Professional Documents
Culture Documents
WAVIN HDPE BOOKLET - Lowres Proof PDF
WAVIN HDPE BOOKLET - Lowres Proof PDF
1 General 7
1.1 Quantities 7
- Domestic waste water 7
2 Principles of waste water discharge 9
2.1 General design principles 9
- Overpressures and underpressures
- Primary discharge system
- Secondary discharge system
- Restricted secondary discharge system
- Air admittance valves
- Direct separated discharge system
- Balancing lines
2.2 Filling of pipework 10
2.3 Fall 10
2.4 Access fittings 11
3 Peripheral requirements for removal of waste water 12
3.1 Traps 12
3.2 Connecting pipes 12
3.3 Collecting pipes 12
3.3.1 General requirements 13
3.3.2 Connections to collecting pipes 14
3.3.3 Connection separations and sequence 16
3.4 Stacks 16
3.4.1 Connections to stacks
- Method 17
CONTENTS
7 Installation 23
7.1 Design 23 HEPWORTH PME ( LLC ) is the region’s premier At both its purpose-built facility in Dubai and on site,
manufacturer and supplier of a comprehensive range of training covering the proper installation and use of the
7.1.1 Fixings
high quality plastic pipes, fittings and accessories used range of products is provided to customer’s technicians.
- HDPE Here they are instructed in using best-practice
for the distribution and transmission of water,
7.1.2 Brackets 23 wastewater and gas. Established in Dubai for well over techniques for jointing of the various piping materials,
- support bracket three decades and represented by a chain of branch correct installation of fittings and accessories and
- clamping bracket offices throughout the area HEPWORTH PME ( LLC ) operation and maintenance of their systems. Following
are able to satisfy the requirements of the industry successful completion of such training courses the
- fixed point bracket
professionals from its substantial stock holding of technicians will become certified installers of those
7.1.3 Freely suspended pipework 24 products conforming to the various international HEPWORTH PME ( LLC ) products covered in the
- temperature differences standards in common use in the Middle East. course. The benefits of this training are enormous
• cold pipework because incorrectly installed systems will certainly fail
• warm pipework The demand for readily available high quality pipes and prematurely at substantial cost to the owner or operator,
fittings prompted HEPWORTH PME ( LLC ) to establish particularly on those systems that are installed
• hot pipework
a modern manufacturing facility in Dubai back in 1991. underground or with difficult access.
7.2 Installation methods 24 Using the latest equipment and techniques the company
7.2.1 Flexible installation 25 produces PVC-U, Polyethylene and GRP pipes in a wide To complement the range of items manufactured in
- flexible installation with expansion range of diameters. Following further investment in Dubai, HEPWORTH PME ( LLC ) also represents a select
sleeves and couplers 1999 injection moulding machines were introduced to group of international manufacturers who further
- flexible installation with flexible produce PVC-U, polyethylene and polypropylene enhance the scope of supply to accommodate other
connectors fittings. In addition to this fabrication of standard, aspects of water and gas flow management.
specialized and bespoke fittings using PVC-U, ABS, PPR, Encompassing diverse fields such as irrigation to
- bracket separations for flexible
polypropylene and polyethylene is undertaken to fire-fighting and district cooling to domestic water
installation
provide solutions for the discerning water engineer. supply, complete systems and individual components
- bracket distribution for flexible can be sourced from one professional outlet
installation conveniently located to serve the needs of the specifier
Being the first company of its kind to achieve BS
7.2.2 Rigid installation (HDPE) 27 or contractor.
Kitemarks and ISO 9002 accreditation in the region,
- brackets and bracket separations for they are now designated as an ISO 9001:2000
rigid installation accredited manufacturer. Quality is therefore HEPWORTH PME have a licensing and manufacturing
paramount and this is reflected by the fact that agreement with Wavin to produce the pipes in Dubai.
7.2.3 Cast-in pipework 29 HEPWORTH PME ( LLC ) holds BS Kitemark licences The fittings will be supplied from Wavin overseas. The
8 Assembly 31 covering 109 of the locally produced products. We also pipes are manufactured to EN 1519 specifications which
o
8.1 General 31 have FM approval for polyethylene pipe underground incorporate a test temperature of 110 C.
fire fighting equipments. Optimum performance and
8.1.1 Pipework in the waste removal system 31
longevity is further assured by the company’s
8.1.2 Fixing equipment (brackets) 31 commitment to customer training.
8.1.3 Storage 31
8.1.4 Oval pipe ends 31
8.1.5 Shortening pipes 31
8.2 Brackets 31
8.2.2 Joints in HDPE 31
- butt welding
- electro-weld sockets
- electrical spigot welding
- preparation work
- welding procedure
- use of non-standard pipe
- rubber seals
- expansion sockets
9 Situations during construction 35
4 10 Pressure testing 36
5
11 Maintenance 37
12 Product list 38
Introduction 1. General
The system is manufactured to EN 1519 charges of varying kinds, temperatures, purpose the rainwater may also be used
Wavin Wavin HDPE Product & Technical Guide
specifications which incorporate a test quantities, frequencies and so on. On for flushing toilets, washing clothes or
The Wavin group of companies is one ofthe largest manufactur- This technical manual on HDPE above-ground drainage systems o health, hygiene and odour control consi- cleaning purposes. In that case the
temperature of 110 C.
ers of complete plastic pipe systems for the Building, Civil and deals with the removal of domestic waste water and rainwater derations the system is sealed with traps rainwater is stored in a tank which must
Water is supplied by means of enclosed
Utility markets in Europe. In addition to having its own produc- from houses and residential and commercial properties using pipework systems using internal pres- or siphons. When discharges take place, be provided with an overflow. Before
tion facilities in almost every country on the European continent, plastic piping systems. It covers all aspects from design to sure. Waste water is generated when the air in the system has to make way (ven- proceeding to investigate the principles of
Wavin also participates in the equity of plastic pipe companies in installation. The manual is intended for clients, architects, supplied water is used for cleaning, was- ted) for waste water. The principal drainage it will be as well to determine
Australia, New Zealand and Singapore. In the remainder of the construction specialists, building co-operatives, building inspectors hing, cooking and for flushing away problems of drainage are as follows: the nature and quantity of the drainage
world the company is proud of an ever increasing impressive and of course for installers. If you have any questions, wishes or human waste. In discussing waste water intermittent drainage, enclosed open requirements.
practical problems not covered by this manual then we would ask a distinction is made between black system, complete removal of soil and
network of licensees, distributors and agents. Wavin has manufac-
you to submit them to us together with any suggestions for water (from toilets) and grey water (from water is required. Excess rainwater is also 1.1 Quantities
tured and supplied plastic pipe systems since 1955.The strength
washing machines, showers and similar). led away to the external sewer, nowadays
of the Wavin Group in terms of manufacturing capability and amendments and additions. Since our systems are often utilised in
The black water presents a direct hazard generally to a separate storm drain. If the Domestic waste water
technical resources places the company at the forefront of the circumstances beyond our control, we cannot accept liability for
to health, grey water does not. Black and water is relatively clean it may be led from The quantities of water consumed and
industry for product quality, innovation, technical support and the consequences of applying the information provided in this
grey water are generally discharged the storm drain to balancing ponds or requiring removal vary appreciably
customer service. manual.
together into the above-ground drainage waterways. Alternatively, clean rainwater throughout the day and depending on the
A survey carried out by international consultants for European system which carries the water to the may also be discharged onto the land source of the discharge. 120 to 130 litres
Plastic News, a leading trade journal, identified Wavin as the underground private sewer (U-drain) into around the property or into a collective per person per day are used as the basis
foremost contributor in the development of plastic pipe systems the public sewer or local treatment facility facility. Where the roof is suitable for the of calculations for supplies required for
and the leader in the field of marketing and technology. (septic tank). The above-ground drainage domestic use. The assumption is that the
system is an open system which is water used will be led off at the rate of 10
accessible at several locations for dis- to 12 litres per person per hour.
Wavin Overseas Illustration 1.1 shows the discharge pat-
Wavin Overseas B.V., situated in The Netherlands, is the central tern for a 3 to 4 person household over
24 hours. Basic discharge rates (Q¡) to
export organisation of the Wavin Group dedicated to providing a
determine the required capacity for a
global service. HDPE Fittings are Manufactured in Italy. Wavin
given section of pipework are included in
Overseas sells Wavin products, supplies technology (under licence)
NEN 3215 (see illustration 1.2). Illustration
and equipment to manufacture these products locally. Wavin
1.2 also shows the required diameters for
Overseas is experienced in setting up complete factories, delivering the trap and for the pipe connecting to
a comprehensive package of manufac turing equipment, ancillaries the source of the discharge. The quantity
and services such as production know-how and technical support. of waste water in collecting pipe stacks,
In effect Wavin Overseas can supply all the help you need to that is, those containing discharges from
supply your market. Wavin Overseas operates under a Quality several fittings, can be determined by
Management System, which is accredited to EN ISO 9001:2000 by means of the formula:
the Dutch Council for Accreditation.
Qo = p Σ Q ¡, where Qo and Q¡ are in l/s.
Σ Q ¡ is the sum of the baseline discharge
A Wide Range of Products
rates to be removed by a collecting
Wavin’s extensive range of plastic pipe systems is designed and pipe.
manufactured to meet the highest standards set by the building p is a coefficient for simultaneity:
and construction industry worldwide. Wavin’s products are - houses and residential properties
generally available ex-stock from one of our numerous distri-bu- p = 0,5
tors around the world. - schools, offices, hotels, restaurants,
Bath/shower 41 l/pp.day Illus. 1.1 Mean water consumption for hospitals
Toilet 33 l/pp.day an average household over p = 0,7
Washing machine 20 l/pp.day 24 hours. - laboratories, sustained industrial
Sink 17 l/pp.day discharges p = 1,2
Various 9 l/pp.day - commercial kitchens
6 Total 120 l/pp.day p = 1,4 7
Product list 2. Principles of waste water discharge
In houses and other residential properties cause compression of air, and overpres- this chapter goes on to discuss the
fitting baseline diameter of external diameter reduced external
discharge l/s trap connecting pipe diameter for wall waste water and rainwater must be sures and underpressures will be created. waste water system from the fitting to the
(pipe type) in PVC and PE and floor piping collected separately and led to the These must be kept within limits. Steps building boundary. Requirements and
(mm) (mm) (mm)1)
exterior of the building, or at least up to must also be taken to prevent excessive problems are examined and solutions
mouthwash unit
drinking fontain 0 40 32 the location of a discharge construction overpressures or underpressures created suggested.
leakage removal for the rainwater. It is important in by hydraulic sealing, whereby little or no
overflow hopper
removing waste water that the pipework air can pass over or through a flowing
32 2.1 General design principles
hand washbasin empties thoroughly, that any soil is mass of water. The principles and stipula-
washbasin 0,5 50 40
carried along by the water and that no tions for the removal of waste water are In order to prevent traps being emptied
shower without tray
bidet waste water or sewer gases enter the based upon these assumptions. Having by suction or pressure, overpressures
automatic washing machine building via the trap. Discharges will dealt with general construction principles, and underpressures must not exceed
domestic dishwasher
urinal
300 Pa (30 mm water column). Air must
footbath 0,75 be able to escape from the system
kitchen sink (single or double) 63
(HDPE) (venting) and to enter the system
slop sink
40 or 50 (admittance). A ventilated discharge pipe
bath 75
shower with tray 1,0 (PVC) is used for this purpose. Good practice is
sink with capacity over 30 l to create a primary discharge system
Toilet 2,0 - 110 90 extending the discharge stack above roof
siphonic closet level (see illustration 2.1). This system
2,5 - 110 90
bedpan sluice
allows air to continually enter and vent
floor drain 32 mm 0,5 - 50 40
40 mm 0,75 - 63/75 50 from the main sewer. In the case of a
50 mm 1,0 - 63/75 50 secondary discharge system, each fitting
70 mm 1,5 - 75 -
100 mm 2,0 - 110 - or branch pipe is connected to a separa-
1) reduction permissible if te ventilation system. A secondary dis-
• total length of connecting pipework is no more than 3,5 m. charge system may be taken through the
• length of wall-mounted pipe (horizontal) is no more than 0,5 m and only a single vertical element is not longer than 1,5 m.
roof or connected to a primary discharge
system prior to this being taken through
50 the roof (illustration 2.2). An unavoidably
40 long branch pipe may give rise to pro-
30
25
blems in a primary system. The section of
20 the branch pipe furthest from the stack
15 may then be connected to a restricted
10 secondary discharge pipe. This may
9
1, 4
8
p= either be led directly through the roof or
Illus. 1.2 Baseline discharge, required 7
Qo (d e s ign d is c ha rge ) (l/s )
6
1, 2 connected to the stack or to the primary
diameter for traps and (reduced) 5
p= 7
4 0, discharge stack. This may be referred to
connecting pipework for a 3,5 p=
3 05
, as a circulating or end discharge system
variety of fittings. 2,5 p=
2 (illustration 2.3). In this case an internal air
1,5 admittance vent on the end of the branch
1,0
pipe may be useful. However these can
0,9
0,8 only admit air to the system, not release
0,7
0,6 it.
Q o can be read off for different values of 0,5
0,4 Where overpressure occurs in the system
p in illustration 1.3 if the sum of Q ¡ is
1 1,5 2 3 4 5 6 7 8 910 15 20 30 40 50 70 100 150 200 300 400 500 700 1000 a membrane is pressed closed, otherwise
known. Q o may never be lower than the
Q i (sum of baseline discharge (l/s) sewer stench would enter the room.
highest value for baseline discharge Q o may never be less than the largest of the baseline discharges The air admittance surface area must be
rates.
as close as possible to the cross
Illus. 1.3. Relationship between Qo , p and Q i.
sectional area of the collection stack. For
Example:
Illus. 2.1 Principles of the primary discharge system. ease of maintenance the air admittance
Calculated using table in 2 gives Q i = 52 l/s
8 Office (p = 0,7) hence Qo = 5 l/s
vent must be fitted in accessible place 9
Principles of waste water discharge Principles of waste water discharge
water flowing away too quickly, which Stacks can often be cleaned from the
above the level of the fittings. An air airflow is possible, a balancing line may Equal discharge and flow are assumed.
can give rise to hydraulic sealing. roof provided the vent cap can be
admittance valve may also be useful in be provided. This line allows the balan- This will not be the case immediately
removed. With high buildings it is
solving problems associated with sepa- cing of overpressures and underpres- downstream of the fittings, but the wave
2.4 Access fittings recommended that an access fitting be
rate discharging fittings. However they sures. One common example arises if of water will be equal after some time
Blockages may occur even in well- provided every 3 to 4 storeys. Ventilation
cannot take the place of the (primary) the stack is not fully vertical but has (and some length of pipe) has passed.
designed discharge systems, for example lines, including secondary ventilation, may
vent pipe. horizontal sections (illustration 2.5). The
as a result of deposits (e.g. solidified fat) become (partly) blocked when rainwater
A separate direct discharge system (or uppermost example, a restricted secon- 2.3 Fall
or improper use of the drain (paint residu- gets in or by deposition of dry matter
direct parallel discharge system) may be dary discharge system, is the most A certain flow rate is required to correctly
es, food remnants, cat litter, potting com- from the environment. Vent lines should
employed to solve problems where addi- common solution. The recommendations remove foul water. A lower limit of 1:200
post, small objects, etc). Access fittings therefore also be provided with access
tional fittings are connected to an existing in this manual are based upon the has been established for this purpose.
should therefore be provided at strategic fittings.
system. This may facilitate air movement, presence of a primary discharge system. 1:400 or 1:500 may be possible with
locations in the pipework, taking account
while hydraulic sealing has less effect and shorter runs, on condition that a calcula-
of the fact that clearing equipment can
the capacity of the stack may increase. 2.2 Filling of pipework tion is provided. In practice the installa-
only cope with limited changes in direc-
Such a discharge pipe will be connected In order to allow a free flow of air the tion will then have to be carried out with
tion. Access fittings should be easily
exclusively to the stack, that is, no pipework must be designed to take great care. Further, any hydraulic distur-
accessible and placed in such way that
branch pipe will be connected (illustration account of the quantities to be removed, bances must be minimised: a fitting
hoses or springs can easily be inserted.
2.4). In places in the system where the fall (= gradient or hydraulic slope) and upstream that is frequently used and/or
The access fitting should where possible
hydraulic sealing may be caused occur the diameter, so that the pipes are no has a fairly large baseline discharge is an
be located on top of the pipe so that in
because of bends, transitions from more than 70% full (water depth is 0.7 x advantage in this case. In general a maxi-
the case of blockages the whole pipe
vertical to horizontal or where insufficient the internal pipe diameter). mum fall of 1:50 is maintained to prevent
does not empty if the cap is removed.
Acces Fitting
alternative
Illus. 2.4 Principles of the direct separate discharge system Illus. 2.5 Examples of balancing pipework.
Illus. 2.2 Principles of secondary discharge system. Illus. 2.3 Example of restricted secondary discharge system.
10 (the stack discharges directly). The uppermost method is most commonly applied. 11
3. Peripheral requirements for removal of waste water Peripheral requirements for removal of waste water
As well as proper calculation and selec- ted using a connecting pipe. During
3.3.1 General Additionally, the maximum permitted
tion of the appropriate diameter, a num- discharge the connecting pipe must be
requirements sum of changes in direction is 135°.
ber of other factors are important to completely filled with water. No require-
The diameter must be determined on a Where these conditions are met the
achieve good operation and prevent ments are therefore set down for the
section by section basis (from connecting flushed contents of the pan can
hydraulic seals, fouling of pipes and minimum fall. Some fall is certainly requi-
section to connecting section). reach the vertical stack or under-
excessive overpressures and under- red however as the pipe must empty fully.
Collecting pipes must be as straight ground pipe in one go and blockages
pressures. This chapter deals with these If the pipe is completely filled a plug of
and as short as possible. and deposits are prevented. Length
peripheral requirements. For this purpose water is created which can cause under-
Bends must not be tighter than 45°. is taken to mean the horizontal length
we now follow the pipework from the pressure. This empties the trap by suc-
To prevent soil being left behind, from the toilet to the vertical stack or
source of the discharge onwards. tion and gives rise to gurgling sounds
a < 0,5 m the maximum sum of changes in underground pipe.
(illustration 3.1). Complete filling of the
b < 1,5 m; if b > 1,5 m direction depends on the fall (illustra- All reductions in the collecting pipe
3.1 Traps pipe must therefore make way as rapidly
calculate as a stack tion 3.3). If the sum of changes in must be eccentric (top of pipe at a
Each discharging fitting must be provided as possible for partial filling. Significant
a + b + c < 3,5 m; if > 3,5 m direction is larger, the next largest single level).
with a trap. A certain diameter will be here are the length of the connecting
calculate as a collecting pipe diameter should be selected for the
required, depending on the baseline pipe, its diameter, whether the pipe runs
extra length, unless discharge takes
discharge level (see illustration 1.2). If too vertically or horizontally and the number
place upstream.
small a diameter is chosen then emptying of changes in direction. The required dia-
For a section with no toilet, the maxi-
of the fitting will take too long. Self- meter is stated in illustration 1.2. If the
mum length may be 12 metres, if two
siphoning (emptying of the trap through total length of the connecting pipework
Illus. 3.2 Conditions for reduction in fittings are connected, where the Q¡
suction when the fitting is discharged) from the trap to the common stack is
diameter of a connecting pipe, for one of these is no greater than
may occur, and noise will increase. On greater than 3.5 metres then a diameter
see also illustration 1.2. 0.5 l/s (illustration 3.4).
the other hand, an excessive diameter required for the excess must be determi-
For a section including a toilet and
will lead to a lower speed of flow. This ned as if it were a collecting stack, using
other fittings with Q¡ less than 0.75
results in greater difficulty in carrying 3.3 and illustration 4.1. The total length of
l/s, the permitted maximum length is
away soiling and blockages may result. a connecting section may not exceed 12
dependent on the fall (illustration 3.4).
There must be at least 50 mm of water metres. The diameters of parts a and b in
(500 Pa) in a trap. The seal will remain illustration 3.2 may be smaller provided
intact if a maximum underpressure of 300 the following conditions are met:
Pa arises in the system, even if some of total length less than 3.5 metres
the water in the trap has evaporated. part a less than 0.5 metres
Traps with rubber seals are to be part b less than 1.5 metres
preferred because of easier cleansing and (total of the vertical sections).
Illus. 3.1 Self-siphoning or suction replacement. This also prevents problems
emptying of the trap. arising from the use of different materials. The diameter thereby permitted is stated
There are two main types of trap, the in illustration 1.2. In view of the possibility
tubular (M,D,P,S types) and the bottle of damage and for maintenance it is
type (which includes floor-mounted varie- recommended that a rubber sleeve
ties). Each type has its advantages and should be used in the floor (at location x).
disadvantages. The bottle types are more
readily blocked, but also more easily 3.3 Collecting pipes
cleared. The bottle types lose less water Many different factors may affect collec- from to max sum of changes
example:
to evaporation and are less sensitive to ting pipes. of direction
1:50 1:75 221/2 ° 1:200 section d larger Ø
pressure differences (there is more water This accounts for the many conditions 1:75 1:100 45° 1:150 section d larger Ø
to be put into motion). A tubular trap is set down to achieve the problem-free 1:100 1:140 671/2 ° 1:100 section c en d larger Ø
1:140 1:180 90° 1:50 section b,c en d larger Ø
less prone to blocking because the removal of waste water. 1:180 1:200 1121/2 °
speed of flow is higher and the shape These requirements serve two main aims:
Where these limits are exceeded, the next diameter up should be selected for the extra length, unless discharge takes place
allows free flow. To ensure that free-flowing air remains upstream.
available above the water.
3.2 Connecting pipes To ensure that no fouling takes place.
Illus. 3.3 Maximum permissible sum of changes of direction for a particular fall in collecting pipes.
12 Every fitting must be separately connec- 13
Peripheral requirements for removal of waste water Peripheral requirements for removal of waste water
14 15
Peripheral requirements for removal of waste water Peripheral requirements for removal of waste water
In general, it is considered good practice gravity and a thick wall are therefore
Taking account of the minimum diameters to keep the noise caused by discharge, appropriate. Contact noise is a trouble-
stated in illustration 1.2 the required as low as possible. In the Netherlands, some phenomenon. All materials in
diameters can be read off for: requirements are set for noise reduction contact with one another will vibrate
collecting pipes and underground in NEN 1070 and NPR 5075. together, little damping takes place and
pipes for removal of waste water An optimal situation can be achieved by amplification may even occur. As the
(illustration 4.1); chosing a low noise pipe in combination E-modulus of a material falls there is less
stacks for removal of waste water with good installation practices. In living spreading of noise. In order to reduce
(illustration 4.2). areas in an adjacent residence the level contact noise it is important that pipe
may not exceed 30 dB(A) while for edu- walls do not make contact with one
cational and working areas the figure is another or with other bodies.
35 dB(A). The Wavin range includes a ASTOLAN®, the material used to make
special low-noise waste removal system Wavin AS combines a number of positive
designed to meet these requirements, characteristics in a unique way: it has a
Wavin AS. In this chapter we investigate low specific gravity, a thick wall and a
the generation and transmission of noise relatively low E-modulus. The expansion
in waste pipework and the measures that compensator ensures that a Wavin AS
can be taken to limit noise nuisance. pipe has no direct contact with the next Noise from stacks
pipe. The pipes must be secured with
5.1 The generation of brackets with rubber inserts so that 1 = PVC without jacketing, pipework in
noise minimal noise is transmitted to walls and test area.
Noise is generated in various ways in a floors. These walls and floors should 2 = Wavin AS without jacketing,
pipe with flowing water: the sounds of preferably be of substantial mass so that pipework in test area
flowing water and air, the noise of water it is difficult to bring them into vibration. 3 = PVC with cellular concrete duct
impacting on water and of water impac- A notorious source of noise is the (56 kg/m2)
ting on the tube wall. Combating noise transition from a vertical stack to 4 = Wavin AS with cellular concrete duct
nuisance in waste pipework requires a horizontal pipework. The Wavin AS range (56 kg/m2)
combination of measures, the most includes a variety of accessories to allow
important of which is: to prevent as far as this transition to take place smoothly and
possible that noise is generated. The few sharp changes in direction.
design for a waste pipework installation Additionally this section is freely suspen-
must therefore ensure an optimal layout: ded in rubber in the Wavin AS range and
little impact (so good pipe routing) with there are no brackets. Even with all these
proper ventilation to ensure that the water measures in place waste pipework may
can flow unhindered to counter bubbling not pass through frequently occupied
and differences in flow rates. The pipe areas. Try to arrange routing so that
wall must be smooth to prevent pipework is kept as far as possible away
Illus.4.1 Capacity of horizontal HDPE pipework; 70% full, k = system wall roughness = 1 mm. irregularities in flow. from areas that must be kept low-noise.
There must be at least one intervening
5.2 Noise transmission wall between pipework and a frequently
Noise will occur even with correctly occupied room.
D 40 50 63 75 90 110 125 160 200 routed pipework. Transmission of noise
Qo in l/s 0,45 0,77 1,30 1,89 2,80 4,30 5,62 9,22 14,41 takes place in two ways: through the air
(airborne noise) and through solid bodies
in contact with one another (contact
Illus. 4.2 Capacity of HDPE stacks with a maximum pressure difference of 300 Pa (30 mm of water). noise). A heavy intervening wall is
required to limit the transmission of noise
through the air. The lighter the pipe wall,
the more easily the airborne noise
20 escapes to the outside. High specific 21
Noise 6. Casting in heat cured concrete and extrusion shrinkage
5.3 Noise reducing 7. Fixing to a heavy wall damps down 5.4 Fittings HDPE pipework gives excellent results when limits are set down in the standards The degree of extrusion shrinkage
measures contact noise (preferably > 220 Noise from fittings can be limited by: cast into concrete floors and walls (see against set temperatures, and are for HDPE: depends on the maximum temperature
1. Waste pipework should not be located kg/m ). 2
anti-vibration insulation and anti-vibra- Chapter 7, Installation). Concrete is at 110°C max. 3%. achieved.
in the vicinity of occupied areas, and 8. No brackets should be located in tion fixing of the toilet pan sometimes brought to very high tempera- It is clear that the temperature of the
must never be led openly through impact zones. removal of reverberation by placing tures in order to allow shuttering to be The pipe will expand during heating of pipes may be no higher than 80 to 90°C
occupied areas. 9. A (heavy) intervening wall damps damping material below baths and struck the following day, particularly in the liquid concrete. The degree of expan- to cut out all risk. Since the variation in
2. Good routing and ventilation cut down down transmission by air. shower trays tunnelling work. The temperature gauge sion is limited as the pipework is fixed at temperature in the concrete can be fairly
noise generation: 10. With dummy wall constructions the reduce noise from water jets by using controlling the burners may sometimes various points and (the mass of) the great, it is stipulated that the measured
Falling waste water should be led pipework should be secured to the a small angle against the wall or by be defective. It is also sometimes the concrete restricts expansion. Once the temperature shall be no higher than 50 to
down smoothly in stages, abrupt bearing wall rather than to the means of a perlator. case that the control of the burners is concrete has hardened the pipe will 60°C. Higher temperatures are in any
descents are bad from a noise point dummy wall. carried out using the outermost tunnel shrink due to thermal shrinkage and case not good for the quality of the
of view. 11. All wall and ceiling penetrations sections, because these cool most rapid- extrusion shrinkage. This is resisted by concrete.
At the foot of the stack a calming should be provided with rockwool or ly. The temperature in the enclosed tunnel the hardened concrete as the pipework is
section of 250 mm should be used at other elastic materials. This prevents may then be appreciably higher. Extrusion held fast by bends, sleeves, T-pieces and HDPE pipes for above-ground drainage
the transition from the stack to the direct contact between the pipework shrinkage becomes significant for plastic similar, so that tensile forces arise in the are sometimes "tempered" for safety
horizontal pipework. The use of 2 and the wall and the transmission of pipework in these circumstances. pipe. The tensile forces give rise to con- reasons. That means that they are heat
bends of 45° with long legs is airborne noise from one room to Extrusion shrinkage is the single- centrations of stress which may lead to treated during or following manufacture
recommended here. another along the pipework. occurrence shrinkage measurable when breakage. T-pieces are particularly (extrusion), largely removing extrusion
Waste pipework should be dimensio- 12. Where a pipe duct is present, the the pipe is heated and then cooled. The susceptible to stress concentrations. shrinkage.
ned so that air can circulate freely inside of the duct wall must be
along with the waste water. provided with absorbent material
7. Installation
A gradually tapered reducer creates (mineral wool).
less noise than an inserted reducer 13. With horizontal pipework below a
does. false ceiling, provide extra insulation The installation of waste pipework can be Butt welding creates ridges on the interior without excessive deflection.
Connections to collecting pipework or with lead foil at bends and connec- divided into the installation design and and exterior of the pipe. The internal This method allows any changes in
to underground pipes should prefera- tions. the installation itself with the actual work ridges can hinder the proper flow of foul length to be transferred to places where
bly be by means of side connections. of fitting. The installation must be such water. An experienced welder will be able these can be dealt with by means of
Where top connection is unavoidable, Since the method of installation affects that the pipework system can fulfil its to make a sound welded joint with only bends, flexible pipe, expansion sleeves
then an angle should be employed. the generation of noise it is recommen- function without problems and with the minimal ridging. Electro-welded sleeves and so on. With HDPE pipework systems
At the foot of the stack the axis of the ded that the installation is carried out by minimum of maintenance. The system can be applied in critical situations. the pipes can be fixed so that no
horizontal pipe can be shifted around well-trained fitters. Where the measures must be able to handle changes in use, changes in length can occur. The forces
1 x D with respect to the axis of the outlined above are implemented such as changes to the frequency of 7.1.2 Brackets generated can be taken up by the pipe-
stack. This allows the water to cling consistently, no additional noise discharges or the temperature of the Brackets must have sufficient strength to work itself and transferred to the
better to the walls creating less noise. insulation will generally be required. medium. The most important condition is carry the weight of the complete pipe- structure via fixed point brackets. We
3. A plastic pipe wall is and remains that the system must be able to with- work when full. Illustration 7.1 shows the then talk about "rigid installation" with
smooth so that flows are not stand the loading generated in installation suspension forces for filled HDPE pipework fixed point brackets. Rigidly installed
disturbed. and use. These include: loading through for various bracket separations. Brackets pipework has a tendency to undulate.
4. The special ASTOLAN® pipe wall the contents and the weight of the may have different functions: support, This can be prevented with the use of
(Wavin AS) prevents airborne noise pipework itself; flotation forces when clamping or fixing. A support bracket rails or bearers (see 7.2.2).
and contact noise. casting into concrete floors and in some serves to carry the weight of the pipe-
5. The Wavin AS expansion compensa- cases with underground pipework; forces work. If the pipework expands or shrinks
tor prevents transmission of contact arising from changes in length due to it must be able to slide through the
noise. fluctuations in temperature. This imposes bracket (or the bracket must be able to
6. A rubber insert in the brackets a number of requirements on the design follow the movement with little resistance,
prevents transmission to the wall, and installation of the system. for example through the use of a long,
pipework must never make contact slender suspension leg which will easily
with walls or other materials. 7.1 Design bend). Clamping brackets serve to fix the
7.1.1 Fixings pipe with respect to the structure. The
Welded connections in HDPE may be either bracket must therefore hold the pipe
22 butt welds or electro-welded sleeves. securely and be attached to the structure 23
Installation Installation
Hence
7.2.1 Flexible expansion socket is provided on each
L = L x 0.75 x l x T
installation storey, with the floor of each storey
L = Change in length in mm.
Flexible installation means that pipe serving as the fixed point. In order to
L = Length between two points in m.
lengths determined in advance can easily allow the pipe room for expansion it must
l = coefficient of expansion
be shortened or lengthened. They slide not be inserted right up to the stop in the
(HDPE 0.2 mm/m °C)
through support brackets. The change in socket. The free length within the socket
T = temperature difference in °C
length is taken up by expansion sleeves is dependent upon the temperature
T depends on the type of pipework:
or flexible connectors. In order to achieve during installation. Expansion sockets are
cold pipework T = 20°C
this, clamping brackets are used as fixed available with the insertion length stated
warm pipework T = 40°C
points at the expansion socket or flexible in relation to the ambient temperature
hot pipework T 60°C
connector. Fixed points can also be during installation. Since the socket end
achieved by casting-in elements of the always points upwards it is possible that
Modifications to the building or its use
pipework (illustration 7.2). It is recommen- soiling will enter the socket via the pipe
may alter the temperature range.
ded that expansion pieces should be from outside during construction. This
Sufficient safety must therefore be
used only in vertical pipework and flexible can be prevented by sealing the socket
incorporated into the building. Good
connectors in horizontal pipework. with tape. Expansion sockets should be
Illus. 7.1 Relationship between bracket separations, pipe diameter and suspension routing of pipework can be of assistance
placed as close as possible to the least
forces with filled HDPE pipework. here. This allows maximal freedom of
- Flexible installation with expansion moveable side connection. In residential
movement so that the minimum tension
sleeves and couplers properties this will be the toilet connec-
or elongation arises in the material.
Illus. 7.2 Fixed points and fixing points tion. The expansion socket is then
7.1.3 Freely suspended
via casting-in. With expansion sleeves located directly above the toilet
pipework Small diameter pipework may sag when
There is a risk when expansion pieces are connection T-piece (illustration 7.3).
- Temperature differences. applications, as the medium temperature warm or hot, so that the necessary fall is
used horizontally that fouling will occur
Plastics have a fairly high coefficient of exceeds 70°C. Temperatures may vary lost. It is then sometimes necessary to
between the socket and the pipe. Use of Using couplers
thermal expansion. widely for rainwater drainage under the provide continuous support to the pipe-
expansion pieces is therefore recommen- With HDPE pipework, if the socket is firmly
For HDPE it is 0.2 mm/m °C. Pipework will roofs of large buildings. It is recommen- work. Support with half-shell brackets is
ded only in the case of vertical pipework. attached to the pipework, the fixed point
therefore become longer or shorter ded that 40°C to 50°C be taken as air recommended for HDPE-pipework
For the same reason expansion sockets clamp must be placed by the socket.
through temperature fluctuations. temperature and +5°C as water (illustration 7.8). The pipework will
should be fitted with the socket end With a permissible L of 10 mm, the per-
Extreme temperature fluctuations may temperature in winter rain. The effective generally not move easily if half-shell
upwards. Expansion sockets are fixed missible pipe length for "cold" pipework is
also arise during construction, from 50°C temperature difference is then around brackets are used. This can therefore not
with fixed point brackets above which the L = 10 mm = L x 0.75 x 0.2 x 20.
in the sun to -20°C in winter when sites 35°C. The largest variation in temperature be termed flexible installation.
pipe must be free to change in length. L = 3.33 m.
shut down. Temperature fluctuations arise in rainwater downpipes on walls will arise
A sliding bracket is therefore generally With "warm" HDPE pipework L = 1.66 mm.
during use, from the varying temperature when the water is not drained off. Large 7.2 Installation methods
used to support the socket. Good align- With this type of pipework it is important
of the discharged water and of the temperature differences can occur under The installation method is determined by
ment is important. The pipework between to prevent grit entering the pipes. The
environment. 40°C may be adopted as a the influence of frost and sun and a the manner in which the changes in
the expansion sockets must be resistant sliding back and forth in the rubber seal
maximum mean temperature difference in maximum variation of 60°C can be length resulting from temperature
to tensile stress. As a rule of thumb, the can in time allow grit to enter between
the walls of connecting pipes and reckoned upon. Through this temperature fluctuations are taken up. Two possible
length between expansion sockets is the pipe wall and the rubber seal, causing
collecting pipes for domestic above- difference pipework will become shorter methods are available:
Illus. 7.3 Expansion socket at the least generally 6 m for HDPE, provided there are leaks.
ground drainage, even where occasional or longer. Practice shows that the Flexible installation, divided into:
moveable side connection. no side connections. In practice an
brief discharges of waste water at 80°C difference in length will be around 0.75 - flexible installation with expansion
to 90°C occur. A 20°C temperature diffe- times what was calculated. We can sleeves and compression sockets
rence can be adopted for stacks and distinguish between cold pipework - flexible installation with flexible
underground pipework. Note: This relates (max. temperature difference 20°C), warm connectors
to the mean wall temperature along the pipework (max. temperature difference Rigid installation
full length of the pipework; the variation 40°C) and hot pipework (max. The method to be employed is
in discharge temperatures may be far temperature difference 60°C). These dis- determined by the designer.
greater. For extended discharge of large tinctions apply to domestic discharges. In
quantities of hot water a 60°C the case of extended discharges of large
temperature difference may be adopted; quantities of (hot) water the categorisa-
24 HDPE will usually be selected for such tion should move up one place. 25
Installation Installation
- Flexible installation with flexible Apart from brackets at fixed points, all - Bracket distribution with flexible
connectors brackets must be support brackets. installation
For horizontal pipework this method is Another solution is to select (threaded) With expansion sockets
preferred over expansion sockets. In support clamp suspension legs of With expansion sockets the clamping
general only a small change in alignment materials and dimensions that will bend brackets must always be located at
is required (illustration 7.4). For long to follow the changes in length. This does fixed points. The distance between
sections of pipework it may be necessary however open the way to undulation of these is divided, taking account of the
to create horizontal "jumps" (illustration pipework. This last point need not maximal bracket separation, and the
7.5). If this is appreciated in good time present a functional problem provided the support brackets placed accordingly.
there need be no difficulties with any fall is not reversed. It is however often With flexible connectors
other pipework or cables. As with regarded as less pleasing to the eye. The brackets are to be placed at the
expansion sockets, support brackets are The change in length ( L) for a particular maximum permitted distance from the
Illus. 7.4 Minor changes in alignment to used, with clamping brackets for fixed length of HDPE pipework and the required nodes (branches, bends etc), see
create flexible pipe sections. points. The permissible pipe length from length (L) of a flexible section for various illustration 7.6. The distance between
the fixed point (clamping bracket) to the temperature differences can be read off these is divided, taking account of the
flexible section is dependant on the from illustration 7.7. maximal bracket separation.
bending the flexible section can take.
The pipes should be bent so as to - Bracket separations with flexible 7.2.2 Rigid installation
provide the maximal flexible length. installation (HDPE)
This gives clarity in assembly and Clamp separations are selected so that Illus. 7.7 Relationship between temperature difference, freely moving pipework length, In the case of rigid installation the system
maximum flexibility. Halving the permis- the pipe does not sag enough to prevent changes in length and length of flexible section for various diameters of HDPE pipes. is installed in such a way that changes in
sible clamp separation distance will give proper emptying even when hot water is length cannot occur. The forces genera-
the permissible length for the flexible carried. The pipework must still be able ted are transferred to the building
section (illustration 7.6). to slide through the support brackets. structure by shell brackets, fixed point
The pipework must also be prevented brackets and suspension constructions.
from excessive sagging for aesthetic Rigid installation is only required with HDPE.
Illus. 7.5 Horizontal "jump" to create reasons. A rail system or half-shell bracket support
flexible section in long stretch From strengh point of view horizontal system is always required with rigid
of horizontal waste pipework. pipework in HDPE can be suspended with installation. With shell brackets alignment
clamp separations from 20 to 25 x D. is achieved by securing the pipe to the
7.8 System without/with shell brackets. shell bracket at the location of the 0.2
HDPE waste pipework can be installed with metre overlap, using a clamp or 2 strong
or without half round shell brackets Tie raps. The pipe is also fixed to the
(illustration 7.8). The shell brackets are in shell brackets every 10 x D (min. 0.5 m;
galvanised steel and may be black. Shell max. 1 m) with Tie raps or bands.
brackets are used with horizontal
pipework where neat, straight runs are
required, without sagging. With "hot"
pipework ( T = 60°C) shell brackets are
necessary with HDPE pipes. Shell brackets
are often used with small diameters to
allow a greater separation between
brackets. Since the pipe cannot easily
slide through the shell brackets, rigid
mounting is always used with half-shell
brackets (see 7.2.2).
26 Illus. 7.6 Flexible installation with flexible connectors, and distribution of brackets.
27
Installation Installation
In order to calculate the external over- As well as the design of the installation oval shape. Oval pipes create extra work tension-resistant connection. There are
Length Pipe diameter there is also the actual assembly. The when welding joints. Bear in mind that two methods of welding: hot plate
pressure in kPa the height in metres of threaded
liquid concrete must be multiplied by 24. bracket leg design is complete, but many decisions pipes can get very hot in the sun. Once welding and electro-welding using fittings
mm 40 50 63 75 90 110 125 160 200 remain to be taken by the fitter which will out of the sun they will shrink again. If the with integral heating elements. Flange
If the pipe is filled with water to
counteract flotation the multiplication 100 1/2” 1/2” 3/4” 3/4” 3/4” 1” 1 1/4” 1 1/4” 1 1/4” impact on the quality of the work and the pipe is at 70°C and the temperature joints are also resistant to tension, but
factor is 14. problem-free operation of the waste inside is 20°C, a 5 metre long HDPE pipe this technique is very rarely used in
150 3/4” 3/4” 1” 1” 1” 1 1/4” 1 1/4” 1 1/2” 1 1/2”
removal system. will be 0.2 x 50 x 5 = 50 mm shorter. above-ground drainage work. Rubber
200 3/4” 1” 1” 1” 1” 1 1/4” 1 1/2” 2” 2” Leave accessories in the packaging as O-ring joints are found in insertion
Example: 6 metres of liquid concrete,
pipe Ø 110 mm without water filling, 8.1 General long as possible. HDPE electro-weld sleeves couplings and expansion sockets in HDPE.
250 1” 1” 1” 1 1/4” 1 1/4” 1 1/2” 2” 2” 2”
pressure 6 x 24 = 144 kPa. Minimum should be stored indoors and left as long
300 1” 1” 1 1/4” 1 1/4” 1 1/4” 2” 2” - - 8.1.1 Pipework in the as possible in the packaging to prevent
required for HDPE: 110 x 34.
With water filling the external overpres- 350 1” 11/4” 1 1/4” 1 1/4” 1 1/2” 2” 2” - - waste removal oxidation from sunlight. Oxidation on the
sure is 6 x 14 = 84 kPa. In HDPE SDR 26 system interior can badly affect welds.
will suffice. Illus. 7.12 Required threaded leg diameter for a given pipe diameter, and maximum The pipework must be installed with a
bracket leg length for fixed point brackets with rigid installation in HDPE waste particular fall as indicated on the 8.1.4 Oval pipe ends
removal system. drawings using brackets, bands and Excessively oval shape HDPE pipe ends
supports. They must not be fitted should first be made rounder. This can
horizontally, but there must not be too be done by clamping the pipe with one
great a fall. Excessive fall leads to the or two brackets with one or two pieces
complete closure of the pipe and to poor of padding between, placed a little back
ventilation. Where reducing pieces are from the eventual coupling insertion Butt welding
used the top of the pipework should be depth at the end of the pipe. Both pipe ends are placed against a
at the same level. The desired installation The brackets are only removed after the hot plate at a constant temperature
method must be known (see 7.2). weld has cooled. and pressure. The plastic pipe ends
are now pressed together so that the
Illus. 7.13 Bracket for casting-in HDPE in 8.1.2 Brackets 8.1.5 Shortening pipes molecules of the material are
concrete. All types can be used with support The best and simplest method is to use transferred between them. Wavin HDPE
brackets; from light nylon band brackets, a proper pipe cutter. The cut is then pipes and accessories can be hot
light or heavy PVC brackets to galvanised straight and no burrs are generally plate welded with good results. Hot
sewer brackets, and suspension bands. created. If a saw is used, care needs to plate welding creates small ridges
Ensure that any sliding brackets do be taken to ensure that the cut is inside and outside the pipe. It is
HDPE actually slide (avoid over-tightening). straight: mark the cut, use a stiff saw recommended that a training course
calculated Brackets used for clamping must be blade and use a saw horse with Ø above should be followed. Before starting
SDR HDPE resistance
strong. For fixed point brackets (only 50 mm. Remove internal and external with hot plate welding the equipment
Du/e pipe size (kPa)
with HDPE) galvanised steel brackets must burrs with steel wool or a knife. For should be checked over.
13,3 40x3 635
50x3; 63x3,6; 75x4,3 be used. sawing HDPE use a fairly coarse-toothed - The hot plate temperature should be
17 90x5,1; 110x6,3; 125x7,1 348 blade with a wide set. 210° C.
160x9,1; 200x11,4 8.1.3 Storage - The hot plate must be clean and
21 63x3 178 Rubber O-rings must be kept in a cool 8.2 Joints free of grease; clean as necessary
75x3; 90x3,5; 110x4,3 and dark place and not exposed to Joints fall in principle into two categories, with a clean cloth and alcohol.
26 125x4,9; 160x6,2; 92 sunlight (not even behind glass). those resistant to tension and those not - Ensure that the two pipe brackets
200x7,7
Pipes must be stored as flat as possible resistant to tension. Welded and flanged and the two pipe supports are
30 90x3 58
to prevent sagging. It is difficult to joints are resistant to tension. Expansion correctly aligned. This can be
32 110x3,5; 125x3,9; 50
160x5,0; 200x6,2 produce neat, straight work with bent sockets and connections using rubber achieved by clamping 1 section of
pipes. Keep pipes as clean as possible; seals are not resistant to tension. pipe in both clamps and both pipe
this saves time when preparing and supports. If necessary adjust the
making connections. Covering is 8.2.2 Joints in HDPE two pipe supports until they are
Illus. 7.14 Resistance to underpressure (=external recommended during extended storage HDPE pipes can not be joined using solvent correctly aligned with the pipe.
overpressure) of HDPE pipes at a mean wall outdoors. Ensure that HDPE pipes, and cement as PVC can. However welding of - Both pipe clamps must be adjusted
30 temperature of 30°C. particularly the ends, do not take on an HDPE gives excellent results. This creates a so that they hold the pipe tightly 31
Assembly Assembly
enough to withstand the force of the welding sleeve has projections to plastic layers together. However this is
1 2 3 welding process. The pipe clamps allow their exact distance apart to be only possible if the HDPE surface is
can be used to make an oval pipe determined. This is particularly completely free from contamination.
round (but they will also do the important with prefabrication. Welding Pipes in storage develop an oxidised
opposite). The tension must there equipment is required. layer in production and storage which
fore not be either too high or too Also required are: impedes welding. This must be
low. - A pipe cutter or a saw with teeth set removed before welding by cutting,
wide. scraping or abrasion, followed by
Welding itself is carried out as follows: - Clean, lint-free cloths or white crepe cleaning. Furthermore the material
1. Check that the hot plate is up to paper (not printed). must be free of moisture and must
temperature. - Emery cloth, grit 40. not move during and for a brief period
1. Check that the hot plate is up to 2. Clamp the pipes and use the trimmer 3. Check that the pipe ends match 2. Clamp the pipes and use the trimmer - A scraper or knife for de-burring. after the welding. If these conditions
temperature. on the ends. Stop the trimmer only precisely. If necessary clamp and trim on the ends. Stop the trimmer only - Felt tip pen or crayon. are not met there will be adhesion but
when the pipes no longer contact the again. when the pipes no longer contact the - Tape measure or ruler. without fusion. The weld will be
blade; this prevents "hooking". blade; this prevents "hooking". - The electro-weld sleeve. weaker and high loading or bending
3. Check that the pipe ends match The HDPE electro-weld sleeve is provi- may later cause leaks. In order to
precisely. If necessary clamp and trim ded with 2 socket ends which can be achieve an even weld all round the
4 5 6 again. welded in a single operation. The pipe must be stress-free. Bent or oval
4. Press the pipe ends against the hot welding equipment sends current pipes may require support. The
plate with a brief application of high through the resistance wires in the components to be welded must be
pressure, then continue with electro-weld socket for a set period. fixed with respect to one another,
application of very low pressure until a Both electro-weld sockets are welded particularly when welding accessories
ridge of 1 mm has formed. at the same time. The electro-weld and short sections of pipe.
5. Quickly remove the hot plate and socket has stops on the interior. In
slowly increase the welding pressure order to use the socket as a slide-on Preparation work
(see the table on the machine for the collar the stops can easily be remo- Select the appropriate welding equip-
4. Press the pipe ends against the hot 5. Quickly remove the hot plate and slow- 6. Hold the welding pressure steady and welding pressure). ved with a knife or screwdriver. The ment. Check that the welding
plate by briefly applying a high pres- ly increase the welding pressure (see allow the weld to cool. 6. Hold the welding pressure steady and socket has two contact pins on the equipment is suitable for the diameter
sure. Continue heating with very low the table on the machine for the wel- allow the weld to cool. outside for connection of the welding to be welded. The welding equipment
pressure until an upstand of 1 mm has ding pressure). 7. Remove the joint and inspect the equipment. There are also two wel- must be protected from moisture and
formed. weld. An irregular ridged seam should ding indicators which appear during dirt. The voltage required is 220 Volts.
Before welding: be rejected. and after the welding operation. In case of doubt the welding time can
These indicate that the welding be checked. Full instructions for use
7 A. The hot plate temperature should be 210° C.
Electrical spigot welding temperature has been reached and should be provided with the welding
B. The hot plate must be clean and free of grease; clean as necessary with a clean
cloth and alcohol. HDPE accessories are provided with that the welding pressure has been equipment.
C. Ensure that the two pipe brackets and the two pipe supports are correctly aligned. spigot ends to allow butt and sleeve applied. They do not however give
This can be achieved by clamping 1 section of pipe in both clamps and both pipe welding. The spigot ends are provided any indication of the quality of the Welding equipment, tools and
supports. If necessary adjust the two pipe supports until they are correctly aligned with low irregularities (ribbing) and the weld. The quality of the weld is pipework components must be in
with the pipe. dependent on a great many other good condition. That means:
D. Both pipe clamps must be adjusted so that they hold the pipe tightly enough to factors. See "Principles and - The welding equipment must be
withstand the force of the welding process. The pipe clamps can be used to make Preparation". regularly inspected and the welding
an oval pipe round (but they will also do the opposite). The tension must therefore time must be correct.
7. Remove the joint and inspect the weld. not be either too high or too low. Principles of electro-welded sockets - The contact shoes on the welding
rejected. Most important data for hot plate welding of waste pipework: During welding the surface of the - The contacts on the electro-weld
interior of the socket and the exterior sockets must be clean.
of the pipe are brought to a plastic - The pipe end to be welded must
warming up time ridge height welding pressure cooling with
state. Expansion of the pipe and not be excessively oval.
(at very low pressure) (up to 160 mm) application time welding force
shrinkage of the socket (the shrinkage - The cloths used must be clean and
applied
32 is built in during manufacture) fuse the lint free. 33
45 - 70 sec 1mm 5 -6 sec 6 - 10 min
Assembly Assembly
- The pipe end must be free of burrs. Welding procedure of pipe ends may call for modified sockets. The pipe must be inserted Ambient Table showing insertion depths for pipe of length 5000 mm
- If a spigot end is very dirty it must A user manual describing the welding processing. into the expansion socket up to the temperature
ø63 ø75 ø90 ø110 ø125 ø160 ø200 ø250 ø315
first be cleaned with HDPE cleaner. procedure should accompany every temperature indication point for the Insertion depth in mm
If this is not done the dirt will be item of welding equipment. Rubber seals then prevailing ambient temperature -10°C 60 60 65 70 75 90 100 115 135
ground into the pipe when it is - First connect to the power. Two types of rubber seal are in use (measure and mark on the pipe). 0°C 65 65 75 80 85 100 110 125 145
- The following maximum lengths +10°C 75 75 85 90 95 110 120 135 155
abraded later. - The "voltage" indicator lamp will with HDPE waste systems.
+20°C 85 85 95 100 105 120 130 145 165
- A layer must be removed from the illuminate. If the lamp flashes check 1 With a round O-ring: apply to pipe sections between 2
spigot end. This is always required!! voltage and connections. - The O-ring housing and the ring expansion sockets: "cold" pipework
HDPE oxidises in air and in light. The - Attach the connector cables to the itself must be clean. 13.2 metre; "warm" pipework 6.6 Illus. 8.1 Insertion depth for HDPE expansion sockets with "hot pipework" for a range of
oxidised layer must be removed to electro-weld socket. Note: for safety - The HDPE pipe must be cut square, metres and "hot" pipework 4.4 to ambient temperatures.
achieve an optimal weld. The oxidi- reasons these cables must not be bevelled off at around 30° and 5 metres (see also flexible installa-
sed layer can easily be seen after extended. deburred. tion with expansion sockets 7.2.1).
extended storage in the open air. - The "connection" indicator lamp will - Introduce the components to one
Extra care will then be required. illuminate. another, up to the stop. Illustration 8.1 may also be used to deter-
The outer layer is best removed by - Press start button. The welding 2 Sealing sleeve connection: mine the insertion depth.
abrading with clean emery cloth, indicator lamp will illuminate. Once - The sleeve and the chamber
grit 40. Remove the abraded welding time is complete this lamp behind it must be clean.
particles. automatically extinguishes and the - Apply Wavin lubricant to the 9. Situations during construction
The following points are also current supply switches off. sleeve.
significant: - Check the weld indicators. They - Insert the deburred, square cut
- Electro-weld sleeves have a short should have emerged by around and bevelled pipe. Fouling, damage and movement of the Pressure test pipework before
insertion depth, so that a pipe 2 mm. installed waste removal system must be pouring concrete.
which is not cut square will weld Note 1: If the welding indicator lamp Expansion sockets avoided during construction. Prevent grit from roofs entering waste
poorly and provides a risk of fire. flashes the welding process Unlike the twin sockets used with pipework. This can be extremely
- Check the fit between sleeve and has been interrupted for one PVC, expansion sockets in HDPE are in Possible measures include: difficult to flush out and can give rise
spigot end. If this is oval refer to reason or another. Identify a single piece into which the pipe is Closing off pipework with protective to problems especially with rubber
"Oval Pipe ends" (8.1.4). and rectify the cause, allow inserted. A rubber sleeve is used as a caps. Use caps that fit over the pipe seals.
- The pipe and fitting must not move the joint to cool completely seal. wherever possible so that they are Lead rainwater out of the building as
during welding and cooling. If (1 hour) and repeat the not accidentally left in place. When quickly as possible (illustration 9.1).
necessary fix with clamps. If the entire procedure. - Install expansion socket at using caps that fit within pipes, this
pipe or fitting sags or creeps the Note 2: The welding process may previously determined locations and should be clearly indicated.
welding threads in the sleeve may only be interrupted by use brackets as for a fixed point. Seal off spigot ends that are still to be
sag inward. This may cause a fire. switching off the supply. - With the socket end facing connected (by insertion, welding or
- With large installations a powerful upwards in vertical pipework. cement).
stream of air may flow through the If the use of an isolating transformer is - Attach the HDPE pipe firmly to the Expansion socket sleeves in vertical
pipework which can act as a flue. required for safety reasons, say in a spigot end of the expansion socket pipework should be protected from
This may cause appreciable damp area, then this may be done (using a welded joint). materials such as mortar that might
cooling to the interior. The without problems. Extensive testing has - Align the expansion socket and get into the sleeve.
pipework should therefore be shown that this does not affect the weld pipework correctly at both ends. Protect around 20 mm of pipe ends
sealed with a protective cap. quality. Fit an extra support bracket if emerging vertically from concrete
- The exterior of the electro-weld required. The pipe end to be floors by sealing with plastic foam or
socket will become warm only after Use of non-standard pipe inserted must be correctly bevelled similar prior to pouring concrete. This
welding has commenced. The joint Electro-weld sockets are designed for (min. 4 mm, 15°). often prevents damage when the floor
may only be loaded after the use with HDPE waste pipes from KOMO - Apply Wavin lubricant to the rubber is worked on later.
socket has cooled. series I and II (see table in Illustration ring and the end of the spigot. Ensure adequate anchoring to
- The ends of pipes and fittings must 7.14). Pipes with thicker walls may - Where a stack is to be enclosed in prevent flotation or bending of pipes
be bone dry. If necessary pre-heat also be welded using the electro-weld a duct, protect the joint from mate- during concrete pouring.
to prevent condensation. socket. Liaison with the supplier rials like mortar that might fall in. Check direction and height of
would then be recommended, since - Temperature indications appear on pipework before ceilings or ducts
34 varying tolerances and greater rigidity the outside of HDPE expansion are installed. Illus. 9.1 Temporary situation during construction. 35
10. Pressure testing 11. Maintenance
A well-designed, properly installed and This means that a section of the blocked
Pressure testing is carried out most The pipework must not be exposed
correctly used waste removal system will pipework does not need to empty
quickly and simply using air under a to radiant heat, including the heat of
require little or no maintenance. through the opened access fitting. Where
limited overpressure. This is also possible the sun.
Inadequacies in design and installation, the access fitting cap is more than
with internal rainwater systems. The Where this nevertheless occurs
and above all incorrect discharge around 100 to 150 mm from the exterior
simplest procedure is to close off all (usually prior to pouring of concrete)
activities may cause poor or slow removal of the pipe, the use of a 45° fitting is
openings, apply air pressure of 2 to 3 then pressurisation with air and soap
of water or a blockage. Usually no action recommended. Obstruction of drainage
kPa (0.2 to 0.3 metre water column) and testing of the joints is a good
is taken until the water begins to drain from roofs, gutters, gullies, overflows,
apply soapy water to the joints. alternative.
slowly or there is a complete blockage. rainwater drainage and other drainage
Specialised companies sometimes use A test is carried out immediately prior
Checks on drainage and periodic constructions must be prevented by
smoke-testing. to the pressure test in order to
maintenance are therefore recommen- means of periodic maintenance.
demonstrate that the equipment is in
ded. In the event of blockages or Special attention must be paid to
It is recommended that sections to be good order. For this purpose the
threatened blockages which are not drainage where granular roof coverings
cast in concrete be pressure tested internal pressure in an enclosed
located in the traps, a clearing spring are installed after the drainage system is
before pouring. This is not only because pipeline or hose of say ø10 mm and
may be used. Care must be taken to in place. Grit which enters horizontal
repairs are so difficult afterwards, but also 2 metres in length, with the pressure
prevent damage, especially in bends. pipework is difficult to flush away using
to establish whom is to bear the cost of meter attached, is brought up to
High pressure cleaning with a jet head is the normal speed of flow, and
any subsequent repairs. If it is decided to 400 kPa. The pressure drop may not
a better approach. The use of explosive encourages fouling. Flushing clean
carry out pressure testing (to NEN 3215) exceed 10 Pa (1 mm water column)
charges to cause pressure shocks in the before handover and after around a
then the procedure is as follows: in a period of 15 minutes. When that
pipes is not recommended. year is strongly recommended.
The system is pressure tested with an is the case the waste removal system
The usual drain-clearing agents may be
air pressure of 400 Pa (40 mm water may be placed under pressure and
used provided the instructions on flushing
column). Where the total capacity of the actual test carried out.
are followed.
the system to be tested is greater
Roof channels, roofs, roof gullies and the
than 0.3 m3, then it must be tested in
like should be periodically cleared of dirt,
sections of 0.3 m3.
leaves etc.
All open joints are to be sealed with
ball-type valves and all traps are to be
Specialist firms may carry out major
filled.
maintenance or the clearing of serious
After 15 minutes the drop in pressure
blockages. It is useful to build in a
must not exceed 50 Pa (= 5 mm
number of cleansing facilities to aid
water column). If the drop in pressure
cleaning or removal of blockages:
exceeds that, the test must be
removable traps
continued up to 60 minutes. After that
connections to underground pipes
period the drop in pressure may not
with rubber sleeves
exceed 200 Pa (= 20 mm water
access fittings at strategic points
column).
such as at the transition from
The drop in pressure may be caused
underground pipework to the
by moving connections, such as toilet
domestic pipework, around hydraulic
sealing sleeves and sealing sleeves
problem areas such as after a series
between horizontal pipes and
of bends and with longer pipe runs,
connecting pipes, as well as by
and in cast-in pipework.
temperature differences during the
test.
Access fittings must be accessible and
The temperature difference may be
where possible be located higher than
up to 0.3°C, measured in the spaces
the horizontal pipework, or better still
occupied by the waste pipework.
higher than the discharge level of fittings.
36 37
12. Product list Product List
Art.nr. d1 di S1 L A cm 2 Pipes
920 002 32 26,0 3,0 5000 5,3
920 003 40 34,0 3,0 5000 9,0
920 005 50 44,0 3,0 5000 15,2
920 007 63 57,0 3,0 5000 25,4
920 008 75 69,0 3,0 5000 37,3
920 009 90 83,6 3,5 5000 54,1
920 010 110 101,6 4,2 5000 81,0
920 011 125 115,4 4,8 5000 104,5
920 013 160 147,6 6,2 5000 171,1
920 015 200 187,6 6,2 5000 276,4
920 017 250 234,6 7,7 5000 432,0
920 019 315 295,6 9,7 5000 686,0
Pipes:
From Ø 75 to Ø 160 pipe series S12,5
From Ø 200 to Ø 315 pipe series S16
Nominal diameters according to EN 1519
Art.nr. d1/d2 X1 X2 H
Concentric reducer
920 508 40/132 30 30 80
920 516 50/140 30 30 80
920 525 63/140 30 30 80
920 526 63/150 30 30 80
920 530 75/140 30 30 80
920 531 75/150 30 30 80
920 533 75/163 30 30 80
920 535 90/140 30 30 80
920 536 90/150 30 30 80
920 538 90/163 30 30 80
920 539 90/175 30 30 80
920 542 110/140 30 30 80
920 543 110/150 30 30 80
920 545 110/163 30 30 80
920 546 110/175 30 30 80
920 547 110/190 30 30 80
920 550 125/150 30 30 80
920 552 125/163 30 30 80
920 553 125/175 30 30 80
920 554 125/190 30 30 80
920 555 125/110 30 30 80
920 558 160/110 32 29 100
920 560 160/125 32 32 100
920 562 200/160 100 100 250
920 564 250/200 120 120 270
920 566 315/250 130 130 325
38 39
Product list Product List
42 43
Product list Product List
44 45
Product list Product List
Type D - 135°
Art.nr. d1/d2 X1 X2 X3 H Access fitting 88 1/2°
920 863 40/ 40 75 70 50 125
Art.nr. d1/d2-d3-d4 X1 X2-X3-X4 H
920 865 50/ 50 90 85 60 150
922 667 110/150 100 120 200
920 867 63/ 63 105 80 70 175
922 670 110/175 100 120 200
920 868 75/ 75 105 90 70 175
922 671 110/190 100 120 200
920 869 90/ 90 120 100 80 200
922 672 110/110 100 120 200
920 870 110/110 135 125 90 225
922 673 125/150 100 125 200
920 871 125/110 150 130 100 250
922 676 125/175 100 125 200
920 873 160/110 210 150 140 350
922 678 125/110 100 125 200
920 875 200/110 180 170 180 360
920 877 250/110 220 190 220 440
920 879 315/110 280 210 280 560
Type E - 90°
Art.nr. d1/de t H Floor mounted toilet
923 021 90/132 60 90 connector
Art.nr. d1/d2-d3-d4 X1 X2-X3-X4 H
923 031 110/132 60 90
922 617 110/150 100 120 200
922 620 110/175 100 120 200
922 621 110/190 100 120 200
922 622 110/110 100 120 200
922 623 125/150 100 125 200
922 626 125/175 100 125 200
922 628 125/110 100 125 200
46 47
Product list Product list
Art.nr. d1 X1 X2 Connecting
921 139 190 270 50 elbow 90° - smooth Art.nr. d1/d2 de X1 X2 t H Long-spigot toilet
921 140 110 300 60 926 010 190/40 120 270 180 120 160 elbow with double stub
926 011 190/50 120 270 180 120 160
926 012 110/40 120 300 150 140 185
926 013 110/50 120 300 150 140 185
Art.nr. d1/de X1 t H Universal toilet * Allows the connection between the toilet discharge fitting and
923 087 110/132 300 120 185 elbow Type C the long toilet elbow.
EPDM
Flange connections Art.nr. d1 de S
904 402 132 170 3
904 403 140 182 3
904 404 150 192 3
904 405 163 107 3
904 406 175 127 3
904 407 190 142 3
904 408 110 162 3
904 461 140
904 462 160 218 3
904 463 200/225 273 4
904 467 280
54 55
Product list Product list
Roof gullies
Art.nr. d1 G t H Internal thread joints
307 031 40 1/2” 20 55 Art.nr. di de Flow capacity Gullies without
307 033 40 3/4” 20 55 982 502 53 FM 2” 12 l/s counterflange
307 035 40 1” 20 55 982 632 69 FM 2” 1/2 24 l/s
307 039 50 1/2” 20 55
307 041 50 3/4” 22 55
307 043 50 1” 24 55
307 045 50 1-1/4” 20 55
307 047 50 1-1/2” 22 55
307 049 50 2” 24 87
307 051 63 2” 24 94
Other Ø on request.
56 57
Product list Product list
Art.nr. Description
982 610 Guiding rail 6 mt
982 611 Fixing system 6 mt, ø 40
982 612 Fixing system 6 mt, ø 50
982 613 Fixing system 6 mt, ø 63
982 614 Fixing system 6 mt, ø 75
982 615 Fixing system 6 mt, ø 90 Art.nr. Sheet in TG 66
982 616 Fixing system 6 mt, ø 110 982 514
982 617 Fixing system 6 mt, ø 125
982 618 Fixing system 6 mt, ø 160
The fixing system includes the guiding rails and fixing brackets.
58 59
Product list Product list
Art.nr. D O-ring
982 621 50
Art.nr. Flow stabiliser T5 in
982 622 63
982 504 aluminium
Art.nr. Sheet
982 513
60 61
Product list Product List
- with termostat
- teflon-coated
- complete with supports
- metal carrying case
- 800 W
- supply voltage 220 V ~ 50 Hz
AL AIN
P.O. Box: 80862, Al Ain, UAE
Tel: +971 3 7210727
Fax: +971 3 7211292
Email: hepaln@emirates.net.ae
QATAR
P.O. Box 50207, Mesaieed, Qatar
Tel: +974 44760588
Fax: +974 44760525
Email: info@hepworthpme.com.qa
BAHRAIN
P.O. Box 143, Manama, Bahrain
Tel: +973 17672050
Fax: +973 17672583
Email: info.bahrain@corys.ae
OMAN
P.O. Box 117, PC 130, Oman
Tel: +968 24216938
Fax: +968 24210032
Email: info.oman@corys.ae
SAUDI ARABIA
Al Nuwar Bint Malik Street
Tel: +966 547900444
Email: info.ksa@corys.ae
customer.service@corys.ae www.hepworth.ae