Professional Documents
Culture Documents
ISOLATION
TOPIC 3 CONTENT
1 INTRODUCTION ................................................................................................ 3
2 Instrument Isolation............................................................................................. 4
2.1 Isolation Introduction .................................................................................. 4
2.2 Process Isolation ....................................................................................... 4
2.2.1 Spool Piece ............................................................................................ 5
2.3 Signal Isolation .......................................................................................... 5
2.4 Electrical Isolation ...................................................................................... 6
2.5 Control System Isolation ............................................................................ 6
2.6 Duty Standby ............................................................................................. 6
3 Plant Shutdowns ................................................................................................. 7
3.1 Scheduled Plant Shutdown ........................................................................ 7
3.2 Unscheduled Plant Shutdown .................................................................... 7
4 Example of Isolation Tags ................................................................................... 8
5 Work Permit ...................................................................................................... 10
5.1 Work Permit Introduction.......................................................................... 10
5.2 What is a Work Permit? ........................................................................... 10
5.2.1 Reduce Risk ........................................................................................ 10
5.2.2 Document ............................................................................................ 11
5.3 Cold Work Permit ..................................................................................... 11
5.4 Hot Work Permit ...................................................................................... 12
5.5 Confined Space Entry Permit ................................................................... 12
5.6 Excavation Permit .................................................................................... 13
5.7 Bypass Certificate .................................................................................... 13
5.8 Blind List and Isolation Diagram ............................................................... 13
5.9 Electrical Isolation Permit ......................................................................... 13
5.10 Limitations on Work ................................................................................. 13
5.11 Responsibility of the Permit Issuer ........................................................... 14
5.12 Responsibility of the Permit Holder .......................................................... 14
5.13 Closing off a Work Permit ........................................................................ 15
Prior to isolating any instrument, the instrument technician should consider the
impact that the isolation will have on the process. The instrument technician may
perform four different types of isolations prior to taking an instrument out of service.
There are the process connection, signal connection, electrical power connection,
and the control system overrides they may be required. The work permit system will
not be discussed at this point. The intention is to have you focus on what an
instrument technician should think about above and beyond the work permit system
of your plant.
Before an instrument can be taken out of service for maintenance or replacement,
there are isolation and operational procedures that must be followed. It is critical that
you don’t just focus on the instrument but think about the operational impact the lost
of the instrument signal may have. A Piping and Instrument Diagram (P&ID), if it
shows the control, is very useful is seeing the interrelationships between the loops.
The operator may have to place one or more control loops in manual to avoid
process upset while you are working on the instrument. An instrument technician will
have a much closer relationship with the operators than an electrician or a mechanic.
The PI&D will show the instrument process connection, type of signal, control
functions, but not if the instrument has an external power source. As you develop
experience in instrumentation, you will become familiar with typical power
requirements of the instruments.
Your company work permit system and isolation procedures MUST be
followed. If you do not have a work permit, do not do any work on any
instrument connected to a process.
Prior to removing an instrument from a process line, the instrument must be isolated
in accordance with your plant isolation and work permit procedures.
The instrument process connection will be either screwed or flanged. The instrument
may mount in the process line (inline), on the process line, or remote to the process
line.
on
line
remote
Your work permit will most likely focus on the process and electrical isolations. As an
instrument technician, you must consider what impact there will be on the control
system. If you are not responsible to look at control logic impacts, at least ensure
yourself that the responsible person has thought of the implications of your actions.
You do not want to drop out a signal and have alarms and interlocks going off. It
could be embarrassing and costly. In Control & Signals, the control system will be
discussed in detail.
In an industrial plant, equipment such as pumps, filters, generators etc. often have a
backup to allow the plant to run while the equipment is out of service. Often there are
duty and standby pumps. The purpose of having two pumps is that if the duty pump
requires maintenance, the standby pump can continue to run the plant while the duty
pump is out of service. With duty and standby, often the instrumentation required for
each pump set is also duplicated but not the instrumentation on the process line once
the two process pipes join. With duty standby pump system that has duplicated the
instrumentation, it is relativity easy to isolate the system to do required work on the
instruments.
In instrumentation, we also have a similar situation to a duty/standby pump. On
important installations with safety concerns, the instruments may also be duplicated
or even in triplicate. The control system will looked at the signals from the
instruments to see if there is a difference. If there is, then an alarm is raised and an
instrument technician called to resolve the problem. When there are three
transmitters measuring the same point, it works on the control system trusting the
two that match to continue controlling while alarming that the third appears to have
malfunctioned.
A scheduled plant shutdown is just that. It is planned for in advance. For a major
shutdown, the planning may start a year in advance. For a short duration one shift
shutdown, planning may occur a few days before.
During a scheduled plant shutdown, regular maintenance is performed. It is also the
time for new construction to be completed. With instrumentation, since the
instruments are not large, the instruments are usually hung next to installation prior to
shutdown and wiring completed. During shutdown, the process connections are
made, installation completed, tested, control system modified, and the loop
commissioned.
During an unscheduled plant shutdown, you will be called upon to fix instrument
problem, and if time allows test/repair an active loop. An unscheduled shutdown is
not good for business. It means something went wrong and a fix is required. Time is
of the essence to get the plant back up and running. Millions of dollars can be lost
during unscheduled shutdowns. If the unscheduled plant shutdown was a result of an
instrument problem, you will be busy and you will learn.
Every industrial plant will have a work permit system that states the required isolation
procedures. It is imperative that the instrument technician follows the company
procedures. It is not acceptable to assume that all industrial plants follow the same
procedures and that what you learned at one plant is applicable at another. Work
permit system may be similar but never assume identical.
Your company work permit system and isolation procedures MUST be
followed. If you do not have a work permit, do not do any work on any
instrument connected to a process.
The permit to work system was implemented to help reduce the risk of:
Explosion or fire during hot work
Asphyxiation during confined space entry
Endanger personnel in the immediate environment
Electric shock when electrical work is being carried out
Physical injury from mechanical plant that has not been isolated
Injuries which lead to debilitating injury or death when recommended personal
protective equipment (PPE) is not used
Cold work is work which will not generate any source of ignition, such as flame, spark
or temperature sufficient to ignite any flammable material. This could include the use
of non-power operated hand tools, erecting scaffold, inspection, painting, equipment
and clean up.
Typical examples of cold work are:
Opening of pipe work by the movement of blinds, the breaking of flanges or
the removal of bonnets and glands from valves. Flammable vapours may be
released.
Opening of all process machinery, both driven and driver, including where
applicable, sumps and crankcases. This also includes topping up and
repacking of all associated glands.
Opening of all vessels, columns, drums, heat exchangers, condensers,
coolers, filters, furnaces and tanks. Flammable vapours may be released.
Carrying out some equipment alignments.
Hot work is work which could generate fire, naked flame, heat or spark to ignite
flammable gases or combustible dusts.
Hot work includes, but is not limited to:
Welding, soldering, cad welding, hot riveting
Burning, flame cutting, flame heating
Grinding, shot blasting
Concrete chipping
Use of electrical hand tools, power driven cutters
Use of internal combustion engines
Lighting a fire of any kind
Use of any equipment which may provide a source of ignition
Work on live electrical circuits which are not in electrical substations
Use of cameras with external or inbuilt flash
Use of x-ray generating equipment.
Non-intrinsically safe test equipment
Opening flame-proof enclosures
Excavation permit is the digging or penetration into any ground surface and includes
such work as:
Electrical and instrument cable installation
Pegging (wooden or metal)
Hand excavation
Mechanical excavation
Grading of leases
Laying of piping
Isolation points can be identified from the Piping and Instrument Diagrams (P&ID’s)
and by site inspection of the pipeline or vessel to be isolated. Once identified, details
must be recorded on a Blind List Drawing attached to the Work Permit. These lists
identify all isolation points, the flange size and rating (where applicable) and whether
each isolation point has been reinstated upon completion of the work to be done.
Electrical work can be defined as any work carried out on equipment or systems
which are heated, powered, driven or controlled by electricity, either AC or DC, e.g.
pump motors, mixers, switch racks, energised instrument electrical enclosures.
Electrical isolation of pumps, fans, compressors and other electrical equipment can
be registered into an electrical isolation permit which is attached to the work permit.
Under the work permit system only work stated on the permit may be carried out. Any
other work outside the scope of work stated on the permit will require a new permit to
be issued. Permits are not interchangeable. Hot work may not be carried out under
cold work permit even if it is deemed safe to do so.
It is the responsibility of the permit issuer to ensure that the scope and location of
work complies with the permit issued. This includes, but is not limited to, the
following:
Inspecting the work site area with due regard to the identification of hazards
and proposed controls
Ensuring that the work description or the format is correct
Having necessary gas testing performed
That the work is compatible with existing conditions
Ensuring that all precautions or special conditions are in place before the
permit is signed
Ensuring that other personnel in the area are aware of the work taking place
Conducts regular inspections of the work site to ensure all conditions in the
permit are being met
Ensure that the permit recipient fully understands the work to be undertaken
and safety precautions are met
Ensuring that the worksite is left in a clean and safe condition
Inform permit holder of any changes which may effect the validity of the
permit
Once a job has been completed or put on hold, the permit is cancelled and must be
closed off in accordance with procedures. To close off the permit, the worksite is
checked to ensure that equipment has been reinstated or has been isolated and that
the area has been made safe. To close off a permit, the permit responsible authority
will sign the permit cancellation section.