Professional Documents
Culture Documents
SUMMARY
In July 1993, Indian Railways awarded the contract to ABB Transportation Systems Ltd., Switzerland to
design and manufacture 11 high-speed passenger locomotives and 22 freight locomotives featuring state-of
the-art GTO traction technology. The contract also included a complete Transfer of Technology (TOT) of
both the electrical and mechanical design and manufacture to enable production of the first indigenously
produced GTO three phase drive locomotives in the history of Indian Railways.
For the execution of this project a consortium was established between ABB Transportation Systems Ltd.
(Switzerland) and ABB Transportation Systems (Australia) Ply Ltd.
Part of the fleet of freight locomotives was shipped in kit form directly to India. Final assembly and
commissioning was undertaken by Indian Railways staff, under the guidance of Adtranz representatives, at
the Chittaranjan Locomotive Works (CLW) in the State of West Bengal. Thereby started the "the hands on"
Transfer of Technology for manufacture of state-of-the-art GTO locomotives to Indian Railways.
In November 1998, Indian Railways "rolled ouf' the first indigenously produced locomotive, featuring three
phase propulsion with microprocessor control, demonstrating satisfactory execution of the Transfer of
Technology by Adtranz.
WAG 9
WAP5
- worn
The locomotives are of a dual cab design for Tread dresser brake units are provided to
operation from either end. Each cab features condition the wheels. Flange lubrication
two external access doors leading directly into it. equipment is also fitted.
Controls have been laid out to be within easy
reach of the operators. Air conditioning was not 4.2 Freight Locomotive (WAG9)
required for these locomotives.
The salient features of the WAG9 freight
From each of the cabs, an access door is locomotives are shown in Figure 1. This vehicle
provided to the machine room. The body width is of CoCo configuration and is capable of being
(3150 mm) makes full use of the wide loading ballasted up to 135 tonne. A brief description of
gauge, resuHing in excellent access to the the major features of the vehicles where they
machine room equipment. The layout optimised differ from the WAP5 locomotives is outlined in
the weight distribution and the cable and the following sections.
pipework routing.
4.2.1 Electrical equipment
The design of the carshell extensively utilised
FEA techniques. To achieve the light axle load The electrical equipment is virtually identical
required as well as the high buff load (300 except that the hotel load winding in the main
tonne), the principles of monocoque design transformer has been deleted. The traction
were used. motors are of 850 kW continuous rating.
4.2.2 Mechanical equipment
Two compressors mounted on the underframe
provide the compressed air required for braking.
20.4 Conference on Railway Engineering
Adelaide, 21-23 May 2000
Neal lawson and David Gale Indian Railways Electric Locomotives -
Daimler Chrysler Rail Systems (Australia) Ply Ud Supply and Transfer of Technology
The general layout of locomotives is essentially ups of the electrical equipment. The end result
identical, except for the repositioning of some was that there were very few problems
items in the machine room. This is partly due to experienced in Zurich when the locomotives
the requirement to be able to accommodate an were finally assembled there.
additional 12 tonnes of ballast to improve the
adhesion. Due to the extremely tight delivery schedule, the
first two and last WAP5 locomotives and the first
The carshell is substantially heavier. WAG9 locomotive were actually air freighted to
Zurich in the cargo hold of a Russian Antonov
4.2.3 Bogie aircraft. The remainder of the finished carshells
was transported from Australia to Zurich by sea
The CoCo design is based on the diesel-electric freight.
bogie design of the Pakistan Railways HGMU-
30 locomotives. Once in Zurich, the locomotives were fitted out
with the electrical equipment and installed on
Axle hung, nose-suspended traction motors, bogies that were shipped separately from
interface to the pressed on main gear via a Australia. Initial commissioning was also carried
pinion pressed into the traction motor shaft. out at these facilities before shipping to India.
Australian personnel were based in Zurich to
Pneumatic braking is made by a conventional assist in the final assembly and commissioning
cast iron tread brake arrangement, featuring a of the vehicle.
clasp mechanism.
The finished locomotives were transported by
Secondary and primary suspension is again road to Basel and from there by barge to
provided by coil springs. For the ballasted Rotterdam. The locomotives were then loaded
condition of 135 tonnes, additional smaller onto a ship bound for Calcutta.
springs can be fitted inside the standard units.
5.2 Interaction between Adtranz Australia
The use of aluminium components was avoided and Germany.
on this bogie.
The bogies were built in Australia under license
5 PROJECT EXECUTION from Adtranz, Germany. The contractual
relationship was such that Germany was
The execution of this project was made responsible for the design and to transfer the
extremely difficult by the huge geographical, production technology to Australia, who would in
time and cultural differences of the customer, turn transfer it to IR.
major consortium partners and suppliers. The
logistics involved with a project of this global This transfer of technology was well executed
scale are complex. Some of the major hurdles with a full set of production drawings provided
encountered are detailed below. from Germany in the English language. Visits by
personnel from Germany further assisted this
5.1 Interaction between Adtranz process.
Switzerland and Australia
The only real difficulty encountered was the
The locomotive superstructure, including need to indigenise the information - a problem
complete cabs, was designed and built in again encountered when the TOT occurred to
Australia. The secondary members required to IR. The materials and processes selected in
support the electrical equipment in the machine Germany were not readily available in Australia
room, underframe and cabs were fabricated into and so a process of determining local
the structure and so design interaction was equivalents had to be undertaken. The extent of
necessary between Australia and Switzerland. this exercise was underestimated as it also
This meant that apart from volumes of involved a sequence of approval by the licensor
correspondence, there were numerous meetings in Germany, who often had to be educated in
held in Zurich. During construction of the first how local standards were to be applied. Cultural
carshell, a team visited from Switzerland and differences were a source of some strain in this
conducted a trial fit out of the cabling and mock- regard.
6 TRANSFER OF TECHNOLOGY
5.3 Interaction between Adtranz and Indian
Railways Indian Railways purchased these locomotives
including full TOT to update their large fleet of
During the design and build phase, regular vehicles using out·dated technology. They
design review meetings were held with the selected Adtranz to be the provider of these
customer in Lucknow, India. At these meetings, services because of their extensive experience
all design documentation was presented, in three-phase propulsion.
discussed and eventually approved.
The TOT from Adtranz to Indian Railways was a
During this phase of the supply contract, the comprehensive program of training, technical
design approval documentation was also information, and collaboration to enable IR to
supplied to the CLW Engineering Group so that manufacture, test and commission these three
they could obtain an appreciation of the design phase state of the art locomotives wtth
of the locomotives that they would eventually microprocessor control. It involved the granting
manufacture. Furthermore, CLW representatives of non-exclusive rights to IR to produce these
participated in the numerous design reviews locomotives in India at a site to be determined.
held in Lucknow. The site selected by IR was Chtttaranjan
Locomotive Works.
There was also a series of running tests to be
carried out before acceptance by IR. These 6.1 Chittaranjan Locomotive Works
tests were carried out in difficult conditions
including temperatures up to 50°C and tropical Chittaranjan Locomotive Works (CLW) in West
storms. The workshop facilities were not of the Bengal was originally established in 1950 to
same standard to which Adtranz staff were used produce steam locomotives. Electric
to and were shared by local wildlife. Sickness locomotives were first produced in 1961. Since
was also a constant problem. then, over 2500 Electric locomotives have rolled
out of the factory. Diesel Hydraulic locomotives
have also been produced at CLW.
The initial visit of Adtranz staff to CLW was In parallel to the TOT to IR staff, Adtranz also
made in November 1993. The result of this was transferred knowledge to Adtranz India staff so
a preliminary report that identified some of the that they could support the vehicles when they
investments and upgrades that CLW should arrived in India. This has been successful, with
make to ensure a smooth transition from the Adtranz India staff still continuing to provide
existing tap changer locomotives to the three warranty and other support for these vehicles in
phase locomotives. A large portion of the running depots and at CLW.
available equipment dated back to the start of
the production of these locomotives. Another important factor in the successful TOT
process was the "indigenisation" of material
A full survey was conducted in March 1995 with during the design phase. Whenever possible
full collaboration of CLW staff, with a during the design approval, materials and
comprehensive report submitted to CLW on the processes that were locally available were
recommended improvements to the factory. The selected in preference to those that were not.
following areas were particularly investigated: There were some instances where this was not
possible due to contractual constraints in the
1. Final Assembly of SKD/CKD locomotives supply specification. During the TOT and build
2. Material storage for the first CLW built locomotive, some effort
3. Locomotive and Bogie fabrication was still involved in finding local substitutes for
4. Pre-assembly manufacture these materials and processes. This task was
5. Traction Motor manufacture made a little easier as contractual restraints that
6. Testing and Commissioning. applied to Adtranz for locomotives of their
supply were relaxed for CLW where necessary.
The resulting recommended changes included
investment in some machinery (e.g. welding During this phase, complete manufacturing
machines, painting equipment and electrical test documentation was provided to CLW in the
equipment), a complete re-Iayout of the existing areas of:
plant to ensure smooth workflow and a general
site clean up. Necessary jigs, fixtures and A. Locomotive body
tooling were also identified. Some areas where B. Bogies
final assembly was to occur were recommended C. Traction motors
to have an access pit installed and a more D. Main transformer
substantial improvement in the work E. Power converters
environment. F. Electronic and_ microprocessor control
equipment
6.2.2 TOT during design, manufacture and G. Auxiliary converter
commissioning by Adtranz H. Locomotive assembly
I. Locomotive testing
During the design, manufacture and K. System engineering
commissioning phases, IR staff started the initial L. Others
process of TOT. IR design staff traveled to the
design offices in both Australia and Switzerland This information took the form of production
to be trained in the design of locomotives. drawings, work instructions, material
Representatives of major sub-suppliers were specifications, schedules, test procedures etc.
present to transfer some of their knowledge
also. Although there was no obligation for sub
suppliers to transfer their production technology,
some IR staff were also taken to the factories of
these major sub-suppliers.
During the build of the first WAG9, and currently Another important aspect to the success of the
the WAP5, locomotives Adtranz staff were TOT is the selection, nurturing and TOT to key
present in CLW. Management at CLW had suppliers. All major sub-suppliers have
embraced the recommendations of the 1995 established local manufacturing and/or support
report and great improvements had been made companies wfthin India. Adtranz India is
in the factory. Investments had been made in producing the traction converters and other
equipment as recommended. equipment at their facilities in Bangalore. A local
manufacturer for the main transformer was also
Adtranz staff conducted structured training selected and full documentation handed over.
courses in the facets of locomotive manufacture
selected by CLW management. The trainers CLW has capacity to produce traction motors in
were then available on site to provide on the job house. The technology for producing these was
advice. Comments on product quality were also transferred to them.
passed, but all care was taken to ensure that
CLW was responsible for their own Local manufacturers of minor equipment have
workmanship. also been sourced. These local suppliers have
been crucial in minimising the cost to Adtranz of
Full documentation for the build and its warranty obligations but more importantly, will
commissIoning were available at CLW and provide the same support to IR for the future.
updated as modifications were found to be
necessary on the in-service vehicles. Adtranz 6.4 Roll out ceremony and future
assisted in the selection of local materials and milestones
processes as described above, but IR maintains
responsibility for the as-built documentation for On the 14 November 1998, the first CLW built
their locomotives. WAG9 locomotive - christened the "NAVYUG"
was inaugurated at a ceremony in the Works.
With this inauguration, IR has entered the
modern era of three-phase GTO traction
technology wfth microprocessor control. These
locomotives were the first to be produced in the
7 CONCLUSIONS