Professional Documents
Culture Documents
DPWH Sbp2003-03a PDF
DPWH Sbp2003-03a PDF
Commission on Audit
MANAGEMENT SERVICES
Commonwealth Avenue, Quezon City, Philippines
Telephone Nos. 931-9235, 931-74455
Sir:
The audit covered the implementation of the School Building Program for
Elementary Education for CYs 2002-2003. The audit included, in addition to
that Department, the Department of Education with ocular inspection on selected
Division/District Offices within the National Capital Region and Regional
Offices Nos. VI and X, the Provincial Government of Bukidnon and the City
Government of Iloilo.
Introduction 2
Audit Objective 4
Audit Scope and Methodology 4
Audit Conclusion 5
Management’s Reaction to Audit Observations 6
i
Contents Page
Part IV Recommendations 73
ii
Part 1
Executive Summary
1
EXECUTIVE SUMMARY
INTRODUCTION
The shortage of classrooms is a long standing issue which is being raised every
enrolment period. To ensure that substantial number of classrooms are built, the
government is appropriating P2.0 Billion annually for the School Building
Program (SBP). For this purpose, the government had devised an allocation
system that is perceived to address equitable and fair allocation of resources. The
allocation as defined under Section 4 of R.A. No. 7880, otherwise known as the
“Fair and Equitable Access to Education Act”, is shown below:
10%
40% based on unallocated
classroom shortage (Discretion of DepEd 50% based on
Secretary) student population
2
EXECUTIVE SUMMARY
Under the Act, 90% of the Annual Appropriation will be released to the
Department of Public Works and Highways (DPWH) for the implementation of
the program while the 10% will be administered by the DepEd.
The budgets for CYs 2002 and 2003 were expected to produce 6,154 and 5,330
classrooms, respectively, for elementary and secondary schools considering an
average cost of P325,000/classroom in CY 2002 and P375,000/classroom in CY
2003. These units were distributed to the 210 Legislative Districts in accordance
with the above RA 7880 allocations as follows:
CY 2002 CY 2003
Region # of CL Amount # of CL Amount
These allocations are not sufficient to eliminate the classroom shortage of both
elementary and secondary schools of 35,986 for SY 2001-2002. The National
Government is, however, not alone in this endeavor. The Local Government Units
(LGUs) and a number of government and private entities are also constructing
school buildings to help the National Government.
3
EXECUTIVE SUMMARY
AUDIT OBJECTIVE
The audit was conducted to determine whether or not the implementation of the
school building program has been effectively and economically managed giving
consideration to:
The audit focused on the implementation of the school building program for
elementary education covering allocation for SY 2002-2003. The agencies
included in the audit are the DepEd and DPWH with ocular inspection in selected
Division/District Offices in the National Capital Region (NCR) and Regional
Offices Nos. VI and X, the City Government of Iloilo and the Provincial
Government of Bukidnon.
The performance of the DPWH was assessed using the following criteria:
To meet the audit objective, the team performed the following procedures:
4
EXECUTIVE SUMMARY
The audit was conducted from July 7 to November 28, 2003 in compliance with
COA MS/TS Office Order No. 2003-009 dated June 24, 2003 and TS Office
Order No. 2003-068 dated October 17, 2003.
AUDIT CONCLUSION
Overall, the audit concluded that the implementation of the school building
program was not effectively and economically managed. The implementation
was affected by deficiencies in the process of implementation from selection of
school building site to monitoring of contractor’s performance and a slow paced
performance by the DepEd and DPWH as discussed below:
¾ There is no single standard design and costing for school buildings. Each
implementing agency is adopting its own design and standards which are
based on its cost allocation per unit. This practice led to a situation where
school premises are crowded with different designs and structures which
is no longer in conformity with the government’s policy of properly
laying out school buildings in the school ground to achieve the most
advantageous display. The absence of uniform designs and costs hinders
the opportunity for comparing and evaluating the performance of the
implementing agencies involved in the construction of school buildings.
5
EXECUTIVE SUMMARY
The results of the audit were discussed with the Undersecretary and Chairman for
DPWH Task Force on School Buildings and other concerned officials of the
Department in an exit conference held on July 5, 2004. Overall, the Officials
acknowledged the team’s observation and is in accord with the proposed
recommendations.
6
Part II
7
SCHOOL BUILDING PROGRAM
INTRODUCTION
The provision of adequate resources for education is one of the priority concerns of
the government. One of the components under this program which the government
is committed to provide is adequate school buildings. For this reason, the national
government is allocating P2.0 Billion annually to address the school building
shortage. As reflected in the DepEd records for SY 2001-2002, the government
schools offering elementary education is short by 8,040 classrooms nationwide as
tabulated below:
I 19,392 5,722 0
II 12,998 2,994 0
III 30,044 4,841 310
IV 39,975 4,574 4,042
V 23,164 3,998 47
VI 30,952 8,008 10
VII 23,173 3,514 769
VIII 20,221 6,002 0
IX 13,228 1,244 584
X 12,722 1,993 202
XI 19,262 1,220 622
XII 8,682 1,179 51
CARAGA 9,651 1,445 155
NCR 13,955 2,545 900
CAR 7,566 2,686 0
ARMM 10,414 862 348
It can be gleaned from the above tabulation that while there is a need to construct
8,040 classrooms to address the shortage of other unserved schools, the number of
classrooms in some other schools is more than enough for their academic needs by
52,827. These numbers are even several times sufficient to address the existing
needs.
8
SCHOOL BUILDING PROGRAM
9
SCHOOL BUILDING PROGRAM
SOURCES OF FUNDS
For CY 2002, these agencies, excluding the LGUs’ budget out of the Special
Education Fund (SEF), have allocated about P3.72 Billion for school building
construction.
Budget 2002
Funding Source
(Billion)
GAA P 2.000
DPWH 90%
DepEd 10%
Loans (FAP-TEEP) (P17.0B for 5 years ) 1.400
PMS 0.055
CIA/CDF 0.100
FFCCCII (P350 M for 2 years) 0.165
Total P3.720
10
SCHOOL BUILDING PROGRAM
The DPWH, being the State’s engineering and construction arm, is tasked to
implement the School Building Program of the DepEd. The DPWH’s
participation on this program is defined under Rule VIII of the Rules and
Regulations for the Effective Implementation of RA 7880 adopted on March 31,
1995. It provides that appropriation for the construction, rehabilitation,
replacement and repair of school buildings shall be directly released to and
administered by the DPWH.
To ensure the smooth administration by the DPWH of the 90% appropriation, the
DepEd and DPWH entered into a Joint Memorandum on July 10, 2003 defining
the following:
¾ The DepEd and DPWH should agree on the average cost per classroom.
The costs may be adjusted upwards especially for multi-storey school
buildings provided that the total/target number of school buildings are
met within the approved GAA budget (P1.80 Billion or 90% of the SBP
component).
11
SCHOOL BUILDING PROGRAM
¾ The DPWH Project Engineer shall furnish the Principal with a copy of
each of the following reports, during the Construction Stage:
12
Flowchart for Monitoring DPWH Constructed School Buildings Figure 1
TE C H N IC AL D IV IS IO N R E G IO N AL C E N TR AL
C O N TR AC TO R DPW H SCHOOL
C O M M ITTE E O FF IC E O FF IC E O F FIC E
IDENTIFICATION
ST AR T ID EN T IF IC AT IO N O F SC H O O L S IT E AN D C L ASS R O O M N E ED
C O N D U C T S IT E
AP P R AIS AL & P R E P AR E
SITE
D E S IG N S & P L AN S ,
P R O G R AM O F W O R K
F U R N ISH A C O P Y O F
PL AN S, S P EC S & R E V IE W P L AN S , S P E C S
P R O G R AM O F W O R K AN D P R O G R AM O F W O R K
T O P R IN C IPAL
NO
CONSTRUCTION
R E S O L V E S C O N F L IC T IF
N O T S E T T LE D R E F E R T O
S U P E R IN T E N D E N T & AC C E PT AB L E
PROCUREMENT D IS T R IC T E N G IN E E R
Y ES
PRE-
AC C E PT S AW AR D & S T AG E (B U D D IN G ,
N O T IC E T O PR O C E E D C O N T R AC T IN G &
AW AR D IN G )
R E C E IV E S N O T ICE O F
AW AR D & C O N T R AC T O R
IN T R O D U C E D
M O B IL IZ AT IO N 1. M O N IT O R S
C O N S T R U C T IO N
S U P E R V IS IO N C O N S T R U C T IO N W O R K
2. O B S E R V E C R IT IC AL P R O G R E S S M O N IT O R IN G
S T AG E S O F
C O N S T R U C T IO N
CONSTRUCTION
R E S O L V E S C O N F L IC T IF
N O T S E T T LE D R E F E R T O NO AC C E P T AB L E
P R O G R E S S /Q U AL IT Y
S U P E R IN T E N D E N T &
D IS T R IC T E N G IN E E R Y ES C O N S T R U C T IO N
P AR T IC IP AT E S IN
R E Q U S T P U N C H L IS T IN G C O N D U C T P U N C H L IS T IN G
P U N C H LIS T IN G
R E C T IF Y P U N C H LIS T E D
P U N C H LIS T E D IT E M S
IT E M S
NO
CO MPLETED?
POST-CONSTRUCTION
RECOM MENDS
AC C E P T AN C E
Y ES
R E S O LV E S C O N FL IC T AN D
S E E K S AP P R O V AL O F
AC C E P T AB L E
S U P E R IN T E N D E N T AN D
D IS T R IC T E N G IN E E R
NO
Y ES
S IG N S CE R T IFIC AT E O F
AC C E P T AN C E (FO R M 1), P R E P AR E S F IN AL R E P O R T
P R E P AR E S P R E P AR E S
B O O K S U P AS S E T & (D E P E D -D P W H R E V IE W
P AY M E N T O F R E T E N T IO N C O N S O L ID AT E D R E P O RT C O N S O LID AT E D R E P O R T
P R E P AR E S C O M P L E T IO N C O M M IT T E E )
(U S E FO R M N O . 3) (U S E F O RM N O . 4)
R E P O R T (U S E FO R M N O . (U S E FO R M N O . 5)
2)
END
13
SCHOOL BUILDING PROGRAM
ALLOCATION
To partially address the more than 8,000 classroom shortage for elementary
education, the DepEd scheduled the construction of 5,094 new classrooms
during CYs 2002 and 2003, distributed as follows:
No. of Classrooms
Region CY 2002 CY 2003
14
SCHOOL BUILDING PROGRAM
CY 2002 CY 2003
Particulars Number % Number %
The existing buildings at present are of different sizes and designs as tabulated
below:
NS - Not Specified
FFCCCII - Federation of Filipino Chinese Chamber of Commerce and Industry, Inc.
15
SCHOOL BUILDING PROGRAM
REPORTS TO BE RENDERED
Department of
Public Works & ¾ DepEd Physical Status Report
Highways ¾ Summary Report – DepEd School Building
(DPWH) Program
16
Part III
Audit Observations
17
Chapter 1
18
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
INTRODUCTION
The government’s and private organization's efforts to provide funds for school
building would only be meaningful if the funds are used efficiently and
effectively. The funds are considered effectively used if the same, upon use,
address the very purpose for which the funds were appropriated/allocated. The
school building funds were intended to address the surmounting classroom
shortage the schools are experiencing at present.
Considering that the funds allocated are not enough to completely address this
concern, the prioritization of the needs to be addressed is crucial. For this reason,
the DepEd had formulated guidelines on the selection of schools that should be
allocated with classrooms. Thus, as soon as the Planning and Program Division
of the DepEd had completed the allocation of funds per Legislative District, the
respective Division Offices is informed of the same and furnished with the
guidelines on the selection of schools qualified to receive classroom allocation.
The audit disclosed that the criteria for the selection of schools most in need may
be considered adequate. However, the team noted that in the selection process,
the Division Offices did not consider the plans of other funding agencies. Thus,
there were a number of cases where the needs were being addressed by different
sectors.
These cases could have been addressed by the DPWH and the DepEd before the
construction of the project started. After discovering that there were on-going
construction of classrooms by other agencies or new buildings constructed, the
DPWH should have informed the DepEd and worked out for the realignment of
the fund to another school in need within the same legislative district.
OBSERVATION
19
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
To maximize the benefits derived from the SBP funds, the DepEd is issuing
annually, guidelines on the selection of schools to be allocated with classrooms.
For CYs 2002 and 2003, the DepEd set the following criteria:
CY 2002 CY 2003
• Barangays without an elementary school and those • The results of the Basic Education Information
that can have one. This is in response to the SONA System (BEIS) Quick Count for SY 2002-2003.
commitment of providing schools in every These data present the classroom needs at the
barangay. At least 50% of the priority barangays school level and should be used as basis for
identified by the field offices for each division allocation of classroom needs. The following
should be targeted for inclusion in the 2002 School color spectrum has been devised to determine
building Program. At least a two-room school which schools are in greatest need of
building should be proposed for a new elementary classrooms:
school.
Pupil : CL Ratio Color Code
• School buildings which were damaged by
calamities such as fires, typhoons, earthquakes, etc.
45 and below Blue
• Schools with large classroom shortages due to 46 – 50 Yellow
expanding enrolment. 51 - 55 Gold
56 & above Red
• Provision of schools in fast growing areas such as no classroom Black
resettlement/relocation sites.
• Installation of water supply system and electrical Preference should be given to the hot colored
connections (to be considered as new project schools in terms of classroom allocation (i.e.
categories). gold, red & black).
20
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
The team noted that these criteria maybe considered valid and adequate to guide
the Division Offices in their selection process. However, considering that the
school building program is also implemented by the LGUs and a number of
government and private organizations, the Division Offices should have
considered the plans of these agencies in their respective district.
The consultation process among the funding agencies is important to ensure that
the actual needs are addressed and to avoid duplication of actions and wastage of
meager resources.
Required
Province/
Existing
Existing
CIA/ CDF
Excess
City/
FFCCII
Total
DPWH
TEEP/
Deped
Municipality School
AR
AR
SMP
10%
PPC
SEF
NCR
Quezon City GSIS Village ES 32 4 36 34 2
Camp Crame ES 24 12 36 33 14
Mandaluyong FP Javier ES 4 8 12 8 4
Hi-Way Hills ES 46 15 61 39 22
Region VI
Iloilo City Arevalo ES 29 2 3 31 28 3
repairs
Ticud Es 20 3 2 2 2 26 20 6
repairs
Bo. Obrero ES 24 2 3 2 28 25 3
repairs
Taal ES 9 2 2 13 12 1
A. Montes II ES 27 1 Sci. 2 29 26 3
Lab
L. Mirasol ES 11 2 13 12 1
Sambag ES 27 2 29 26 3
Sto. Nino Sur ES 21 2 23 21 2
21
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
Existing AR
Required
Existing
Region/
Excess
CDF/CIA
Province/City/
FFCCII
DPWH
Total
DepEd
TEEP/
AR
SMP
10%
PPC
SEF
Municipality School
Region VI
Iloilo City A. Bonifacio ES 30 2 32 29 3
NJ Ingore ES 17 2 19 15 4
MV Hechanova 15* 2 17 13 4
ES
I. Arroyo ES 25 4 29 25 4
Capiz
Pontevedra Dna. VC Dais ES 21 2 23 20 3
Hipona ES 20 2 22 19 3
Pres. Roxas Pres. Roxas East 25 2 27 25 2
ES
Tapaz Bag-ong Barrio 6 1 7 6 1
ES
Camburanan ES 7* 1 8 6 2
Sapian Dapdapan ES 12 1 13 12 1
Jamindan Lucero ES 13 1 14 13 1
Mambusao Manibad ES 6 1 7 6 1
Dao Dao CES 36 3 39 34 5
Antique
Sebaste Aguilar ES 6 1 7 6 1
Nauhon ES 5 2 7 6 1
Barbaza Igpalge ES 7 2 9 7 2
Bugalong Cubay ES 13 2 15 13 2
Culasi Fe Caridad ES 5 2 7 6 1
Valderrama ES 8 2 10 7 3
Lana-an Guisijan ES 17 3 20 18 2
Libertad Bulanao ES 7 4 11 7 4
San Roque Es 5 2 7 6 1
Aklan
New
Washington Polo ES 12 2 14 12 2
Region X
Cagayan de Oro
City Camaman-an ES 63 2 65 63 2
Kauswagan ES 43 1 44 41 3
South City ES 49 4 53 50 3
Bukidnon
Valencia Kilangi ES 2 1 3 2 1
San
Fernando Halapitan ES 29 2 31 27 4
Camiguin
Mahinog Mahinog CS 18 2 20 18 2
Maramag Musuan ES 23 2 1 26 23 3
22
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
The excess classrooms were found during inspection being used for non-academic
purposes such as Principal’s Office, Property Room, PE Room and the like.
The team further noted that the possibility of using the excess classrooms in the
near future for the intended purpose is remote considering the declining/negative
growth in enrollment on some of these schools ranging from 0.26% to 23.63% as
tabulated below:
GROWTH
ENROLLMENT RATE
CONSTRUCTIONS
EXISTING
EXCESS
CY 2001
CY 2002
CY 2003
CY 2002
CY 2003
SCHOOL
TOTAL
NEEDS
(In %)
(In %)
Camp Crame ES 1,820 1,590 1,519 -1.85 -4.47 24 12 36 22 14
Taal ES 401 384 361 -4.24 -5.99 9 4 13 12 1
A. Bonifacio ES 1,134 1,083 1,056 -4.50 -2.49 30 2 32 29 3
NJ Ingore ES 851 684 680 2.00 2.41 17 2 19 15 4
MV Hechanova ES 581 572 545 -3.21 -4.72 15* 2 17 13 4
I. Arroyo ES 1,097 1,093 1,007 -0.36 -7.87 25 4 29 25 4
Dna Victoria Dais ES 890 825 734 -7.30 -11.03 21 2 23 20 3
Hipona ES 692 677 675 -2.17 -0.30 20 2 22 19 3
Panay CES 1,229 1,182 1,126 -3.82 -4.74 31 3 34 30 4
Pres Roxas East ES 848 808 792 -4.73 -1.74 25 2 27 25 2
Dapdapan ES 381 378 377 -0.79 -0.26 12 1 13 12 1
Lucero ES 437 413 392 -5.49 -5.08 13 1 14 13 1
Maribad ES 181 180 174 -0.55 -3.33 6 1 7 6 1
Polo ES 582 519 488 -7.65 -5.97 12 2 14 12 2
South City ES 2,269 2,243 2,219 -1.15 -1.07 49 4 53 50 3
Halapitan ES 1,219 1,179 1,114 -3.28 -5.51 29 2 31 27 4
Mahinog CS 809 574 562 -5.75 -2.09 18 2 20 18 2
The duplication of actions could have been avoided by the DPWH, as the
implementing arm of the SBP, and the DepEd had there been proper coordination
before the construction of the project. The DPWH should have properly informed
the DepEd before starting the project that there were on-going or about to start
construction by other agencies or new building constructed. That way, the funds
intended for construction or repair should have been realigned to another school
also in need within the same legislative district.
23
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
It was further provided that the realignment/relocation shall be made upon the
initiative and consent of the representative of the district office concerned with the
concurrence of any one of the following regardless of the cost of the project being
realigned/relocated:
This school was not among the priority schools identified by the DepEd, hence,
was not allocated any classroom for CYs 2002 and 2003. To accommodate all
students, the school adopted 3 shifts for grades 2 and 3 with classes from 6:00-
10:00am, 10:00am – 2:00pm and 2:00 – 6:00 pm. Under this condition, the
number of minutes per subject for Grades 2 and 3 were reduced as illustrated
below:
Number of Minutes
Subject Should Be Actual Difference
The team also noted that this school, together with a number of schools in the
Regions inspected by the team, resorted to the use of temporary classrooms such
as stage, open hallways, enclosed corridors and makeshift structures made of
bamboo, plywood or corrugated galvanized iron just to conduct classes as
illustrated on the next pages.
24
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
25
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
26
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
This condition is also experienced by other schools that could not be provided
with adequate classrooms.
It is the role of the DepEd to The team agrees that the identification
identify/select the sites per item 4.A of school sites is primarily a
of the Joint Memorandum of DepEd responsibility of the DepEd. However,
and DPWH, regarding the Guidelines for as discussed in the report, under Rule
Coordination and Monitoring of DPWH- VI of the Rules and Regulations for
Constructed School Buildings dated 10 the Effective Implementation of RA
July 2003. Likewise, per Memorandum 7880, a realignment/relocation of
of Agreement between DPWH and project should be undertaken when
DepEd, Deped shall prepare allocation there were project duplication or
list and see to it that there is no overlapping of funding source. It was
duplication or overlapping of projects further provided that such relocation
while DPWH ensures that the allocation should be made upon the initiative of
list is followed. the District Office concerned with the
27
SOUND IDENTIFICATION/SELECTION OF SCHOOL SITE
The partial construction of three (3) storey Even after the demolition of the two
twelve (12) classroom building at Camp storey building with eight classrooms,
Crame Elem. School, which is located at the existing classrooms are still adequate
Barangay Bagong Lipunan, Quezon City, for the needs of the school. There are
was funded under CYs 2001 & 2002 even classrooms which were being
School Building Program (DECS), in the utilized only in the morning or in the
amount of P2.550 Million and P5.2 afternoon and another eleven good
Million, respectively. The construction was classrooms being used for non-academic
a replacement of a demolished two-storey purposes. The newly constructed school
building with eight (8) classrooms, that building is not yet being used as of
was gutted by fire on April 1997. Funds for inspection date.
completion was released under CY 2003
School Building Program (DECS) with an
allocation of P2.0 Million. Thus, the final
completion included construction of CHB
partition, plastering and floor tapping at the
3rd floor, installation of grills and
fabricated materials, construction of
ceilings, electrical works and painting of
the whole building.
28
Chapter 2
29
REASONABLE COST MEASURES
INTRODUCTION
It is the policy of the State to safeguard life, health, and property consistent with
the principles of sound environmental management and control, and to provide for
all buildings and structures, a framework of minimum standards and
requirements.
To attain this end, buildings proposed for construction shall comply with existing
regulations and specifications set forth governing quality, characteristics and
properties of materials, methods of design and construction, type of occupancy
and classification. All buildings or structures, as well as accessory facility thereto,
shall conform to the principles of sound construction and must be suited to the
purpose for which they are designed. The designs and requirements, however, are
in most cases, dependent on the costs allocated for the purpose.
The team, however, noted that the practice of the implementing agencies of
adopting its own designs and standards within the same school did not support the
government’s policy of properly laying out school buildings on the school
grounds to achieve the most advantageous display. It resulted in crowded
vicinities due to the difficulty of arranging site locations. This also hinders an
effective comparative evaluation and assessment of the performance of different
implementing agencies.
The team also noted that the DPWH is contracting scope of works not sufficient
to construct a completed classroom at a cost set by both DepEd and DPWH for a
complete construction. Thus, there are a number of school buildings which could
not yet be used. As provided in the DepEd-DPWH Joint Memorandum, costs
constraints should not be used by the DPWH as a ground for delivering
unfinished classrooms.
The audit further disclosed that the DPWH failed to prepare a standard Program
of Work (POW) for each plan. In the absence of a standard POW, an individual
POW is prepared for every project to be bid out using the same plan. Ironically,
each POW reflects different quantities for the same item covered by the same
scope of works. This condition contributed in the DPWH’s failure to complete the
project at the prescribed unit cost.
30
REASONABLE COST MEASURES
OBSERVATIONS
The team noted that these agencies were constructing school buildings
with different designs and costs. Apparently, due to absence of specific
pronouncement on the designs and standards to be followed, these
agencies have been adopting their own designs and policies which are
based on the costs allocated for the purpose.
For CY 2003, these agencies have set the following costs based on their
respective designs:
DPWH One storey one (1) classroom building, rafter type P 375,000.00
(7m x 9m/ One storey two (2) classroom building, rafter type 690,000.00
classroom) One storey three (3) classroom building, rafter type 1,020,000.00
31
REASONABLE COST MEASURES
It can be noted that the DPWH and LGUs in the Province of Bukidnon
were all constructing one-classroom, one-storey building at a cost of
P375,000 and a range of P220,000 to P296,744, respectively. The
FFCCCII was not constructing one classroom building. However, at a
cost of P350,000 for two classroom building, it may be able to construct
one classroom at P175,000. Considering the differences in costing, the
team compared the features and other related aspects of the different
designs using their respective plans and specifications.
EARTHWORKS
Footing .70x.70x.70mx6 9x.9x1.05mx6 1.1x.8x.8mx8 .8x.8x1.25mx8 .75x.75x1.55mx4
.60x.60x1.55mx3
Wall Footing .10x.50x28.80m 26.3x.3x.55m .25x.35x28.8 .3x.5x38.8m .45x1x2.75mx6
.40x.15x.25mx2
Corridor .10x.30x11m None none none .10x1.80x15mx1
SV None None 1.2x1.8x1.8mx1 none None
EMBANKMENT
Filling Materials 8.902 22.40 15.00 Not in POW 16.25
Footing .70x.70x.50mx6
Wall Footing .10x0.35x28.80m
Concrete Slab 8.0x8.50x0.05x1.00
Gravel (cu.m.) 4.000 5.600 Not in POW 18.170 6.16
CONCRETING,
REBARS,
FORMWORKS
Footing .70x.70x.20mx6 .90x.90x.25mx6 .2x.8x.8x8 .25x.8x.8mx8 .75x.75x.25mx4
.60x.60x.25mx3
Wall Footing .40x.15x28.80mx1 26.3x.30x.15mx1 .25x28.8x_ .01x.3x34.3m .45x.25x2.75mx6
.40x.25x2.75mx2
Slab Fill .10x8.50x8x1 8x7x.05x1 .09x7x8mx8 .1x7x8m .10x7x7m
Corridor 8x1x.05x1 .09x1x8mx1 .1x1.7x8m .1x1.8x7m
32
REASONABLE COST MEASURES
MASONRY
WORKS
CHB Laying 76.425 74.930 67.920 135.640 77.54
Plastering 152.850 148.560 102.450 271.280 155.08
PRE-FAB
COMPONENTS
Steel Columns 150x90x20mmx2LC None none none None
250x90x5500mmxL 2”x6”channel
Steel Rafters
Z rafters
Steel Purlins 100x40x150mm LC 2”x4” C- Purlins
2”x1.5”x3/16”( Rafters
Steel Truss
Angle bar)
Wood Truss 2” x 6” 2”x6”
DOORS &
WINDORS
Door
Steel Door 2.1x.90mx2
Wood Panel 2.1x1.0mx1 2.1x.90mx2 2.1x1mx1 1x2.10mx1
2.1x.60mx1 2.1x.60mx1 .80x2.10mx1
Windows
Wood Louver none 3.2x1.2mx2 1.8x2m .8x1.5mx1
Jalousy 1.5x1.8mx2 2.4x1.2mx2 2.1x1.5mx2
1.5x2.5mx3 0.6x0.6mx1 1.5x1.5mx1
Quantity 17.00 21.600 1 lot 14.4 9.75
CARPENTRY
Ceiling Insulation 48.000 56.00 56.00 49
COMFORT
ROOM
Excavation 1.4x3.3x1.5x1 1.5x1.5mx2
Quantity 6.930
Ceramic Tiles Not in POW 1 1 1 None
33
REASONABLE COST MEASURES
34
REASONABLE COST MEASURES
The team further noted that the lack of uniform design of school building
resulted in crowded vicinity due to different sizes and designs and the
improper selection by schools for the most appropriate site for the design.
As a policy, a school building should be properly laid out in the school
grounds to achieve the most advantageous display. The laying out of the
different school buildings, as a general rule, should be according to
functional groupings. The distances between school buildings should be
such that:
• Ventilation is not obstructed
• Natural illumination is not obstructed
• Sounds in one building do not permeate through adjacent or next
building
35
REASONABLE COST MEASURES
DPWH will adopt single and uniform The team appreciates the DPWH’s
school building designs to arrive at reaction to this observation.
uniform costings.
Anchored through the VISION and The team was aware that the District
MISSION of the Department (DPWH), Offices merely implement the designs
the District offices, being the prepared by the DPWH Central Office
implementing arm of various and appreciates its response of
infrastructure project especially the upholding the team’s campaign for an
DepEd School Building Program (SBP), integrated uniform and homogenous
is bound to adopt the Agency’s (DPWH) design and standards for SBP.
Plan, Design and Standards as a guiding
tool for implementing projects. It is
therefore emphasized that the District
level is not in the position to prepare,
establish and adopt its own standards
and even designs. Except, however, in
cases where the Agency’s Standard
Plan and Designs are not feasible nor
suitable to actual field condition or
where schools have already existing
unfinished structures which they, as
end-users, would prefer to be
completed or expanded. In instant cases,
the District Office is forced to redesign
and prepare the corresponding Program
of Work (POW) as deemed from the
Standard Plan, Designs and Standards as
set forth by the Department for SBP.
Consistent with the basic principles in
programming, accuracy and economy
were also religiously observed.
Notwithstanding, the District Offices
will strongly uphold the audit team’s
campaign whose plan envisioned is
geared towards attaining an integrated
uniform and homogenous design and
standards for SBP which is to be adopted
by all participating agencies in the
succeeding implementation years.
36
REASONABLE COST MEASURES
37
REASONABLE COST MEASURES
a. cemented floor
b. smooth finished walls
c. painted walls, ceiling and roofing
d. full cathedral-type ceiling ( for single storey construction) or
drop-ceiling ( for multi-storey building)
e. complete set of windows (2 facing walls)
f. two entrance with doors
g. complete electrical wires and fixtures
h. roofing or weather protection
It was further explained in the guidelines that the average cost set by both
parties per classroom is based on required specifications and for budget
purposes only, and should not be used by the DPWH as a cost constraint
to deliver unfinished classrooms.
The team, however, noted that while the contracted amount almost equal
the total budget set for each classroom, the contracted scope of works
were not sufficient to deliver completed classrooms. Not all components
of a completed classroom enumerated above were included in the
38
REASONABLE COST MEASURES
contract. Moreover, audit disclosed that the scope of works differ from
one project to another with almost the same contract cost.
39
REASONABLE COST MEASURES
Bugo CS
Macabalan ES
40
REASONABLE COST MEASURES
Bulua ES
Macasandig
ES
41
REASONABLE COST MEASURES
East City CS
It would then appear that the prescribed cost of P400,000 per classroom
for two-storey building would not be sufficient to deliver completed
classroom. This only shows that the adoption of multi-storey building is
costly when compared with one-storey building. This is evident upon
analysis of the costs estimates of DPWH on the following structures:
The schedule shows that the cost of constructing one classroom under the
multi-storey structure is twice or thrice the costs of one-storey classroom.
With limited resources then, the adoption of multi-storey building and the
DPWH practice of contracting unfinished classrooms would delay the
realization of the government’s objective of providing adequate resources
in due time. The construction of multi-storey structure is, however,
applicable in schools with limited sites.
42
REASONABLE COST MEASURES
Due to congestion problem and/or The team agrees that in some schools,
limited school sites, the construction of the construction of multi-storey school
multi-storey school building is building is the only solution to address
recommended. However, due to limited the limited school site. Considering
budget annually which is usually based the limited budget, however, in
on the ceiling allocation per schools with sufficient sites for
congressional district, phase-by-phase construction of additional building, the
construction is allowed as long as a construction of one-storey building is
continuing allocation is assured to recommended. The team also
complete the building. Again, DepEd recognized that the budget allocation
should look into the funding scheme for per congressional district is limited.
multi-year projects that should ensure For this reason, the simultaneous
completeness of the building in doing construction of several buildings in
their programming works. different sites within the same
congressional district is not advisable
as it would only result in several
incomplete projects which could not
be used unless additional fund is
allocated. Such practice could not be
considered sound as these buildings
would remain idle when these could
have been used had the funds been
Response provided by Cagayan De concentrated on completing one
project after another.
Oro District Engineering Office
Cagayan de Oro City District The team recognized the efforts being
Engineering Office, which is one of exerted by the District in ensuring that
the implementing District in DPWH-10, the required school buildings are
consistently implemented the delivered in accordance with the
government thrust in providing Quality standard plan and designs under the
Education as mandated by the pre-determined budget per classroom.
constitution by constructing School However, as the budget for each
Building Projects through Optimum classroom is limited, the District
utilization of available resources. The should properly inform the DepEd,
District Office adopts the Standard Plan thru the DPWH Central Office, that
and Designs in the derivation of the with the amount budgeted for each
Scope of Work using the pre- classroom, the District could not
determined Budget per classroom. deliver a completed school building.
Likewise, unit costs are prepared based This way, the problem on delivering
on a fair and reasonable approved incomplete school buildings could be
current prices as projected over the resolved by the two departments.
proposed construction period. In so
doing, the district office is really It would be a sound decision to
43
REASONABLE COST MEASURES
The construction of (2) two storey type The team does not question the
SBP covering one to two classrooms clustering of classrooms into one
were clustered into one contract package contract package. Rather, the
to initiate simultaneous construction of contracting of scope of work which is
the project, thus, the agency could not sufficient to complete a classroom.
deliver early completion of the SBP as
per approved plan and program of work.
3. The DPWH does not have a standard program of work for each
plan. Thus, for every contract, an individual program of works is
prepared covering only the scope of work intended to be
contracted. The different programs of works which were based
on the same plan, however, reflect different quantities for the
same item of works. This condition contributed in the DPWH’s
failure to complete the classroom at the prescribed unit costs.
Likewise, the District Offices did not prepare a standard POW for each
plan. Rather, as a matter of practice, individual POW is prepared for
every project to be constructed covering only the specific scope of work
intended to be contracted.
1) Scope of Works : Construction of 1-CL (2 storey type) School Building (Ground Floor)
Bulua ES Macasandig ES East City
Items P385,639.81 P384,998.74 P385,293.61
Qty. % Qty. % Qty. %
2) Scope of Works : Construction of 1-CL (2 storey type) School Building (Second Floor)
Camama-an ES West City ES Tablon CS Suntingon ES Bonbongon ES
Items P384,138.54 P384,508.97 P385,051.37 P378,722.51 P384,921.60
Qty. % Qty. % Qty. % Qty. % Qty. %
Reinforce Steel Bar 245.83 130 739.25 392 188.70 100 1,653.62 876 1,837.50 974
Structure Concrete 1.32 181 5.69 779 0.73 100 6.26 858 7.84 1,120
CHB Laying 46.37 111 41.70 100 57.04 137 112.66 270 86.19 207
Rough Carpentry 2.07 309 1.59 273 4.30 642 0.67 100 NS
Finished Carpentry 261.04 1,673 134.80 864 316.00 2026 NS 15.60 100
Rough Hardware 49.00 136 56.50 157 70.50 196 46.00 128 36.00 100
Corrugated Roofing,
Gauge 26 14.40 100 131.60 914 NS 118.58 823 122.40 850
Cement Plaster
Finish 128.03 112 776.26 680 114.06 100 275.84 226 136.87 120
3) Scope of Works : Construction of 2-CL (2 storey type) School Building (Ground & Second Floor)
Gusa ES Bugo CS Macabalan ES City CS
Items P764,659.47 P770,463.04 P771,422.05 P769,778.65
Qty. % Qty. % Qty. % Qty. %
CHB Laying 123.11 100 143.23 116 126.11 102 140.21 113
Smooth Finish 541.10 123 439.74 100 530.39 120 530.39 120
Trusses/Purlins 1,036.94 100 1,373.12 132 1,036.94 100 1,036.94 100
Corrugated Roofing G#26 96.00 100 108.00 112 96.00 100 96.00 100
Cement Plaster Finish 300.77 175 171.54 100 282.89 165 312.39 182
45
REASONABLE COST MEASURES
Reinforce Steel Bar 2,952.50 107 2,745.30 100 2,815.60 102 2,745.30 100
CHB Laying 197.14 111 177.67 100 186.60 105 177.67 100
Smooth Finish 328.99 100 470.12 143 489.40 149 470.12 143
Cement Plaster Finish 353.71 109 323.65 100 359.50 111 323.65 100
DepEd and DPWH has already agreed to We appreciate the efforts exerted by
come up with a standard program of both departments in coming up with a
work, bill of materials and quantity take- standard program of work (POW), bill
off, and will only vary on the prices of of materials and quantity take-off.
the construction materials and other This move would facilitate the
indirect costs. However, a “balancing” preparation of POW as only the unit
cost adjustment thru clustering of costs of construction materials and
projects or contract packaging will indirect costs would be settled in the
substantiate any difference in cost such as District Offices.
terrain, handling, earth-moving and other
additional costs.
46
REASONABLE COST MEASURES
The implementing district really The team appreciates the actions taken
extended its unceasing effort in by the District Office in coming up
maintaining consistency in the with a standard Program of Work for
preparation of programs of work in each Plan. We also agree that there
conformance with the existing would be minor variations of quantities
guidelines, policies, rules, and regulation. depending on the actual field
Comparatively, computations of conditions and the presence of standard
quantities for two programs of same POW would provide a guidance in
item of work may always vary depending evaluating such variance.
on the conditions of the existing
structures, site grade line elevations, and
other physical and environmental factors
within the periphery. Though
programmers/estimators may differently
perceive a single idea, but technically, it
is also a fact that in terms of computation
of quantities for a detailed structural
member given a specific dimensions and
sizes would surely result a nearly zero
disparity since the process is only
procedural. As discussed earlier, actual
field conditions would be the governing
factor in computing quantities obtained
in a program. It is irrefutable that the
Standard Plan and Designs do not have a
standard program of work and the
district office welcomes the
recommendation of the team to come up
with a Standard Program for a Standard
Plan, especially on SBP which are yet to
be constructed, as guiding tool in
programming with reservations on
minor variations of quantities depending
on the actual field conditions.
47
Chapter 3
48
EFFECTIVE QUALITY ASSURANCE
INTRODUCTION
To ensure the smooth implementation of the school building program and assure
quality of its projects, the DepEd and DPWH established guidelines defining their
specific responsibilities from pre-construction stage to post occupancy evaluation.
The audit, however, disclosed that both DPWH and DepEd officials were not able
to ensure the quality of projects delivered by the contractors as manifested in the
construction deficiencies noted by the team during inspection which remained
uncorrected. The deficiencies included cracks on interior walls and flooring, poor
workmanship, non installation of the required materials and failure to comply
with the specifications, among others. These lapses in monitoring and evaluation
affect the quality in construction of school buildings.
49
EFFECTIVE QUALITY ASSURANCE
OBSERVATION
The DepEd and DPWH were not able to ensure quality performance of
the contractors resulting in construction deficiencies in a number of
school buildings constructed by the DPWH, DepEd, and FFCCCII,
which remained unrectified at the time of inspection. The deficiencies
include cracks on interior walls and flooring, poor workmanship, non-
installation of the required materials and non compliance with the
required specifications. These deficiencies would result in costly
maintenance, pose danger to students and lessen the effective life of the
structures. Moreover, the recently issued guidelines requiring the school
principals to monitor contractor’s performances may not be appropriate
as they are not technical personnel to be able to evaluate contractor’s
accomplishments.
• The DepEd shall implement the unallocated portion of the fund amounting to
P200 Million yearly;
• The DPWH shall implement the balance of the fund amounting to P1.8 Billion
yearly;
• The DPWH will transfer to DepEd, P6 Million for monitoring and evaluation
purposes.
For the efficient and successful execution of the program, the DepEd agreed to
accept the projects completed in accordance with the approved program of work
and to monitor and assess the progress of construction work. Inspection of
completed school buildings, however, revealed that apparently, both the DPWH
and DepEd were not able to ensure quality performances of contractors as
manifested in the construction deficiencies on the projects contracted by the
District Offices in Region VI as illustrated on the next pages.
50
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Macarena Elementary School (1 CL), Septic tank provided was not in accordance
Patnungon, Antique, implemented by with the plans and specifications. No
DPWH-Antique Eng’g. District manhole was provided.
Malacañang Elementary School (2 CL), Entrance cap for electrical works was
Culasi, Antique, implemented by DPWH- provided at a lower portion of the end wall
Antique Eng’g. District posing hazard for the end-user if the
electricity will be commissioned.
Bacay Elementary School (1 CL), 1. Some jalousie blades were already missing.
Dumangas, Iloilo, implemented by 2. Different specifications for C-Purlins.
DPWH 2nd Engineering District
51
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
New Lucena Central School (1 CL), New 1. Installed clear glass instead of smoke glass
Lucena, Iloilo, implemented by DPWH for door transom.
2nd Engineering District 2. Several jalousie blades missing.
3. Wire screen for air vent were not provided
though said item was not indicated in the
detailed bid estimate, same was included in
the preparation of plan and work program.
4. Different specifications for slip angle bars.
Sapao Elementary School (1 CL), Absence of 2 sheets clear transom glass for
Dumangas, Iloilo, implemented by wooden doors.
DPWH 2nd Engineering District
Passi Central Elementary School (1 CL), 1. Several jalousie blades were missing.
Passi, Iloilo, implemented by DPWH 2nd 2. Cracks were observed on door jamb.
Engineering District
Calao Elementary School (1 CL), 1. Hairline cracks were observed at the interior
Dumangas, Iloilo, implemented by floor slab.
DPWH 2nd Engineering District 2. Roof leaks as evidenced by wood stains on
inside ceiling board.
3. Wooden door frames and jamb were already
termite infested.
4. Door frames not properly smooth finished.
5. Surface finish of baseboard at the interior
plastered walls were not properly
finished/plastered.
Mangorocoro Eleementary School, Ajuy, 1. 1 set frosted door transom glass already
Iloilo, implemented by DPWH broken.
2. Installation of windows and window jamb not
properly leveled.
3. Installed frosted glass instead of clear glass
for window transom area.
4. Ceiling boards (inside and outside) were not
properly nailed.
5. Electrical works were not functional/
operational
6. Design of roof eaves were not observed to be
too short for the constructed corridor,
resulting to flashing back of rain water.
7. Convenience outlets and three gang switch
were installed without cover.
Cabilauan Elementary School, Barotac 1. Several window jalousie blades were already
Nuevo, Iloilo, implemented by the DPWH missing.
2nd Eng’g. District
52
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Leganes Central School (1 CL), Leganes, 1. Wire screen on wood framing were not
Iloilo, implemented by DPWH 4th Eng’g. provided on air vents.
District 2. Submitted Change Order not supported with a
detailed estimate.
Pavia Pilot Elementary School (1 CL), Airvents were not provided with wire screen.
Pavia, Iloilo, implemented by DPWH 4th
Eng’g. District
53
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Buntatala Elementary School (Annex) Wire screen was installed to 1 unit airvent
(1CL), Leganes, Iloilo, implemented by (one side) only.
DPWH 4th Eng’g. District
AKLAN PROVINCE PROJECTS
Cabugao Elementary School, Batan, 1. Temperature cracks on plastered walls.
Aklan, implemented by Aklan Eng’g. 2. Roof leaks as evidenced by wood stain on
District ceiling board.
3. Installed ordinary plywood in combination
with marine plywood.
Tabayon Primary School (SONA Project), 1. Misalignment of Facia Board installed at right
Banga, Aklan, implemented by Aklan side portion.
Eng’g. District 2. Hairline cracks on plastered walls.
Naisud Elementary School (CDF Funded), With damaged door knobs allegedly supplied
Ibajay, Aklan, implemented by Aklan by the school.
Eng’g. District
Nabas Central Elementary School, Nabas, 1. Misaligned installation of fascia board at the
Aklan, implemented by Aklan Eng’g. left side portion.
District 2. Installed frosted glass on door and window
transom with aluminum frame instead of clear
glass with quarter round mouldings.
Tondog Elementary School, Tangalan, 1 unit bay window was converted to entrance
Aklan, implemented by Aklan Eng’g. door leading to the comfort room.
District
Makato Central Elementary School, 1. Roof leaks (inside and outside of ceiling)
Makato, Aklan, implemented by Aklan 2. Temperature cracks on some portion of
Eng’g. District plastered walls.
54
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Alaminos Elem. School, Madalag, Aklan, Roof leaks at the outside portion of ceiling.
implemented by Aklan Eng’g. District
Kinalangay Viejo Elementary School, 1. Installed folded plain G.I. for louver window
Malinao, Aklan, implemented by Aklan instead of wooden fixed louver window
Eng’g. District (airvent window)
2. Portion of ceiling not properly nailed.
CAPIZ PROVINCE PROJECTS
President Roxas East Elementary School Installed Hapslock door lock instead of Yale
(2 CL), Pres. Rozas, Capiz, implem. by Brand.
Capiz Eng’g. Dist.
Pasugue Elem.School (2 CL), Panit-an, Installed Guli door lock instead of Yale
Capiz, implemented by Capiz Eng’g. brand.
District
Don Catalino Andrada Memorial School 1. Installed door knob bear no brand (POW –
(1 CL), Brgy. Mianay, Ivisan, Capiz, Yale brand)
implemented by Capiz Eng’g. District 2. Absence of clear glass in some steel
casement.
3. Easily detached glass putty for window steel
casement.
55
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Don Panfilo Mendoza Memorial School(1 1. Easily detached glass putty for window steel
CL), Brgy. Mianay, Ivisan, Capiz, casement.
implemented by Capiz Eng’g. District 2. 1 set steel casement window glass was
already broken/missing.
Ivisan ES (1 CL), Brgy. Poblacion - 1. Easily detached glass putty for window steel
Norte, Ivisan, Capiz, implemented by casement.
Capiz Eng’g. District 2. Ceiling (exterior and interior) was termite
infested and with roof leaks.
The monitoring and supervision of projects implemented by DPWH was also one
of the mandated functions of the Task Force Engineering, Assessment and
Monitoring (TFEAM) created under DECS Order No. 32 series of 1999.
Confirmation from the TFEAM showed that apparently, these projects were not
among the projects randomly inspected and validated or have been the subject of
their review. In a letter dated March 1, 2004 by the TFEAM Head, the team was
informed that their monitoring, assessment and evaluation were concentrated on
these areas:
Areas Visited
Calendar Year
Regional Offices Provinces/Cities
56
EFFECTIVE QUALITY ASSURANCE
The team noted that recently, the DepEd and DPWH issued guidelines on
monitoring of DPWH constructed projects. The guidelines, released on July 10,
2003, was intended to address the following objectives:
To attain these objectives, the coordination and monitoring procedures from pre-
construction to post construction evaluation were defined for each activity to be:
• Pre-Construction Stage
¾ The DPWH District Office shall provide the DepEd Division Office and
the Heads of the recipient school copies of the plans, specifications,
program of works and schedules of construction of the projects under
their areas of jurisdiction for review and comments prior to
construction. All comments should be sent to the DPWH District Office
within seven days from receipt of the documents.
¾ The DPWH Project Engineer shall furnish the Principal with a copy of
each of the following reports:
57
EFFECTIVE QUALITY ASSURANCE
• Post-Construction Stage
¾ The DepEd and DPWH Central Office shall create a-DPWH SBP
Review Committee to discuss SBP status and actions taken on the
Monitoring and Assessment Reports. The Committee shall submit
additional observations and comments on the program.
• Post-Occupancy Evaluation
¾ For purposes of determining the impact of the project, Form No. 6: Post
Occupancy Evaluation Questionnaire is provided. It will be filled out by
the teachers and students randomly picked by the school principal. This
survey tool will provide information about the experiences and
satisfaction levels of the stakeholders one year after the acceptance and
usage of the classroom.
• Protection Clause
58
EFFECTIVE QUALITY ASSURANCE
The team noted that under these guidelines, the responsibility to ensure that the
construction was undertaken in accordance with the standards and detecting
deficiencies rests with the School Principal. This set up may not be ideal
considering that the School Principals are not technical personnel and may not be
in a position to perform this function. This function could be better performed by
the DPWH personnel considering that they themselves prepared the designs, plans
and program of works and contracted the project.
Interviews with the School Principals during inspection revealed that they were
not yet provided by the District Office, copies of the plans and specifications and
were not involved in the inspection of the projects. They admitted that they have
not been observing the critical stages of construction as they were not yet aware
of their responsibility under the guidelines.
The team was informed by Ms. Ester T. Dijamco, Chief, Physical Facilities
Division that the guidelines issued on July 10, 2003 is applicable for CY 2003
SBP. However, said guidelines were disseminated to the field offices only
through DepEd Order No. 77 on September 17, 2003, while the guidelines for the
utilization of monitoring funds was disseminated only through DepEd
Memorandum 73 dated February 16, 2004. The corresponding funds for this
purpose has yet to be transferred by the DPWH to DepEd.
The presence of deficiencies was likewise observed on the DepEd and FFCCCII’s
implemented projects as tabulated below:
School/Location Observations
Sto. Niño Sur Elementary School (2 1. Cracks on wall and flooring can be
CL), Iloilo City, implemented by noticed. Repair is needed.
FFCCCII 2. Leakages on roofing exist as proofs of
stain mark on ceiling can be noticed.
3. Ceiling needs re-fixing.
59
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Arevalo Elementary School (2 CL), 1. Doors and jamb are infested with
Iloilo City, CDF Funded, implemented termites. Treatment is needed.
by FFCCCII 2. Cracks on wall and flooring can be
noticed.
Taal Elementary School (2 CL), Iloilo 1. Cracks along lintel beam (window jamb)
City, implemented by FFCCCII can be noticed.
2. Warping on ceiling board can be noticed.
Balilao Elementary School (2 CL), 1. Cracks on wall and flowing can be noticed.
Iloilo City, implemented by FFCCCII 2. Interior and exterior ceiling boards need
fixing.
ILOILO PROVINCE PROJECTS
Barroc Elementary School (2 CL), 1. Interior ceiling board not properly nailed.
Tigbauan, Iloilo, implemented by 2. With damaged jalousie aluminum frame.
FFCCCII. 3. With glass jalousie missing/broken.
60
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Antonio Belo Memorial School (2 CL), 1. Sliding tracks (Aluminum) for partition walls
Timpas, Panit-an, Capiz, implemented by was not provided.
DepEd (TEEP) 2. Installed 14 blader window clear glass jalousie
on alum. frame instead of 17 blader.
61
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
Cabugao Elementary School (1CL), Bronze marker including anchor was not
Brgy. Cabugao, Ivisan, Capiz, installed.
implemented by DepEd (TEEP)
Antonio Belo Memorial Elementary 1. Painting on fascia board and wall need
School (1CL), Brgy. Timpas, Panit-an, retouching.
Capiz, implemented by DepEd (TEEP) 2. Need to clean aluminum window
framing/glass jalousie blades.
3. Ceiling fan outlets not provided with screw
type male socket plug.
4. Need to remove paint stains on flooring.
5. Need to clean aluminum window
frames/glass jalousie blades.
6. Painting on exterior wall need retouching.
7. Need to clean tile/tile grout.
Exterior:
1. Need to retouch baseboard at front wall.
62
EFFECTIVE QUALITY ASSURANCE
School/Location Observations
The DPWH has a QAU team tasked to Apparently, the QAU team was not able
check and ensure quality of completed to monitor the deficiencies noted by the
works in the region and district for team during inspection. They should
whatever deficiency or rectification therefore devise a mechanism where a
works. greater sample could be covered in their
monitoring activities to ensure the
quality of schools delivered to the end-
users.
63
Chapter 4
64
RESPONSIVE PROJECT ADMINISTRATION
INTRODUCTION
One of the projects that is expected to be delivered on time, in time for the
opening of classes are newly constructed, repaired, rehabilitated or replaced
classrooms. The delivery of these projects became significant in the light of the
acute classroom shortage experienced by a number of elementary and secondary
schools nationwide.
The audit disclosed that it took the DepEd and DPWH from 344 to 450 days to
complete the construction of a school building reckoning from January 1, 2003.
As a result, as of March 31, 2004, only about 2.29% or 68 of the 2,971 classrooms
programmed to be constructed during the year were completed. Also, out of the
CY 2002 programmed construction of 5,134, only about 84.57 % was
accomplished or 4,347 classrooms completed, as of March 31, 2004. As it is
then, while funds were already appropriated, the students had to wait for quite
sometime before the benefits to be derived therefrom could be realized.
OBSERVATION
The slow paced activity of the DepEd and DPWH from the issuance of
Memorandum for selection of sites to awarding of contract and
construction activities adversely affected the timely delivery of school
buildings. It took the two Offices 344 to 450 days to complete a project
reckoning from January 1, 2003. This resulted then in the completion of
only 68 classrooms as of March 31, 2004 out of the total 2,971classrooms
to be constructed in CY 2003. Even the school buildings programmed in
65
RESPONSIVE PROJECT ADMINISTRATION
CY 2002 were not completed as of March 31, 2004 with only about
84.57% accomplishment. This condition then deprives the students on
the timely delivery of benefits to be derived from such appropriations.
The audit disclosed that of the total classrooms to be constructed, only 4,342 and
68 were completed as of March 31, 2004 representing only 84.57% and 2.29% for
CYs 2002 and 2003, respectively, as tabulated below:
STATUS OF IMPLEMENTATION
NOT YET
AMOUNT (in Php ‘000) COMPLETED ON-GOING STARTED
REGION PROGRAMMED RELEASED PROGRAM No. % No. % No. %
2003
NCR 112,033.00 109,085.00 147 15 10.20 53 36.05 79 53.74
CAR 15,810.00 15,810.00 66 0 0 0 0 66 100.00
I 53,534.00 53,533.60 143 0 0 0 0 143 100.00
II 35,764 34114.00 110 0 0 0 0 110 100.00
III 129,141.00 53,449.80 96 40 41.67 47 48.96 9 9.38
IV-A 172,631.00 172,631.00 524 0 0 19 3.63 505 96.37
IV-B 44,775.00 44,775.00 283 5 0 0 0 278 98.23
V 59,586.00 59,586.00 209 0 0 0 0 209 100.00
VI 86,504.00 86,311.40 257 0 0 0 0 257 100.00
VII 84,971.00 84,971.00 383 4 1.04 115 30.02 264 68.93
VIII 45,701.00 45,701.00 132 0 0 0 0 132 100.00
IX 51,405.00 56,435.50 161 0 0 57 35.40 104 64.60
X 45,926.00 45,925.50 134 0 0 21 15.67 113 84.33
XI 63,668.00 0.00 75 0 0 0 0 75 100.00
XII 46,648.00 42,176.00 122 4 3.28 0 0 118 96.72
XIII 27,710.00 27,710.00 129 0 0 0 0 129 100.00
ARMM 52630.00 0.00 0 0 0 0 0 0 0
TOTAL 1,128,437.00 932,214.80 2,971 68 2.29 312 10.50 2,591 87.21
2002
NCR 135,850.00 134,075.00 405 405 100.00 0 0.00 0 0.00
CAR 25,025.00 19,035.00 54 41 75.26 5 9.26 8 14.81
I 65,975.00 65,975.00 188 188 100.00 0 0.00 0 0.00
II 56,875.00 56,735.00 170 150 88.23 20 11.76 0 0.00
III 128,876.00 128,956.00 510 510 100.00 0 0.00 0 0.00
IV-A 184,600.00 166,229.30 843 843 100.00 0 0.00 0 0.00
IV-B 51,350.00 51,480.00 166 162 97.59 4 2.41 0 0.00
V 95,550.00 89,283.00 305 305 100.00 0 0.00 0 0.00
VI 107,250.00 102,425.00 453 353 77.92 92 20.31 8 1.77
VII 128,050.00 62,653.00 220 140 63.63 80 36.36 0 0.00
VIII 80,600.00 79,134.00 251 224 89.24 24 9.56 3 1.20
IX 73,125.00 71,938.00 225 165 73.33 60 26.67 0 0.00
X 69,395.00 69,395.00 626 257 41.05 5 0.80 364 58.15
XI 86,125.00 74,141.00 278 278 100.00 0 0.00 0 0.00
XII 74,750.00 58,480.00 205 166 80.98 39 19.02 0 0.00
XIII 56,550.00 55,760.00 197 147 74.62 50 25.38 0 0.00
ARMM 69,805.00 21,135.00 38 8 21.05 10 26.32 20 52.63
TOTAL 1,489,751.00 1,306,829.30 5,134 4,342 84.57 389 7.58 403 7.85
66
RESPONSIVE PROJECT ADMINISTRATION
The team noted that the DPWH’s performance was affected by the slow paced
movement from one activity to another in implementing the program. The DepEd
and DPWH undertook the following activities:
OFFICES NARRATIVE
PROCESS FLOW
INVOLVED DESCRIPTION
67
RESPONSIVE PROJECT ADMINISTRATION
BATCHES Range
Number of Days Lapsed in between Activities per
Particulars 1 2 3 4 5 Activity
DepED
a. Issuance of guidelines by
the DepEd (Reckon from
01/01/03) 100 100 100 100 100 100
• Date Issued 4/11/03 4/11/03 4/11/03 4/11/03 4/11/03
b. Submission of Priority List
by the Division Offices to
DepEd - CO (Reckon
from the issuance of
guidelines) 17 - 38 46 – 90 101 - 109 157 - 184 203 - 228 17 – 228
• Date of 4/28- 5/27- 7/22- 9/18- 11/04-
Submission 5/19/03 7/11/03 8/01/03 10/15/03 12/09/03
c. Submission of Priority List
by batch to DBM for
funding (Reckon from the
date of receipt of priority
list) 6 - 28 4 – 48 46 - 55 15 - 42 34 – 69 6 – 69
• Date of
Submission 5/26/03 7/15/03 9/17/03 10/30/03 1/13/04
Sub-total 123 - 397
DBM
d. Releasing of SARO by
DBM to DPWH (Reckon
from the date of
submission of priority list no SARO
to DBM) 30 91 53 31 yet 30 – 91
• Date of Receipt
by DPWH 6/26/03 10/16/03 11/10/03 12/01/03 - -
Sub-total 30-91
DPWH Main Office
e. Releasing of SAA** by
DPWH Main Office to
DPWH Engineering
District Offices (Reckon
from the date SARO
received) 14 21 9 21 N/A 9 – 21
• SAA Date 7/10 11/17 11/19 12/22 - -
Sub-total 9 - 21
68
RESPONSIVE PROJECT ADMINISTRATION
BATCHES Range
Number of Days Lapsed in between Activities per
Particulars 1 2 3 4 5 Activity
It may be noted that the lapses in the implementation of the SBP started from the
issuance of Memorandum setting the criteria for selection of sites. For CY 2003,
the Memorandum was issued by the DepEd only on April 11, 2003. Considering
that this is a regular activity of the DepEd and the appropriation for SBP is almost
certain yearly, the DepEd should have issued the Memorandum at least two
months before the beginning of the year to allow the Division Offices enough
time to prepare the priority list.
Apparently, the submission of the priority list by the Division Offices was also
not properly monitored by the DepEd. It would appear that the preparation of this
list and submission of the same to the DBM for funding is a year round activity of
the DepEd. The Division Offices started to submit the list on April 28, 2003 and
completed the list only on December 9, 2003. Consequently, these lists were
forwarded to the DBM only between the period May 26, 2003 to January 13,
2004. It may be emphasized that unless the DBM released the funding
requirements, the DPWH would not be able to commence with its mandated
functions.
69
RESPONSIVE PROJECT ADMINISTRATION
As borne by records, the DPWH started receiving SARO only on June 26, 2003
and has yet to receive the SARO for batch 5 as of March 31, 2004. This condition
greatly affected the performance of the DPWH as enough time is also needed by
the DPWH to complete the construction. It took the DPWH District Office 21 to
238 days from the date of receipt of SAA to conduct the bidding and release the
Notice to Proceed and another 6 to 178 days to complete the construction.
For CY 2002 projects, it took the DPWH 10 to 335 days to bid out the project
from the time the SARO was released and another 7 to 147 days to issue the
Notice to Proceed. The projects were constructed within another 30-331 days.
This lag time per activity then contributed in the completion of only 68
classrooms from CY 2003 appropriation and failure to complete the construction
of 792 classrooms from CY 2002 appropriation as of March 31, 2004. This
condition then deprived the students on the timely delivery of benefits that could
be derived from such appropriations.
For CY 2002 – Major reason why some These reasons were not evident on the
projects were delayed in construction is documents evaluated by the team. In
due to non-payment of contractor’s fact, based on the documents
claim. Although the projects were supporting payments, the delay in
clustered per congressional district and to construction was due to issuance of
be implemented simultaneously, some suspension orders on account of
contractors did not implement the demolition of existing structures,
projects simultaneously as planned. curing period of the floor slab,
Moreover, there are cases where there are unfavorable weather condition and
no takers of the projects, while other issuance of various change and extra
delays are caused by the requests of the work orders.
representatives concerned to undertake
the projects by administration.
For CY 2003 – Some projects were not The DPWH started its activities only
yet started due to delayed in the after the lifting of the election ban as
tendering of documents due to the the 1st SARO for CY 2003
scheduled election ban. However, as of appropriation was received only on
May 2004 contracts of some projects June 26, 2003. Hence, the election ban
were just approved now with NTP. did not in any way affect the DPWH
performance. As discussed above, the
The slow pace implementation of the CY delay can be attributed to the failure of
2003 DepEd School Building Program the District Office to immediately bid
wherein the two Offices undertook 344 to out the projects upon receipt of SAA.
450 days could be attributed to the It took the District Office 21 to 238
following factors:
70
RESPONSIVE PROJECT ADMINISTRATION
71
RESPONSIVE PROJECT ADMINISTRATION
72
Part IV
Recommendations
73
RECOMMENDATIONS
74
Submitted in compliance with MS & TS Office Order No. 2003-009 dated June
24, 2003 and TS Office Order No. 2003-068 dated October 17, 2003.
EMMA L. RACELIS
Team Supervisor
Reviewed by :
SUSAN P. GARCIA
Director III
Approved by: