You are on page 1of 8

UTIC SERVICES SDN. BHD.

THE PROPOSED SEWER NETWORK RECTIFICATION


AT INDAH WATER KONSORTIUM SDN BHD’S,
SEWAGE TREATMENT PLANT (ASSET NO. SAM058)
LOCATED AT JALAN NELAYAN, SEKSYEN 19, SHAH
ALAM, SELANGOR DARUL EHSAN

CONTRACT NO.: IWK/CW1/254/BSAM/C.SM.15.0013

PIPE LAYING WORK BY USING OPEN CUT


(USING SHEET PILE)
TABLE OF CONTENT

1. INTRODUCTION.................................................................................................................. 3
2. LIST OF VEHICLE MACHINERY AND EQUIPMENT..........................................................3
3. MANPOWER....................................................................................................................... 4
4. PROCEDURE...................................................................................................................... 4
4.1. Survey works........................................................................................................... 4
4.2. Removing of trees...................................................................................................4
4.3. Sheet Pile Installation.............................................................................................4
4.4. Excavation of line pipe............................................................................................5
4.5. Piling Work............................................................................................................... 5
4.6. Concreting work......................................................................................................7
4.7. Pipe Laying.............................................................................................................. 7
4.8. Backfilling and Compaction...................................................................................7
4.9. Manhole construction.............................................................................................7
4.10. Traffic Management.............................................................................................8
4.11. Dewatering........................................................................................................... 8
5. SAFETY HEALTH AND ENVIROMENT (SHE)...................................................................8

UTIC SERVICES SDN BHD (459079-W)


Head Office Klang Valley
No.12 Crossvent Subang, Jalan Lira U3/41, Pekan Baru Subang
Seksyen U3, 40150 Shah Alam, Selangor, MALAYSIA
Tel: (603) 78327030 Fax: (603) 78327830 www.uticservices.com
2
1. INTRODUCTION

Generally, this document is developed as a method used for the pipe laying work by using open
trench excavation and the shoring method is by using sheet pile.

2. LIST OF VEHICLE MACHINERY AND EQUIPMENT

2.1. Removal of trees


2.1.1. Boom Lift
2.1.2. Chainsaw

2.2. Sheet pile Installation

2.1.1. Excavator mounted vibrator


2.1.2. Sheet pile 9m
2.1.3. I beam Frame

2.3. Excavation line of pipe

2.3.1. Dump Truck


2.3.2. Excavator
2.3.3. Hand shovel
2.3.4. Box shoring with metal steel plate

2.4. Piling work


2.4.1. Piling Machine
2.4.2. Electric generator
2.4.3. Demolition hammer

2.5. Pipe laying


2.5.1. Excavator
2.5.2. Lifting hook

2.6. Safety equipment

2.6.1. Personnel protective equipment (PPE)


2.6.2. Safety cone / plastic barrier
2.6.3. Safety signage

UTIC SERVICES SDN BHD (459079-W)


Head Office Klang Valley
No.12 Crossvent Subang, Jalan Lira U3/41, Pekan Baru Subang
Seksyen U3, 40150 Shah Alam, Selangor, MALAYSIA
Tel: (603) 78327030 Fax: (603) 78327830 www.uticservices.com
3
3. MANPOWER

3.1. Site agent

3.2. Supervisor

3.3. Site Safety Supervisor

3.4. Excavator operator

3.5. Mobile crane operator for piling work

3.6. Skilled labour

3.7. General worker

4. PROCEDURE

4.1. Survey works

4.1.1. Before any works are commenced, Licensed Surveyor (LS) should be engaged
to verify the entire dimension and level as shown on drawings.
4.1.2. Data of existing structure such as pipe culvert, retaining wall, drains, road kerb
and underground utilities shall be checked and recorded
4.1.3. A joint survey shall be carried out in the presence of S.O. to confirm any
discrepancy, which may affect to the dimension, level or any part of the works.

4.2. Removing of trees

4.2.1. Before starting excavation work, trees that is higher than 3m had to be removed
for mobilization of machine purpose.
4.2.2. Tree branches will be cut to the point where there is only trunk and will be cut
using boom lift and chainsaw.
4.2.3. Trees that had been cut will then be planted at a site where it is approved by
MBSA.

4.3. Sheet Pile Installation

4.3.1. Machine will be mobilized to site with a 9m sheet pile.


4.3.2. An installation of sheet pile will be made by section whereby a section consists of
25m of length.

UTIC SERVICES SDN BHD (459079-W)


Head Office Klang Valley
No.12 Crossvent Subang, Jalan Lira U3/41, Pekan Baru Subang
Seksyen U3, 40150 Shah Alam, Selangor, MALAYSIA
Tel: (603) 78327030 Fax: (603) 78327830 www.uticservices.com
4
4.3.3. For the first point, a 2 section of sheet pile will be installed starting from MH 18Z
to MH 19 Z.
4.3.4. Next, installation of I beam at the top of sheet pile will be done. (Refer picture for
detail)
4.3.5. After finish 2 section of sheet pile, procedure 4.4 to 4.8 will be followed by.
4.3.6. After completion of procedure 4.8, the first section of sheet pile will be dismantled
and will be installed to continue to section 3 and continues the process until
MH8Z.

4.4. Excavation of line pipe

4.4.1. The trench for pipe shall be excavated to the requirement depth as per drawing.
4.4.2. Excavated earth shall be stored on one side of the trench for re-use in backfilling.
Temporary shoring of trenches will be using box shoring and steel plate at side of
the box shoring.
4.4.3. Excavation work by using excavator will scoop in between box shoring beam
which have clearance of 5m length in between.
4.4.4. Detail of box shoring is attached at Appendix A.

4.5. Piling Work


4.5.1. After excavation reached the required depth, piling work will start.
4.5.2. Before piling to peg location of piling whereby 1.5m distance between one pile to
another centre to centre pile as stated in construction drawing.
4.5.3. Finished pegging, piling work will start by using hammer pile method using
mobile crane.
4.5.4. We will carry out 2 points of pile for test with the same size of 230 x 230 mm
square pile. First point will be using 9 m initial and 6 m extension bar and second
point is only using 9 m initial pile.
4.5.5. PDA test will be carried out to test both point to achieve test load of 150 kN, we
will get consultant approval to propose with the balance works.
4.5.6. Next, excess pile will be left out 125mm (Lean con 50 mm, excess pile 75 mm)
from excavated ground level and reinforcement starter bar to be left out for
300mm.

UTIC SERVICES SDN BHD (459079-W)


Head Office Klang Valley
No.12 Crossvent Subang, Jalan Lira U3/41, Pekan Baru Subang
Seksyen U3, 40150 Shah Alam, Selangor, MALAYSIA
Tel: (603) 78327030 Fax: (603) 78327830 www.uticservices.com
5
SHEET PILE

I BEAM

PIPE 375

RAF FOUNDATION

PILE

Figure 1: Diagram of box shoring with steel plate and lay of pipe

UTIC SERVICES SDN BHD (459079-W)


Head Office Klang Valley
No.12 Crossvent Subang, Jalan Lira U3/41, Pekan Baru Subang
Seksyen U3, 40150 Shah Alam, Selangor, MALAYSIA
Tel: (603) 78327030 Fax: (603) 78327830 www.uticservices.com
6
4.6. Concreting work
4.6.1. 50 mm lean concrete will be lay at the base of excavation before laying down 2
layers of A10 BRC.
4.6.2. 2 layers of BRC will be tied out with reinforcement starter bar of pile as shown in
Construction drawing.
4.6.3. Pile raft foundation will use concrete grade 30.

4.7. Pipe Laying

4.7.1. RCP size diameter 375mm will be laid in sequence after 200 mm base concrete
has harden and will continue concreting the remaining raft foundation to desired
height.
4.7.2. Joints on pipe shall be of slip-in type spigot and socket joint and flanged fittings.
4.7.3. All safety measures will be followed to keep the open trench free from accident.

4.8. Backfilling and Compaction


4.8.1. A layer of approved backfilling material i.e. Sand is spread above pipe.
4.8.2. Subsequent layer of approved backfill material is spread and compacted with
roller.
4.8.3. The remaining area shall be filled with compacted approved backfill material up
to bottom of pavement layers.

4.9. Manhole construction


4.9.1. Once invert level confirmed and checked by the surveyor; a 2100mm diameter or
1800 mm diameter of precast concrete chamber will be lowered down by caisson
method as a sleeve and shoring for the manhole.
4.9.2. Next, the concrete base should be lowered down.
4.9.3. Manhole chambering shall be fixed one by one up to the required level including
all the make-up pieces.
4.9.4. Grade 20 concrete shall be used as concrete surround using required sizes steel
mould to hold the chambering as per the drawings.
4.9.5. The completed manhole shall be backfilled and compact up to the required level.

UTIC SERVICES SDN BHD (459079-W)


Head Office Klang Valley
No.12 Crossvent Subang, Jalan Lira U3/41, Pekan Baru Subang
Seksyen U3, 40150 Shah Alam, Selangor, MALAYSIA
Tel: (603) 78327030 Fax: (603) 78327830 www.uticservices.com
7
4.10. Traffic Management
4.10.1. The objective is to minimize inconvenience and prevent potential hazard to the
public.
4.10.2. The road will be temporary closed during the delivery of machineries or
materials. The Scheme 2 will be applied upon loading and unloading of materials
and machineries as per Appendix A. The road will be re-open as soon as
practicable.
4.10.3. The precautions will be implemented as per following:
a) Subcontractors and suppliers adhere to the safety and traffic procedures
set out during the work.
b) Prevent unauthorized personnel parking and congest the traffic.
c) Maintain roads in a clean and safe condition.

4.11. Dewatering

4.11.1. Proper steps will be taken to ensure that all water disposals is done in line with
good engineering practices and is in compliance with local authorities laws.
4.11.2. Proper steps will be taken to ensure that the open cut works are free from water
until completion of works. This can be achieved by continually dewatering from
working area to the water tank.
4.11.3. The water pumps will be arranged sufficiently so that the dewatering process can
be proceeded with no obstruction.

5. SAFETY HEALTH AND ENVIROMENT (SHE)

5.1. Workers are compulsory to wear suitable PPE during working (especially during
handling of cement slurry).

5.2. Entry into the confined space (manhole), if any, shall strictly follow DOSH ICOP
2010 – Industrial code of practice to safe working in a confined space.

5.3. Vehicle, machinery and equipment shall be inspected and to insure in good working
condition prior to use at site.

5.4. If night work is required, site shall be equipped with enough lighting and proper
vehicles arrangement (TMP) to prevent disruption to the existing

UTIC SERVICES SDN BHD (459079-W)


Head Office Klang Valley
No.12 Crossvent Subang, Jalan Lira U3/41, Pekan Baru Subang
Seksyen U3, 40150 Shah Alam, Selangor, MALAYSIA
Tel: (603) 78327030 Fax: (603) 78327830 www.uticservices.com
8

You might also like