Professional Documents
Culture Documents
MS-Pipe Laying by Open Cut (SHEET PILE)
MS-Pipe Laying by Open Cut (SHEET PILE)
1. INTRODUCTION.................................................................................................................. 3
2. LIST OF VEHICLE MACHINERY AND EQUIPMENT..........................................................3
3. MANPOWER....................................................................................................................... 4
4. PROCEDURE...................................................................................................................... 4
4.1. Survey works........................................................................................................... 4
4.2. Removing of trees...................................................................................................4
4.3. Sheet Pile Installation.............................................................................................4
4.4. Excavation of line pipe............................................................................................5
4.5. Piling Work............................................................................................................... 5
4.6. Concreting work......................................................................................................7
4.7. Pipe Laying.............................................................................................................. 7
4.8. Backfilling and Compaction...................................................................................7
4.9. Manhole construction.............................................................................................7
4.10. Traffic Management.............................................................................................8
4.11. Dewatering........................................................................................................... 8
5. SAFETY HEALTH AND ENVIROMENT (SHE)...................................................................8
Generally, this document is developed as a method used for the pipe laying work by using open
trench excavation and the shoring method is by using sheet pile.
3.2. Supervisor
4. PROCEDURE
4.1.1. Before any works are commenced, Licensed Surveyor (LS) should be engaged
to verify the entire dimension and level as shown on drawings.
4.1.2. Data of existing structure such as pipe culvert, retaining wall, drains, road kerb
and underground utilities shall be checked and recorded
4.1.3. A joint survey shall be carried out in the presence of S.O. to confirm any
discrepancy, which may affect to the dimension, level or any part of the works.
4.2.1. Before starting excavation work, trees that is higher than 3m had to be removed
for mobilization of machine purpose.
4.2.2. Tree branches will be cut to the point where there is only trunk and will be cut
using boom lift and chainsaw.
4.2.3. Trees that had been cut will then be planted at a site where it is approved by
MBSA.
4.4.1. The trench for pipe shall be excavated to the requirement depth as per drawing.
4.4.2. Excavated earth shall be stored on one side of the trench for re-use in backfilling.
Temporary shoring of trenches will be using box shoring and steel plate at side of
the box shoring.
4.4.3. Excavation work by using excavator will scoop in between box shoring beam
which have clearance of 5m length in between.
4.4.4. Detail of box shoring is attached at Appendix A.
I BEAM
PIPE 375
RAF FOUNDATION
PILE
Figure 1: Diagram of box shoring with steel plate and lay of pipe
4.7.1. RCP size diameter 375mm will be laid in sequence after 200 mm base concrete
has harden and will continue concreting the remaining raft foundation to desired
height.
4.7.2. Joints on pipe shall be of slip-in type spigot and socket joint and flanged fittings.
4.7.3. All safety measures will be followed to keep the open trench free from accident.
4.11. Dewatering
4.11.1. Proper steps will be taken to ensure that all water disposals is done in line with
good engineering practices and is in compliance with local authorities laws.
4.11.2. Proper steps will be taken to ensure that the open cut works are free from water
until completion of works. This can be achieved by continually dewatering from
working area to the water tank.
4.11.3. The water pumps will be arranged sufficiently so that the dewatering process can
be proceeded with no obstruction.
5.1. Workers are compulsory to wear suitable PPE during working (especially during
handling of cement slurry).
5.2. Entry into the confined space (manhole), if any, shall strictly follow DOSH ICOP
2010 – Industrial code of practice to safe working in a confined space.
5.3. Vehicle, machinery and equipment shall be inspected and to insure in good working
condition prior to use at site.
5.4. If night work is required, site shall be equipped with enough lighting and proper
vehicles arrangement (TMP) to prevent disruption to the existing