FACTORY ACCEPTANCE TESTS CERTIFICATE
ASHTART REVAMPING PROJECT
SUPPLY OF GENERATOR CONTROL PANEL FOR Gl & Gill
CONTRACT N°: 20-0679 DATED: 26 July 2011
Between: Serept (hereinafter called COMPANY)
and: Actemium hereinafter called CONTRACTOR)
1. Inaccordance with the CONTRACT, and in compliance with the agreed inspection and test
plan, it is hereby certified by CONTRACTOR and COMPANY that all provided Factory
Tests are performed by the CONTRACTOR with successful result. (*)
2. Issuance of this Factory Test Acceptance Certificate shall not relieve CONTRACTOR from
his warranty obligations and other provisions of the CONTRACT which expressly or by
their nature survive the said certificate,
Serept Actemium
(COMPANY) (CONTRACTOR)
= —
Name: Name: Ramin Esfandiarinia
Position: Position: Business Unit Manager
In the presence of: In the presence of:
‘Signature: Signature: oad
Date: Date: 26 July 2011
(*) CONTRACTOR shall communicate Manufacturing Data Book and third party Certificate,