GTG Generator Protection and First Synchronisation Test Programme

1 Preparation
6.6kV swbd NC0-SWG-810-1001 Bus A and Bus B energised: Supply by Aggreko Diesel Gensets. A17
Incomer and A09 Bus-Tie CB's closed
A01 Confirm Rack-out CB & Line Earthing switch are CLOSED
A01 Disconnect Line VT's
Disable GTG hydraulic start system
Disconnect Generator VT's
Open Generator TB
Open NER switch
A01 Open Line Earthing switch
IR Resistance test Stator winding and Cables
A01 CLOSE Line Earthing switch
CLOSE NER switch
Close Generator TB
Reconnect Generator VT's
A01 Reconnect Line VT's

2 Generator Differential Protection Stability Test


A01 Confirm Rack-out CB & Line Earthing switch are CLOSED
A01 Install Links for L!-L2-L3 in primary circuit between Line CT's and CB
A01 Disable GTG trips by Electrical Protection if any
Disable Turbine & Generator trips/lock-out by Generator Protection
A01 Open Line Earthing switch
Enable GTG hydraulic start system
Start Turbine, run rated speed
Manually control AVR, test Generator Differential Protection current stability
Monitor NER current during test
Reinstate Turbine & Generator trips/lock-out by Generator Protection
Generator Differential Protection simulate fault, trip & Lock-out Generator and Turbine
A01 Close Line Earthing switch
A01 Remove Links for L!-L2-L3 in primary circuit between Line CT's and CB
A01 Enable GTG trips by Electrical Protection if any

3 Stator Single Phase Earth-Fault test


A01 Confirm Rack-out CB & Line Earthing switch are CLOSED
NER switch confirm CLOSED
Disable GTG hydralic start system
Open Generator TB, install Phase to Earth connection
Close Generator TB
Disable Turbine trips/lock-out by Generator Protection
A01 Open Line Earthing switch
Enable GTG hydraulic start system
Start Turbine, run rated speed
Manually control AVR, test Generator Stator 1-Ph Earth-Fault protection
Stop Gasturbine
Disable GTG hydralic start system
A01 CLOSE Line Earthing switch
Re-instate Turbine trips/lock-out by Generator Protection
Open Generator TB, remove Phase to Earth connection
Close Generator TB
4 Voltage Control, Rotor Fault & AVR Test
A01 Confirm Rack-out CB
A01 Line Earthing switch OPEN
Disable Turbine trips/lock-out by Generator Protection
Enable GTG hydraulic start system
Start Turbine, run rated speed
Manually control AVR, perform Generator Voltage tests
Switch off Excitation
Install Excitation to Earth connection
Switch on Excitation, perform Rotor Earth-Fault test
Switch off Excitation
Remove Excitation to Earth connection
Switch on Excitation, perform AVR tests incl Automatic Voltage ramp-up
Stop Gasturbine
Re-instate Turbine trips/lock-out by Generator Protection

5 Pre Synchronisation checks


6.6kV swbd NC0-SWG-810-1001 transfer all load from Bus A to Bus B, LOTO all outgoig feeders
A08 confirm Bus A VT connected, confirm Bus A LIVE
A09 Bus-Tie OPEN CB and LOTO
A08 confirm Bus A DEAD
A09 confirm Line VT connected
A09 OPEN Line Earthing Switch
A01 Rack-in CB
Enable GTG hydraulic start system
Start Gasturbine, run rated speed
Manually control AVR, slow voltage ramp-up check votage on A01 Line VT metering
Confirm DEAD Bus A on GSP and CLOSE A01 CB from GSP
A08 confirm Bus A LIVE
Carry-out Pre-sync Phase Rotation, Sequence & Voltage Checks as per attached schedule
A01 Check correct functionality Synchrocheck
GSP Check correct functionality of Synchro & other devices
A01 OPEN CB from GCP
Stop Gasturbine, observe AVR auto voltage ramp-down

6 First Synchronisation (Local / GCP & GSP)


A09 Bus-Tie CLOSE CB
A08 confirm Bus A LIVE
Disable/disconnect A01 CB Closing coil (at A01 or at GSP)
Run at least 3 Aggreko Gensets, ensure stable and sufficient load > 600 kW ???
Enable GTG hydraulic start system
Start Gasturbine, run rated speed and voltage
Manually synchronise GTG on Bus A (dummy sync), check sync devices and A01 sync check functionality
Reconnect A01 CB Closing coil (at A01 or at GSP)
Manually synchronise GTG on Bus A check sync devices and A01 sync check functionality
Check GTG load sharing (Droopmode) MW and MVAr
Unload GTG and open A01 CB
Auto synchronise GTG on Bus A, check functionalities
Perform after Sync Protection test: Fuse Failure, Under exitation and Reverse Power

7 Synchronisation of NC0-SWG-810-1001 Bus A and Bus B at Bus-Tie A09


To be discussed

8 Synchronisation and Loadsharing (Remote / DCS)


Similar to First Sync (Local), to be discussed.