or
from the former, the instrument may be reformed. 
stipulations in a contract shall not favor the party who
 Article 1364. When through the ignorance, lack of
caused the obscurity.
skill, negligence or bad faith on the part of the person
 Article 1378. When it is absolutely impossible to settle
drafting the instrument or of the clerk or typist, the
doubts by the rules established in the preceding
instrument does not express the true intention of the
articles, and the doubts refer to incidental
parties, the courts may order that the instrument be
circumstances of a gratuitous contract, the least
reformed.
transmission of rights and interests shall prevail. If the
 Article 1365. If two parties agree upon the mortgage
contract is onerous, the doubt shall be settled in favor
or pledge of real or personal property, but the
of the greatest reciprocity of interests.
instrument states that the property is sold absolutely
 If the doubts are cast upon the principal object of the
or with a right of repurchase, reformation of the
contract in such a way that it cannot be known what
instrument is proper.
may have been the intention or will of the parties, the
 Article 1366. There shall be no reformation in the
contract shall be null and void.
following cases:
 Article 1379. The principles of interpretation stated in
(1) Simple donations inter vivos wherein no condition
Rule 123 of the Rules of Court shall likewise be
is imposed; (2) Wills; (3) When the real agreement is
observed in the construction of contracts.
void.
 Article 1367. When one of the parties has brought an
CHAPTER 6 Rescissible Contracts rendered in any instance or some writ of
 Article 1380. Contracts validly agreed upon may be attachment has been issued. The decision or
rescinded in the cases established by law. attachment need not refer to the property
 Article 1381. The following contracts are rescissible: alienated, and need not have been obtained
◦ (1) Those which are entered into by by the party seeking the rescission.
guardians whenever the wards whom they  
represent suffer lesion by more than one- ◦ In addition to these presumptions, the design
fourth of the value of the things which are to defraud creditors may be proved in any
the object thereof; other manner recognized by the law of
◦ (2) Those agreed upon in representation of evidence.
absentees, if the latter suffer the lesion ◦ Article 1388. Whoever acquires in bad faith the things
stated in the preceding number; alienated in fraud of creditors, shall indemnify the
◦ (3) Those undertaken in fraud of creditors latter for damages suffered by them on account of the
when the latter cannot in any other manner alienation, whenever, due to any cause, it should be
collect the claims due them; impossible for him to return them.
◦ (4) Those which refer to things under ◦ If there are two or more alienations, the first
litigation if they have been entered into by acquirer shall be liable first, and so on
the defendant without the knowledge and successively.
approval of the litigants or of competent ◦ Article 1389. The action to claim rescission must be
judicial authority; commenced within four years.
◦ (5) All other contracts specially declared by ◦ For persons under guardianship and for
law to be subject to rescission. absentees, the period of four years shall not
◦ Article 1382. Payments made in a state of insolvency begin until the termination of the former's
for obligations to whose fulfillment the debtor could incapacity, or until the domicile of the latter is
not be compelled at the time they were effected, are known.
also rescissible. REPORTER: Arellano, James Rupert
◦ Article 1383. The action for rescission is subsidiary; it CHAPTER 7 VOIDABLE CONTRACTS
cannot be instituted except when the party suffering
Art. 1390. The following contracts are voidable or annullable,
damage has no other legal means to obtain
even though there may have been no damage to the
reparation for the same.
contracting parties:
◦ Article 1384. Rescission shall be only to the extent
necessary to cover the damages caused.   (1) Those where one of the parties is incapable of giving
◦ Article 1385. Rescission creates the obligation to consent to a contract;
return the things which were the object of the
contract, together with their fruits, and the price with (2) Those where the consent is vitiated by mistake, violence,
its interest; consequently, it can be carried out only intimidation, undue influence or fraud.
when he who demands rescission can return These contracts are binding, unless they are annulled by a
whatever he may be obliged to restore. proper action in court. They are susceptible of ratification. (n)
◦ Neither shall rescission take place when the
things which are the object of the contract Art. 1391. The action for annulment shall be brought within four
are legally in the possession of third persons years.
who did not act in bad faith.
This period shall begin:
◦ In this case, indemnity for damages may be
demanded from the person causing the loss. In cases of intimidation, violence or undue influence, from the
◦ Article 1386. Rescission referred to in Nos. 1 and 2 of time the defect of the consent ceases.
article 1381 shall not take place with respect to
contracts approved by the courts. In case of mistake or fraud, from the time of the discovery of
◦ Article 1387. All contracts by virtue of which the the same.
debtor alienates property by gratuitous title are Art. 1392. Ratification extinguishes the action to annul a
presumed to have been entered into in fraud of voidable contract. (1309a)
creditors, when the donor did not reserve sufficient
property to pay all debts contracted before the Art. 1393. Ratification may be effected expressly or tacitly. It is
donation. understood that there is a tacit ratification if, with knowledge of
◦ Alienations by onerous title are also the reason which renders the contract voidable and such
presumed fraudulent when made by persons reason having ceased, the person who has a right to invoke it
against whom some judgment has been should execute an act which necessarily implies an intention to
waive his right. (1311a) Art. 1406. When a contract is enforceable under the Statute of
Frauds, and a public document is necessary for its registration
Art. 1399. When the defect of the contract consists in the in the Registry of Deeds, the parties may avail themselves of
incapacity of one of the parties, the incapacitated person is not the right under Article 1357.
obliged to make any restitution except insofar as he has been
benefited by the thing or price received by him. (1304) Art. 1407. In a contract where both parties are incapable of
giving consent, express or implied ratification by the parent, or
Art. 1402. As long as one of the contracting parties does not guardian, as the case may be, of one of the contracting parties
restore what in virtue of the decree of annulment he is bound shall give the contract the same effect as if only one of them
to return, the other cannot be compelled to comply with what is were incapacitated.
incumbent upon him. (1308)
Art. 1408. Unenforceable contracts cannot be assailed by third
CHAPTER 8 UNENFORCEABLE CONTRACTS persons.
Art. 1403. The following contracts are unenforceable, unless CHAPTER 9 VOID AND INEXISTENT CONTRACTS
they are ratified:
Art. 1409. The following contracts are inexistent and void from
1. Those entered into in the name of another person by one the beginning:
who has been given no authority or legal representation,
or who has acted beyond his powers; (1) Those whose cause, object or purpose is contrary to
2. Those that do not comply with the Statute of Frauds as set law, morals, good customs, public order or public
forth in this number. In the following cases an agreement policy;
hereafter made shall be unenforceable by action, unless (2) Those which are absolutely simulated or fictitious;
the same, or some note or memorandum, thereof, be in (3) Those whose cause or object did not exist at the time
writing, and subscribed by the party charged, or by his of the transaction;
agent; evidence, therefore, of the agreement cannot be (4) Those whose object is outside the commerce of men;
received without the writing, or a secondary evidence of its (5) Those which contemplate an impossible service;
contents: (6) Those where the intention of the parties relative to the
 An agreement that by its terms is not to be performed principal object of the contract cannot be ascertained;
within a year from the making thereof; (7) Those expressly prohibited or declared void by law.
 A special promise to answer for the debt, default, or
Art. 1411. When the nullity proceeds from the illegality of the
miscarriage of another;
cause or object of the contract, and the act constitutes a
 An agreement made in consideration of marriage,
criminal offense, both parties being in pari delicto, they shall
other than a mutual promise to marry; have no action against each other, and both shall be
 An agreement for the sale of goods, chattels or things prosecuted. Moreover, the provisions of the Penal Code
in action, at a price not less than five hundred pesos, relative to the disposal of effects or instruments of a crime shall
unless the buyer accept and receive part of such be applicable to the things or the price of the contract.
goods and chattels, or the evidences, or some of
them, of such things in action or pay at the time some This rule shall be applicable when only one of the parties is
part of the purchase money; but when a sale is made guilty; but the innocent one may claim what he has given, and
by auction and entry is made by the auctioneer in his shall not be bound to comply with his promise. (1305)
sales book, at the time of the sale, of the amount and
kind of property sold, terms of sale, price, names of Art. 1412. If the act in which the unlawful or forbidden cause
the purchasers and person on whose account the consists does not constitute a criminal offense, the following
sale is made, it is a sufficient memorandum; rules shall be observed:
 An agreement of the leasing for a longer period than (1) When the fault is on the part of both contracting
one year, or for the sale of real property or of an parties, neither may recover what he has given by
interest therein; virtue of the contract, or demand the performance of
 A representation as to the credit of a third person. the other's undertaking;
3. Those where both parties are incapable of giving consent (2) When only one of the contracting parties is at fault, he
to a contract. cannot recover what he has given by reason of the
contract, or ask for the fulfillment of what has been
Art. 1404. Unauthorized contracts are governed by Article
promised him. The other, who is not at fault, may
1317 and the principles of agency in Title X of this Book.
demand the return of what he has given without any
Art. 1405. Contracts infringing the Statute of Frauds, referred obligation to comply his promise. (1306)
to in No. 2 of Article 1403, are ratified by the failure to object to
Art. 1413. Interest paid in excess of the interest allowed by the
the presentation of oral evidence to prove the same, or by the
usury laws may be recovered by the debtor, with interest
acceptance of benefit under them.
thereon from the date of the payment.
Art. 1414. When money is paid or property delivered for an
illegal purpose, the contract may be repudiated by one of the
parties before the purpose has been accomplished, or before
any damage has been caused to a third person. In such case,
the courts may, if the public interest will thus be subserved,
allow the party repudiating the contract to recover the money
or property.
Art. 1415. Where one of the parties to an illegal contract is
incapable of giving consent, the courts may, if the interest of
justice so demands allow recovery of money or property
delivered by the incapacitated person.
Art. 1416. When the agreement is not illegal per se but is
merely prohibited, and the prohibition by the law is designated
for the protection of the plaintiff, he may, if public policy is
thereby enhanced, recover what he has paid or delivered.
Art. 1417. When the price of any article or commodity is
determined by statute, or by authority of law, any person
paying any amount in excess of the maximum price allowed
may recover such excess.
Art. 1418. When the law fixes, or authorizes the fixing of the
maximum number of hours of labor, and a contract is entered
into whereby a laborer undertakes to work longer than the
maximum thus fixed, he may demand additional compensation
for service rendered beyond the time limit.
Art. 1419. When the law sets, or authorizes the setting of a
minimum wage for laborers, and a contract is agreed upon by
which a laborer accepts a lower wage, he shall be entitled to
recover the deficiency.
Art. 1420. In case of a divisible contract, if the illegal terms can
be separated from the legal ones, the latter may be enforced.
Art. 1421. The defense of illegality of contract is not available
to third persons whose interests are not directly affected.
Art. 1422. A contract which is the direct result of a previous
illegal contract, is also void and inexistentsN