You are on page 1of 135

Government of Nepal

National Reconstruction Authority


Central Level Project Implementation Unit (Education)
District Level Project Implementation Unit (Education),Gorkha
Emergency School Reconstruction Project (ESRP), JICA Loan No. : NE-P11
Contract Bills
FINAL INTERIM PAYMENT CERTIFICATE
Period: 15th November 2018 to 10th August 2020
Name of School: Shree Jhimrek Mahipate S. School Payment Voucher no:
Name of Contractor:Sharma-A.M Joint Venture Date of payment:
Contract Number:ESRP/MOE/CLPIU/074/075-GORKHA-15 Page no of measurement book:
Serial no. of previous payment bills:
Voucher no.of previous payment bills:
Date of order for commencement of work: 3rd October,2018
Date of work to be completed: 2nd February,2020
Date of completion of work:
Description Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
%
Item Unit Quantity As Remarks
Rate Amount Quantity Amount Quantity Amount Quantity Amount completion
No. per Contract

GENERAL
1. MOBILIZATION AND DEMOBILIZATION
1 L.S. 1.00 500,000.00 500,000.00 1.00 500,000.00 0.50 250,000.00 0.50 250,000.00 100.00%
Mobilization of the construction by constructing
temporary
2. SITE OFFICE acomodation for labours and site staff with
ESTABLISHMENT Per
2 required 19.00 25,000.00 475,000.00 19.00 475,000.00 14.00 350,000.00 5.00 125,000.00 100.00%
Providingsuitable facilities and
and Maintaining keeping
Site Officetheofsametwo in Rooms Month
good
having hygenic condition
total Area for entire
20 sq.m for the project completion
use of Client and
3. PROJECT INFORMATION BOARD
3 time. Demolition
Consultant of the
including samechair,
office and cleaning the site after
Table, Lockable file nos. 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 - - 100.00%
Providing and Fixing of Project Information board with
completion
cabinet, of the construction
Stationery Items (Ink, activities
Paper, Pen,allPencils
complete.
approved
4. SAFETY TextSIGN in BOARD
appropriate location includingetc.), all
[Note:
1 50% payment
Computer and 1 Printershall be made
with after completion
set up.ofall nos.
4 required
Providingfixing and accessories
Fixing perall
ofas50%
Safety
necessary
drawing
Sign all complete.
Board with
1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 - - 100.00%
mobilization
complete asandper remaining
instruction after
of completion
engineer. ofThe
approved
5. BARRICADING
works Textcontract]
as per and Sinage
WORKS including required fixing
5 Specification of computer shall not be less than (19.5" R.m 179.00 2,000.00 358,000.00 175.00 350,000.00 175.00 350,000.00 - - 97.77%
accessories
Barricading asbetween
per drawing all complete.
led monitor with Core the School
i5, 7th Academic
Generation, 500areagb Hdd,and
Construction
6.
8gb ddr DISMANTLING area with
4 ram), Printer 1.8should
mOF highfunction
CGI Sheet
COMPLETELY fixed of
at least to
6 Bamboo support frame all complete as per instruction sq.m 350.33 3,000.00 1,050,990.00 346.45 1,039,350.00 346.45 1,039,350.00 - - 98.89%
DAMAGED
Printing, Scanning BUILDING and Photocopy of A4 size
of Engineer.
Demolition
documents. of existingand damaged building safelyitemsand
7. SAFETYProvidingMATERIALS Maintaining
& SITE all above
SAFETY
7 handover
on Rental Basis ofandthe reusable
forMaintaining
entire materials
project completionto the time.school L.S. 1.00 100,000.00 100,000.00 1.00 100,000.00 0.81 81,000.00 0.19 19,000.00 100.00%
Providing Construction Safety
authority,
Measures storing
in them to the
Construction Sitelocation
with shown by the
8. RELOCATING OF EXISTING TLCproper Safety
8 school
measures andtodisposing
person and debris
work including
area (Helmet,transportation
Shoes, of sq.m
First 191.28 3,000.00 573,840.00 186.30 558,900.00 186.30 558,900.00 - - 97.40%
Relocating of Existing Temporary Learning Centre
debrisKit,
Aid ,cleaning
Clothing, site Glove,
etc. as Guard per specification
Rail placefor edge and
(TLC),
9. LAB from
TEST(WATERconstruction TEST) site to other by
9 instruction of
protection, Engineer.
Safety Net, existing
Safety rope, Fall Protection etc.) job 1.00 - - - - - - - 0.00%
Demolition
Testing and and using
Providing Lab Testmaterials
Report forobtained
Quality fromof
as requiredof by
demolition TLC the
to theContract
place Clause byGCC SMC.24 and
Water
10. in Water
TEMPORARY Stream TOILET (Up anddecided
Down streem) located
10 Specification
near by Construction
division 1 "GENERAL REQUIREMENT nos.
site toilet
before Starting and fixed
after 2.00 150,000.00 300,000.00 2.00 300,000.00 2.00 300,000.00 - - 100.00%
Construction
CLAUSE 8(C)". of temporary
The number with CGI Sheet
of Safety Materials
completion
to Bamboo ofsupport
constructionframe work.
and This Test has items
all(PPE)
necesary to be
11. ROADProtecting
Personal REPAIR AND MAINTENANCE
Equipments shall be
11 done to
including mark the affect of construction work in water Km. 22.00 50,000.00 1,100,000.00 22.00 1,100,000.00 22.00 1,100,000.00 - - 100.00%
minimum Septic
Providing and not
but pit, Pipeline,
Maintaining
limited to the
35Toilet
roadsPan
sets. as etc.
Payment for
necessary entire
shall to
be
stream.
project completion time
avoid
made in blockage
Prorata by Basis forall
Landslides complete
entire and as of
Rockfall
duration perproject.
Instruction
for regular
of Engineer.
transport Rate shall include
of construction materials alland
Material cost with
site inspection - - - - - #DIV/0!
fixing,
during construction
overall constructioncharges and demolition
period. Rate shall & cleaning
include
CIVIL
of the WORKS-
samecost BUILDING
afterwith completion
all Material demolitionof charges,
the construction
cleaning, - - - - - - - #DIV/0!
activities&allconstruction
fixing complete. charges of the same after
1 EARTH WORKS - - - - - - - #DIV/0!
completion
SITE CLEARANCE of the construction activities all complete.
& MOBILIZATION:
1.1 Clearing and grubbing the site for construction by sq.m 1,110.32 100.00 111,032.00 1,137.14 113,714.12 1,081.28 108,128.25 55.86 5,585.86 102.42%
removing
1.2 EARTHWORK 150mm thick INtop soil including bushes,
EXCAVATION : small
1.2 trees, leveling of undulated ground, shorting and cu.m 490.54 400.00 196,216.00 484.60 193,841.26 427.25 170,898.27 57.36 22,942.99 98.79%
Excavation in foundations in all type of soils for
stacking/storing
foundation, selected toppitssoil forthereuse in
1.3 EARTHtrenches,
landscaping BACKdisposing
works,
footing,
FILLING : etc. tomaterials
unsuitable
required
from cu.m
1.3 depth including dewateringandby manual or mechanical 297.29 300.00 89,187.00 322.21 96,664.27 282.42 84,727.31 39.79 11,936.96 108.38%
Back filling
site, etc., in foundation
allascomplete sides
as per drawings, of foundation with
means
approved etc.soil per specifications
obtained with allspecifications
from the excavation contractor’s
at site and
and
owninstructions
machinery of the Engineer.
stacked at site and equipment's,
or brought from providing
outside incrossing
layer not of
track, shoring,
exceeding 15 cm strutting, timbering and
thick (compacted buttressing
thickness) with
including
appropriate materials
transportation of soil,and all suchinmeasures
spreading required necessary
line and
to retainsprinkling
level, in positionwater, the sides of the foundation
ramming, compactingpitwith and
including
Prepared by contractor refilling the
mechanical rammers, testing, excavated
Checked material
etc., all with watering,
complete as per
by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
ramming,specification
drawing, leveling the andsite and disposing
instructions off the
of the Engineer.
Description Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
%
Item Unit Quantity As Remarks
Rate Amount Quantity Amount Quantity Amount Quantity Amount completion
No. per Contract

1.4 BOULDER SOLING :


1.4 cu.m 158.07 6,000.00 948,420.00 155.08 930,451.08 135.00 809,985.00 20.08 120,466.08 98.11%
Providing and laying uncoursed hand packed Dry
Rubble
1.5 SAND Stone soling in
FILLING : foundation, under floor plinth
1.5 with out any special dressing of stone including filling cu.m 7.40 6,000.00 44,400.00 7.84 47,040.00 - - 7.84 47,040.00 105.95%
Providing and filling sand in soak pit. all complete as
interstices
perCONCRETE with suitable
drawings, specifications quarry and wasteinstruction
or stone chips of theor
2. WORKS
quarry
Engineer. sand, watering, compacting using appropriate
2.1 P.C.C
mechanical compaction means with all contractors
2.1 2.1.1 P.C.C (1:3:6)
materials, handling, placing etc. all complete as per cu.m 23.47 14,000.00 328,580.00 24.05 336,727.56 22.88 320,320.00 1.17 16,407.56 102.48%
Providing and laying machine mixed Plain Cement
drawings, specifications and instruction of the
Concrete of nominal mix 1:3:6 (1 cement : 3 sand : 6
Engineer. The complete item including all lead & lift.
coarse aggregate ) for leveling course in foundations
2.1.2 P.C.C (1:2:4) WORKS
2.1.2 and under floor of building, etc. in all level with broken cu.m 51.60 16,000.00 825,600.00 51.93 830,958.12 31.58 505,280.00 20.35 325,678.12 100.65%
Providing
stone aggregate and laying of size machine
not more mixed thanPlain 25 Cement
mm of
Concrete
P.C.C.ofFOR
approved
2.2 nominal
quality R.C.C. mixWORKS
1:2:4 (1formwork
including cement
: : 2wherever
sand : 4
2.2 coarse aggregate
necessary, and dewatering, ) for leveling course in foundations cu.m 516.67 20,000.00 10,333,400.00 524.40 10,488,023.00 527.94 10,558,747.08 (3.54) (70,724.08) 101.50%
Providing laying inbatching,
position mixing,
machinetransporting,
mixed and
and undercompacting,
placing,
machine floor of building,
vibrated curing,
cement etc.
concrete in alloflevel
including all
mix with
lead broken
and
1:1.5:3 lift,
(1
2.3 SILICA CEMENT ADMIXTURE
stone
2.3 cement:1.5
etc. all aggregate
complete asof3persize not
drawings, more than
specifications 25grademm
and of kg 5,166.70 300.00 1,550,010.00 5,244.02 1,573,206.00 5,279.39 1,583,816.93 (35.37) (10,610.93) 101.50%
sand: coarse
Providing and mixing Silica Cement Admixture aggregate) M20 ofthe
for
in
approved
instructions
reinforced quality
of the Engineer.
cement including formwork wherever
structural
2.4 STEEL concrete at concrete
REINFORCEMENT the rate of work 2.50% usingby weight approved
of the
necessary,
cement for
2.4 cement dewatering,
withpromoting batching,
20 mm workability,
graded machine mixing, transporting,
crushed stone Mt. 82.69 130,000.00 10,749,700.00 83.60 10,868,343.02 81.33 10,573,399.32 2.27 294,943.71 101.10%
Providingcompacting,
and fixing in position all improving
Felead strength,
500andsteel
placing,
aggregate of approved curing,
qualityincluding
inproperties,
various locations lift,
and
achieving
reinforcement waterproofing
ofas per
various diameter confirming bleeding to
2.5
etc. FORM
all complete
heights WORKS
including drawings,
transportation specifications
of concrete to and
site the
of
prevention,
2.5 relevant ISetc.code Silica Cement
in R.C.C. Admixtureworks shall be the
including sq.m 3,542.65 800.00 2,834,120.00 3,616.06 2,892,849.05 3,469.37 2,775,494.00 146.69 117,355.05 102.07%
Supplying
instructions
placing, and
of the
compaction, laying centering,
Engineer.
finished shuttering
to required lineof and various
level,
product of
straightening, Silica Japan
cutting, or superior
bending, bindingand shall
with meet
20 SWGthe
pattern
3. BRICK
protection formworks
MASONRY
and withetc. 19/12
WORKS mm thickaswater proof ply
requirements
annealed ascuring,
mentioned all complete
specificationper
inreinforcement of drawings,
materials
3.1 wood
3.1 & wire
BRICK
specifications
for
steelMASONRY
and
tying theprops
adjustable WORKS
the instructions for all 1kinds
(the
bars at RCC
4 c/sofWorks,
:Engineer,
each
) ONE
and Workmanship,
junctions (binding Division wire shall– 4:ofnotConcrete
be measured
but cu.m 156.82 20,000.00 3,136,400.00 - - - - - - 0.00%
works
SIDE
excluding for
FAIRFACEfoundations,
the cost of centering, shuttering,beams,
columns, shear walls, and
Article
separately)2.4 including all sill,
wastepergola,
and cut pieces, provision
slab,
Providingstaircase,
and
reinforcement,SILICON lintel,
laying first
all complete class selected including
factory
as per drawings, nails,
pressed
CLEAR
for adequate
propping numbers staging,
scaffolding, of spacers, WATER-REPELLANT
chairs, providing
supporting and bracing and
7.2.3 wire
COATNG
placing
cut Fair
specifications
in proper cement
lines
Faceinstructions
and
Providing
mortar
and
brick
level,and(machine
(1:1)
sealing
of
Applyingthemade
covertheblocks
joints
brick)
Engineer.
Water to keep
with
one or
Repellant the
heavy sq.m 749.48 550.00 412,214.00 - - - - - - 0.00%
more
Coating brick thick
on Exposed wall in
Brick cement mortar 1:4 (1 cement :
bars inbrown
duty intended selfinposition
adhesive at Surface
all levels
tape, using Silicone
all complete
aligning lineasBase
to specified per
and
4coarse sand)SH
MC-Nisiwa or,superstructure
equivalent or and other
superior including
drawings,
POINTING
levels specifications
including WORK Ties, IN and
PVC instructions
BRICK Spacer, MASONRY of the
Providing
places in brick all heights and level including thechemical,
cost of
8.1.1 cleaning
Engineer. (Authorized
Providing
openings/
single or and
cutouts/
multi
surface
applying
stage pockets,
using
lap length
selfatstanding
brick
all levels andcleaning
applying for the
Pointing bar
Works
De-shuttering
scaffolding,
length
soakingin sq.m 749.48 400.00 299,792.00 - - - - - - 0.00%
single
exceeding
Cement
chemical, orMortar
multi-stage
10 meter 1:2 in
De-shuttering (1scaffolding,
length
cement shall
:2
as approved etc. all the
be sand)
fine measured
by complete as
forface
onEngineer
the the
bricks,
per curing,
manufacturer's raking joints,
instruction, provision
project for
specificationrecesses,
and
payment,
of brick except
masonry to column).
allwall including mixing
etc.,
BOQ complete
openings,Total
instruction
atitems
ofofthe
toothing levels
3.1.,
etc.,
Engineer.
as
7.2.3
all per
complete8.1.1:asmortar,
&drawing, per drawing,laying
specifications - - - - - - - #DIV/0!
in
andperfect line,
instructions
specifications level
and of theand plumbofand
Engineer.
instructions the finishing
Engineer. in regular
Replaced items 3.1, 7.2.3 and 8.1.1 with following
and even surface ,all complete as per drawing , - - - - - - - #DIV/0!
items for 3-6C(S)-B and T(S)F
specification and instruction of the Engineer.
Brick Masonry Works (1:4 c/s) cu.m 18,000.00 - - - - - - - #DIV/0!
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 - - - - - - - #DIV/0!
Exterior Weather Coat Paint sq.m 350.00 - - - - - - - #DIV/0!
- - - - - - - #DIV/0!
3.2 BRICK MASONRY WORKS ( 1 : 4 c/s )
3.2 cu.m 128.04 18,000.00 2,304,720.00 297.23 5,350,053.25 329.76 5,935,633.52 (32.53) (585,580.27) 232.13%
Providing and laying first class chimney fired brick one
or more
3.3 HALF brickBRICKthick wall in cement
WORKS ( 1mortar
: 4 c/s 1:4) (1 cement
Providing
3.3 : 4 coarse sand) in foundation up to plinth, sq.m 77.44 1,500.00 116,160.00 87.53 131,299.80 23.29 34,929.00 64.25 96,370.80 113.03%
and laying non-fairfaced half brick work masonry in
superstructure
cement mortar and other
1:4BRICK
(1 specified
cement:4 sand) places
in c/s)in all heights
superstructure
HONEY COMB WORKS (1:3
and level
3.4 with approved including the fired
first class cost ofbricks single or multiline
in perfect stage
Providing and laying honey & cu.m 4.52 9,000.00 40,680.00 5.87 52,861.95 5.87 52,861.95 129.95%
scaffolding,
level, required soakingandbricks, atcuring, raking and joints,
comb brick one size shapethick
or more brick any
wallheight
in cement level,
provision
including for costrecesses, openings, multi toothing etc., all
4. DOORS
mortar 1:3the(1&cement
WINDOWSof :single
3 coarse or sand)
WORKS stage
in soakscaffolding,
pit in 4.1
all
4.1 complete
cleaning,and
METAL as
FRAME per drawing,
soaking of the specifications
bricks, packing andofinstructions
the joints, - - - - - - - #DIV/0!
heights level including the cost of soaking bricks,
of the Engineer.
raking joints,
Providing and provision
fixing in position
for recesses,in recesses,
required
openings,line and
curing,
4.1.1 curing, raking
Door pressed
level Frame
providing 25x3mm
joints,
(folded)
provision
GISteel
Straps
for
Fixed towindow
columns
openings,
at every rm. 260.84 1,100.00 286,924.00 260.68 286,748.00 258.08 283,888.00 2.60 2,860.00 99.94%
toothing etc., all complete asdoor
per and
drawing, frame of
4.1.2 size
Window
5th course
shown Frame
of
in brick
drawings and 60mm
manufacture width 14
from gauge
galvanizedwelded rm. 764.58 1,100.00 841,038.00 750.15 825,165.00 722.25 794,475.00 27.90 30,690.00 98.11%
specifications and instructions of the Engineer.
4.2 iron
METAL
GI sheetSHUTTER
mesh anchored
of 1.20 mmtothick GI strap,
including all hinges,
complete jamb,as per - - - - - - - #DIV/0!
design,
lock
WINDOW jamb, drawing,
head,
SHUTTER basespecifications
tiesProviding,
of 1.2 mminstructions
pressed GIand
fabrication of the
4.2.1 welded
Engineer. on rigidly fixed35 together by mechanical means, sq.m 145.87 7,500.00 1,094,025.00 117.39 880,398.38 129.38 970,350.00 (11.99) (89,951.63) 80.47%
installation in position mm thick glazed window and
adjustable
4.3 ventilator
WOODEN lugs
shutter with
SHUTTER split end tail to each
made with 1.2mm thick galvanized jamb - - - - - - - #DIV/0!
including
iron steel
sheetDOORfolded butt
in hinges
required 2.5size
mmand thick
shape with mortar
including
FLUSH SHUTTER (32MM) Providing &
guards, reinforcing
4.3.1 glazing with 5thick to door
mm solid
thick hardware,
clear float door strike-plate,
glass with glazing shock sq.m 99.84 8,000.00 798,720.00 86.70 693,592.80 93.08 744,665.60 (6.38) (51,072.80) 86.84%
fixing 32mm core flush shutters, in
absorbers
beads, as required,
washer and factory
special glazing applied
putty, Zinc Rich Primer
required
single
4.4 UPVC leaf or DOORdouble leaf as per detailed drawing. The
etc., all complete
numbers andshall ashardware
sizesbe per drawings, specification
like hinges, and
tower-bolts,
flush doors factory made solid core block board
4.4.1 4.4.1 SHUTTER/FRAME
instruction
handles, of the Engineer.
eye-hook, applying priming coat with Zinc sq.m 14.28 9,000.00 128,520.00 13.53 121,770.00 13.53 121,770.00 94.75%
shutters bonded with
Providingphenolandformaldehyde
fixing to door resin.
frames The
Rich
lipping Primer
shall of
be approved
of teakwood make, etc.,
all-round all complete
the flush as24
door per
mm thick factory
drawings, specificationmade andPVCinstruction
door shutter of made of
the Engineer.
with a and
styles minimum
rails ofthickness
UPVC hollow of 12mm. sectionThe offollowing
size 59 x 24
C.P. and
mm fittings
wallshall be used:
thickness 2 mm (a) � - 2-150
0.2 mm mmwith Handles
inbuiltin
each leaf;
edging on (b)
bothTower-bolt
sides. The–styles300 mm and long
rails at top 1 and
motred in
each leaf and 200 at bottom in each
jointed at the corners by means of galvanized/plastic leaf; ( c ) 1 no. 300
mm longof
brackets C.P. sizeAldrops
75 x 220 withmmGodrej
havingmade wall padlock;
thickness(d) 1.0
125 mm
mm heavy duty
and stainless
Prepared by contractor GIscrews.
steel ButChecked
Hinges 3by
The styles nos. in the
of eachshutter
Consultant, leaf.
DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
(rate shall include
reinforced by inserting all required
galvanized doortube hardware).
of size 20 x20
Description Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
%
Item Unit Quantity As Remarks
Rate Amount Quantity Amount Quantity Amount Quantity Amount completion
No. per Contract

WINDOW GRILL Providing, MS solid bars of


4.5
required size and fixing in position mild steel grille sq.m 135.08 2,500.00 337,700.00 124.17 310,416.13 108.02 270,050.00 16.15 40,366.13 91.92%
made with required MS flats, strips, bars fabricated as
COLLAPSIBLE GATE
4.6 per drawings, fixing in position using approved sq.m 17.45 10,000.00 174,500.00 17.45 174,500.00 17.45 174,500.00 - - 100.00%
fasteners includingSupplying 2 coat of enamel and fixing andinZinc positionRich local
make collapsible
Primer base coat, gate
etc., ofallapproved
complete size
as and make
detailed in
5. FLOORING WORKS
5.1 properly
drawing, fabricated
HARDENED specification
CEMENT
with and vertical
instructions
CONCETE
doubleofchannels the Engineer. 20 x sq.m 1772.90 900.00 1,595,610.00 1,766.58 1,589,926.46 373.98 336,582.00 1,392.60 1,253,344.46 99.64%
10 x 2mm at 100mm centers and bracedFLOOR with M.S. flat
diagonalCEMENT 20 x 5mm,SKIRTING Providing, laying
with top and bottom rails of T iron in required
NEAT
5.2 line,
-40
level
dox -40
and pattern
xabove,
6mm
asconcrete with
but
40 mm
38mm
for 100 diathick
mm steelIPS floorcomplete
pulleys finish with r.m 941.47 100.00 94,147.00 916.70 91,670.00 205.9 20,590.00 710.80 71,080.00 97.37%
cement
with bolts nuts lockingof mix 1:2:4
arrangements (1 highcement skirting.
: 2 sand
steppers :4
handles
crushed
includingstone
TERRAZZO applyingaggregate
CAST-IN a priming 12SITUmm coat and
DADO ofdown
Zinc Rich grade)Primer laid in
5.3 alternate
Providing
carriage panel or
and laying
hoisting providing
25 mm thick
all complete glass dividing
as perterrazzo strips
specificationcast-in-situand
and sq.m 92.43 1,500.00 138,645.00 89.87 134,803.50 89.87 134,803.50 97.23%
finished
dado
direction with
up toofthe approved
theheight
Engineer. shown in drawing with marbleof
floor hardener (Dreitop FH
6 ROOFING/
equivalent
chips rubbed TERRACING
floorandhardener)
polished applied to WORKS
granolithic as per finish
manufacturer's
under - - - - - - - #DIV/0!
METAL
layer of 19WORKS(TRUSS)
instructions including
mm thick cement mixingconcrete Providing
laying in1:2:4 and (1
required fixing slope, :
cement
6.1 tubular
intrigal kg 5,076.09 220.00 1,116,739.80 5,712.66 1,256,784.37 5,418.93 1,192,163.80 293.73 64,620.56 112.54%
2 sand :roof finishingtrusses
4 crushed usingwithappropriate
stone rafters, purlins,
aggregate power
10 mmwind trowelling
and ties,down
equipment,
brackets
grade) baseetc.,etc.
andmadeall
top complete
with
layer required
of 6asmm pergradedrawing,
thick mild
with steel
required tubes
CGImild SHEET
specification
and ROOFING
steelchips
andsections
instructions
of required of the Providing
sizes,
Engineer. & fixing
color marble
6.2 precoated galvanized of iron
sizes from
profile 1Terracota
mm toincluding
4 mmcolour sq.m 353.64 2,000.00 707,280.00 354.67 709,334.00 354.66 709,324.00 0.00 10.00 100.29%
hoisting,
nominal fixing
size laidininposition
cement with
marble MS bed plates,
powder mix shoe
3:1 (3
sheets
angles, (size,
anchor shape
bolts and pitch
etc., and of corrugation
concrete grouting, as approved
cement
by Engineer): 1 marble powder mix : 7 marble chips) by
CGI
volume SHEET
concreting nut0.52
including ROOFING
bolts, mm
cement
+/- 5%
fabrication,RIDGE
slurry,
total coated
fixing
required and thickness
treated with
pigment,
6.3 (TCT),
twoProviding
coats
grinding,
Base Material
& laying
of anticorrosive
polishing,
Thickness
buffing prefinished
paints
and
(BMT)plainof(colour
all complete
applying
0.50
sealer
mm,
as coat,
per rm. 35.85 1,200.00 43,020.00 35.85 43,020.00 35.85 43,020.00 - - 100.00%
Zinc coating
matching
drawings, to 120gsmsheet)
roofing
specifications as perand CGIIS: 277
Sheet
instructions , 5-7Ridge microns
of Cover
the epoxy
of
etc., allon
primer complete
both side as ofperthe drawing,
sheet and specification
polyester andcoat
top
0.52
GI mm +/-
Engineer.
FACIA
instruction Rate
of 5%
(EAVES)
the total
shallEngineer.coated
include
Providing, thickness
preparing (TCT),
shop
fabrication toBase
drawings,
required
6.4 15-18
Material microns. Sheet should ofhave protective guard film kg 278.04 250.00 69,510.00 314.04 78,510.78 330.75 82,686.41 (16.70) (4,175.63) 112.95%
size and Thickness
obtaining Engineer's
shape and (BMT) or
fixing Client's
in 0.50 mm1.2
approval,
position (Coating
supplying,
mm thick and GI
of 25
Primer microns
fabricating, as above) minimum
delivering over ridgeto avoid
with
at site, hoisting scratches
all required while
and including fixing
fixing in the
folded
CEMENT plates BOARD of sizeFALSE shown in drawing
CEILING
transportation
accessories
position, like
temporary andself should
tapping
staging, be supplied
screw,
preparation clips,in single
clamps,
of surface, length
6.5 cost
up
fixing
toProviding
6 meter
brackets,
orandas fixing
flats,atscrews,
desired byall height
Engineer.
painting
6 mmThe
with
thickenamel shall sq.m 320.71 1,600.00 513,136.00 338.23 541,168.00 335.989 537,582.40 2.24 3,585.60 105.46%
washer
applying
with Zincetc.all
Richcomplete
Zinc Rich
Primer,Primer on building
ofincluding
required one floors
coat before
scaffolding as sheet
per
andwork
to one at
Cement
be fixed Board
using false
self ceiling,
drilling /self tapping providing
screws ofandsize
design,
coat
any
7. afterdrawing,
height,
PLASTERING/ erection
etc., specifications
including
all complete
WALL two instructions
as
FINISHING coats
per of
design, of the
synthetic
WORKS drawing,
fixing
(5.5x of frame
55mm) withwork EPDM madeseal of special
etc., all sections
complete powerup to
Engineer.
enamel paint
specifications of approved
instructions make
of 7.1theand colorzinc
Engineer. etc.PLASTER
all
7.1 pressed
any pitchfrom
complete
MS
in horizontal/
as perangle
sheet Galvanized
drawing, vertical
specification orCEMENT
with
curved andsurfaces
coating
instruction - - - - - - - #DIV/0!
WORKS
and consisting
excluding the cost of hanger
purlins, ofrafters
25x25x0.55 and of required
trusses and
of the Engineer.
length at 1250mm
including cutting toc/c sizefixedandtoshape purlins with nut
wherever ans bolts
required.
ON
and INNER
other end WALL
of angle (1:6)
hanger being fixed with nut and sq.m
7.1.1 1764.21 600.00 1,058,526.00 1,397.21 838,324.20 1,201.36 720,817.20 195.85 117,507.00 79.20%
bolts to GI main Providing channel and45x18x0.6
applying atrunning all levels at the andrate
shape
of 900mm
ON 20
CEILING mm thick
c/c to(1:4) which ceiling section 0.55mm thickin
cement plaster in building inside
7.1.2 specified
bottom wedge cement of mortar
45mm in two layers as 6 plaster
to 8ofmm sq.m 843.48 500.00 421,740.00 1,001.66 500,831.90 629.30 314,650.20 372.36 186,181.70 118.75%
12.5.mm, thickwith cement tapered and sand flanges 26mmwork
thick
each
of mix final
having coat
(1clips
1:4OUTER with
cement 1:6
ofWALL & 4(1sand)
2.3mm cement
at 613mm :6 fine
in concrete with sand)
ceiling
surface, cement
7.1.3 ON (1:6):
mortar
section
7.1.3.1 ceiling over
surface theat12alltoheight
and perimeter 14 mmincluding
channels thick 1:6mixing
of 0.5mm (1 cement
thick 25mm
mortar, :6 sq.m 875.99 600.00 525,594.00 1,745.33 1,047,197.09 1,518.64 911,182.05 226.69 136,015.04 199.24%
EXTERNAL PLASTER
coarse
high having
laying sand)
in perfectunder
flanges line,coat
ofand in all
20mm
level and surface
andplumb 30mm atand
alllong,
height
finishingthe
Providing applying at all levels and in
including
perimeter
regular mixing
ofevenceiling mortar, laying
fixedincluding
toplaster in
wall/partition perfect line, level
withexterior
the help
INTERNAL
shape 20and mm PALSTER
thick surface
cement ON WALL allbuilding
in necessary
(1:4)WITH single
7.1.4 and
of rawplumb
or specifiedplugsand
multi-stage
CEMENT
in PUNNING
cement
finishing
atscaffolding,
450mm mortar c/cin providing
regular
with
with
and
finished
1:6 (1and
even
25mm
fixing
cement
surface
:6long
200
12.5.mm, fine sq.m 36.14 700.00 25,298.00 35.65 24,955.00 35.65 24,955.00 98.64%
including
drive
mm
thick all
wide
cement all gauge
screws
24 necessary
and @ 230mm
sandGI single
plaster
Chicken or
interval,
work multi-stage
wire jointing
ofmeshmix at
1:4and
junction
(1 fixing of
sand) in all surface at all height including mixing
scaffolding,
7.2 cement
PAINTING
to in required making
WORKS
pattern, grooves
finished and with recesses,
recommended throating, - - - - - #DIV/0!
R.C.C.
mortar, and
& 4 masonry,
laying sand) and
in perfect making
3 mm line,thickgrooves
level cement
and andplumbrecesses,
punning and filler,
over
dusting,
makingfor dripping,
openings wetting,
for light curing,
fittings, protection,
access panel, providing
DISTEMPER
throating,
plaster
finishing industing,
water PAINT
regular dripping,
tank,Septic
and even wetting,
tank,Man
surface curing,
hole
including e.t.c allcutouts
protection,
on
7.2.1 chicken
made
etc. allwith
concrete wire mesh
frameor
Providing
complete
surface, as at the
ofmulti-stage
perimeter
anddrawing
per
ceiling junction
applying
surface channels
,andof concrete
twowall orsuitably
specification more
surface andandfixed
coats at allof sq.m 2897.52 200.00 579,504.00 2,737.10 547,420.16 2,737.10 547,420.16 94.46%
necessary single scaffolding, making
masonry
all complete
washable
instruction.
height etc.,
including asallper
distemper
[Rate complete
drawing
mixing paint
shall also ofasinclude
mortar,and perspecification
approved drawing
laying , specification
formanufacturer
providing
in perfect and line,dripsand
grooves
EXTERIOR and recesses,
WEATHER throating, COAT dusting,
PAINT dripping,
and
shade
band,
level instruction
direction over
and
moulds,of athe
plumb coat of thealkali
Engineer
of
groove,
and Engineer.
finishing but
chicken resistant [Rate
excluding
inwire shall
cement
regular
mesh the
and also
atcost
primer
junction
even include
of of of
7.2.2 wetting,
for providing
curing, protection,
dripsallband, Providing providing and chicken
applying wire
two or sq.m 1280.46 350.00 448,161.00 1,745.33 610,865.24 1,745.33 610,865.24 136.30%
painting.
approved
RCC
mesh and
surface manufacturer
masonry,
at including
the junction etc., astomoulds,
necessary
of per
concrete singlegroove,
manufacturer's
complete the
andpercentor works
masonry
chicken
multi-stage at any
etc.,
wire
all
more coats
mesh at junction
specifications
heights.
scaffolding, of first
to the
providing quality
of RCC surface
, hundred
andofmasonry,
making wall,
grooves etc.,
ceiling,and acrylic
to complete
beams
recesses, paint
complete
ENAMEL
of approved asPAINT
per drawing , specification and instruction
the at shade
workscanopies, and
any heights]. pattern to the exterior walls of
7.2.4 columns,
throating,
of the Engineer.
buildings
dusting,
Providing
etc., The [Rate
and
staircase,
dripping,
rates shall
applying
shall
lobbies
wetting,
also by
includeinclude etc.,for
curing,
spray/brush
allproviding
for scrapping
complete
protection,
two or , sq.m 743.97 400.00 297,588.00 690.19 276,077.18 690.19 276,077.18 92.77%
as
etc.per
drips drawings,
allband,
completemoulds, specifications
as per
groove,drawing chickenand instruction.
, specification
wire mesh The
and
at
more
washing coats the of 1st
surface quality
with synthetic
water, enamel
applying a paint
coat of
of
8 rates
junction shall
instruction.
MISCELLANEOUS include
[Rateand
ofmanufacturer
RCC for
shall scraping,
also
masonry, include washing
etc., for
to the
providing
complete surface thedrips - - - - - - - #DIV/0!
approved
approved quality water (Asian,
base Berger or equivalent)
with
band,
works
over
water,
moulds, surface
at anyBOARD
wooden orgroove,
heights. preparation,
metalWALL etc.,
surface tocement
complete primer,
scaffolding
requiredthe
in complete
surface
etc.,
works
shade
allat
CEMENT
preparation,
complete
any heights. scaffolding
as per etc., all
the manufacturer's as perattheany
recommendations
8.2 height, shape, including surface preparation,
Supplying, sq.m 22.01 6,500.00 143,065.00 31.22 202,930.00 16.28 105,820.00 14.94 97,110.00 141.84%
manufacturer's
and as approvedrecommendations by the Engineer.fabrication, and as approved fixing by of
fillers/putty,
cement
the Engineer. boardscaffolding,
in position for protection
internaletc. andall complete
external made as
per drawings, specifications and instructions. The
RAILING
8.3 with 9mm thick cement board (Shera or Siam Cement kg 3,086.12 220.00 678,946.40 3,120.80 686,576.32 2,685.95 590,909.01 434.85 95,667.32 101.12%
finished
Board orsurface
Providing, shall from
fabrication
equivalent) give
as per even
both designand drawings
sides uniform
fixed tosurface. and X
75mm
installation
0.6mm
PUMP thick SHED inC-stud
position fixedMild to Steel
U-Track railingwithinspacing
staircase,
8.4 verandah
300mm o/c and ofother
horizontalareas including
frame, cutting
central coretofilledrequired with nos 1.00 80,000.00 80,000.00 1.00 80,000.00 1.00 80,000.00 100.00%
Supply, fabrication, installation of 2mx1.5m and 1m
shape
cement
high and
pump size,
mortar shedwithwelding
made PEwith joints,
granules50x50x6 installation
having MScombined of base
Angle frame ,
anchor
density plates
covered outside of and
approximately appropriate
roof900 size
kg/m3,
with CGI with required
including
sheet, numbers
sealing
locakable
of expansion
joints
door, with fiber
including bolts tapes
pad oflock,
required
andbase jointsize,
PCCsealing providing
(1:2:4)compound,
75mm required all
size
fillingbends,
screw finishing
heads as weld
per joints
manufacturer's
complete as per design, drawing, and instructions of the to produce smooth
installation
surface,
guidelines,
Engineer. applying
sealingone coat of gaps
perimeter Metalwith Primer siliconandsealant,
two or
more
etc., allcoats of enamel
complete as per paint of required
drawing, shade, etc.,
specifications andall
complete
instructions as ofperthe drawings,
Engineer. specifications
Rate shall include and instruction
the cost
of the Engineer.
metal framing, joint and screw head sealing, required
Prepared by contractor
additional strengthening member Checked forby theConsultant,
wall length DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
exceeding 3 meter in length or around door and window
Description Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
%
Item Unit Quantity As Remarks
Rate Amount Quantity Amount Quantity Amount Quantity Amount completion
No. per Contract

SEWER, RAIN AND WASTE WATER


INSTALLATION
8.5 PVC SWR (Soil, Waste, Rain) pipes with all necessary rm. 44.80 1,500.00 67,200.00 41.80 62,700.00 0.00 - 41.80 62,700.00 93.30%
ring gaskets, PVC fittings, including MS clamps,
hangers, cutting, jointing, sealing, installation of pipes
and specials including making holes and cutting - - - - -
grooves
BILL NO. on 3.
walls or floor and repairing
ELECTRICAL WORKSthe same to its - - - - - #DIV/0!
A original
A. Common finish.Installation
Pipes to be installed on trenches or walls - - - - - #DIV/0!
1.1 or floorAlone
Stand or duct
40 asA per
DP drawings,
MCB withspecifications,
Enclosure No 2 12,000.00 24,000.00 2.00 24,000.00 2.00 24,000.00 100.00%
manufacturer's recommendations, instructions, cleaning
1.2 Stand Alone 6 A DP MCB with Enclosure No 2 8,500.00 17,000.00 2.00 17,000.00 2.00 17,000.00 100.00%
of the system, testing and ready for operation. The rate
shall include for all labour and materials required. The - - - - - #DIV/0!
2 Cables and Wires
measurement shall be done for running meters, fittings - - - - - #DIV/0!
2
etcNos
not10 Sq mmseperately.
payable Multistranded Cu Wire + 1 No 6 Sq
2.1 mm Multistranded Cu wire Rm 100 800.00 80,000.00 90.00 72,000.00 90.00 72,000.00 90.00%
- 110 mm ED 6 kg/sqcm
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq
2.2 Rm 95 250.00 23,750.00 90.00 22,500.00 90.00 22,500.00 94.74%
mm Multistranded Cu wire
- - - - - #DIV/0!
B SCHOOL BLOCKS - - - - - #DIV/0!
1 DISTRIBUTION BOARDS - - - - - #DIV/0!
DB (DB-1) Incoming: 1 x 40A DP MCB Outgoing:
1.1 2 x 25 A DP MCB 7 x 6 A SP MCB 3 x 16 A SP MCB No 1 30,000.00 30,000.00 1.00 30,000.00 1.00 30,000.00 100.00%

DB (DB-1) Incoming NEA: 1 x 40A DP MCB


Incoming Solar: 1 x 16A DP MCB Outgoing NEA: 1 x
1.2 16 A DP MCB 2 x 25 A DP MCB 2 x 16 A SP MCB 6 No 1 30,000.00 30,000.00 1.00 30,000.00 1.00 30,000.00 100.00%
x 6 A SP MCB
DB ( DB-2) & DB ( DB-3) Incoming:
1.3 1 x 25A DP MCB No 1 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 100.00%
DB ( DB-2) Incoming NEA: 1 x 25A DP MCB
1.4 Incoming Solar: 1 x 10A DP MCB O No 1 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 100.00%
DB ( DB-3) Incoming NEA: 1 x 25A DP MCB
1.5 Incoming Solar: 1 x 10A DP MCB No 1 22,000.00 22,000.00 1.00 22,000.00 1.00 22,000.00 100.00%
1.6 6A DP MCB with Enclosure No 2 8,500.00 17,000.00 2.00 17,000.00 2.00 17,000.00 100.00%
- - - - - #DIV/0!
2 CABLES & WIRES - - - - - #DIV/0!
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq
2.1 mm Multistranded Cu wire Rm 10 600.00 6,000.00 10.00 6,000.00 10.00 6,000.00 100.00%
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq
2.2 mm Multistranded Cu wire Rm 20 500.00 10,000.00 10.00 5,000.00 10.00 5,000.00 50.00%
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq
2.3 Rm 60 250.00 15,000.00 60.00 15,000.00 60.00 15,000.00 100.00%
mm Multistranded Cu wire
- - - - - #DIV/0!
3 General service light point wiring - - - - - #DIV/0!
3.1 One way light point Pts 123 700.00 86,100.00 122.00 85,400.00 122.00 85,400.00 99.19%
3.2 Two Way Light Point Pts 3 900.00 2,700.00 3.00 2,700.00 3.00 2,700.00 100.00%
3.3 Ceiling and Exhaust Fan Point Wiring Pts 4 900.00 3,600.00 4.00 3,600.00 4.00 3,600.00 100.00%
4 6A Universal pin Light power point wiring Pts 127 900.00 114,300.00 128.00 115,200.00 128.00 115,200.00 100.79%
- - - - - #DIV/0!
5 Switch Socket Outlets - - - - - #DIV/0!
5.1 6A Universal power Switch Socket No 127 700.00 88,900.00 128.00 89,600.00 128.00 89,600.00 100.79%
6 Sweep Ceiling/Exhaust Fan/Wall Fan - - - - - #DIV/0!
6.1 225 mm dia M/D exhaust fan No 4 6,000.00 24,000.00 4.00 24,000.00 4.00 24,000.00 100.00%
- - - - - #DIV/0!
7 Light Fixtures/Luminaires & Accessories - - - - - #DIV/0!
7.1 24 W LED Surface Mounted Square type Nos. 6 4,500.00 27,000.00 6.00 27,000.00 6.00 27,000.00 100.00%
7.2 24 W LED Reccesed Mounted Square type Nos. 6 4,500.00 27,000.00 6.00 27,000.00 6.00 27,000.00 100.00%
7.3 18 W LED Surface Mounted Square type Nos. 52 2,700.00 140,400.00 52.00 140,400.00 52.00 140,400.00 100.00%

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Description Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
%
Item Unit Quantity As Remarks
Rate Amount Quantity Amount Quantity Amount Quantity Amount completion
No. per Contract
7.4 18 W LED Recessed Mounted Square type Nos. 4 2,700.00 10,800.00 4.00 10,800.00 4.00 10,800.00 100.00%
7.5 12 W LED Surface Mounted Cylindrical type Nos. 30 2,400.00 72,000.00 30.00 72,000.00 30.00 72,000.00 100.00%
7.6 12 W LED Recessed Mounted Cylindrical type Nos. 8 2,400.00 19,200.00 8.00 19,200.00 8.00 19,200.00 100.00%
7.7 LED Wall Light made Nos. 4 1,800.00 7,200.00 4.00 7,200.00 4.00 7,200.00 100.00%
7.8 9 W LED Surface Mounted Cylindrical type Nos. 2 2,000.00 4,000.00 2.00 4,000.00 2.00 4,000.00 100.00%
7.9 6 W LED Recessed Circular type C Nos. 6 1,800.00 10,800.00 6.00 10,800.00 6.00 10,800.00 100.00%
7.10 7 W LED T5 Slim Mirror Light Nos 2 2,000.00 4,000.00 2.00 4,000.00 2.00 4,000.00 100.00%
8 Pull Box No 6 700.00 4,200.00 6.00 4,200.00 6.00 4,200.00 100.00%
9 External post top light pole No 6 7,500.00 45,000.00 6.00 45,000.00 6.00 45,000.00 100.00%
10 Post Top External Light Fixtures No 6 9,800.00 58,800.00 6.00 58,800.00 6.00 58,800.00 100.00%
- - - - - #DIV/0!
11 Earthing and Lightning protection - - - - - #DIV/0!
11.1 11.1. Chemical Earhting Nos. 6 45,000.00 270,000.00 6.00 270,000.00 6.00 270,000.00 100.00%
11.2 Earthing Bar Nos. 6 2,200.00 13,200.00 6.00 13,200.00 6.00 13,200.00 100.00%
GI Strip/Cu wire Earthing
12.1 12.1. 25 x 3 mm GI Strip Mtr. 130 300.00 39,000.00 127.00 38,100.00 127.00 38,100.00 97.69%
12.2 12 SWG Cu wire Mtr. 30 200.00 6,000.00 28.00 5,600.00 28.00 5,600.00 93.33%
13 Earth Test link No 2 1,500.00 3,000.00 2.00 3,000.00 2.00 3,000.00 100.00%
14 Lightning Arrester No. 1 7,500.00 7,500.00 1.00 7,500.00 1.00 7,500.00 100.00%
- - - - - #DIV/0!
C SOLAR PV SYSTEM - - - - - #DIV/0!
1. Solar PV Panel
1.1 1.1. 24V 250W PV Module No 8 26,000.00 208,000.00 8.00 208,000.00 8.00 208,000.00 100.00%
2. Tubular Deep cycle Battery
2.1 2.1. 12V, 200Ah@C10 Tubular Solar Battery No 4 30,000.00 120,000.00 4.00 120,000.00 4.00 120,000.00 100.00%
3 Hybrid Inverter No 1 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 100.00%
FIRE EXTINGUISHER
a) Supplying Fire extinguisher ABC stored Pressure
D 5.0kg size ABC stored pressure type Fire extinguisher. Nos. 6 8,000.00 48,000.00 6.00 48,000.00 6.00 48,000.00 100.00%

- - - - - #DIV/0!
Bill No. 4 Sanitary Works - - - - - #DIV/0!
A Piping Works - - - - - #DIV/0!
1 WATER SUPPLY INSTALLATION - - - - - #DIV/0!
a CPVC pipes SDR-11 - - - - - #DIV/0!
40 mm r.m 152.00 1,600.00 243,200.00 150.00 240,000.00 150.00 240,000.00 98.68%
20mm r.m 22.00 1,000.00 22,000.00 22.00 22,000.00 22.00 22,000.00 100.00%
15mm r.m 8.00 700.00 5,600.00 7.00 4,900.00 7.00 4,900.00 87.50%
c CPVC Ball Valve - - - - - #DIV/0!
40 mm nos. 5.00 2,000.00 10,000.00 5.00 10,000.00 5.00 10,000.00 100.00%
25 mm nos. 2.00 900.00 1,800.00 2.00 1,800.00 2.00 1,800.00 100.00%
d Electrical Centrifugal Water Pump nos. 1.00 12,500.00 12,500.00 1.00 12,500.00 1.00 12,500.00 100.00%
e 2000 litres Capacity Water Storage Tank nos. 1.00 3,400.00 3,400.00 1.00 3,400.00 1.00 3,400.00 100.00%
2 Sewer, Rain and Waste Water Installation - - - - - #DIV/0!
110 mm r.m 43.00 1,400.00 60,200.00 40.00 56,000.00 40.00 56,000.00 93.02%
75mm r.m 49.00 1,200.00 58,800.00 50.00 60,000.00 50.00 60,000.00 102.04%
50mm r.m 22.00 350.00 7,700.00 21.00 7,350.00 21.00 7,350.00 95.45%
- - - - - #DIV/0!
B School Blocks - - - - - #DIV/0!
1 Sanitary Installation - - - - - #DIV/0!
a Lab Sink set 5.00 30,000.00 150,000.00 5.00 150,000.00 5.00 150,000.00 100.00%
b PVC Multi Floor Trap nos. 10.00 600.00 6,000.00 10.00 6,000.00 10.00 6,000.00 100.00%
- - - - - #DIV/0!
2 Sanitary Installation - - - - - #DIV/0!
a Water Closet Set set 2.00 34,000.00 68,000.00 2.00 68,000.00 2.00 68,000.00 100.00%
b Orissa Pan set 4.00 3,100.00 12,400.00 4.00 12,400.00 4.00 12,400.00 100.00%

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Description Bill of Quantities Up to Date of work till now Previous Bill Currently Accomplished work
Pay
%
Item Unit Quantity As Remarks
Rate Amount Quantity Amount Quantity Amount Quantity Amount completion
No. per Contract
c Hand Wash Basin set 2.00 8,000.00 16,000.00 2.00 16,000.00 2.00 16,000.00 100.00%
d Ladies Urinal set 2.00 110,000.00 220,000.00 2.00 220,000.00 2.00 220,000.00 100.00%
e Self Closing Bib Cock nos. 12.00 4,000.00 48,000.00 12.00 48,000.00 12.00 48,000.00 100.00%
f CP Spreader in Urinal set 4.00 2,500.00 10,000.00 4.00 10,000.00 4.00 10,000.00 100.00%
g Toilet Paper Holder nos. 2.00 2,600.00 5,200.00 2.00 5,200.00 2.00 5,200.00 100.00%
h Commode Spray nos. 2.00 2,000.00 4,000.00 2.00 4,000.00 2.00 4,000.00 100.00%
i PVC Multi Floor Trap nos. 10.00 600.00 6,000.00 10.00 6,000.00 10.00 6,000.00 100.00%
j Waste Coupling and PVC Bottle Trap nos. 4.00 1,500.00 6,000.00 4.00 6,000.00 4.00 6,000.00 100.00%
k 40mm SS Grab Bar-Side nos. 2.00 4,500.00 9,000.00 2.00 9,000.00 2.00 9,000.00 100.00%
l 40mm SS Grab Bar-Rear nos. 2.00 4,500.00 9,000.00 2.00 9,000.00 2.00 9,000.00 100.00%
m CP Foldable Hinge nos. 4 5,500.00 22,000.00 4.00 22,000.00 4.00 22,000.00 100.00%
- - - - -
CIVIL WORKS - SITE DEVELOPMENT - - - - -
1 SITE CLEARANCE & MOBILIZATION: sq.m 149.07 100.00 14,907.00 220.18 22,018.00 220.18 22,018.00 147.70%
2 EARTHWORK IN EXCAVATION : cu.m 3079.63 400.00 1,231,852.00 126.16 50,464.81 126.16 50,464.81 4.10% 1,181,387.20
3 EARTH BACK FILLING : cu.m 245.00 300.00 73,500.00 56.15 16,844.22 56.15 16,844.22 22.92% 56,655.78
4 BOULDER SOLING : cu.m 56.98 6,000.00 341,880.00 46.54 279,232.19 46.54 279,232.19 81.68%
5 P.C.C (1:3:6) WORKS cu.m 7.23 14,000.00 101,220.00 7.54 105,610.40 7.54 105,610.40 104.34%
6 P.C.C (1:2:4) WORKS cu.m 24.08 16,000.00 385,280.00 28.87 461,857.78 28.87 461,857.78 119.88%
7 P.C.C. FOR R.C.C. WORKS : cu.m 0.99 20,000.00 19,800.00 0.99 19,766.20 0.99 19,766.20 99.83%
8 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 2,970.00 9.88 2,964.93 9.88 2,964.93 99.83%
9 STEEL REINFORCEMENT Mt. 0.10 130,000.00 13,000.00 0.10 13,343.25 0.10 13,343.25 102.64%
10 FORM WORKS sq.m 9.12 800.00 7,296.00 30.32 24,256.00 30.32 24,256.00 332.46%
11 STONE MASONRY WORKS (1:6 c/s) cu.m 117.07 10,000.00 1,170,700.00 84.68 846,754.50 84.68 846,754.50 72.33% 323,945.50
13 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 0.22 18,000.00 3,960.00 0.72 13,032.72 0.72 13,032.72 329.11%
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 472.00 4.40 440.00 4.40 440.00 93.22%
15 METAL WORKS FOR FENCE k.g 2726.47 220.00 599,823.40 2,707.00 595,539.12 2,707.00 595,539.12 99.29%
16 METAL WORKS FOR GATE k.g 130.78 220.00 28,771.60 123.31 27,128.09 123.31 27,128.09 94.29%
17 PLASTER ON OUTER WALL (1:6) sq.m 7.92 600.00 4,752.00 7.80 4,679.04 7.80 4,679.04 98.46%
18 EXTERIOR WEATHER COAT PAINT sq.m 8.87 350.00 3,104.50 8.27 2,895.20 8.27 2,895.20 93.26%
19 CHAIN LINK FENCE (50 x 50 MESH) sq.m 370.74 1,000.00 370,740.00 380.40 380,400.00 380.40 380,400.00 102.61%
20 FLAG POLE nos. 2.00 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00 100.00%
21 50 DIA PVC WEEP PIPE sq.m 58.10 100.00 5,810.00 13.20 1,320.00 13.20 1,320.00 22.72%
22 GEOTEXTILE FABRIC sq.m 57.31 200.00 11,462.00 36.32 7,263.68 36.32 7,263.68 63.37%
- - - - -
CIVIL WORKS-RESERVOIR TANK - - - - -
1 EARTH WORK - - - - -
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 2,231.00 22.31 2,231.00 22.31 2,231.00 - - 100.00%
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 9,832.00 24.57 9,828.72 24.57 9,828.72 - - 99.97%
1.3 EARTH BACK FILLING cu.m 4.02 300.00 1,206.00 4.01 1,202.85 4.01 1,202.85 - - 99.74%
1.4 BOULDER SOLING cu.m 2.08 6,000.00 12,480.00 2.08 12,462.00 2.08 12,462.00 - - 99.86%
2 CONCRETE WORKS - - - - -
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 10,920.00 0.78 10,904.25 0.78 10,904.25 - - 99.86%
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 148,400.00 7.41 148,295.00 7.41 148,295.00 - - 99.93%
2.3 SILICA CEMENT ADMIXTURE kg 74.2 300.00 22,260.00 74.15 22,244.25 74.15 22,244.25 - - 99.93%
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 189,800.00 1.47 191,574.92 1.47 191,574.92 - - 100.94%
2.5 FORMWORKS sq.m 54.93 800.00 43,944.00 54.67 43,738.00 54.67 43,738.00 - - 99.53%
3 PLASTERING/WALL FINISHING WORKS - - - - -
INTERNAL PLASTER ON WALL (1:4) WITH
3.1.1 sq.m 33.66 700.00 23,562.00 33.66 23,565.25 33.66 23,565.25 - - 100.01%
CEMENT PUNNING
4 WATERPROOFING WORKS sq.m 33.66 550.00 18,513.00 33.66 18,515.55 33.66 18,515.55 - - 100.01%
- - #DIV/0!
Furniture Works lot 1 5,300,000.00 5,300,000.00 1.00 5,300,000.00 1.00 5,300,000.00 100.00%
Total 64,188,296.70 62,553,688.88 46,798,426.13 15,755,262.74

Prepared by contractor Checked by Consultant, DSC Verified by (Engineer), DLPIU Recommended by DLPIU Chief Checked and forwarded by CLPIU DPD Approved by CLPIU, project Director
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block, 3-9C(XS)-A, 2LiAC(S1), Tc(S)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
Abstract of Cost - Civil Works
Type Design
Pay
Quantity in Total
Item Description of Works Unit Rate (NRs.) Site Amount Remarks
BOQ 3-12C(MsF)-D 2-LaLi-EC Tc(S) Water Tank Quantity
No. Development
GENERAL
1 MOBILIZATION AND DEMOBILIZATION L.S. 1.00 500,000.00 1 500,000.00
2 SITE OFFICE ESTABLISHMENT Per Month 19.00 25,000.00 19.00 475,000.00
3 PROJECT INFORMATION BOARD nos. 1.00 10,000.00 1.00 10,000.00
4 SAFETY SIGN BOARD nos. 1.00 10,000.00 1.00 10,000.00
5 BARRICADING WORKS R.m 179.00 2,000.00 175 350,000.00
6 DISMANTLING OF COMPLETELY DAMAGED BUILDING sq.m 350.33 3,000.00 346.45 1,039,350.00
7 SAFETY MATERIALS & SITE SAFETY L.S. 1.00 100,000.00 1 100,000.00
8 RELOCATING OF EXISTING TLC sq.m 191.28 3,000.00 186.30 558,900.00
9 LAB TEST(WATER TEST) job 1.00 0.00 -
10 TEMPORARY TOILET nos. 2.00 150,000.00 2.00 300,000.00
11 ROAD REPAIR AND MAINTENANCE Km. 22.00 50,000.00 22.00 1,100,000.00

CIVIL WORKS- BUILDING -


1 EARTH WORKS -
1.1 SITE CLEARANCE & MOBILIZATION: sq.m 1,110.32 100.00 500.25 401.89 235.001 1,137.14 113,714.12
1.2 EARTHWORK IN EXCAVATION : cu.m 490.54 400.00 250.56 149.66 84.39 484.60 193,841.26
1.3 EARTH BACK FILLING : cu.m 297.29 300.00 147.01 108.14 67.07 322.21 96,664.27
1.4 BOULDER SOLING : cu.m 158.07 6,000.00 82.05 53.76 19.26 155.08 930,451.08
1.5 SAND FILLING : cu.m 7.40 6,000.00 4.91 2.93 7.84 47,040.00
2. CONCRETE WORKS
2.1 2.1 P.C.C cu.m 23.47 14,000.00 15.19 336,727.56
2.1.1 P.C.C (1:3:6) 6.05 2.82 24.05
2.1.2 P.C.C (1:2:4) WORKS cu.m 51.60 16,000.00 22.41 19.51 10.01 51.93 830,958.12
2.2 P.C.C. FOR R.C.C. WORKS : cu.m 516.67 20,000.00 368.73 127.78 27.89 524.40 10,488,023.00
2.3 SILICA CEMENT ADMIXTURE kg 5,166.70 300.00 3,687.32 1,277.80 278.90 5,244.02 1,573,206.00
2.4 STEEL REINFORCEMENT Mt. 82.69 130,000.00 58.05 21.92 3.63 83.60 10,868,343.02
2.5 FORM WORKS sq.m 3,542.65 800.00 2,445.82 947.41 222.83 3,616.06 2,892,849.05
3. BRICK MASONRY WORKS
3.1 3.1 BRICK MASONRY WORKS ( 1 : 4 c/s ) ONE SIDE cu.m 156.82 20,000.00 -
FAIRFACE 0.00
7.2.3 CLEAR SILICON WATER-REPELLANT COATNG sq.m 749.48 550.00 0.00 -
8.1.1 POINTING WORK IN BRICK MASONRY sq.m 749.48 400.00 0.00 -
BOQ Total of items 3.1., 7.2.3 & 8.1.1: 0.00 -
Replaced items 3.1, 7.2.3 and 8.1.1 with following items for 3-
6C(S)-B and T(S)F -
0.00
Brick Masonry Works (1:4 c/s) cu.m 18,000.00 0.00 -
Cement Plaster Works on Outer Wall (1:6) sq.m 600.00 0.00 -
Exterior Weather Coat Paint sq.m 350.00 0.00 -
0.00 -
3.2 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 128.04 18,000.00 160.34 89.26 47.63 297.23 5,350,053.25
3.3 HALF BRICK WORKS ( 1 : 4 c/s ) sq.m 77.44 1,500.00 9.30 49.15 29.08 87.53 131,299.80
3.4 HONEY COMB BRICK WORKS (1:3 c/s) cu.m 4.52 9,000.00 4.28 1.59 5.87 52,861.95
4. DOORS & WINDOWS WORKS
4.1 -
4.1 METAL FRAME 0.00
4.1.1 Door Frame rm. 260.84 1,100.00 188.78 71.90 260.68 286,748.00
4.1.2 Window Frame rm. 764.58 1,100.00 494.55 255.60 750.15 825,165.00
4.2 METAL SHUTTER 0.00 -
4.2.1 WINDOW SHUTTER sq.m 145.87 7,500.00 72.76 44.63 117.39 880,398.38
4.3 WOODEN SHUTTER 0.00 -
4.3.1 FLUSH DOOR SHUTTER (32MM) sq.m 99.84 8,000.00 62.34 24.36 86.70 693,592.80
4.4 UPVC DOOR
4.4.1 4.4.1 SHUTTER/FRAME sq.m 14.28 9,000.00 121,770.00
13.53 13.53
4.5 WINDOW GRILL sq.m 135.08 2,500.00 72.76 45.18 6.23 124.17 310,416.13
4.6 COLLAPSIBLE GATE sq.m 17.45 10,000.00 9.90 7.55 17.45 174,500.00
5. FLOORING WORKS
5.1 HARDENED CEMENT CONCETE FLOOR sq.m 1772.90 900.00 1,589,926.46
1,219.24 452.25 95.10 1,766.58
NEAT CEMENT SKIRTING
5.2 - do - as above, but for 100 mm high skirting. r.m 941.47 100.00 91,670.00
686.66 205.90 24.14 916.70
5.3 TERRAZZO CAST-IN SITU DADO sq.m 92.43 1,500.00 2.40 22.60 64.87 89.87 134,803.50
6 ROOFING/ TERRACING WORKS 0.00 -
6.1 METAL WORKS(TRUSS) kg 5,076.09 220.00 4,712.85 999.81 5,712.66 1,256,784.37
6.2 CGI SHEET ROOFING sq.m 353.64 2,000.00 295.74 58.93 354.67 709,334.00
6.3 CGI SHEET ROOFING RIDGE rm. 35.85 1,200.00 23.75 12.10 35.85 43,020.00
6.4 GI FACIA (EAVES) kg 278.04 250.00 170.52 143.52 314.04 78,510.78
6.5 CEMENT BOARD FALSE CEILING sq.m 320.71 1,600.00 289.83 48.40 338.23 541,168.00
7. PLASTERING/ WALL FINISHING WORKS
7.1 CEMENT PLASTER WORKS -
0.00
7.1.1 ON INNER WALL (1:6) sq.m 1764.21 600.00 664.16 599.03 134.02 1,397.21 838,324.20
7.1.2 ON CEILING (1:4) sq.m 843.48 500.00 674.67 291.97 35.03 1,001.66 500,831.90
7.1.3 ON OUTER WALL (1:6):
7.1.3.1 EXTERNAL PLASTER sq.m 875.99 600.00 1,047,197.09
1295.52 343.47 106.34 1,745.33
INTERNAL PALSTER ON WALL (1:4)WITH CEMENT
7.1.4 PUNNING sq.m 36.14 700.00 24,955.00
35.65 35.65
7.2 PAINTING WORKS 0.00 -
7.2.1 DISTEMPER PAINT sq.m 2897.52 200.00 1338.83 1,180.83 217.44 2,737.10 547,420.16
7.2.2 EXTERIOR WEATHER COAT PAINT sq.m 1280.46 350.00 1295.52 343.47 106.34 1,745.33 610,865.24
7.2.4 ENAMEL PAINT sq.m 743.97 400.00 421.13 256.60 12.46 690.19 276,077.18
8 MISCELLANEOUS 0.00 -
8.2 CEMENT BOARD WALL sq.m 22.01 6,500.00 29.04 2.18 31.22 202,930.00
8.3 RAILING kg 3,086.12 220.00 2,431.61 689.19 3,120.80 686,576.32
8.4 PUMP SHED nos 1.00 80,000.00 1.00 1.00 80,000.00

Prepared By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Type Design
Pay
Quantity in Total
Item Description of Works Unit Rate (NRs.) Site Amount Remarks
BOQ 3-12C(MsF)-D 2-LaLi-EC Tc(S) Water Tank Quantity
No. Development
8.5 SEWER, RAIN AND WASTE WATER INSTALLATION rm. 44.80 1,500.00 41.80 41.80 62,700.00
0.00 -
BILL NO. 3. ELECTRICAL WORKS 0.00 -
A Common Installation 0.00 -
1.1 Stand Alone 40 A DP MCB with Enclosure No 2 12,000.00 1.00 1.00 2.00 24,000.00
1.2 Stand Alone 6 A DP MCB with Enclosure No 2 8,500.00 2.00 2.00 17,000.00
0.00 -
2 Cables and Wires 0.00 -
2 Nos 10 Sq mm Multistranded Cu Wire + 1 No 6 Sq mm 45.00 45.00
2.1 Multistranded Cu wire Rm 100 800.00 72,000.00
90.00
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm Rm 95 250.00 45.00
2.2 45.00 22,500.00
Multistranded Cu wire 90.00
0.00 -
B SCHOOL BLOCKS 0.00 -
1 DISTRIBUTION BOARDS 0.00 -
DB (DB-1) Incoming: 1 x 40A DP MCB Outgoing: 2 x 25 A DP 1.00
1.1 MCB 7 x 6 A SP MCB 3 x 16 A SP MCB No 1 30,000.00 30,000.00
1.00
DB (DB-1) Incoming NEA: 1 x 40A DP MCB Incoming Solar: 1 x 1.00
1.2 16A DP MCB Outgoing NEA: 1 x 16 A DP MCB 2 x 25 A DP MCB No 1 30,000.00 30,000.00
2 x 16 A SP MCB 6 x 6 A SP MCB 1.00
DB ( DB-2) & DB ( DB-3) Incoming: 1.00
1.3 1 x 25A DP MCB No 1 22,000.00 22,000.00
1.00
DB ( DB-2) Incoming NEA: 1 x 25A DP MCB Incoming Solar: 1 x 1.00
1.4 10A DP MCB O No 1 22,000.00 22,000.00
1.00
DB ( DB-3) Incoming NEA: 1 x 25A DP MCB Incoming Solar: 1 x 1.00
1.5 10A DP MCB No 1 22,000.00 22,000.00
1.00
1.6 6A DP MCB with Enclosure No 2 8,500.00 2.00 2.00 17,000.00
0.00 -
2 CABLES & WIRES 0.00 -
2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm Multistranded Rm 10 600.00 6.00 4.00
2.1 6,000.00
Cu wire 10.00
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm Rm 20 500.00 6.00 4.00
2.2 Multistranded Cu wire 5,000.00
10.00
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm Rm 60 250.00 36.00 24.00
2.3 15,000.00
Multistranded Cu wire 60.00
0.00 -
3 General service light point wiring 0.00 -
3.1 One way light point Pts 123 700.00 73.00 37.00 12.00 122.00 85,400.00
3.2 Two Way Light Point Pts 3 900.00 2.00 1.00 3.00 2,700.00
3.3 Ceiling and Exhaust Fan Point Wiring Pts 4 900.00 4.00 4.00 3,600.00
4 6A Universal pin Light power point wiring Pts 127 900.00 79.00 49.00 128.00 115,200.00
0.00 -
5 Switch Socket Outlets 0.00 -
5.1 6A Universal power Switch Socket No 127 700.00 79.00 49.00 128.00 89,600.00
6 Sweep Ceiling/Exhaust Fan/Wall Fan 0.00 -
6.1 225 mm dia M/D exhaust fan No 4 6,000.00 4.00 4.00 24,000.00
0.00 -
7 Light Fixtures/Luminaires & Accessories 0.00 -
7.1 24 W LED Surface Mounted Square type Nos. 6 4,500.00 6.00 6.00 27,000.00
7.2 24 W LED Reccesed Mounted Square type Nos. 6 4,500.00 6.00 6.00 27,000.00
7.3 18 W LED Surface Mounted Square type Nos. 52 2,700.00 48.00 4.00 52.00 140,400.00
7.4 18 W LED Recessed Mounted Square type Nos. 4 2,700.00 4.00 4.00 10,800.00
7.5 12 W LED Surface Mounted Cylindrical type Nos. 30 2,400.00 23.00 7.00 30.00 72,000.00
7.6 12 W LED Recessed Mounted Cylindrical type Nos. 8 2,400.00 8.00 8.00 19,200.00
7.7 LED Wall Light made Nos. 4 1,800.00 1.00 1.00 2.00 4.00 7,200.00
7.8 9 W LED Surface Mounted Cylindrical type Nos. 2 2,000.00 2.00 2.00 4,000.00
7.9 6 W LED Recessed Circular type C Nos. 6 1,800.00 6.00 6.00 10,800.00
7.10 7 W LED T5 Slim Mirror Light Nos 2 2,000.00 2.00 2.00 4,000.00
8 Pull Box No 6 700.00 3.00 3.00 6.00 4,200.00
9 External post top light pole No 6 7,500.00 3.00 3.00 6.00 45,000.00
10 Post Top External Light Fixtures No 6 9,800.00 3.00 3.00 6.00 58,800.00
0.00 -
11 Earthing and Lightning protection 0.00 -
11.1 11.1. Chemical Earhting Nos. 6 45,000.00 3.00 3.00 6.00 270,000.00
11.2 Earthing Bar Nos. 6 2,200.00 3.00 3.00 6.00 13,200.00
GI Strip/Cu wire Earthing 63.00 64.00
12.1 Mtr. 130 300.00 38,100.00
12.1. 25 x 3 mm GI Strip 127.00
12.2 12 SWG Cu wire Mtr. 30 200.00 14.00 14.00 28.00 5,600.00
13 Earth Test link No 2 1,500.00 1.00 1.00 2.00 3,000.00
14 Lightning Arrester No. 1 7,500.00 1.00 1.00 7,500.00
0.00 -
C SOLAR PV SYSTEM 0.00 -
1. Solar PV Panel No 8 26,000.00 8.00
1.1 1.1. 24V 250W PV Module 208,000.00
8.00
2. Tubular Deep cycle Battery No 4 30,000.00 4.00
2.1 120,000.00
2.1. 12V, 200Ah@C10 Tubular Solar Battery 4.00
3 Hybrid Inverter No 1 100,000.00 1.00 1.00 100,000.00
FIRE EXTINGUISHER Nos. 6 8,000.00 2.00 4.00
D a) Supplying Fire extinguisher ABC stored Pressure 5.0kg size ABC 48,000.00
stored pressure type Fire extinguisher. 6.00
0.00 -
Bill No. 4 Sanitary Works 0.00 -
A Piping Works 0.00 -
1 WATER SUPPLY INSTALLATION 0.00 -
a CPVC pipes SDR-11 0.00 -
40 mm r.m 152.00 1600.00 150.00 150.00 240,000.00
20mm r.m 22.00 1000.00 22.00 22.00 22,000.00
15mm r.m 8.00 700.00 7.00 7.00 4,900.00

Prepared By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Type Design
Pay
Quantity in Total
Item Description of Works Unit Rate (NRs.) Site Amount Remarks
BOQ 3-12C(MsF)-D 2-LaLi-EC Tc(S) Water Tank Quantity
No. Development
c CPVC Ball Valve 0.00 0.00 -
40 mm nos. 5.00 2000.00 5.00 5.00 10,000.00
25 mm nos. 2.00 900.00 2.00 2.00 1,800.00
d Electrical Centrifugal Water Pump nos. 1.00 12500.00 1.00 1.00 12,500.00
e 2000 litres Capacity Water Storage Tank nos. 1.00 3400.00 1.00 1.00 3,400.00
2 Sewer, Rain and Waste Water Installation 0.00 0.00 -
110 mm r.m 43.00 1400.00 40.00 40.00 56,000.00
75mm r.m 49.00 1200.00 50.00 50.00 60,000.00
50mm r.m 22.00 350.00 21.00 21.00 7,350.00
0.00 0.00 -
B School Blocks 0.00 0.00 -
1 Sanitary Installation 0.00 0.00 -
a Lab Sink set 5.00 30000.00 5.00 5.00 150,000.00
b PVC Multi Floor Trap nos. 10.00 600.00 10.00 10.00 6,000.00
0.00 0.00 -
2 Sanitary Installation 0.00 0.00 -
a Water Closet Set set 2.00 34000.00 2.00 2.00 68,000.00
b Orissa Pan set 4.00 3100.00 4.00 4.00 12,400.00
c Hand Wash Basin set 2.00 8000.00 2.00 2.00 16,000.00
d Ladies Urinal set 2.00 110000.00 2.00 2.00 220,000.00
e Self Closing Bib Cock nos. 12.00 4000.00 12.00 12.00 48,000.00
f CP Spreader in Urinal set 4.00 2500.00 4.00 4.00 10,000.00
g Toilet Paper Holder nos. 2.00 2600.00 2.00 2.00 5,200.00
h Commode Spray nos. 2.00 2000.00 2.00 2.00 4,000.00
i PVC Multi Floor Trap nos. 10.00 600.00 10.00 10.00 6,000.00
j Waste Coupling and PVC Bottle Trap nos. 4.00 1500.00 4.00 4.00 6,000.00
k 40mm SS Grab Bar-Side nos. 2.00 4500.00 2.00 2.00 9,000.00
l 40mm SS Grab Bar-Rear nos. 2.00 4500.00 2.00 2.00 9,000.00
m CP Foldable Hinge nos. 4 5,500.00 4.00 4.00 22,000.00
0.00 -
CIVIL WORKS - SITE DEVELOPMENT 0.00 -
1 SITE CLEARANCE & MOBILIZATION: sq.m 149.07 100.00 220.18 220.18 22,018.00
2 EARTHWORK IN EXCAVATION : cu.m 3079.63 400.00 126.16 126.16 50,464.81
3 EARTH BACK FILLING : cu.m 245.00 300.00 56.15 56.15 16,844.22
4 BOULDER SOLING : cu.m 56.98 6,000.00 46.54 46.54 279,232.19
5 P.C.C (1:3:6) WORKS cu.m 7.23 14,000.00 7.54 7.54 105,610.40
6 P.C.C (1:2:4) WORKS cu.m 24.08 16,000.00 28.87 28.87 461,857.78
7 P.C.C. FOR R.C.C. WORKS : cu.m 0.99 20,000.00 0.99 0.99 19,766.20
8 SILICA CEMENT ADMIXTURE Kg 9.90 300.00 9.88 9.88 2,964.93
9 STEEL REINFORCEMENT Mt. 0.10 130,000.00 0.10 0.10 13,343.25
10 FORM WORKS sq.m 9.12 800.00 30.32 30.32 24,256.00
11 STONE MASONRY WORKS (1:6 c/s) cu.m 117.07 10,000.00 84.68 84.68 846,754.50
13 BRICK MASONRY WORKS ( 1 : 4 c/s ) cu.m 0.22 18,000.00 0.72 0.72 13,032.72
14 NEAT CEMENT SKIRTING r.m 4.72 100.00 4.40 4.40 440.00
15 METAL WORKS FOR FENCE k.g 2726.47 220.00 2,707.00 2,707.00 595,539.12
16 METAL WORKS FOR GATE k.g 130.78 220.00 123.31 123.31 27,128.09
17 PLASTER ON OUTER WALL (1:6) sq.m 7.92 600.00 7.80 7.80 4,679.04
18 EXTERIOR WEATHER COAT PAINT sq.m 8.87 350.00 8.27 8.27 2,895.20
19 CHAIN LINK FENCE (50 x 50 MESH) sq.m 370.74 1,000.00 380.40 380.40 380,400.00
20 FLAG POLE nos. 2.00 25,000.00 2.00 2.00 50,000.00
21 50 DIA PVC WEEP PIPE sq.m 58.10 100.00 13.20 13.20 1,320.00
22 GEOTEXTILE FABRIC sq.m 57.31 200.00 36.32 36.32 7,263.68
0.00 -
CIVIL WORKS-RESERVOIR TANK 0.00 -
1 EARTH WORK 0.00 -
1.1 SITE CLEARANCE AND MOBILIZATION sq.m 22.31 100.00 22.31 22.31 2,231.00
1.2 EARTHWORK IN EXCAVATION cu.m 24.58 400.00 24.57 24.57 9,828.72
1.3 EARTH BACK FILLING cu.m 4.02 300.00 4.01 4.01 1,202.85
1.4 BOULDER SOLING cu.m 2.08 6,000.00 2.08 2.08 12,462.00
2 CONCRETE WORKS 0.00 -
2.1 P.C.C (1:3:6) cu.m 0.78 14,000.00 0.78 0.78 10,904.25
2.2 P.C.C FOR R.C.C WORKS cu.m 7.42 20,000.00 7.41 7.41 148,295.00
2.3 SILICA CEMENT ADMIXTURE kg 74.2 300.00 74.15 74.15 22,244.25
2.4 STEEL REINFORCEMENT Mt 1.46 130,000.00 1.47 1.47 191,574.92
2.5 FORMWORKS sq.m 54.93 800.00 54.67 54.67 43,738.00
3 PLASTERING/WALL FINISHING WORKS 0.00 -
3.1.1 INTERNAL PLASTER ON WALL (1:4) WITH CEMENT PUNNING sq.m 33.66 700.00 33.66 33.66 23,565.25
4 WATERPROOFING WORKS sq.m 33.66 550.00 33.66 33.66 18,515.55
0.00 -
Furniture Works lot 1 5,300,000.00 0.5 0.5 1.00 5,300,000.00
Total 62,553,688.89

Prepared By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

S. No. Description No. Length Breadth Height Qty. Unit


1 Mobilization and Demobilization 1 1 L.S

2 Site Office Establishment 1 16 Per month

3 Project Information Board 1 1 No.

4 Safety Sign Board 1 1 No.

5 Barricading Works 1 45 45 Rm

Dismantling of completely damaged


6
building
Building 1 1 15.00 8.00 120.00 sq.m

7 Safety materials and site safety L.S

8 Relocating of existing TLC 1 3.7 3.5 12.95 sq.m

10 Construction of Temporary Toilet 2 2 Nos.

11 Road Repair and maintenance 12 km

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Remarks

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Block :3-12C(MsF)-D
School Name : Shree Jhimrek Mahipate Secondary School
Location : Thalajung Gorkha

Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 EARTH WORKS
1.1 Site Clearance 1 34.50 14.50 500.25
Total 500.25 sq.m

1.2 Earth Work Excavation


For Isolated Foundation
F1 2 2.80 2.80 1.50 23.52
F2 4 3.30 3.30 1.50 65.34
For Combined Foundation
CF1 3 2.10 5.30 1.50 50.09
CF2 1 3.30 5.30 1.50 26.24
CF3 2 3.10 5.30 1.50 49.29

Along Lower Tie Beam


Along Grid A,B,C,D,E,F/ 1-2 6 3.50 0.55 0.75 8.66
Along Grid 1 1 12.49 0.55 0.75 5.15
Along Grid 2,3 2 14.80 0.55 0.75 12.21

Drain 1 29.00 0.60 0.05 0.87


Pavement Along Drain 1 29.00 0.98 0.15 4.24
External Steps 1 27.90 0.70 0.15 2.93

Ramp
For Slope 1 1.30 0.52 Area 0.67
Wall Along Grid B 1 0.50 0.45 0.45 0.10
Wall Parallel to Ramp 1 6.80 0.45 0.41 1.25
Total 250.56 cu.m

1.3 Earth Back Filling


Total Excavation 1 250.56 250.56
Deduction
Boulder Soling -1 27.04 -27.04
PCC (1:3:6) -1 15.19 -15.19
RCC -1 97.42 -97.42
Brick Masonry -1 5.96 -5.96

Filling in Floor
Classroom 4 6.70 5.70 0.18 26.73
Staircase 1 6.70 4.20 0.18 4.92
Corridor 4 5.70 2.20 0.18 8.78
1 4.20 2.20 0.18 1.62
Total 147.01 cu.m

1.4 Boulder Soling


Footing
Isolated F1 2 2.50 2.50 0.20 2.50
Isolated F2 4 3.00 3.00 0.20 7.20
Combined CF1 3 1.80 5.00 0.20 5.40
Combined CF2 1 3.00 5.00 0.20 3.00
Combined CF3 2 2.80 5.00 0.20 5.60

Below Foundation Beam


Along Grid A,B,C,D,E,F/ 1-2 6 4.55 0.40 0.10 1.09
Along Grid 1 1 23.50 0.40 0.10 0.94
Along Grid 2,3 2 16.30 0.40 0.10 1.30

Pavement along Drain 1 29.00 1.00 0.10 2.90


External Steps 1 28.58 0.70 0.10 2.00

Ramp
Slopped Portion 1 1.30 1.36 Area 1.77

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Wall Along Grid B 1 0.50 0.45 0.10 0.02
Wall Parallel to Ramp 1 6.80 0.45 0.10 0.31
Classroom
Class Room 4 5.70 6.70 0.20 30.55
Corridor 4 5.70 2.20 0.20 10.03
1 4.20 2.20 0.20 1.85
Below Staircase 1 4.20 6.65 0.20 5.59
Total 82.05 cu.m

2 CONCRETE WORKS
2.1 P.C.C.
2.1.1 P.C.C.(1:3:6) Works
Footing
Isolated F1 2 2.50 2.50 0.10 1.25
Isolated F2 4 3.00 3.00 0.10 3.60
Combined CF1 3 1.80 5.00 0.10 2.70
Combined CF2 1 3.00 5.00 0.10 1.50
Combined CF3 2 2.80 5.00 0.10 2.80

Below Foundation Beam


Along Grid A,B,C,D,E,F/ 1-2 6 4.55 0.40 0.10 1.09
Along Grid 1 1 23.50 0.40 0.10 0.94
Along Grid 2,3 2 16.30 0.40 0.10 1.30
Total 15.19 cu.m

2.1.2 P.C.C.(1:2:4) Works


Pavement along Drain 1 29.00 1.00 0.05 1.45
Below External Steps 1 28.58 0.70 0.05 1.00
Above External Steps 1 27.08 0.90 0.05 1.22

Ramp
Sloped 1 1.30 0.51 Area 0.66
Wall Top 1 1.33 0.25 0.05 0.02
1 6.80 0.13 0.05 0.04

Class Room 4 5.70 6.70 0.08 11.46


Corridor 4 5.70 2.20 0.08 3.76
1 4.20 2.20 0.08 0.69
Below Staircase 1 4.20 6.70 0.08 2.11
Total 22.41 cu.m

2.2 P.C.C For R.C.C. Works


A Foundation
Isolated F1 Base 2 2.50 2.50 0.20 2.50
Isolated F1 Slope 2 3.63 Area 0.35 2.54
Isolated F2 Base 4 3.00 3.00 0.20 7.20
Isolated F2 Slope 4 5.00 Area 0.35 7.00
Combined CF1 3 1.80 5.00 0.60 16.20
Combined CF2 1 3.00 5.00 0.60 9.00
Combined CF3 2 2.80 5.00 0.60 16.80

Beam
Foundation beam (300x400)
Along Grid A,B,C,D,E,F/ 1-2 6 6.50 0.30 0.40 4.68
Along Grid 1 1 26.00 0.30 0.40 3.12
Along Grid 2,3 2 26.00 0.30 0.40 6.24

Plinth Tie beam(300x450)


Along grid 1,2,3 3 26.00 0.30 0.45 10.53
Along Grid A,B,C,D,E,F 6 8.50 0.30 0.45 6.89

First floor level


Main beam(300x525)
Along grid 1,2,3 3 26.00 0.30 0.40 9.36
Along Grid A,B,E,F 6 8.50 0.30 0.40 6.12
Along grid C,D 2 9.40 0.30 0.40 2.26
Secondary beam(250x425)

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Grid 1a 4 5.45 0.25 0.30 1.64
Grid 1b 1 4.20 0.25 0.30 0.32
Grid A1,B1,D1,E1 4 8.90 0.25 0.30 2.67

Conceal beam (150*525) 6.00 0.15 0.40 0.36

Second floor level


Main beam
Along grid 1,2,3 3 26.00 0.30 0.40 9.36
Along grid A,B,C,D,E & F 6 8.50 0.30 0.40 6.12

Secondary Beam
Along grid 1a 2 11.40 0.25 0.30 1.71
Along grid 1b 1 4.20 0.25 0.30 0.32
Along grid A1,B1,D1 & E1 4 8.65 0.25 0.30 2.60

Top floor Beam


Main beam
Along grid 1,2,3 3.00 26.00 0.30 0.40 9.36
Along grid A,B,C,D,E & F 6.00 8.50 0.30 0.40 6.12

Secondary Beam
Along grid 1a 2.00 11.40 0.25 0.30 1.71
Along grid 1b 1.00 4.20 0.25 0.30 0.32
Along grid A1,B1,D1 & E1 4.00 8.65 0.25 0.30 2.60

Roof floor level


Main beam(300x525)
Along grid 1,2,3 3 4.00 0.30 0.40 1.44
Along Grid C,D 2 8.50 0.30 0.40 2.04

Secondary beam(250x425)
Grid 1a 1 4.20 0.25 0.30 0.32

Column
Column below Plinth level
Total columns(500x500) 18 0.50 0.50 1.05 4.73

Ground floor plan


Total columns(500x500) 18 0.50 0.50 3.00 13.50

First floor plan


Total columns(500x500) 18 0.50 0.50 3.00 13.50

Second floor plan


Total columns(500x500) 18 0.50 0.50 3.00 13.50

Top Floor Plan


Total columns(500x500) 6 0.50 0.50 2.63 3.94

Slab
First floor level (+3.00m Lvl) 1 29.00 10.00 0.13 36.25
Deduction
Column deduction -18 0.50 0.50 0.13 -0.56
Staircase Void -1 4.78 4.20 0.13 -2.61

Projections
At Back 2 11.50 0.70 0.13 2.01
At Front 1 6.20 1.00 0.13 0.78

Second floor level (+6.00m Lvl) 1 29.00 10.00 0.13 36.25


Deduction
Column deduction -18 0.50 0.50 0.13 -0.56
Staircase Void -1 4.78 4.20 0.13 -2.61

Projections
At Back 2 11.50 0.70 0.13 2.01

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Top floor level (+9.00m Lvl) 1 29.00 10.00 0.13 36.25
Deduction
Column deduction -18 0.50 0.50 0.13 -0.56
Staircase Void -1 4.78 4.20 0.13 -2.61

Projections
At Back 2 13.10 1.10 0.13 3.60
At Front 2 12.00 1.10 0.13 3.30
1 7.00 1.60 0.13 1.40
At Sides 2 9.80 1.10 0.13 2.70

Roof floor level (+11.625m Lvl) 1 11.50 6.50 0.13 9.34


Column deduction -6 0.50 0.50 0.13 -0.19

Staircase
Ground floor level
Bottom 1 2.07 2.00 0.20 0.83
Landing 1 4.20 1.90 0.20 1.60
Waist Slab 1 6.75 2.00 0.21 2.77
Steps 20 0.02 Area 2.00 0.90
Landing Beam 1 4.05 0.25 0.38 0.38

First floor level


Landing 1 4.20 1.90 0.20 1.60
External Slab 1 4.05 0.73 0.13 0.37
Waist Slab 1 6.75 2.00 0.21 2.77
Steps 20 0.02 Area 2.00 0.90
Landing Beam 1 4.05 0.25 0.38 0.38

Second floor level


Landing 1 4.20 1.90 0.20 1.60
External Slab 1 4.05 0.73 0.13 0.37
Waist Slab 1 6.75 2.00 0.21 2.77
Steps 20 0.02 Area 2.00 0.90
Landing Beam 1 4.05 0.25 0.38 0.38

Projections 3 4.00 0.70 0.13 1.05

Vertical Bands
Ground Floor level
Along Grid 2 8.00 0.08 0.23 2.48 0.34
First floor level
Along Grid 2 8.00 0.08 0.23 2.48 0.34
Second floor level
Along Grid 2 8.00 0.08 0.23 2.48 0.34
Partition Wall Principal/Administration 1.00 0.08 0.23 2.10 0.04

Lintel Bands
Ground floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.23 0.08 0.67
Along grid 1 1.00 22.20 0.23 0.08 0.38
Along grid 2 1.00 21.60 0.23 0.08 0.37
First floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.23 0.08 0.67
Along grid 1 1.00 22.20 0.23 0.08 0.38
Along grid 2 1.00 21.60 0.23 0.08 0.37

Second floor level


Along grid A,B,C,D,E,F 6.00 6.50 0.23 0.08 0.67
Along grid 1 1.00 22.20 0.23 0.08 0.38
Along grid 2 1.00 21.60 0.23 0.08 0.37
Partition Wall Principal/Administration 1.00 4.25 0.13 0.08 0.04
1.00 1.50 0.23 0.08 0.03
Deduction of Doors/Windows for Lintels
Ground floor level
D1 -8 1.10 0.23 0.08 -0.15
First floor level
D1 -8 1.10 0.23 0.08 -0.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Second floor level
D1 -8 1.10 0.23 0.08 -0.15
D3 -1 1.00 0.23 0.08 -0.02

Sill Bands
Ground floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.23 0.08 0.67
Along grid 1 1.00 26.20 0.23 0.08 0.45
Along grid 2 1.00 21.60 0.23 0.08 0.37

First floor level


Along grid A,B,C,D,E,F 6.00 6.50 0.23 0.08 0.67
Along grid 1 1.00 26.20 0.23 0.08 0.45
Along grid 2 1.00 21.60 0.23 0.08 0.37

Second floor level


Along grid A,B,C,D,E,F 6.00 6.50 0.23 0.08 0.67
Along grid 1 1.00 26.20 0.23 0.08 0.45
Along grid 2 1.00 21.60 0.23 0.08 0.37
Partition Wall Principal/Administration 1.00 4.25 0.13 0.08 0.04
1.00 1.50 0.23 0.08 0.03

Top floor level


Along grid C,D 2.00 8.50 0.23 0.08 0.29
Along grid 1,3 2.00 4.00 0.23 0.08 0.14

Deduction of Doors For Sill


Ground floor level
D1 -8 1.10 0.23 0.08 -0.15
D4 -1 1.00 0.13 0.08 -0.01
First floor level
D1 -8 1.10 0.23 0.08 -0.15
Second floor level
D1 -8 1.10 0.23 0.08 -0.15
Top floor level
D2 -2 1.10 0.23 0.08 -0.04
D3 -1 1.00 0.23 0.08 -0.02

Pedestal
Base Block 14 0.50 0.25 0.25 0.44

Parapet Wall
Top Floor 2.00 71.00 0.35 0.10 4.97
1.00 7.50 0.35 0.10 0.26
Roof Level 1.00 33.00 0.35 0.10 1.16

Bench
Bench Top Slab 2 2.40 0.50 0.08 0.18
Total 368.73 cu.m

2.3 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10 368.73 3687.31
Total 3687.32 Kg

2.4 Formworks
A Foundation
Isolated footing
Isolated F1 2 10.00 0.20 4.00
Isolated F2 4 12.00 0.20 9.60
Combined footing
Combined CF1 3 13.60 0.60 24.48
Combined CF2 1 16.00 0.60 9.60
Combined CF3 2 15.60 0.60 18.72

Beam
Foundation beam (300x400)
Along Grid A,B,C,D,E,F/ 1-2 6 6.50 0.80 31.20
Along Grid 1 1 26.00 0.80 20.80

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along Grid 2,3 2 26.00 0.80 41.60

Plinth Tie beam(300x450)


Along grid 1,2,3 3 26.00 0.90 70.20
Along Grid A,B,C,D,E,F 6 8.50 0.90 45.90

First floor level (+3.00m Lvl)


Main beam(300x525)
Along grid 1,3 3 26.00 0.93 72.15
Along grid 2 1 26.00 0.80 20.80
Along Grid A,F 2 8.50 0.93 15.73
Along Grid B,E 2 8.50 0.80 13.60
Along Grid C,D 2 9.25 0.80 14.80

Secondary beam(250x425)
Grid 1a 4 5.45 0.60 13.08
Grid 1b 1 4.20 0.60 2.52
Grid A1,B1,D1,E1 4 8.90 0.60 21.36

Edge Beam(125x525)
Grid B,C 1 7.90 0.93 7.31

Second floor level (+6.00m Lvl)


Main beam(300x525)
Along grid 1,3 3 26.00 0.93 72.15
Along grid 2 1 26.00 0.80 20.80
Along Grid A,F 2 8.50 0.93 15.73
Along Grid B,C,D,E 4 8.50 0.80 27.20

Secondary beam(250x425)
Grid 1a 4 5.45 0.60 13.08
Grid 1b 1 4.20 0.60 2.52
Grid A1,B1,D1,E1 4 8.90 0.60 21.36

Top floor level (+9.00m Lvl)


Main beam(300x525)
Along grid 1,3 3 26.00 0.93 72.15
Along grid 2 1 26.00 0.80 20.80
Along Grid A,F 2 8.50 0.93 15.73
Along Grid B,C,D,E 4 8.50 0.80 27.20

Secondary beam(250x425)
Grid 1a 4 5.45 0.60 13.08
Grid 1b 1 4.20 0.60 2.52
Grid A1,B1,D1,E1 4 8.90 0.60 21.36

Roof floor level (+11.625m Lvl)


Main beam(300x525)
Along grid 1,3 2 4.00 0.93 7.40
Along grid 2 1 4.00 0.80 3.20
Along Grid C,D 2 8.50 0.93 15.73

Secondary beam(250x425)
Grid 1a 1 4.20 0.80 3.36

Landing beam 3 0.85 4.00 10.20

Column
Column below Plinth level
Total columns(500x500) 18 2.00 1.05 37.80

Ground floor plan


Total columns(500x500) 18 2.00 2.88 103.50

First floor plan


Total columns(500x500) 18 2.00 2.88 103.50

Second floor plan

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Total columns(500x500) 18 2.00 2.88 103.50

Top Floor Plan


Total columns(500x500) 6 2.00 2.50 30.00

Slab
First floor level (+3.00m Lvl) 1 29.00 10.00 290.00
Deduction
Column deduction -18 0.50 0.50 -4.50
Staircase Void -1 4.78 4.20 -20.06

Projections
At Back 2 11.50 0.70 16.10
At Front 1 6.20 1.00 6.20

Second floor level (+6.00m Lvl) 1 29.00 10.00 290.00


Deduction
Column deduction -18 0.50 0.50 -4.50
Staircase Void -1 4.78 4.20 -20.06

Projections
At Back 2 11.50 0.70 16.10

Top floor level (+9.00m Lvl) 1 29.00 10.00 290.00


Deduction
Column deduction -18 0.50 0.50 -4.50
Staircase Void -1 4.78 4.20 -20.06

Projections
At Back 2 13.10 1.10 28.82
At Front 2 12.00 1.10 26.40
1 7.00 1.60 11.20
At Sides 2 9.80 1.10 21.56

Roof floor level (+11.625m Lvl) 1 11.50 6.50 74.75


Column deduction -6 0.50 0.50 -1.50

Staircase
Ground floor level
Bottom 1 1.93 0.20 0.39
Waist Slab 1 6.75 2.00 13.50
Landing 1 4.20 1.90 7.98
1 1.08 0.21 0.22
Steps 20 0.02 Area 0.45
Riser 20 2.00 0.15 6.00

First floor level


External Slab 1 4.00 0.73 2.90
1 5.20 0.13 0.65
Waist Slab 1 6.75 2.00 13.50
Landing 1 4.20 1.90 7.98
1 1.08 0.21 0.22
Steps 20 0.02 Area 0.45
Riser 20 2.00 0.15 6.00

Second floor level


Top Floor Passage 1 2.20 0.13 0.28
External Slab 1 4.00 0.73 2.90
1 5.20 0.13 0.65
Waist Slab 1 6.75 2.00 13.50
Landing 1 4.20 1.90 7.98
1 1.08 0.21 0.22
Steps 20 0.02 Area 0.45
Riser 20 2.00 0.15 6.00

Vertical support bands


Ground Floor level

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along Grid 2 8.00 0.28 2.48 5.54
First floor level
Along Grid 2 8.00 0.28 2.48 5.54
Second floor level
Along Grid 2 8.00 0.28 2.48 5.54
Partition Wall Principal/Administration 1.00 0.28 2.10 0.59

Lintel Bands
Ground floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 22.20 0.15 3.33
Along grid 2 1.00 21.60 0.15 3.24
First floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 22.20 0.15 3.33
Along grid 2 1.00 21.60 0.15 3.24
Second floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 22.20 0.15 3.33
Along grid 2 1.00 21.60 0.15 3.24
Partition Wall Principal/Administration 1.00 4.25 0.15 0.64
1.00 1.50 0.15 0.23

Deduction of Doors/Windows for Lintels


Ground floor level
D1 -8 1.10 0.15 -1.32
First floor level
D1 -8 1.10 0.15 -1.32
Second floor level
D1 -8 1.10 0.15 -1.32
D3 -1 1.00 0.15 -0.15

Sill Bands
Ground floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 26.20 0.15 3.93
Along grid 2 1.00 21.60 0.15 3.24
First floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 26.20 0.15 3.93
Along grid 2 1.00 21.60 0.15 3.24
Second floor level
Along grid A,B,C,D,E,F 6.00 6.50 0.15 5.85
Along grid 1 1.00 26.20 0.15 3.93
Along grid 2 1.00 21.60 0.15 3.24
Partition Wall Principal/Administration 1.00 4.25 0.15 0.64
1.00 1.50 0.15 0.23
Top floor level
Along grid C,D 2.00 8.50 0.15 2.55
Along grid 1,3 2.00 4.00 0.15 1.20

Deduction of Doors For Sill


Ground floor level
D1 -8 1.10 0.15 -1.32
D4 -1 1.00 0.15 -0.15
First floor level
D1 -8 1.10 0.15 -1.32
Second floor level
D1 -8 1.10 0.15 -1.32
Top floor level
D2 -2 1.10 0.15 -0.33
D3 -1 1.00 0.15 -0.15

Pedestal
Base Block 14 1.25 0.25 4.38

Parapet Wall
Top Floor 2.00 36.53 0.30 21.92

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
1.00 7.50 0.30 2.25
Roof Level 1.00 33.00 0.30 9.90
Bench
Bench Top Slab 2 5.80 Perimeter 0.08 0.87
Bottom 2 5.80 0.60 6.96
Deduction -4 0.13 0.50 -0.25
Total 2445.82 sq.m

3 BRICK WORKS
3.2 Brick Masonary Works (1:4 c/s)
Brick Works upto Plinth Beam
Along grid A,B,C,D,E,F/1-3 6 8.50 0.23 0.20 2.35
Along grid 1, 2, 3/A-F 3 26.20 0.23 0.20 3.62

Ground floor level


Along grid A,B,C,D,E,F 6 6.50 0.23 2.33 20.86
Along grid 1 4 5.50 0.23 2.33 11.76
1 4.00 0.23 2.02 1.86
Along grid 2 4 5.50 0.23 2.33 11.76

External Steps 1 0.09 Area 26.48 2.45


3 0.60 0.50 0.30 0.27
Ramp
Wall Along -B 1 1.33 0.25 Area 0.33
1 6.91 0.17 Area 1.19

First floor level


Along grid A,B,C,D,E,F 6 6.50 0.23 2.33 20.86
Along grid 1 4 5.50 0.23 2.33 11.76
1 4.00 0.23 2.02 1.86
Along grid 2 4 5.50 0.23 2.33 11.76

Second floor level


Along grid A,B,C,D,E,F 6 6.50 0.23 2.33 20.86
Along grid 1 4 5.50 0.23 2.33 11.76
1 4.00 0.23 2.02 1.86
Along grid 2 4 5.50 0.23 2.33 11.76
Partition Wall Principal/Administration 1.00 1.50 0.23 2.43 0.84

BRICK MASONRY WORKS ( 1 : 4 c/s )


Top floor level
Along grid C,D/1-3 2.00 8.50 0.23 2.03 7.92
Along grid 1 1.00 4.00 0.23 2.03 1.86
Along grid 3 1.00 4.00 0.23 2.03 1.86

Parapet Wall
Top Floor 2.00 71.00 0.23 0.80 26.13
1.00 7.50 0.23 1.40 2.42
Roof Level 1.00 33.00 0.23 0.90 6.83

Deduction for doors and windows


Ground floor level
W1 -16 1.10 0.23 1.13 -4.55
V1 -16 1.10 0.23 0.53 -2.13
W3 -1 1.50 0.23 0.37 -0.13
D1 -8 1.10 0.23 2.29 -4.62
First floor level
W1 -16 1.10 0.23 1.13 -4.55
V1 -16 1.10 0.23 0.53 -2.13
W2 -1 1.50 0.23 1.00 -0.35
D1 -8 1.10 0.23 2.29 -4.62
Second floor level
W1 -16 1.10 0.23 1.13 -4.55
V1 -16 1.10 0.23 0.53 -2.13
W2 -1 1.50 0.23 1.00 -0.35
D1 -8 1.10 0.23 2.29 -4.62
D3 -1.00 1.00 0.23 1.95 -0.45
Third floor level

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
W2 -1.00 1.50 0.23 1.00 -0.35
D2 -2.00 1.10 0.23 1.83 -0.92
Total 160.34 cu.m

3.3 Half Brick (125 mm) Works (1:4c/s)


Below Staircase(Store)
1 1.57 Area 1.57
1 1.42 Area 1.42
1 2.00 1.59 3.18
Ramp
Grid 3AB
1 1.40 0.22 0.31
1 5.12 0.22 1.13
Bench
Below external bench 8 0.50 0.43 1.70
Total 9.30 Sq.m

4 DOORS & WINDOWS


4.1 Metal Frame
4.1.1 Doors Frame
Ground floor
D1 8 7.07 Perimeter 56.56
D4 1 4.10 Perimeter 4.10
First floor
D1 8 7.07 Perimeter 56.56
Second floor
D1 8 7.07 Perimeter 56.56
D3 1 5.20 Perimeter 5.20
Top floor
D2 2 4.90 Perimeter 9.80
Total 188.78 r.m

4.1.2 Windows Frame


Ground floor
W1 18 5.58 Perimeter 100.35
V1 18 3.25 Perimeter 58.50
First Floor
W1 18 5.58 Perimeter 100.35
W2 1 6.00 Perimeter 6.00
V1 18 3.25 Perimeter 58.50
Second Floor
W1 18 5.58 Perimeter 100.35
W2 1 6.00 Perimeter 6.00
V1 18 3.25 Perimeter 58.50
Top floor
W2 1 6.00 Perimeter 6.00
Total 494.55 r.m

4.2 Metal Shutter


4.2.1 Windows shutter
W1 48 0.97 1.04 47.94
W2 3 1.37 0.91 3.73
V1 48 1.01 0.44 21.09
Total 72.76 sq.m

4.3 Wooden Shutter


4.3.1 Flush Door Shutter
D1 24 0.97 2.39 55.35
D2 2 1.01 1.86 3.75
D3 1 0.91 2.06 1.87
D4 1 0.91 1.51 1.37
Total 62.34 sq.m
4.4 Window Grill
Shutter Area of Window
W1 48 0.97 1.04 47.94
W2 3 1.37 0.91 3.73
V1 48 1.01 0.44 21.09

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Total 72.76 sq.m

4.5 Collapsable Gate


1.00 4.00 2.48 9.90
Total 9.90 Sq.m

5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan
Class Room 2 5.75 6.75 77.63
2 5.78 6.75 77.96
Corridor 1 24.30 2.53 61.36
1 4.50 2.53 11.36
Staircase Below 1 4.75 2.25 10.69
Staircase
Staircase Tread 18 0.30 2.00 10.80
Riser 20 0.15 2.00 6.00
Staircase landing 1 2.00 2.20 4.40
1 2.13 2.00 4.25

Pavement along Drain 1 29.00 1.00 29.00


Ramp 1 6.52 1.30 8.48
Exterior Steps 1 26.48 1.05 27.80
3 0.60 0.50 0.90
First floor plan
Class Room 2 5.75 6.75 77.63
2 5.78 6.75 77.96
Corridor 1 24.30 2.53 61.36
1 4.50 2.53 11.36
Staircase
Staircase Tread 18 0.30 2.00 10.80
Riser 20 0.15 2.00 6.00
Staircase landing 1 2.00 2.20 4.40
1 2.13 2.00 4.25
Second floor plan
Class Room 2 5.75 6.75 77.63
2 5.78 6.75 77.96
Corridor 1 24.30 2.53 61.36
1 4.50 2.53 11.36
Staircase
Staircase Tread 18 0.30 2.00 10.80
Riser 20 0.15 2.00 6.00
Staircase landing 1 2.00 2.20 4.40
1 2.13 2.00 4.25
Top floor plan
Corridor 1 4.45 4.20 18.69
Top Floor Slab 2 12.94 11.54 298.66
1 4.00 1.50 6.00

Roof plan
Roof Floor Slab 1 5.50 10.50 57.75
Total 1219.24 sq.m

5.2 Neat Cement Skirting works


Ground floor plan
Class Room 2 25.30 50.60
2 25.35 50.70
Column 6 2.00 12.00
Corridor 1 30.23 30.23
Store Below Landing 1 17.00 17.00
1 4.00 4.00
Staircase/Landing 1 14.25 14.25
Staircase Waist Slab 2 3.00 6.00
Deduction
D1 -16 1.10 -17.60
D4 -2 1.00 -2.00

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
First floor plan
Class Room 2 25.30 50.60
2 25.35 50.70
Corridor 1 30.23 30.23
Column 2 0.80 1.60
4 0.70 2.80
Staircase/Landing 1 14.25 14.25
Staircase Waist Slab 2 3.00 6.00
Deduction
D1 -16 1.10 -17.60

Second floor plan


Class Room 2 25.30 50.60
2 25.35 50.70
Partition Wall Principal/Administration 2 5.88 11.75
Column 2 0.80 1.60
4 0.70 2.80
Corridor 1 30.23 30.23
Staircase/Landing 1 14.25 14.25
Staircase Waist Slab 2 3.00 6.00
Deduction
D1 -16 1.10 -17.60
D3 -2 1.00 -2.00
Top floor Plan
Corridor 2 13.80 27.60
Top Floor inner wall 2 26.00 52.00
Top Floor Outer wall 2 26.00 52.00
On Parapet Walls 2 35.00 70.00
Roof Plan
Along Wall 1 33.00 33.00
Total 686.66 r.m

5.3 25mm Terrazo Finishing


Bench 2 2.40 0.50 2.40
Total 2.40 sq.m

6 PLASTER/PAINTING WORKS
6.1 Cement Plaster
6.1.1 Internal Plaster on Wall (1:6)
First Floor
Classroom 2.00 25.35 2.88 145.76
2.00 25.30 2.88 145.48
Staircase 1.00 17.45 2.88 50.17
Column
Grid 2C,2D 2.00 1.23 2.88 7.04
Grid 2B,2E 2.00 0.75 2.88 4.31

Deductions
W1 -16.00 1.10 1.13 -19.80
V1 -16.00 1.10 0.53 -9.24
W2 -1.00 1.50 1.00 -1.50
D1 -8.00 1.10 2.44 -21.43

Second Floor
Class Room 2.00 25.30 2.88 145.48
2.00 25.35 2.88 145.76
Staircase 1.00 17.45 2.88 50.17
Column
Grid 2C,2D 2.00 1.23 2.88 7.04
Grid 2B,2E 2.00 0.75 2.88 4.31

Deductions
W1 -16.00 1.10 1.13 -19.80
V1 -16.00 1.10 0.53 -9.24
W2 -1.00 1.50 1.00 -1.50
D1 -8.00 1.10 2.44 -21.43
Top Floor
Along Grid 1&3/ C-D 2.00 4.00 2.50 20.00

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Along Grid C&D/ 1-3 2.00 9.65 2.50 48.25
Deductions
W2 -1.00 1.50 1.00 -1.50
D2 -2.00 1.10 1.90 -4.18
Total 664.16 sq.m

6.1.2 Internal Plaster on Ceiling (1:4)


Second Floor Level (+6.00m Lvl)
Class Room 2.00 5.75 6.75 77.63
2.00 5.78 6.75 77.96
Corridor 1.00 28.80 2.63 75.60
1.00 2.07 4.20 8.70
Staircase 1.00 6.75 2.00 13.50
Staircase Landing 1.00 1.90 4.20 7.98

Main Beam (300x525)


Grid 2/C-D 1.00 4.00 0.68 2.70
Grid 3/A-F 4.00 5.55 0.93 20.54
1.00 4.00 0.93 3.70
Grid A,B,C,D,E,F /2-3 6.00 2.00 0.80 9.60

Secondary Beam (250x425)


Grid A1,B1,D1,E1 1.00 8.90 0.60 5.34
Grid 1a 1.00 18.20 0.60 10.92
Grid 1b 1.00 4.20 0.60 2.52

Top Floor Level (+9.00m Lvl)


Class Room 2.00 5.75 6.75 77.63
2.00 5.78 6.75 77.96
Corridor 1.00 28.80 2.63 75.60
1.00 2.07 4.20 8.70
Staircase 1.00 6.75 2.00 13.50
Staircase Landing 1.00 1.90 4.20 7.98

Main Beam (300x525)


Grid 2/C-D 1.00 4.00 0.68 2.70
Grid 3/A-F 4.00 5.55 0.80 17.76
1.00 4.00 0.80 3.20
Grid A,B,C,D,E,F /2-3 6.00 2.00 0.80 9.60

Secondary Beam (250x425)


Grid A1,B1,D1,E1 1.00 8.90 0.60 5.34
Grid 1a 1.00 18.20 0.60 10.92
Grid 1b 1.00 4.20 0.60 2.52

Roof Floor Level (+11.625m Lvl)


Staircase with Corridor 1.00 4.20 9.25 38.85

Main Beam (300x525)


Grid 2/C-D 1.00 4.00 0.80 3.20

Secondary Beam (250x425)


Grid 1a/C-D 1.00 4.20 0.60 2.52
Total 674.67 sq.m

6.1.3 External Plaster


6.1.3.1 Outer Plaster
Beam Plaster
First Floor Level
Main Beam (300x525)
Along grid 1 1.00 26.20 0.53 13.76
Slab Extension 1.00 23.50 1.23 28.79
Landing Beam 1.00 4.00 0.56 2.24
Along grid A,F 2.00 6.50 0.53 6.83

Second Floor Level


Main Beam (300x525)
Along grid 1 1.00 26.20 0.53 13.76

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Slab Extension 1.00 23.50 1.23 28.79
Landing Beam 1.00 4.00 0.81 3.24
Landing Beam Extension 1.00 4.00 1.23 4.90
Along grid A and F 2.00 6.50 0.53 6.83

Third Floor Level


Main Beam (300x525)
Along grid 1 1.00 26.20 0.53 13.76
Slab Extension (All Sides) 1.00 88.77 Area 88.77
Slab Extension (Top Side) 1.00 20.45 Area 20.45
Landing Beam 1.00 4.00 0.81 3.24
Landing Beam Extension 1.00 4.00 1.23 4.90
Along grid A and F 2.00 6.50 0.53 6.83

Roof Floor Level


Main Beam (300x525)
Along Perimeter 1.00 25.00 0.53 13.13
Slab Extension (All Sides) 1.00 28.30 Area 28.30
Slab Extension (Top Side) 1.00 8.75 Area 8.75

Column Plaster
Ground Floor
Along grid 1
Grid 1A,1F 2.00 1.25 3.00 7.50
Grid 1B,1C,1D,1E 4.00 0.75 3.00 9.00
Along grid 3
Grid 3A,3B,3C,3D,3E,3F 2.00 0.80 2.50 4.00
6.00 1.20 2.50 18.00
Grid 3A,3B,3C,3D 2.00 1.20 3.00 7.20
6.00 0.80 3.00 14.40
First Floor
Along grid 1
Grid 1A,1F 2.00 1.25 3.00 7.50
Grid 1B,1C,1D,1E 4.00 0.75 3.00 9.00
Along grid 2
Grid 2A,2F 2.00 1.25 3.00 7.50
Grid 2C,2D 2.00 1.23 2.50 6.13
Grid 2B,2E 2.00 0.75 2.50 3.75
Along grid 3
Grid 3A,3F 2.00 1.20 3.00 7.20
Grid 3B,3C,3D,3E 4.00 0.70 3.00 8.40
Grid 3A,3F 2.00 0.80 2.50 4.00
Grid 3B,3C,3D,3E 4.00 1.30 2.50 13.00
Second Floor
Along grid 1
Grid 1A,1F 2.00 1.25 3.00 7.50
Grid 1B,1C,1D,1E 4.00 0.75 3.00 9.00
Along grid 2
Grid 2A,2F 2.00 1.25 3.00 7.50
Grid 2C,2D 2.00 1.23 2.50 6.13
Grid 2B,2E 2.00 0.75 2.50 3.75
Along grid 3
Grid 3A,3F 2.00 1.20 3.00 7.20
Grid 3B,3C,3D,3E 4.00 0.70 3.00 8.40
Grid 3A,3F 2.00 0.80 2.50 4.00
Grid 3B,3C,3D,3E 4.00 1.30 2.50 13.00

Parapet Wall
Top Floor 2.00 35.90 0.80 57.44
1.00 7.50 1.40 10.50
Roof 1.00 32.00 0.90 28.80

Plaster on Walls
Ground floor level
Along grid A,B,C,D,E,F 6.00 6.50 2.48 96.53
Along grid 1 4.00 5.50 2.48 54.45
1.00 4.00 2.48 9.90
Along grid 2 4.00 5.50 2.48 54.45

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
First floor level
Along grid A,B,C,D,E,F 6.00 6.50 2.48 96.53
Along grid 1 4.00 5.50 2.48 54.45
1.00 4.00 2.48 9.90
Along grid 2 4.00 5.50 2.48 54.45
Second floor level
Along grid A,B,C,D,E,F 6.00 6.50 2.48 96.53
Along grid 1 4.00 5.50 2.48 54.45
1.00 4.00 2.48 9.90
Along grid 2 4.00 5.50 2.48 54.45
Partition Wall Principal/Administration 1.00 1.50 2.58 3.86

Top floor level


Along grid C,D/1-3 2.00 8.50 0.23 2.03 7.92
Along grid 1 1.00 4.00 0.23 2.03 1.86
Along grid 3 1.00 4.00 0.23 2.03 1.86

Parapet Wall
Top Floor 2.00 36.53 2.28 166.58
1.00 7.50 2.88 21.60
Roof Level 1.00 33.00 0.23 2.28 17.31

Deduction for doors and windows


Ground floor level
W1 -16.00 1.10 1.13 -19.80
V1 -16.00 1.10 0.53 -9.24
W3 -1.00 1.50 0.37 -0.56
D1 -8.00 1.10 2.29 -20.11
First floor level
W1 -16.00 1.10 1.13 -19.80
V1 -16.00 1.10 0.53 -9.24
W2 -1.00 1.50 1.00 -1.50
D1 -8.00 1.10 2.29 -20.11
Second floor level
W1 -16.00 1.10 1.13 -19.80
V1 -16.00 1.10 0.53 -9.24
W2 -1.00 1.50 1.00 -1.50
D1 -8.00 1.10 2.29 -20.11
D3 -1.00 1.00 1.95 -1.95
Top floor level
W2 -1.00 1.50 1.00 -1.50
D2 -2.00 1.10 1.83 -4.02
Total 1295.52 sq.m

7.2 Painting Works


7.2.1 Distemper Painting Works
As per Internal plaster on wall 1.00 664.16 Area 664.16
As per Internal plaster on ceiling 1.00 674.67 674.67
Total 1338.83 sq.m

7.2.2 Exterior Weather Coat Paint


As per External plaster 1.00 1295.52 Area 1295.52
Total 1295.52 sq.m

7.2.4 Enamel Painting Factor


Collapsable Gate 1.00 4.00 2.48 2.00 19.80
Doors
D1 24 1.10 2.44 2.00 128.57
D2 2 1.10 1.90 2.00 8.36
D3 1 1.00 2.10 2.00 4.20
D4 1 1.00 1.55 2.00 3.10
Window
W1 48 1.10 1.13 2.00 118.80
W2 3 1.50 1.00 2.00 9.00
V1 48 1.10 0.53 2.00 55.44
Window Grill
W1 48 0.97 1.04 47.94
W2 3 1.37 0.91 3.73

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
W3 1 1.50 0.37 2.00 1.11
V1 48 1.01 0.44 21.09
Total 421.13 sq.m

8 MISCELLANOUS
8.2 Railing
Total
Staircase Railing length Kg/m
Length
Horizontal ISNB 40M 1 22.82 22.82 3.56 81.23
Horizontal ISNB 40M (Top Floor) 1 2.13 2.13 3.56 7.57
Vertical 38mm Square Pipe 6 0.92 5.52 2.82 15.57
Vertical 38mm Square Pipe 20 0.95 19.00 2.82 53.58
Horizontal 25mm Square Pipe 4 22.82 91.27 0.85 77.58
Horizontal 25mm Square Pipe (Top Floor) 4 2.13 8.50 0.85 7.23
Base plate 21 0.00 0.00 7850.00 15.45
12 mm dia. Anchor Bolt, Nut 84 0.13 10.92

Balcony Railing
First Floor
Horizontal ISNB 40M 1 30.20 30.20 3.56 107.51
Horizontal ISNB 32M 2 30.20 60.40 3.10 187.24
Vertical ISNB 32M 23 1.14 26.22 3.10 81.28
Inclined ISNB 32M 23 0.13 3.08 3.10 9.55
Vertical 25mm Square Pipe 208 0.82 170.56 0.85 144.98
Base plate 33 0.00 0.0031 7850.00 24.29
12 mm dia. Anchor Bolt, Nut 132 0.13 17.16

Second Floor
Horizontal ISNB 40M 1 30.20 30.20 3.56 107.51
Horizontal ISNB 32M 2 30.20 60.40 3.10 187.24
Vertical ISNB 32M 23 1.14 26.22 3.10 81.28
Inclined ISNB 32M 23 0.13 3.08 3.10 9.55
Vertical 25mm Square Pipe 208 0.82 170.56 0.85 144.98
Base plate 33 0.00 0.0031 7850.00 24.29
12 mm dia. Anchor Bolt, Nut 132 0.13 17.16

Parapet Wall
ISNB 40M(Horizontal Bars) 2 36.53 73.06 3.56 260.09
ISNB 32M(Horizontal Bars) 2 36.53 73.06 3.10 226.49
Vertical ISNB 32M 60 0.40 24.00 3.10 74.40
Inclined ISNB 32M 60 0.13 8.04 3.10 24.92
Vertical 25mm Square Pipe 492 0.30 147.60 0.85 125.46
Base plate 62 0.00 0.0058 7850.00 45.63
12 mm dia. Anchor Bolt, Nut 248 0.13 32.24

Pedestal
ISNB 40M Pedestal Bars 14 1.54 21.57 3.56 76.80
14 1.20 16.80 3.56 59.81
28 0.40 11.20 3.56 39.87
Base plate 42 0.00 0.0039 7850.00 30.91
12 mm dia. Anchor Bolt, Nut 168 0.13 21.84
Total 2431.61 k.g

8.3 Sewer, Rain and Waste Water Installation


- 110 mm ED 6 kg/sqcm 4 9.00 36.00
2 2.90 5.80
Total 41.80 R.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
1 For Footing
1.1 Footing (F1) 2
X- direction 16 17 2.60 88.40 1.59 140.56 0.1 2.4

Y- direction 16 17 2.60 88.40 1.59 140.56 0.1 2.4

1.2 Footing (F2) 4


X- direction 16 20 3.10 248.00 1.59 394.32 0.1 2..9

Y- direction 16 20 3.10 248.00 1.59 394.32 0.1 2.9

1.3 Combine Footing (CF1) 3


(BLL) 12 33 2.10 207.90 0.89 185.03 0.2 1.7

(BUL) 16 12 5.30 190.80 1.59 303.37 0.2 4.9

(TUL) 12 33 2.10 207.90 0.89 185.03 0.2 1.7

(TLL) 12 12 5.30 190.80 0.89 169.81 0.2 4.9

1.4 Stirrups 10 98 3.95 1161.30 0.62 720.01 1.375


0.1
0.5

1.5 Combine Footing (CF2) 1


(BLL) 12 33 3.30 108.90 0.89 96.92 0.2 2.9

(BUL) 16 20 5.30 106.00 1.59 168.54 0.2 4.9

(TLL) 16 20 5.30 106.00 1.59 168.54 0.2 4.9

(TUL) 12 33 3.30 108.90 0.89 96.92 0.2 2.9

1.6 Stirrups 10 98 5.15 504.70 0.62 312.91 1.975


0.1
0.5

1.7 Combine Footing (CF3) 2


(BLL) 12 33 3.10 204.60 0.89 182.09 0.2 2.7

(BUL) 16 19 5.30 201.40 1.59 320.23 0.2 4.9

(TLL) 12 19 5.30 201.40 0.89 179.25 0.2 2.7

(TUL) 12 33 3.10 102.30 0.89 91.05 0.2 4.9

1.8 Stirrups 10 98 5.10 999.60 0.62 619.75 0.1


0.5
1.95

2 Column
2.1 Grid 1 (A ,B,E &F) 4
Main Bar 16 6 3.59 86.11 1.59 136.92 16mm
16 6 6.59 158.11 1.59 251.40 6.18 3.18 16mm

0.10
0.31 0.31
2.2 Grid 1 ( C ) 1
Main Bar 20 4 4.07 16.27 2.47 40.19
16 2 3.59 7.18 1.59 11.41 20mm
16 6 6.59 39.53 1.59 62.85 16mm 6.18
3.42 3.18

0.12 0.1
0.53 0.31

2.3 Grid 1 ( D ) 1
Main Bar 20 6 4.07 24.42 2.47 60.32
20 6 7.07 42.41 2.47 104.75 20mm 20mm

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
6.42 3.42

0.12
0.53 0.53

2.4 Grid 2(A,B,E & F) 4


Main Bar 20 4 4.07 65.12 2.47 160.85
16 2 3.59 28.72 1.59 45.66 16mm
16 6 6.59 158.16 1.59 251.47 20mm 16mm 6.18
3.42 3.18

0.12 0.10
0.53 0.53 0.53

2.5 Grid 2 ( C &D) 2


20 6 4.07 48.84 2.47 120.63
20 6 7.07 84.82 2.47 209.50 20mm 20mm
3.42 6.42

0.12
0.53 0.53
2.6 Grid 3 (A,B,C,D,E & F) 6
Main Bar 20 6 4.07 146.52 2.47 361.90
20 6 7.26 261.23 2.47 645.23 20mm 20mm
3.42 6.42

0.12
0.53 0.53

2.7 Stirrups 18
For 18 columns 8 12 1.84 397.44 0.40 158.98 0.08
8 24 1.28 552.96 0.40 221.18 0.42 0.14 0.08
0.42
0.42
3 For Lower Tie Beam
3.1 Grid 1,2 & 3 3 8.73
Top Bar 16 2 10.04 60.24 1.59 95.78 0.96
0.35
End bar from both
direction
16 2 11.46 68.76 1.59 109.33 11.46
8.73
16 2 10.04 60.24 1.59 95.78 0.96

2.94
Middle bar 16 1 4.25 12.75 1.59 20.27 0.96
0.35

16 1 12.00 36.00 1.59 57.24


12

16 1 12.00 36.00 1.59 57.24


12
2.94
16 1 4.25 12.75 1.59 20.27 0.96

Bottom Bar
End bar from both direction 16 2 3.33 19.98 1.59 31.77
0.66
1.71 0.96

16 2 9.00 54.00 1.59 85.86 9

16 2 11.46 68.76 1.59 109.33 0.96 10.5

16 2 9.33 55.98 1.59 89.01

0.96 7.1

Middle Bar 16 1 5.37 16.11 1.59 25.61


0.66
3.75 0.96

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
16 1 11.84 35.51 1.59 56.45 11.835

16 1 10.55 31.64 1.59 50.30 9.585


0.96

16 1 5.37 16.11 1.59 25.61


0.96 3.75

3.2 Grid A,B,C, D,E & F 6


Top Bar 16 3 8.12 146.16 1.59 232.39 7.42
0.35

Bottom Bar 16 3 8.74 157.32 1.59 250.14


0.35
7.42

3.3 Stirrups (LTB)


1 8 1113 1.36 1513.68 0.40 605.47 0.8
0.35

0.25

4 Plinth tie beam


4.1 Grid 1,2 & 3 3 8.61 1.2
Top Bar 20 2 10.24 61.41 2.47 151.68
0.425
End bar from both
direction 20 2 11.70 70.20 2.47 173.39 11.7

8.61
20 2 10.24 61.41 2.47 151.68 1.2

2.94
Middle bar 16 1 4.33 12.98 1.59 20.63 0.96
0.425
16 1 12.00 36.00 1.59 57.24 12

16 1 12.00 36.00 1.59 57.24 12

2.94
16 1 4.33 12.98 1.59 20.63 0.96

Bottom Bar
End bar from both 20 2 11.65 69.90 2.47 172.65
0.94
direction 9.51 1.2

20 2 11.70 70.20 2.47 173.39 11.7

20 2 9.85 59.10 2.47 145.98


1.2 7.71

Middle Bar 16 1 9.33 27.99 1.59 44.50


0.66
7.71 0.96

16 1 11.46 34.38 1.59 54.66 11.46

16 1 11.37 34.11 1.59 54.23 0.96 9.75

4.2 Grid A,B,C,D,E & F 6


Top bar 20 2 11.17 134.04 2.47 331.08
9.92
0.625

16 1 11.17 67.02 1.59 106.56 9.92


0.625

Bottom bar 20 2 11.80 141.60 2.47 349.75


0.94
9.92

16 1 11.24 67.44 1.59 107.23


0.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
0.66
9.92

4.3 Stirrups 1 12 126 1.54 194.04 0.89 172.70 0.12 0.1


10 1113 1.50 1669.50 0.62 1035.09 0.4 0.4

0.25 0.25
5 Column ( Up To 1st Floor Level)
5.1 Grid 1 (A ,B,E & F) 4
Main Bar 16 6 6.96 167.04 1.59 265.59 16mm
6

0.96

5.2 Grid 1 ( C ) 1
Main Bar 20 4 7.20 28.80 2.47 71.14
16 2 6.96 13.92 1.59 22.13 20mm 16mm

0.12 0.96

5.3 Grid 1 ( D ) 1
Main Bar 20 6 7.20 43.20 2.47 106.70
6 20mm
2.47

1.2

5.4 Grid 2(A,B,E & F) 4


Main Bar 20 4 7.20 115.20 2.47 284.54
16 2 6.96 55.68 1.59 88.53 6 6.00 16mm
20mm

1.20 0.96

5.5 Grid 2 ( C &D) 2


20 6 7.20 86.40 2.47 213.41
20mm
6

1.2

5.6 Grid 3 (A,B,C,D,E & F) 6


Main Bar 20 6 7.20 259.20 2.47 640.22
20mm
6

1.20

5.7 Stirrups 18
For 18 columns 8 31 1.84 1026.72 0.40 410.69 0.08
8 62 1.28 1428.48 0.40 571.39 0.42 0.14 0.08
1.59 0.42
0.42
6 For Staircase
(Plinth level to 1st floor level)
1.703
Main Bar (top bar) 1 16 21 8.23 172.81 1.59 274.77

3.354
2.472
0.4

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)

Bottom Bar 1 16 21 3.27 68.71 1.59 109.25

2.042 1.03
0.2

1
Extra Bar 1 16 21 2.00 42.00 1.59 66.78
1

1.853
Landing bottom bar 1 16 21 3.00 63.06 1.59 100.27 1

1.2
Landing Extra bar 1 16 21 2.20 46.20 1.59 73.46 1

Distribution Bar 1 10 23 4.16 95.68 0.62 59.32 4.16

Bar in middle of landing 1 16 4 1.84 7.34 1.59 11.67 1.8


(20cm gap)
1 10 65 1.96 127.40 0.62 78.99 1.96

Top Bar 1 16 21 8.13 170.81 1.59 271.59


1.54
0.4
3.397

Bottom Bar 1 16 21 3.30 69.24 1.59 110.09

1
2.147

1
Extra Bar 1 16 21 2.20 46.20 1.59 73.46 1.2

1.82
Bottom bar( Slab level) 1 16 21 3.02 63.42 1.59 100.84 0.2 1

Extra Bar 1 16 21 2.00 42.00 1.59 66.78 1


1

Distribution Bar 1 10 100 1.96 196.00 0.62 121.52 1.96

1 10 42 4.16 174.72 0.62 108.33 4.16


0.15 0.565
Nosing Ties(Plinth Level To 0.112 0.162 0.112
First Floor Level ) 0.15 0.15
First type 8 35 0.67 23.59 0.40 9.44 0.565 0.15
Second type 8 7 0.98 6.84 0.40 2.74 0.412
Third type 8 14 1.13 15.86 0.40 6.34 0.268 0.112
Forth type 8 7 0.83 5.81 0.40 2.32 0.15
Fifth type 8 7 0.67 4.72 0.40 1.89 0.268 0.15 0.15
0.262
0.15
Nosing Bar 2 10 10 1.96 39.20 0.62 24.30 1.96

4.92
6.1 Landing Beam 1 20 3 5.62 16.86 2.47 41.64 0.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
1 20 3 5.62 16.86 2.47 41.64 0.35
4.92
6.2 Sturriups 1 8 35 1.22 42.70 0.40 17.08 0.08
0.375

7 Main Beam (First Floor Level) 0.2

7.1 Grid A,B,C,D,E & F


Bottom bar (End Bar) 6 25 2 7.25 87.00 2.47 214.89 1.29

4.46 1.5

6 25 2 6.75 81.00 3.86 312.66 5.46

Bottom Bar (mid-bars) 6 20 2 11.80 141.60 2.47 349.75


0.94
9.92

Top Bar 6 20 3 11.80 212.40 2.47 524.63 9.92


0.94

Extra Bar 6 25 2 6.50 78.00 3.86 301.08 5.06 0.15


1.29

6 25 2 4.00 48.00 3.86 185.28 2.56 0.15


1.29

Torsion Bars (T/O) 6 16 2 9.80 117.60 1.59 186.98 9.8

7.2 Grid 1
0.94
Bottom Bar (end bar) 1 20 2 5.65 11.30 2.47 27.91 1.2
3.51

20 2 11.40 22.80 2.47 56.32 10.2 1.2

20 2 7.50 15.00 2.47 37.05 7.5

20 2 9.85 19.70 2.47 48.66


1.2 7.71

Middle Bar 16 2 3.33 6.66 1.59 10.59


0.66
1.71 0.96
16 2 9.00 18.00 1.59 28.62
9

16 2 11.46 22.92 1.59 36.44 10.5


0.96

16 2 9.33 18.66 1.59 29.67

0.96 7.71

Top Bar (End Bar) 16 2 10.35 20.70 1.59 32.91 8.73 0.96
0.66

16 2 11.46 22.92 1.59 36.44 11.46

0.96 8.73
16 2 10.35 20.70 1.59 32.91

2.94 0.96
Middle Bar 16 1 4.56 4.56 1.59 7.25
0.66
16 1 12.00 12.00 1.59 19.08 12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)

0.96
16 1 12.00 12.00 1.59 19.08 11.04

16 1 4.56 4.56 1.59 7.25 2.94


0.96

7.3 Grid 2 & 3


Bottom Bar 2 20 4 5.65 22.60 2.47 55.82
0.94
3.51 1.2

20 4 11.40 45.60 2.47 112.63 10.2


1.2

20 4 7.50 30.00 2.47 74.10 7.5

20 4 9.85 39.40 2.47 97.32


1.2 7.71

Middle Bar 20 4 3.85 15.40 2.47 38.04


1.2 1.71
20 4 9.00 36.00 2.47 88.92
9

20 4 9.90 39.60 2.47 97.81 8.7


1.2

20 4 11.65 46.60 2.47 115.10


1.2 9.51
1.2
Top Bar 20 4 10.75 43.00 2.47 106.21 8.61
0.94

20 4 11.70 46.80 2.47 115.60 11.7

20 4 10.75 43.00 2.47 106.21 1.2 8.61

3.06
20 2 5.20 10.40 2.47 25.69 .1.2
0.94

20 2 12.00 24.00 2.47 59.28 10.8


1.2
20 2 12.00 24.00 2.47 59.28
12
1.2
20 2 5.20 10.40 2.47 25.69 3.06

2.21
7.4 Extra Bar Along Grid 1,2 &3 3 25 4 3.65 43.80 3.86 169.07 0.15
1.29
4
3 25 4 4.30 51.60 3.86 199.18 0.15

3.5
3 25 4 3.80 45.60 3.86 176.02 0.15

7.5 Torision bars along grid 1,2 &3


1st arrangement 3 16 1 3.69 11.07 1.59 17.60 3.69

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 4.11 12.33 1.59 19.60 4.11

2nd arrangement 3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)

3 16 1 6.84 20.52 1.59 32.63 6.84

7.6 Secondry Beam


Along Grid A1,B1,D1 & E1
0.35
Bottom Bar 4 16 3 10.45 125.40 1.59 199.39
9.75

Top Bar 4 16 3 10.45 125.40 1.59 199.39 9.75


0.35

Grid 1a (end bottom bar) 2 16 2 2.94 11.74 1.59 18.67


0.35
1.625 0.96

2 16 2 10.85 43.40 1.59 69.01


10.5

middle bar 2 16 1 8.81 17.62 1.59 28.02


0.35
7.5 0.96

2 16 1 4.98 9.95 1.59 15.82


4.625
top bar (end bar) 2 16 2 4.06 16.22 1.59 25.79
2.645 0.96
0.45

2 16 2 10.55 42.20 1.59 67.10 9.605

middle bar 2 16 1 4.06 8.11 1.59 12.89 2.645 0.96


0.45

2 16 1 10.06 20.11 1.59 31.97 9.605

grid 1b
bottom bar 1 12 4 5.45 21.80 0.89 19.40
0.35
4.75

4.75
top bar 1 12 3 5.65 16.95 0.89 15.09 0.45

7.7 Conceal Beam 2 20 6 1.61 19.32 0.89 17.19 1.21


0.4

7.8 Bent up Bar (hunch bar) 1 16 36 3.02 108.72 1.59 172.86


0.96 0.425 0.425

250

7.9 Stirriups( For Main Beam) 1 10 1125 1.65 1856.25 0.62 1150.88 0.10
0.425

0.25
7.10 For Secondry Beam 1 8 540 1.31 707.40 0.40 282.96
0.8
0.375

0.2

8 For Slab (First Floor)


8.1 Main Bars 0.375
Along short span 0.07
straight bar 1 8 76 10.93 830.30 0.40 332.12 10.48
0.375 1.5 1.75
Cranked bar 1 8 76 11.09 842.46 0.40 336.98 0.05
1.975 1.75 1.75
0.525

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
Along Long Span (grid 1 to grid2)
Straight bar 1 8 45 12.00 540.00 0.40 216.00 11.475
1 8 45 2.22 99.90 0.40 39.96 1.695 0.525
0.525 1.5
cranked bar 1 8 44 11.03 485.10 0.40 194.04 0.07 1.5
2.25 0.525
1 8 44 4.75 208.78 0.40 83.51 1.9 0.07
2.25
along long span Grid 2 to 3 0.525
Straight bar 1 8 7 12.00 84.00 0.40 33.60 11.475

1 8 7 12.00 84.00 0.40 33.60 12


0.525
1 8 7 7.20 50.40 0.40 20.16 6.675
0.525 1.5
cranked bar 1 8 7 10.38 72.63 0.40 29.05 1.5 1.5
2.35 1.5
1.15 1.875 1.875
1 8 7 11.72 82.04 0.40 32.82 1.5 2.25
1.5
1.15 1.5
1 8 7 10.38 72.63 0.40 29.05 1.5 1.5 1.5

Infront of stair case


Straight bar 1 8 15 5.69 85.35 0.40 34.14 6.33
1.875 1.095 0.75
Cranked bar 1 8 13 5.97 77.61 0.40 31.04 1.125 0.845 0.07

8.2 Distribution bars


Between Grid 1 &1a
along x-axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y- axis 1 8 80 3.20 256.00 0.40 102.40 3.2

Between grid 1a & 2


along x axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y axis 1 8 84 3.20 268.80 0.40 107.52 3.2

Between grid 2 & 3


except infront of staircas 2.72
along x axis 1 8 64 2.72 174.08 0.40 69.63 2.2
along y axis 1 8 88 2.20 193.60 0.40 77.44
Between grid 1b & 2 infront of
staicase
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 1.29 23.22 0.40 9.29 1.29

between 2 & 3
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Cantilever Slab beyond grid 1


bottom bar 1 10 3 11.46 34.38 0.62 21.32 11.46
top bar 1 10 3 11.46 34.38 0.62 21.32 11.46

Cantilever slab at the front


top bar ( horizontal portion) 1 10 3 7.10 21.30 0.62 13.21 7.1
bottom bar 1 10 3 7.10 21.30 0.62 13.21 7.1

Vertical portion 1 10 4 7.86 31.44 0.62 19.49 7.86


1 10 4 7.86 31.44 0.62 19.49 7.86

8.3 Negative Bars


along Grid 1 2 8 35 2.05 143.50 0.40 57.40 2.05
along grid 1a 2 8 35 2.35 164.50 0.40 65.80 2.35
along grid 1b 1 8 7 1.08 7.56 0.40 3.02 1.08
along grid 2 (except infront of
stair case) 2 8 35 2.10 147.00 0.40 58.80 2.1
along grid 2 in front of
staircase 1 8 14 1.38 19.32 0.40 7.73 1.38

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
along grid a1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid b 1 8 28 2.10 58.80 0.40 23.52 2.1
along b1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid c&d 2 8 9 2.55 45.90 0.40 18.36 2.55
along grid d1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid e 1 8 28 2.10 58.80 0.40 23.52 2.1
along grid e1 1 8 28 2.05 57.40 0.40 22.96 2.05

9 Bands
Ground Floor
9.1 Sill Bands 0.75 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.46 0.075 5.5
1 10 2 4.50 9.00 0.62 5.58 4.5
0.75 0.75
1 10 2 5.65 11.30 0.62 7.01 0.075 4

Grid 2 4 10 2 1.81 14.48 0.62 8.98 1.81

Grid A,B,C,D,E&F 6 10 2 8.15 97.80 0.62 60.64 0.75 6.5 0.75


0.075
9.2 Lintel Band 0.75 5.5 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.46 0.075
Grid 2 4 10 2 1.81 14.48 0.62 8.98 0.75 1.81
Grid A,B,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.075 6.5
9.3 Vertical Band 8 10 2 4.13 66.00 0.62 40.92 0.75 0.75
0.075 2.475
9.4 Sturriups 1 8 1020 0.30 306.00 0.40 36.72 0.06 0.06
0.18

10 Column ( Up To 2nd Floor Level)


10.1 Grid 1 (A ,B,E & F) 4
Main Bar 16 6 6.96 167.04 1.59 265.59 16mm
6

0.96

10.2 Grid 1 ( C ) 1
Main Bar 20 4 7.20 28.80 2.47 71.14
16 2 6.96 13.92 1.59 22.13 20mm 16mm

0.12 0.96

10.3 Grid 1 ( D ) 1
Main Bar 20 6 7.20 43.20 2.47 106.70
6 20mm
2.47

1.2

10.4 Grid 2(A,B,E & F) 4


Main Bar 20 4 7.20 115.20 2.47 284.54
16 2 6.96 55.68 1.59 88.53 6 6.00 16mm
20mm

1.20 0.96

10.5 Grid 2 ( C &D) 2


20 6 7.20 86.40 2.47 213.41
20mm
6

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
1.2

10.6 Grid 3 (A,B,C,D,E & F) 6


Main Bar 20 6 7.20 259.20 2.47 640.22
20mm
6

1.20

10.7 Stirrups 18
For 18 columns 8 31 1.84 1026.72 0.40 410.69 0.08
8 62 1.28 1428.48 0.40 571.39 0.42 0.14 0.08
1.59 0.42
0.42

10.8 Band (First Floor)


Sill Bands 0.75 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.46 0.075 5.5
1 10 2 4.50 9.00 0.62 5.58 4.5
0.75 0.75
1 10 2 5.65 11.30 0.62 7.01 0.075 4

Grid 2 4 10 2 1.81 14.48 0.62 8.98 1.81

Grid A,B,C,D,E&F 6 10 2 8.15 97.80 0.62 60.64 0.75 6.5 0.75


0.075
Lintel Band 0.75 5.5 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.46 0.075
Grid 2 4 10 2 1.81 14.48 0.62 8.98 0.75 1.81
Grid A,B,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.075 6.5
Vertical Band 8 10 2 4.13 66.00 0.62 40.92 0.75 0.75
0.075 2.475

Sturriups 1 8 1020 0.30 306.00 0.40 36.72 0.06 0.06


0.18

11 For Staircase
(1st Floor level to 2nd Floor Level)
1.703
Main Bar (top bar) 1 16 21 8.23 172.81 1.59 274.77

3.354
2.472
0.4

Bottom Bar 1 16 21 3.27 68.71 1.59 109.25

2.042 1.03
0.2

1
Extra Bar 1 16 21 2.00 42.00 1.59 66.78
1

1.853
Landing bottom bar 1 16 21 3.00 63.06 1.59 100.27 1

1.2
Landing Extra bar 1 16 21 2.20 46.20 1.59 73.46 1

Distribution Bar 1 10 23 4.16 95.68 0.62 59.32 4.16

Bar in middle of landing 1 16 4 1.84 7.34 1.59 11.67 1.8


(20cm gap)
1 10 65 1.96 127.40 0.62 78.99 1.96

Landing Level to First Floor level

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
Top Bar 1 16 21 8.13 170.81 1.59 271.59
1.54
0.4
3.397

Bottom Bar 1 16 21 3.30 69.24 1.59 110.09

1
2.147

1
Extra Bar 1 16 21 2.20 46.20 1.59 73.46 1.2

1.82
Bottom bar( Slab level) 1 16 21 3.02 63.42 1.59 100.84 0.2 1

Extra Bar 1 16 21 2.00 42.00 1.59 66.78 1


1

Distribution Bar 1 10 100 1.96 196.00 0.62 121.52 1.96

1 10 42 4.16 174.72 0.62 108.33 4.16


0.15 0.565
Nosing Ties(Plinth Level To 0.112 0.162 0.112
First Floor Level ) 0.15 0.15
First type 8 35 0.67 23.59 0.40 9.44 0.565 0.15
Second type 8 7 0.98 6.84 0.40 2.74 0.412
Third type 8 14 1.13 15.86 0.40 6.34 0.268 0.112
Forth type 8 7 0.83 5.81 0.40 2.32 0.15
Fifth type 8 7 0.67 4.72 0.40 1.89 0.268 0.15 0.15
0.262
0.15
Nosing Bar 2 10 10 1.96 39.20 0.62 24.30 1.96

11.1 Beam 4.92


Landing Beam 1 20 3 5.62 16.86 2.47 41.64 0.35

1 20 3 5.62 16.86 2.47 41.64 0.35


4.92
Sturriups 1 8 35 1.22 42.70 0.40 17.08
0.08
0.375

0.2
12 Main Beam(Second Floor Level)
12.1 Grid A,B,C,D,E & F
Bottom bar (End Bar) 6 25 2 7.25 87.00 2.47 214.89 1.29

4.46 1.5

6 25 2 6.75 81.00 3.86 312.66 5.46

Bottom Bar (mid-bars) 6 20 2 11.80 141.60 2.47 349.75


0.94
9.92

Top Bar 6 20 3 11.80 212.40 2.47 524.63 9.92


0.94

Extra Bar 6 25 2 6.50 78.00 3.86 301.08 5.06 0.15


1.29

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
1.29

6 25 2 4.00 48.00 3.86 185.28 2.56 0.15


1.29

Torsion Bars (T/O) 6 16 2 9.80 117.60 1.59 186.98 9.8

12.2 Grid 1
0.94
Bottom Bar (end bar) 1 20 2 5.65 11.30 2.47 27.91 1.2
3.51

20 2 11.40 22.80 2.47 56.32 10.2 1.2

20 2 7.50 15.00 2.47 37.05 7.5

20 2 9.85 19.70 2.47 48.66


1.2 7.71

Middle Bar 16 2 3.33 6.66 1.59 10.59


0.66
1.71 0.96
16 2 9.00 18.00 1.59 28.62
9

16 2 11.46 22.92 1.59 36.44 10.5


0.96

16 2 9.33 18.66 1.59 29.67

0.96 7.71

Top Bar (End Bar) 16 2 10.35 20.70 1.59 32.91 8.73 0.96
0.66

16 2 11.46 22.92 1.59 36.44 11.46

0.96 8.73
16 2 10.35 20.70 1.59 32.91

2.94 0.96
Middle Bar 16 1 4.56 4.56 1.59 7.25
0.66
16 1 12.00 12.00 1.59 19.08 12

0.96
16 1 12.00 12.00 1.59 19.08 11.04

16 1 4.56 4.56 1.59 7.25 2.94


0.96

12.3 Grid 2 & 3


Bottom Bar 2 20 4 5.65 22.60 2.47 55.82
0.94
3.51 1.2

20 4 11.40 45.60 2.47 112.63 10.2


1.2

20 4 7.50 30.00 2.47 74.10 7.5

20 4 9.85 39.40 2.47 97.32


1.2 7.71

Middle Bar 20 4 3.85 15.40 2.47 38.04


1.2 1.71
20 4 9.00 36.00 2.47 88.92
9

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)

20 4 9.90 39.60 2.47 97.81 8.7


1.2

20 4 11.65 46.60 2.47 115.10


1.2 9.51
1.2
Top Bar 20 4 10.75 43.00 2.47 106.21 8.61
0.94

20 4 11.70 46.80 2.47 115.60 11.7

20 4 10.75 43.00 2.47 106.21 1.2 8.61

3.06
20 2 5.20 10.40 2.47 25.69 .1.2
0.94

20 2 12.00 24.00 2.47 59.28 10.8


1.2
20 2 12.00 24.00 2.47 59.28
12
1.2
20 2 5.20 10.40 2.47 25.69 3.06

2.21
12.4 Extra Bar Along Grid 1,2 &3 3 25 4 3.65 43.80 3.86 169.07 0.15
1.29
4
3 25 4 4.30 51.60 3.86 199.18 0.15

3.5
3 25 4 3.80 45.60 3.86 176.02 0.15

12.5 Torision bars along grid 1,2 &3


1st arrangement 3 16 1 3.69 11.07 1.59 17.60 3.69

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 4.11 12.33 1.59 19.60 4.11

2nd arrangement 3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 6.84 20.52 1.59 32.63 6.84

12.6 Secondry Beam


Along Grid A1,B1,D1 & E1
0.35
Bottom Bar 4 16 3 10.45 125.40 1.59 199.39
9.75

Top Bar 4 16 3 10.45 125.40 1.59 199.39 9.75


0.35

Grid 1a (end bottom bar) 2 16 2 2.94 11.74 1.59 18.67


0.35
1.625 0.96

2 16 2 10.85 43.40 1.59 69.01


10.5

middle bar 2 16 1 8.81 17.62 1.59 28.02


0.35
7.5 0.96

2 16 1 4.98 9.95 1.59 15.82


4.625
top bar (end bar) 2 16 2 4.06 16.22 1.59 25.79

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
2.645 0.96
0.45

2 16 2 10.55 42.20 1.59 67.10 9.605

middle bar 2 16 1 4.06 8.11 1.59 12.89 2.645 0.96


0.45

2 16 1 10.06 20.11 1.59 31.97 9.605

grid 1b
bottom bar 1 12 4 5.45 21.80 0.89 19.40
0.35
4.75

4.75
top bar 1 12 3 5.65 16.95 0.89 15.09 0.45

12.7 Bent up Bar (hunch bar) 1 16 36 3.02 108.72 1.59 172.86


0.96 0.425 0.425

250

12.8 Stirrups( For Main Beam) 1 10 1125 1.65 1856.25 0.62 1150.88 0.10
0.425

0.25
12.9 Stirrups ( For Secondry Beam) 1 8 540 1.31 707.40 0.40 282.96
0.8
0.375

0.2

13 For Slab (2nd Floor Level)


Main Bars 0.375
Along short span 0.07
straight bar 1 8 76 10.93 830.30 0.40 332.12 10.48
0.375 1.5 1.75
Cranked bar 1 8 76 11.09 842.46 0.40 336.98 0.05
1.975 1.75 1.75
0.525
Along Long Span (grid 1 to grid2)
Straight bar 1 8 45 12.00 540.00 0.40 216.00 11.475
1 8 45 2.22 99.90 0.40 39.96 1.695 0.525
0.525 1.5
cranked bar 1 8 44 11.03 485.10 0.40 194.04 0.07 1.5
2.25 0.525
1 8 44 4.75 208.78 0.40 83.51 1.9 0.07
2.25
along long span Grid 2 to 3 0.525
Straight bar 1 8 7 12.00 84.00 0.40 33.60 11.475

1 8 7 12.00 84.00 0.40 33.60 12


0.525
1 8 7 7.20 50.40 0.40 20.16 6.675
0.525 1.5
cranked bar 1 8 7 10.38 72.63 0.40 29.05 1.5 1.5
2.35 1.5
1.15 1.875 1.875
1 8 7 11.72 82.04 0.40 32.82 1.5 2.25
1.5
1.15 1.5
1 8 7 10.38 72.63 0.40 29.05 1.5 1.5 1.5

0.375
Infront of stair case
Straight bar 1 8 15 4.92 73.80 0.40 29.52 4.92
0.375 1.065 0.75

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
Cranked bar 1 8 13 5.12 66.56 0.40 26.62 1.875 0.845 0.07

Distribution bars
Between Grid 1 &1a
along x-axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y- axis 1 8 80 3.20 256.00 0.40 102.40 3.2

Between grid 1a & 2


along x axis 1 8 96 2.72 261.12 0.40 104.45 2.72
along y axis 1 8 84 3.20 268.80 0.40 107.52 3.2

Between grid 2 & 3


except infront of staircas 2.72
along x axis 1 8 64 2.72 174.08 0.40 69.63 2.2
along y axis 1 8 88 2.20 193.60 0.40 77.44
Between grid 1b & 2 infront of
staicase
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 1.29 23.22 0.40 9.29 1.29

between 2 & 3
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Cantilever Slab beyond grid 1


bottom bar 1 10 3 11.46 34.38 0.62 21.32 11.46
top bar 1 10 3 11.46 34.38 0.62 21.32 11.46

Negative Bars
along Grid 1 2 8 35 2.05 143.50 0.40 57.40 2.05
along grid 1a 2 8 35 2.35 164.50 0.40 65.80 2.35
along grid 1b 1 8 7 1.08 7.56 0.40 3.02 1.08
along grid 2 (except infront of
stair case) 2 8 35 2.10 147.00 0.40 58.80 2.1
along grid 2 in front of
staircase 1 8 14 1.38 19.32 0.40 7.73 1.38
along grid a1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid b 1 8 28 2.10 58.80 0.40 23.52 2.1
along b1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid c&d 2 8 9 2.55 45.90 0.40 18.36 2.55
along grid d1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid e 1 8 28 2.10 58.80 0.40 23.52 2.1
along grid e1 1 8 28 2.05 57.40 0.40 22.96 2.05

14 Column ( Up to 3rd Floor Level)


14.1 Grid 1 (A ,B,E & F) 4
Main Bar 16 6 3.34 80.19 1.59 127.50 16mm
2.38

0.96

14.2 Grid 1 (C ) 1 16 6 5.97 35.82 1.59 56.95


5.00625 16mm

0.96

14.3 Grid 1 ( D ) 1
Main Bar 20 2 6.21 12.41 2.47 30.66
16 4 5.97 23.87 1.59 37.95 6 20mm 16mm
5.00625 5.00625

1.2 0.96

14.4 Grid 2(A,B,E & F) 4


Main bar 16 6 3.34 80.16 1.59 127.45 16mm

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
2.38

0.96

14.5 Grid 2 ( C &D) 2


20 2 6.21 24.83 2.47 61.32
16 4 5.97 47.73 1.59 75.89 20mm 5.00625 16mm
5.00625

1.2 0.96

14.6 Grid 3 (A,B,C,D,E & F) 6


Main Bar 20 2 3.58 42.98 2.47 106.15
16 4 3.34 80.16 1.59 127.45 2.38 20mm 2.38
16mm

1.20 0.96

14.7 Stirrups 18
For 18 columns 8 31 1.84 1026.72 0.40 410.69 0.08
8 62 1.28 1428.48 0.40 571.39 0.42 0.14 0.08
0.42
0.42
14.8 Band (Second Floor)
Sill Bands 0.75 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.46 0.075 5.5
1 10 2 4.50 9.00 0.62 5.58 4.5
0.75 0.75
1 10 2 5.65 11.30 0.62 7.01 0.075 4

Grid 2 4 10 2 1.81 14.48 0.62 8.98 1.81

Grid A,B,C,D,E&F 6 10 2 8.15 97.80 0.62 60.64 0.75 6.5 0.75


0.075
Lintel Band 0.75 5.5 0.75
Grid 1 4 10 2 7.15 57.20 0.62 35.46 0.075
Grid 2 4 10 2 1.81 14.48 0.62 8.98 0.75 1.81
Grid A,B,C,D,E&F 5 10 2 8.15 81.50 0.62 50.53 0.075 6.5
Vertical Band 8 10 2 4.13 66.00 0.62 40.92 0.75 0.75
0.075 2.475

Sturriups 1 8 1020 0.30 306.00 0.40 36.72 0.06 0.06


0.18

15 For Staircase
(2nd Floor to Top Foor)
1.703
Main Bar (top bar) 1 16 21 8.23 172.81 1.59 274.77

3.354
2.472
0.4

Bottom Bar 1 16 21 3.27 68.71 1.59 109.25

2.042 1.03
0.2

1
Extra Bar 1 16 21 2.00 42.00 1.59 66.78
1

1.853
Landing bottom bar 1 16 21 3.00 63.06 1.59 100.27 1

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
1.2
Landing Extra bar 1 16 21 2.20 46.20 1.59 73.46 1

Distribution Bar 1 10 23 4.16 95.68 0.62 59.32 4.16

Bar in middle of landing 1 16 4 1.84 7.34 1.59 11.67 1.8


(20cm gap)
1 10 65 1.96 127.40 0.62 78.99 1.96

Landing Level to +9000 level


Top Bar 1 16 21 8.13 170.81 1.59 271.59
1.54
0.4
3.397

Bottom Bar 1 16 21 3.30 69.24 1.59 110.09

1
2.147

1
Extra Bar 1 16 21 2.20 46.20 1.59 73.46 1.2

1.82
Bottom bar( Slab level) 1 16 21 3.02 63.42 1.59 100.84 0.2 1

Extra Bar 1 16 21 2.00 42.00 1.59 66.78 1


1

Distribution Bar 1 10 100 1.96 196.00 0.62 121.52 1.96

1 10 42 4.16 174.72 0.62 108.33 4.16


0.15 0.565
Nosing Ties(Plinth Level To 0.112 0.162 0.112
First Floor Level ) 0.15 0.15
First type 8 35 0.67 23.59 0.40 9.44 0.565 0.15
Second type 8 7 0.98 6.84 0.40 2.74 0.412
Third type 8 14 1.13 15.86 0.40 6.34 0.268 0.112
Forth type 8 7 0.83 5.81 0.40 2.32 0.15
Fifth type 8 7 0.67 4.72 0.40 1.89 0.268 0.15 0.15
0.262
0.15
Nosing Bar 2 10 10 1.96 39.20 0.62 24.30 1.96

4.92
15.1 Landing Beam 1 20 3 5.62 16.86 2.47 41.64 0.35

1 20 3 5.62 16.86 2.47 41.64 0.35


4.92
15.2 Sturriups 1 8 35 1.22 42.70 0.40 17.08
0.08
0.375

0.2
16 Main Beam (Top Floor Level))
16.1 Grid A,B,E & F
Bottom bar (mid bar) 4 20 2 10.87 86.96 2.47 214.79 0.475

9.92

0.475
End Bar 4 25 2 10.87 86.96 3.86 335.67 9.92

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)

Bottom bar along C & D 2 25 2 7.25 29.00 3.86 111.94


1.29
4.46 1.5

2 20 2 6.75 27.00 3.86 104.22


5.46

0.94
Bottom Bar along C & D 2 20 2 11.80 47.20 2.47 116.58 0.92

6 20 3 11.80 212.40 2.47 524.63 0.94 9.92

16.2 Extra Bar 6 25 2 6.50 78.00 3.86 301.08 5.06 0.15


1.29

6 25 2 4.00 48.00 3.86 185.28 2.56 0.15


1.29

16.3 Torsion Bars (T/O) 6 16 2 9.80 117.60 1.59 186.98 9.8

16.4 Grid 1
0.475
Bottom Bar (end bar) 1 20 2 3.39 6.77 2.47 16.72 1.2
1.71

20 2 9.00 18.00 2.47 44.46 9

20 2 11.70 23.40 2.47 57.80 1.2 10.5

20 2 9.39 18.77 2.47 46.36


1.2 7.71

Middle Bar 16 2 3.15 6.29 1.59 10.00


0.475
1.71 0.96
16 2 9.00 18.00 1.59 28.62
9

16 2 11.46 22.92 1.59 36.44 10.5


0.96

16 2 9.15 18.29 1.59 29.08

0.96 7.71

Top Bar (End Bar) 16 2 10.35 20.70 1.59 32.91 8.73 0.96
0.66

16 2 11.46 22.92 1.59 36.44 11.46

0.96 8.73
16 2 10.35 20.70 1.59 32.91

2.94 0.96
Middle Bar 16 1 4.56 4.56 1.59 7.25
0.66
16 1 12.00 12.00 1.59 19.08 12

0.96
16 1 12.00 12.00 1.59 19.08 11.04

16 1 4.56 4.56 1.59 7.25 2.94


0.96

16.5 Extra Bar Along Grid 1 1 25 4 3.65 14.60 3.86 56.36 0.15
1.29

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
1.29
4
1 25 4 4.30 17.20 3.86 66.39 0.15

3.5
1 25 4 3.80 15.20 3.86 58.67 0.15

16.6 Grid 2 & 3


Bottom Bar 2 20 4 3.39 27.08 2.47 66.89
0.475
1.71 1.2

20 4 9.00 72.00 2.47 177.84 9

20 4 11.70 93.60 2.47 231.19 1.2 10.5

20 4 9.39 75.08 2.47 185.45


1.2 7.71

1.2
Top Bar (end Bar) 20 4 10.75 43.00 2.47 106.21 8.61
0.94

20 4 11.70 46.80 2.47 115.60 11.7

20 4 10.75 43.00 2.47 106.21 1.2 8.61

3.06
middle bar 20 2 5.20 10.40 2.47 25.69 .1.2
0.94

20 2 12.00 24.00 2.47 59.28 10.8


1.2
20 2 12.00 24.00 2.47 59.28
12
1.2
20 2 5.20 10.40 2.47 25.69 3.06

2.21
16.7 Extra Bar Along Grid 1,2 &3 2 20 4 3.65 29.20 2.47 72.12 0.15
1.29
4
2 20 4 4.30 34.40 2.47 84.97 0.15

3.5
2 20 4 3.80 30.40 2.47 75.09 0.15

16.8 Torision bars along grid 1,2 &3


1st arrangement 3 16 1 3.69 11.07 1.59 17.60 3.69

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 4.11 12.33 1.59 19.60 4.11

2nd arrangement 3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 12.00 36.00 1.59 57.24 12

3 16 1 6.84 20.52 1.59 32.63 6.84

16.9 Secondry Beam


Along Grid A1,B1,D1 & E1
0.35
Bottom Bar 4 16 3 10.45 125.40 1.59 199.39
9.75

Top Bar 4 16 3 10.45 125.40 1.59 199.39 9.75


0.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
0.35

Grid 1a (end bottom bar) 2 16 2 2.94 11.74 1.59 18.67


0.35
1.625 0.96

2 16 2 10.85 43.40 1.59 69.01


10.5

middle bar 2 16 1 8.81 17.62 1.59 28.02


0.35
7.5 0.96

2 16 1 4.98 9.95 1.59 15.82


4.625
top bar (end bar) 2 16 2 4.06 16.22 1.59 25.79
2.645 0.96
0.45

2 16 2 10.55 42.20 1.59 67.10 9.605

middle bar 2 16 1 4.06 8.11 1.59 12.89 2.645 0.96


0.45

2 16 1 10.06 20.11 1.59 31.97 9.605

grid 1b
bottom bar 1 12 4 5.45 21.80 0.89 19.40
0.35
4.75

4.75
top bar 1 12 3 5.65 16.95 0.89 15.09 0.45

16.10 Bent up Bar (hunch bar) 1 16 36 3.02 108.72 1.59 172.86 0.96

0.425 0.425
0.25

16.11 Stirriups( For Main Beam) 1 10 1125 1.65 1856.25 0.62 1150.88 0.10
0.425

0.25
16.12 For Secondry Beam 1 8 540 1.31 707.40 0.40 282.96
0.8
0.375

0.2

16.13 Beam under slab (250*150) 7.195


Near grid 1 2 12 4 9.09 72.68 0.89 64.69
1.89

7.215
2 12 4 8.41 67.28 0.89 59.88
1.64

7.195
2 12 4 9.09 72.68 0.89 64.69

6.325
2 12 4 7.97 63.72 0.89 56.71

10.15
Infront of Grid A & F 2 12 4 10.15 81.20 0.89 72.27

2 12 4 9.90 79.20 0.89 70.49 9.9

Infront of Grid 3 2 12 4 7.53 60.24 0.89 53.61 0.89

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)

6.64
2 12 2 8.17 32.68 0.89 29.09
7.28

2 12 4 7.14 57.12 0.89 50.84 5.75


0.5
0.89

2 12 2 6.50 13.00 0.89 11.57 6.5

2 12 2 6.00 12.00 0.89 10.68 6

16.14 Stirriups( beam 250*150 ) 1 8 546 0.76 414.96 0.40 165.98 0.0 0.1
8
0.2

17 For Slab (Top Floor)


17.1 Main Bars
Along short span
straight bar 1 8 76 12.00 912.00 0.40 364.80 12

2.025 1.5
Cranked bar 1 8 76 11.66 886.16 0.40 354.46 0.08 0.08 0.08 0.08
1.25 1.075 1.75
0.08 0.08
1.75 1.45
1 8 76 1.45 110.20 0.40 44.08

17.2 Along Long Span (grid 1 to grid2) 0.525


Straight bar 1 8 37 9.96 368.34 0.40 147.33 0.08 9.35

1 8 37 4.53 167.61 0.40 67.04 4.45

0.525 0.95
cranked bar 1 8 36 4.04 145.26 0.40 58.10 0.08 0.08
2.4

0.95 1.5
1 8 36 4.75 170.82 0.40 68.33 0.08 1.5 0.08 0.08
1.5
0.08 0.08 2 0.08
1.5
17.3 along long span Grid 2 to 3
Straight bar 1 8 26 10.45 271.70 0.40 108.68 0.08 10.45

1 8 26 10.90 283.40 0.40 113.36 10.9

1 8 26 10.45 271.70 0.40 108.68 10.45

2 1.5
cranked bar 1 8 24 11.01 264.24 0.40 105.70 0.08 0.08 0.08 0.08
1.5 1.5
0.08 0.08 0.95
1.5
0.95 1.875
1 8 24 11.38 273.12 0.40 109.25 0.08 0.08 0.08 2.25
1.5
0.08 0.08 0.95
1.5
0.95 1.5
1 8 24 11.01 264.24 0.40 105.70 0.08 0.08 0.08 1.5
1.5 2
0.08 1.5 0.08

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
17.4 Infront of stair case 0.08 6.11
Straight bar 1 8 15 6.27 94.05 0.40 37.62
2.405 1.095
Cranked bar 1 8 13 6.69 86.91 0.40 34.76 0.08 0.08 0.08 0.08
1.1 0.695
17.5 Distribution bars
Between Grid 1 &1a
along x-axis 1 8 80 2.70 216.00 0.40 86.40 2.7
along y- axis 1 8 74 3.20 236.80 0.40 94.72 3.2

Between grid 1a & 2


along x axis 1 8 80 2.70 216.00 0.40 86.40 2.7
along y axis 1 8 80 3.20 256.00 0.40 102.40 3.2

Between grid 2 & 3


except infront of staircas 2.7
along x axis 1 8 64 2.70 172.80 0.40 69.12 2.2
along y axis 1 8 68 2.20 149.60 0.40 59.84
Between grid 1b & 2 infront of
staicase
along x axis 1 8 6 4.20 25.20 0.40 10.08 4.2
along y axis 1 8 18 1.28 23.04 0.40 9.22 1.29

between 2 & 3
along x axis 1 8 8 4.20 33.60 0.40 13.44 4.2
along y axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Top near Grid 1( in bottom) 2 10 5 12.00 120.00 0.62 74.40 12


2 10 5 2.20 22.00 0.62 13.64 2.2

Top near Grid 1( on Top) 2 10 4 12.00 96.00 0.62 59.52 12


2 10 4 2.20 17.60 0.62 10.91 2.2

Top near grid A & F (in bottom) 2 10 5 12.00 120.00 0.62 74.40 12
Top near grid A & F (on top) 2 10 4 12.00 96.00 0.62 59.52 12

Top infront of grid 3 (in bottom) 2 10 5 11.98 119.80 0.62 74.28 11.98
Top infront of grid 3 (on top) 2 10 4 11.98 95.84 0.62 59.42 11.98

Top infront of staircase (in bottom) 1 10 6 8.24 49.44 0.62 30.65 8.24
1 10 5 8.24 41.20 0.62 25.54 8.24

17.6 Negative Bars


along Grid 1 2 8 36 2.43 174.96 0.40 69.98 2.43
along grid 1a 2 8 36 2.35 169.20 0.40 67.68 2.35
along grid 1b 1 8 14 1.08 15.12 0.40 6.05 1.08
along grid 2 (except infront of
stair case) 2 8 36 2.10 151.20 0.40 60.48 2.1
along grid 2 in front of
staircase 1 8 14 1.37 19.18 0.40 7.67 1.38
Along grid 3 (except infront of
stair case) 1 8 72 2.13 153.36 0.40 61.34 2.13
Along grid 3 ( infront of
stair case) 1 8 14 2.53 35.42 0.40 14.17 2.53

Along grid A & F 2 8 28 2.28 127.68 0.40 51.07 2.28


along grid a1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid b 1 8 28 2.10 58.80 0.40 23.52 2.1
along b1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid c&d 2 8 10 2.55 51.00 0.40 20.40 2.55
along grid d1 1 8 28 2.05 57.40 0.40 22.96 2.05
along grid e 1 8 28 2.10 58.80 0.40 23.52 2.1
along grid e1 1 8 28 2.05 57.40 0.40 22.96 2.05

Band Parapet Wall Top Floor 7.195


Near grid 1 2 10 2 9.09 36.34 0.62 22.53
1.89

7.215

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
2 10 2 8.41 33.64 0.62 20.86
1.64

7.195
2 10 2 9.09 36.34 0.62 22.53

6.325
2 10 2 7.97 31.86 0.62 19.75

10.15
Infront of Grid A & F 2 10 2 10.15 40.60 0.62 25.17

2 10 2 9.90 39.60 0.62 24.55 9.9

Infront of Grid 3 2 10 2 7.53 30.12 0.62 18.67 0.89

6.64
2 10 2 8.17 32.68 0.62 20.26
7.28

2 10 2 7.14 28.56 0.62 17.71 5.75


0.5
0.89

2 10 2 6.50 13.00 0.62 8.06 6.5

2 10 2 6.00 12.00 0.62 7.44 6

Stirrups 2 8 540 0.30 162.00 0.40 64.80 0.06 0.06


0.18

18 Column ( Up to Roof Floor Level)


18.1 Grid 1 C 1
Main Bar 16 6 2.96 17.76 1.59 28.24 16mm
2.00

0.96

18.2 Grid 1 ( D ) 1
Main Bar 20 2 3.20 6.40 2.47 15.81
16 4 2.96 11.84 1.59 18.83 20mm 16mm
2 2

1.2 0.96

18.3 Grid 2 & 3 ( C &D) 4


20 2 3.20 25.60 2.47 63.23
16 4 2.96 47.36 1.59 75.30 2 20mm 2 16mm

1.2 0.96

18.4 Stirrups 6
For 6 columns 8 26 1.84 287.04 0.40 114.82 0.08
8 52 1.28 399.36 0.40 159.74 0.42 0.14 0.08
0.42
0.42
18.5 Band under wall (Grid C&D) 2 10 2 6.50 26.00 0.62 16.12 6.5
1 10 2 4.50 9.00 0.62 5.58 4.5
0.06 0.06
1 8 30 0.30 9.00 0.40 3.60 0.18
Stirrups 2 8 44 0.30 13.20 0.40 5.28 0.06 0.06
19 Slab Beam 0.18
19.1 Grid C & D
Bottom bar 2 20 2 10.87 43.48 2.47 107.40 0.475

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)

9.92

0.475
2 16 1 10.87 21.74 1.59 34.57 9.92

Top Bar 2 20 2 11.80 47.20 2.47 116.58 0.94 9.92

2 16 1 11.24 22.48 1.59 35.74 0.66 9.92

19.2 Grid 1,2& 3 bottom bar


3 20 2 5.82 34.92 2.47 86.25 0.45
4.92

3 16 1 5.82 17.46 1.59 27.76 0.45

4.92
Top Bar
3 20 2 6.80 40.80 2.47 100.78 0.94 4.92

3 16 1 6.24 18.72 1.59 29.76 0.66 4.92

19.3 Secondry beam


Bottom bar along grid 1a 1 16 3 5.45 16.35 1.59 26.00 0.35
4.75

Top bar along grid 1a 1 16 3 5.65 16.95 1.59 26.95 0.35 4.75

19.4 Stirriups( For Main Beam) 1 10 180 1.65 297.00 0.62 184.14 0.10
0.425

0.25
19.5 For Secondry Beam 1 8 35 1.31 45.85 0.40 18.34
0.8
0.375

0.2

20 For Slab (Roof Floor)


20.1 Main Bars
Along long span
straight bar 1 8 14 11.62 162.68 0.40 65.07 0.08 11.46

1.605 1.5
Cranked bar 1 8 13 11.94 155.22 0.40 62.09 0.08 0.08 0.08
1.25 1.855 1.75
0.08 0.08
1.75
Along Short Span
straight bar 1 8 29 6.62 191.98 0.40 76.79 0.08 6.46

2.105
Cranked bar 1 8 28 6.48 181.44 0.40 72.58 0.08 0.08 0.08
1.95

20.2 Distribution bars


Between Grid 1 &1a
along x-axis 1 8 12 4.20 50.40 0.40 20.16 4.2
along y- axis 1 8 18 3.23 58.05 0.40 23.22 3.23

Between Grid 1a & 2


along x-axis 1 8 12 4.20 50.40 0.40 20.16 4.2
along y- axis 1 8 18 3.23 58.14 0.40 23.26 3.23

Between Grid 2 & 3

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Academic Block,3-12C(MsF)
School Name : Shree Chaturmala Secondary School
Location : Muchhok, Gorkha
BAR BENDING SCHEDULE
Dia. of Cut Total
No. of Wt/m Weight
S. No. Description No. Bar Length Length Bar Shape
Bars (Kg) (Kg)
(mm) (m) (m)
along x-axis 1 8 8 4.20 33.60 0.40 13.44 4.2
along y- axis 1 8 18 2.20 39.60 0.40 15.84 2.2

Top near grid 1 &3


bottom bar 2 8 5 6.46 64.60 0.40 25.84 6.46

Top Bar 2 8 4 6.46 51.68 0.40 20.67 6.46

Top in front of grid C & D


bottom bar 2 8 5 11.46 114.60 0.40 45.84 11.46

Top Bar 2 8 4 11.46 91.68 0.40 36.67 11.46

20.3 Negative Bars


along Grid 1 1 8 13 2.08 27.04 0.40 10.82 2.08
along grid 1a 1 8 13 2.35 30.55 0.40 12.22 2.35
along grid 2 1 8 13 2.10 27.30 0.40 10.92 2.1
along Grid 3 1 8 13 1.78 23.14 0.40 9.26 1.78
along grid C & D 2 8 26 2.48 128.96 0.40 51.58 2.48

21 Band (Roof Floor ) 5.95


Parapet Wall 2 10 2 7.15 28.60 0.62 17.73 0.6
2 10 2 11.95 47.80 0.62 29.64
11.95
Stirrups 2 8 238 0.30 71.40 0.40 28.56 0.06 0.06
Total 58049.18 kgs 0.18
Total 58.05 MT

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.1

0.1

0.1

0.1

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.1

16mm

0.1
0.31

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.12

0.1

0.12

0.12

0.35

0.35

0.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.66

0.35

0.35

0.425

0.425

0.94

0.66

0.625

0.625

0.94

0.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape
0.66

0.3

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.15

2.497
0.3

0.15

0.15

0.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.35

1.29

0.94

0.94

0.94

0.66

0.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.66

0.94

0.94

0.94

0.94

0.94

0.15

0.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.35

0.35

0.35

0.35

0.45

0.45

0.35

0.45

0.96

1.705

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

1.9

1.15

1.15

1.5
0.525

2.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.75
0.075

0.75
0.075

0.075

0.075
0.75
0.075

0.075

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.75
0.075

0.75
0.075

0.075

0.075
0.75
0.075

0.075

0.3

0.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

2.497
0.3

0.15

0.15

0.35

0.35

1.29

0.94

0.94

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.94

0.66

0.66

0.66

0.94

0.94

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.94

0.94

0.94

0.15

0.15

0.35

0.35

0.35

0.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.45

0.45

0.35

0.45

0.96

1.705

1.9

1.15

1.15

1.5
0.525

2.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.75
0.075

0.75
0.075

0.075

0.075
0.75
0.075

0.075

0.3

0.15

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

2.497
0.3

0.15

0.15

0.35

0.35

0.475

0.475

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

1.29

0.94

0.94

0.475

0.475

0.66

0.66

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.15

0.15

0.475

0.94

0.94

0.94

0.15

0.15

0.35

0.35

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape
0.35

0.35

0.35

0.45

0.45

0.35

0.45

0.96

1.89

1.64

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.89

1.75
0.08

0.08

0.08

1.5
0.08

0.08

1.5
0.08

1.875
0.08

1.5
0.08

0.08

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.08

0.91
0.08

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

1.89

1.64

0.89

0.475

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.475

0.94

0.66

0.45

0.45

0.94

0.66

0.35

0.45

0.08

1.75
0.08

0.08

2.105
0.08

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
BAR BENDING SCHEDULE

Bar Shape

0.6

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: 2-LaLiEC
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

2-LaLiEC Total
S. No. Description Unit Remarks
GF FF SF TF Quantity
A Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure 1 1.00 No

2 Cables and Wires


2 Nos 10 Sq mm Multistranded Cu Wire + 1 No 6 Sq mm
2.1 Multistranded Cu wire 45 45.00 Rm
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.2 45 45.00 Rm
Multistranded Cu wire

B SCHOOL BLOCKS
1 DISTRIBUTION BOARDS
DB (DB-1) Incoming NEA: 1 x 40A DP MCB Incoming Solar:
1.2 1 x 16A DP MCB Outgoing NEA: 1 x 16 A DP MCB 2 x 25 A 1 1.00 No
DP MCB 2 x 16 A SP MCB 6 x 6 A SP MCB
DB ( DB-2) & DB ( DB-3) Incoming:
1.3 1 1.00 No
1 x 25A DP MCB
DB ( DB-3) Incoming NEA: 1 x 25A DP MCB Incoming Solar:
1.5 1 x 10A DP MCB 1 1.00 No

2 CABLES & WIRES


2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 Multistranded Cu wire 2 2 2 6.00 Rm
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 Multistranded Cu wire 2 2 2 6.00 Rm
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.3 12 12 12 36.00 Rm
Multistranded Cu wire

3 General service light point wiring


3.1 One way light point 26 22 22 3 73.00 Pts
3.2 Two Way Light Point 1 1 2.00 Pts
4 6A Universal pin Light power point wiring 24 24 31 79.00 Pts

5 Switch Socket Outlets


5.1 6A Universal power Switch Socket 24 24 31 79.00 No

7 Light Fixtures/Luminaires & Accessories


7.3 18 W LED Surface Mounted Square type 16 16 16 48.00 Nos.
7.5 12 W LED Surface Mounted Cylindrical type 6 7 7 3 23.00 Nos.
7.7 LED Wall Light made 1 1.00 Nos.
8 Pull Box 3.00 No
9 External post top light pole 3.00 No
10 Post Top External Light Fixtures 3.00 No

11 Earthing and Lightning protection


11.1 11.1. Chemical Earhting 3.00 Nos.
11.2 Earthing Bar 3.00 Nos.
GI Strip/Cu wire Earthing
12.1 12.1. 25 x 3 mm GI Strip 63.00 Mtr.
12.2 12 SWG Cu wire 14.00 Mtr.
13 Earth Test link 1.00 No
14 Lightning Arrester 1.00 No.

C SOLAR PV SYSTEM
1. Solar PV Panel
1.1 1.1. 24V 250W PV Module 8.00 No
2. Tubular Deep cycle Battery
2.1 2.1. 12V, 200Ah@C10 Tubular Solar Battery 4.00 No
3 Hybrid Inverter 1.00 No
FIRE EXTINGUISHER
D a) Supplying Fire extinguisher ABC stored Pressure 5.0kg size 2.00 Nos.
ABC stored pressure type Fire extinguisher.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Block : 2-LaLiEC
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 EARTH WORKS
1.1 Site Clearance for Bldg 1 27.50 14.50 398.75
Soak pit 1 3.14 Area 3.14
Total 401.89 sq.m

1.2 Earth Work Excavation


For Isolated Foundation
F1 7 1.80 1.80 1.50 34.02
F2 4 2.00 2.00 1.50 24.00
F3 3 2.30 2.30 1.50 23.81
F4 1 2.50 2.50 1.50 9.38
For Lower Tie Beam
Along Grid A,E 2 5.70 0.50 0.90 5.13
Grid B 1 4.95 0.50 0.90 2.23
Grid C 1 5.30 0.50 0.90 2.39
Grid D 1 5.30 0.50 0.90 2.39
Along Grid 1 1 13.40 0.50 0.90 6.03
Along Grid 2 1 12.40 0.50 0.90 5.58
Along Grid 3 1 14.30 0.50 0.90 6.44
Side Drain 1 21.95 0.98 0.18 3.75
Drain 1 21.95 0.60 0.05 0.66
Below Exterior Steps 1 20.95 0.75 0.15 2.36
Ramp
For Slope 1 3.50 1.03 0.28 0.99
For Front wall 3-AB 1 6.50 0.55 0.45 1.61
For Side wall -3B 1 1.33 0.55 0.45 0.33
Soak Pit small 1 6.00 Area 3.10 18.60
Total 149.66 cu.m

1.3 EarthBack filling


Total Excavation Work 1 149.66 149.66
Deduction
Soling -1 12.10 -12.10
PCC Below Foundation Footing and Beam -1 6.05 -6.05
RCC Below Foundation Footing and Beam -1 23.36 -23.36
Tie beam(300 x 525)
Along grid 1,2,3 -3 19.70 0.30 0.08 -1.33
Along grid A,B,C,D,E -5 8.60 0.30 0.08 -0.97
RCC Column Below Ground Level -15 0.45 0.45 0.75 -2.28
Brick Work Below Ground Level
Grid 1,2, 3 -3 19.70 0.25 0.38 -5.54
Grid A,B,C,D & E -3 8.60 0.25 0.38 -2.42
Soak Pit small -1 6.16 Area 3.10 -19.10
Grid AB,BC,DE/1-2 3 5.70 6.70 0.18 20.05
Staircase 1 6.70 3.20 0.18 3.75
Corridor 3 5.70 2.20 0.18 6.58
1 3.20 2.20 0.18 1.23
Total 108.14 cu.m

1.4 Boulder Soling


F1 7 1.50 1.50 0.20 3.15
F2 4 1.70 1.70 0.20 2.31
F3 3 2.00 2.00 0.20 2.40
F4 1 2.20 2.20 0.20 0.97

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Below Foundation Beam
Along grid 1 1 18.10 0.35 0.10 0.63
Along grid 2 1 18.10 0.35 0.10 0.63
Along grid 3 1 18.10 0.35 0.10 0.63
Along Grid A, C, E 3 7.80 0.35 0.10 0.82
Grid B & D 2 7.80 0.35 0.10 0.55

Side Slope of Drain 1 21.95 0.98 0.10 2.14


Below exterior steps 1 20.95 0.60 0.10 1.26

Below ramp
For Slope 1 6.82 1.18 0.20 1.61
For Front wall 3-AB 1 6.50 0.45 0.10 0.29
For Side wall -3B 1 1.33 0.45 0.10 0.06
Building Floor
Grid AB,BC,DE/1-2 3 5.70 6.70 0.20 22.91
Staircase 1 6.70 3.20 0.20 4.29
Corridor 3 5.70 2.20 0.20 7.52
1 3.20 2.20 0.20 1.41
Inside of soak Pit 1 3.77 0.23 0.20 0.17
Total 53.76 cu.m

1.5 Sand Filling


Periphery ot Soak pit 1 2.07 Area 2.37 4.91
Total 4.91 cu.m

2 CONCRETE WORKS
2.1 P.C.C
2.1.1 P.C.C.(1:3:6) Works
F1 7 1.50 1.50 0.10 1.58
F2 4 1.70 1.70 0.10 1.16
F3 3 2.00 2.00 0.10 1.20
F4 1 2.20 2.20 0.10 0.48
Below Foundation Beam
Along grid 1 1 18.10 0.35 0.05 0.32
Along grid 2 1 18.10 0.35 0.05 0.32
Along grid 3 1 18.10 0.35 0.05 0.32
Along grid A,C and E 3 7.80 0.35 0.05 0.41
Along grid B & D 2 7.80 0.35 0.05 0.27
Total 6.05 cu.m

2.1.2 P.C.C.(1:2:4) Works


Under Suraface
Grid AB,BC,DE/1-2 3 5.70 6.70 0.08 8.59
Staircase 1 6.70 3.20 0.08 1.61
Corridor 3 5.70 2.20 0.08 2.82
1 3.20 2.20 0.08 0.53
Other Areas
Below ramp
For Slope 1 6.82 1.30 0.05 0.44
For Front wall 3-AB 1 6.50 0.45 0.05 0.15
For Side wall -3B 1 1.33 0.45 0.05 0.03
Above ramp
For Front wall 3-AB 1 6.52 0.13 0.05 0.04
For Side wall -3B 1 1.33 0.25 0.05 0.02

Below exterior steps 1 20.95 0.68 0.05 0.71


Above exterior steps 1 19.50 0.90 0.05 0.88
Pcc for plinth protection works
Below drain 1 40.50 0.575 0.075 1.75
Above drain 1 38.60 0.875 0.05 1.69

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 41.40 0.125 0.05 0.26
Total 19.51 cu.m

2.2 P.C.C For R.C.C. Works


Foundation
Isolated footing F1
Inclined Part 7 Area 1.49 0.25 2.60
Rectangular Base 7 1.50 1.50 0.20 3.15
Isolated footing F2 0.00
Inclined Part 4 Area 1.81 0.25 1.81
Rectangular Base 4 1.70 1.70 0.20 2.31
Isolated footing F3 0.00
Inclined Part 3 Area 2.36 0.25 1.77
Rectangular Base 3 2.00 2.00 0.20 2.40
Isolated footing F4
Inclined Part 1 Area 2.78 0.25 0.70
Rectangular Base 1 2.20 2.20 0.20 0.97

Beam
Footing beam(250x300)
Along grid 1,2,3 3 19.70 0.25 0.30 4.43
Along grid A,B,C,D,E 5 8.60 0.25 0.30 3.23
Tie beam(300 x 525)
Along grid 1,2,3 3 19.70 0.30 0.53 9.31
Along grid A,B,C,D,E 5 8.60 0.30 0.53 6.77
First floor level
Main beam(300x525)
Along grid 1,2,3 3 19.70 0.30 0.40 7.09
Along grid A,B,C,D,E 5 8.60 0.30 0.40 5.16 300
Secondary beam(250x425)
Along 1a 1 17.10 0.25 0.30 1.28
Along A1,B1,D1 3 8.65 0.25 0.30 1.95
Along 1b 1 3.20 0.25 0.30 0.24
Truss level
Main beam(300x400)
Along grid 1,2,3 3 19.70 0.30 0.40 7.09
Along grid A,B,C,D,E 5 8.60 0.30 0.40 5.16

Column
Column below Plinth level 15 0.45 0.45 1.20 3.65
Ground floor plan
Total columns(450x450) 15 0.45 0.45 3.00 9.11
First floor plan
Total columns(450x450) 15 0.45 0.45 3.00 9.11

Slab
First floor level 1 21.80 9.80 0.125 26.71

Deduction
Staircase Void -1 3.20 4.50 0.13 -1.80

Staircase
Bottom 1 2.29 1.50 0.15 0.51
Landing 1 3.20 1.50 0.15 0.72
Waist Slab 1 6.76 1.50 0.15 1.52
Steps 10 0.15 0.30 1.50 2.25
Landing Beam 1 3.05 0.25 0.38 1.16

Lintel Bands
Ground floor plan
Along grid 1 1 16.65 0.23 0.08 0.29

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Along grid 2 1 12.25 0.23 0.08 0.21
Along grid A,C,D,E 4 6.55 0.23 0.08 0.45
Between BC & 1-2 1 2.05 0.23 0.08 0.04
1 4.70 0.13 0.08 0.04

First floor plan


Along grid 1 1 16.65 0.23 0.08 0.29
Along grid 2 1 12.25 0.23 0.08 0.21
Along grid A,C,D,E 4 6.55 0.23 0.08 0.45
Between BC & 1-2 1 1.75 0.23 0.08 0.03
1 5.00 0.13 0.08 0.05

Sill Bands
Ground floor level
Along grid 1 1 19.70 0.23 0.08 0.34
Along grid 2 1 12.25 0.23 0.08 0.21
Along grid A,E 2 6.55 0.23 0.08 0.23
Along grid C,D 2 6.55 0.23 0.08 0.23
Between BC & 1-2 1 2.05 0.23 0.08 0.04
1 4.70 0.13 0.08 0.04
Below staircase 1 3.90 0.13 0.08 0.04

First floor plan


Along grid 1 1 19.70 0.23 0.08 0.34
Along grid 2 1 12.25 0.23 0.08 0.21
Along grid A,C,D,E 4 6.55 0.23 0.08 0.45
Between BC & 1-2 1 1.75 0.23 0.08 0.03
1 5.00 0.13 0.08 0.05

Vertical Band
Ground Floor 5 2.48 0.23 0.08 0.21
First Floor 4 2.60 0.23 0.08 0.18

Pedestal
Base Block 8 0.50 0.25 0.25 0.25

Bench
Bench Top Slab 1 2.40 0.50 0.08 0.09

Slab for In-built Furniture


Furniture Slab for Lab 4 1.80 0.90 0.10 0.65
Sink slab type-1 1 9.43 0.50 0.10 0.47
Sink slab type-2 1 5.75 0.50 0.10 0.29
Sink slab type-3 1 3.60 0.90 0.10 0.32
Furniture slab in preparation room 1 6.75 0.60 0.10 0.41
Sink Deduction
Sink slab type-1 -2 0.70 0.35 0.10 -0.05
Sink slab type-2 -2 0.70 0.35 0.10 -0.05
Sink slab type-3 -1 0.70 0.35 0.10 -0.02

Soak Pit
RCC slab 1 2.84 Area 0.15 0.43
Total 127.78 cu.m

2.3 Silicon Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10 127.78 1,277.80
Total 1,277.80 Kg

2.5 Formworks
Foundation
Isolated footing

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Rectangular Base F1 7 6.00 0.20 8.40
F2 4 6.80 0.20 5.44
F3 3 8.00 0.20 4.80
F4 1 8.80 0.20 1.76
Beam
Footing beam(250x300)
Along grid 1,2,3 3 19.70 0.60 35.46
Along grid A,B,C,D,E 5 8.60 0.60 25.80

Tie beam(300 x 525)


Along grid 1,2,3 3 19.70 1.12 66.19
Along grid A,B,C,D,E 5 8.60 1.12 48.16

First floor level


Main beam(300x525)
Along grid 1,3 2 19.70 0.93 36.45
Along grid 2 1 19.70 0.80 15.76
Along grid A,E 2 8.60 0.93 15.91
Along grid B,C,D 3 8.60 0.80 20.64
Secondary beam(250x425)
Along 1a 1 16.35 0.60 9.81
Along A1,B1,D1 3 8.65 0.60 15.57
Along 1b 1 3.20 0.60 1.92
Truss level
Main beam(300x400)
Along grid 1,2,3 3 19.70 1.10 65.01
Along grid A,B,C,D,E 5 8.60 1.10 47.30

Column
Column below Plinth level 15 1.80 1.20 32.40
Ground floor plan
Total columns(450x450) 15 1.80 3.00 81.00
First floor plan
Total columns(450x450) 15 1.80 3.00 81.00

Slab
Base area 1 21.80 9.80 213.64
Staircase
Bottom 1 2.29 0.15 0.34
Waist Slab 1 6.76 1.80 12.18
Landing 1 1.50 1.50 2.25
1 1.95 0.20 0.39
1 1.94 1.50 2.90
Steps 20 0.30 0.15 0.90
Riser 20 1.50 0.15 4.50
Landing Beam 1 3.05 0.86 2.62

Lintel Bands
Ground floor plan
Along grid 1 1 16.65 0.25 4.16
Along grid 2 1 16.65 0.25 4.16
Along grid A,C,D,E 4 6.55 0.25 6.55
Between BC & 1-2 1 2.05 0.25 0.51
1 4.70 0.25 1.18

First floor plan


Along grid 1 1 19.70 0.25 4.93
Along grid 2 1 16.65 0.25 4.16
Along grid A,C,D,E 4 6.55 0.25 6.55
Between BC & 1-2 1 1.75 0.25 0.44
1 5.00 0.25 1.25

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)

Sill Bands
Ground floor level
Along grid 1 1 19.70 0.15 2.96
Along grid 2 1 16.65 0.15 2.50
Along grid A,E 2 6.55 0.15 1.97
Along grid C,D 2 6.55 0.15 1.97
Between BC & 1-2 1 2.05 0.15 0.31
1 4.70 0.15 0.71
Below staircase 1 3.90 0.15 0.59
Deduction of door
D1 -4 1.10 0.15 -0.66
D2 -1 1.00 0.15 -0.15

First floor plan


Along grid 1 1 19.70 0.15 2.96
Along grid 2 1 16.65 0.15 2.50
Along grid A,C,D,E 4 6.55 0.15 3.93
Between BC & 1-2 1 1.75 0.15 0.26
1 5.00 0.15 0.75

Deduction of door
D1 -4 1.10 0.15 -0.66
D2 -1 1.00 0.15 -0.15
Pedestal
Base Block 8 1.25 0.25 2.50
Bench
Bench Top Slab 2 5.80 0.125 1.45
Bottom 2 1.90 0.25 0.95

Slab for In-built Furniture


Furniture Slab for Lab 4 1.80 0.90 6.48
4 5.40 0.10 2.16
Sink slab type-1 1 9.43 0.50 4.71
1 10.43 0.10 1.04
2 2.10 0.10 0.42
Sink deduction -2 0.70 0.35 -0.49
Sink slab type-2 1 5.75 0.50 2.88
1 6.75 0.10 0.68
2 2.10 0.10 0.42
Sink Deduction -2 0.70 0.35 -0.49
Sink slab type-3 1 3.60 0.90 3.24
1 9.00 0.10 0.90
1 2.10 0.10 0.21
Sink deduction -1 0.70 0.35 -0.25
Furniture slab in preparation room 1 6.75 0.60 4.05
1 6.75 0.10 0.68
Soak Pit
RCC slab
Base Area 1 2.84 2.84
Along Sides 1 5.97 0.15 0.90
Total 947.41 sq.m

3 BRICK WORKS
3.2 Full Brick (230 mm) Works (1:4c/s)
Brick Masonry Work Below Plinth Beam
Along grid 1,2,3 3 19.70 0.23 0.38 5.10
Along grid A,B,C,D & E 5 8.60 0.23 0.38 3.71

Ground floor
Along grid 1 1 16.65 0.23 2.33 8.90

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 3.05 0.23 2.02 1.42
Along grid 2 1 16.28 0.23 2.33 8.70

Along grid A,B,C,D and E 5 6.55 0.23 2.28 17.14


Between B,C 1 2.05 0.23 2.68 1.26
Grid 2A 1 0.60 0.50 0.45 0.14
Grid 3A 1 0.53 0.40 0.45 0.09
Grid 2D 1 0.60 0.50 0.45 0.14
Deduction for doors and windows
Ground floor plan
W1 -14 1.10 0.23 1.13 -3.98
V1 -14 1.10 0.23 0.53 -1.86
W3 -1 1.50 0.23 0.37 -0.13
D1 -4 1.10 0.23 2.33 -2.35
D3 -1 1.00 0.23 2.03 -0.47
For In-built Furniture
Below Furniture Slab for Lab 4 1.20 0.23 0.65 0.72
Below Sink slab type-3 1 1.50 0.23 0.65 0.22

First floor level


Along grid 1 1 16.65 0.23 2.45 9.38
1 3.05 0.23 2.53 1.77
Along grid 2 1 16.35 0.23 2.45 9.21
Along grid A,B,C,D and E 5 6.55 0.23 2.28 17.14
Store 1 1.75 0.23 2.80 1.13
Partition Wall for Computer Lab 2 3.60 0.23 1.20 1.9872
Deduction
D3 -1 1.00 0.23 2.03 -0.47
Below ramp
For Front wall 3-AB 1 6.50 0.35 0.30 0.68
For Side wall -3B 1 1.33 0.35 0.30 0.14
Above ramp
For Front wall 3-AB 1 1.40 0.23 0.38 0.12
1 4.25 0.23 0.19 0.18
For Side wall -3B 1 1.33 0.23 0.59 0.18
For Drain 1 39.85 0.23 0.15 1.37
External steps 1 19.50 0.48 0.10 1.95
1 19.50 0.18 0.15 2.93
1 19.50 0.08 0.10 1.95
Soak Pit Brick work 1 1.71 0.50 0.86
Total 89.26 cu.m

3.3 Half Brick (125 mm) Works (1:4c/s)


Ground floor
Partition Wall 1 4.70 3.00 14.10
Below Staircase 1 1.83 1.35 2.46
1 1.50 1.82 2.73
1 0.58 1.59 0.91
Sill -1 3.90 0.08 -0.29
D4 -1 1.00 1.55 -1.55
For In-built Furniture
Below Sink slab type-1 1 2.98 0.65 1.93
1 0.33 0.65 0.21
Below Sink slab type-2 1 2.98 0.65 1.93
Below Sink slab type-3 1 0.75 0.65 0.49
Furniture slab in preparation room 1 1.58 0.65 1.02
First floor 0.00
Partition Wall 1 5.00 3.00 15.00

For Ramp
Grid 3AB 1 1.40 0.22 0.30

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 5.12 0.22 1.10
For Bench
2 2.30 0.53 2.42
2 0.15 0.53 0.16
For Drain 1 41.40 0.15 6.21
Total 49.15 sq.m

3.4 Honey Comb Brick (350 mm) Works (1:3c/s)


Soak Pit Brick work 1 1.71 2.50 4.28
Total 4.28 cu.m

4 DOORS & WINDOWS


4.1 Metal Frame
4.1.1 Door Frame
D1 4 7.15 28.60
D2 4 7.20 28.80
D3 2 5.20 10.40
D4 1 4.10 4.10
Total 71.90 r.m

4.1.2 Window Frame


W1 28 5.58 156.10
W2 1 5.00 5.00
V1 14 3.25 45.50
V2 14 3.50 49.00
Total 255.60 r.m

4.2 Metal Shutter


4.2.1 Window Shutter
W1 28 1.01 1.04 29.27
W2 1 1.41 0.91 1.28
V1 14 1.01 0.44 6.15
V2 14 1.01 0.56 7.92
Total 44.63 sq.m

4.3 Wooden Shutter


Flush Door Shutter
D1 4 1.01 2.39 9.64
D2 4 1.01 2.41 9.74
D3 2 0.91 2.01 3.66
D4 1 0.91 1.46 1.33
Total 24.36 sq.m

4.5 Window Grill


Shutter Area of Ventilation
V1 14 1.01 0.44 6.15
V2 14 1.01 0.56 7.92
Shutter Area of Window
W1 28 1.01 1.04 29.27
W2 1 1.41 0.91 1.28
W3 1 1.50 0.37 0.56
Total 45.18 sq.m

4.6 Collapsable Gate


1 3.05 2.475 7.55
Total 7.55 sq.m

5 FLOORING WORKS
5.1 Hardened Cement Concrete Flooring (40mm) With Neat Cement Punning
Ground floor plan

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Laboratory 1 9.43 6.75 63.62
Store 1 2.20 6.75 14.85
ECD 1 5.78 6.75 38.98
Staircase Lobby 1 7.00 3.20 22.40
Corridor 1 21.80 2.50 54.50
Staircase riser 20 1.50 0.15 4.50
Staircase tread 18 1.50 0.30 8.10
Staircase landing 1 3.20 1.80 5.76

First floor plan


Library 1 9.43 6.75 63.62
Store 1 2.20 6.75 14.85
Computer 1 5.78 6.75 38.98
Staircase Lobby 1 3.20 2.40 7.68
Corridor 1 21.80 2.50 54.50

Ramp 1 6.5 1.20 7.80


Exterior steps 1 19.50 0.90 17.55
Drainage 1 39.5 0.88 34.56
Total 452.25 sq.m

5.2 Neat Cement Skirting


Ground floor plan
Laboratory 1 32.75 32.75
Store 1 17.90 17.90
ECD 1 25.00 25.00
Below staircase 1 17.75 17.75
Store Below landing 1 5.80 5.80
Staircase Flight/Landing 1 12.90 12.90
Corridor and Lobby 1 18.00
Column 5 2.25 11.25
Deduction
D1 -8 1.10 -8.80
D3 -2 1.00 -2.00
D4 -2 1.00 -2.00
First floor plan
Library 1 32.75 32.75
Store 1 17.90 17.90
Computer 1 25.00 25.00
Corridor and Lobby 1 23.75 23.75
Column 5 1.35 6.75

Deduction
D2 -8 1.10 -8.80
D3 -2 1.00 -2.00
Total 205.90 r.m

5.3 25mm Terrazo Finishing


For In-built Furniture
Furniture Slab for Lab 4 1.80 0.90 6.48
Sink slab type-1 1 9.40 0.50 4.70
Sink slab type-2 1 5.80 0.50 2.90

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
Sink slab type-3 1 3.60 0.90 3.24
Furniture slab in preparation room 1 6.80 0.60 4.08
Bench 1 2.40 0.50 1.20
Total 22.60 sq.m

6 ROOFING/TERRACING WORKS
6.1 Metal Works
A Truss 1 4,712.85
Total 4,712.85 Kg

6.2 CGI Sheet Roofing


24 Gauge colour CGI Sheet 2 23.75 6.23 295.74
Total For CGI Sheet Roofing Total 295.74 sq.m

6.3 CGI Ridge


Ridge Cover 1 23.75 23.75
Total 23.75 r.m
6.4 Eaves Board
Along Sides of Building 4 6.23 0.0003 7850.00 58.65
Along front and back 2 23.75 0.0003 7850.00 111.86
Total 170.52 Kg

6.5 Cement Board False Ceiling


Library 1 5.70 6.70 38.19
1 3.40 6.70 22.78
Store 1 2.18 6.70 14.57
Classroom 1 5.70 6.70 38.19
Staircase Lobby 3 3.20 6.70 64.32
Corridor 3 5.70 2.20 37.62
1 3.20 2.20 7.04
Outside Below Slope Roof 2 21.95 1.02 44.78
4 6.20 0.90 22.33
Total 289.83 sq.m

7 PLASTER/PAINTING WORKS
7.1 Internal Plaster
7.1.1 Internal Plaster on Wall (1:6)
Ground floor plan
Laboratory 1 32.35 Perimeter 2.91 94.14
Store 1 17.70 Perimeter 2.91 51.51
ECD 1 25.05 Perimeter 2.91 72.90
Staircase 1 17.75 3.00 53.25
For Strore Below Landing 1 3.53 1.25 4.39
2 0.70 1.44 2.01
1 2.88 1.60 4.60
Pedestal 5 1.25 0.25 1.56
5 0.50 0.25 0.63
Column
Grid 2A,2C,2D,2E 4 0.35 0.68 0.95
Grid 2B 1 0.45 0.68 0.30

Grid 2A,2C,2D,2E 4 0.45 2.20 3.96


Grid 2B 1 0.65 2.20 1.43

For In-built Furniture


Furniture Slab for Lab Edge 4 5.40 0.10 2.16
Bottom 4 1.80 0.90 6.48
-8 0.60 0.25 -1.20
Wall 8 1.70 0.65 8.84
Sink slab type-1 Edge & Bottom 1 9.43 0.60 5.66
Deduct Sink -2 0.95 0.43 -0.81

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
-4 0.43 0.13 -0.21
Wall 6 0.98 0.65 3.80
2 0.55 0.65 0.72
Sink slab type-2 1 6.75 0.10 0.68
Bottom 1 5.75 0.50 2.88
Deduct Sink -2 0.95 0.43 -0.81
-3 0.43 0.13 -0.16
Wall 7 0.98 0.65 4.44
Sink slab type-3 1 9.00 0.10 0.90
Bottom 1 3.60 0.90 3.24
Deduct Sink -1 0.75 0.35 -0.26
-2 0.75 0.25 -0.38
-1 0.75 0.13 -0.09
Wall 1 5.75 0.65 3.74
Furniture slab in Store room 1 6.75 0.70 4.73
Deduct Wall -3 0.53 0.13 -0.20
Wall 3 1.18 0.65 2.29

First floor plan


Library 1 32.35 Perimeter 3.00 97.05
Store 1 17.70 Perimeter 3.00 53.10
Computer 1 25.05 Perimeter 3.00 75.15
Computer Partition 2 7.45 1.20 17.88
Partition Top 2 3.60 0.25 1.80
Staircase 1 17.75 3.00 53.25
Pedestal 3 1.00 0.25 0.75
3 0.50 0.25 0.38
Column
Grid 2A,2E 2 0.48 3.00 2.85
Grid 2B 1 0.65 3.00 1.95
Grid 2C,2D 2 0.45 3.00 2.70

Deduction for Doors and Windows 0.00


Ground floor plan 0.00
W1 -14 1.10 1.13 -8.66
V1 -14 1.10 0.53 -4.04
W3 -1 1.50 0.37 -0.28
D1 -4 1.10 2.48 -5.45
D3 -2 1.00 2.10 -2.10
D4 -2 1.00 1.55 -1.55
First floor plan
W1 -14 1.10 1.13 -8.66
W2 -1 1.50 1.00 -0.75
V2 -14 1.10 0.65 -5.01
D2 -4 1.10 2.60 -5.72
D3 -2 1.00 2.10 -2.10
D4 -2 1.00 1.55 -1.55
Total 599.03 sq.m

7.1.2 Internal Plaster on Ceiling (1:4)


Ground floor plan
Laboratory 1 9.43 6.75 63.62
Store 1 2.20 6.75 14.85
ECD 1 5.78 6.75 38.98
Staircase Lobby 1 3.20 2.40 7.68
Corridor 1 21.80 2.50 54.50

Staircase
Waist slab 1 6.76 1.50 10.15
Landing 1 1.47 1.50 2.20
1 1.80 0.20 0.36

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
1 1.94 1.50 2.90
Beam plaster 0.00
First floor level
Along grid A,E 2 2.05 0.40 1.64
Along grid B 1 8.60 0.80 6.88
Along grid C,D 2 2.05 0.80 3.28
Along grid A1 ,B1,D1 3 8.65 0.60 15.57
Along grid 2 1 16.65 0.40 6.66
1 3.05 0.80 2.44
Along grid 3 1 19.70 0.40 7.88
Along grid 1a 1 16.35 0.60 9.81
Along grid 1b 1 3.20 0.60 1.92
0.00
Truss level 0.00
Main beam(300x400) 0.00
Along grid 2 1 16.65 0.40 6.66
1 3.05 1.10 3.36
Along grid 3 1 19.70 0.70 13.79
Along grid A,E 2 2.05 0.70 2.87
Along grid B 1 8.60 1.10 9.46
Along grid C,D 2 2.05 1.10 4.51
Total 291.97 sq.m

7.1.3 External Plaster


Outer Plaster
Beam Plaster
First floor Level
Main Beam(300 x 525)
Along grid 1 1.00 19.70 0.53 10.34
Along grid 3 1.00 19.70 0.53 10.34
Along grid A and E 2.00 8.60 0.53 9.03
Second floor Level
Main Beam(300 x 400)
Along grid 1 1.00 19.70 0.40 7.88
Along grid 3 1.00 19.70 0.40 7.88
Along grid A and E 2.00 8.60 0.40 6.88

Landing Beam 1.00 3.05 0.38 1.16


Column Plaster
Upto Plinth Level
Along grid 1
Grid 1A,1E 2.00 0.90 0.45 0.81
Grid 1B,1C,1D 3.00 0.45 0.45 0.61
Along grid 2
Grid 2A,2E 2.00 0.45 0.45 0.41
Along grid 3
Along grid 3A 1.00 0.08 0.38 0.03
1.00 0.45 0.40 0.18
Grid 3B 1.00 0.08 0.15 0.01
Grid 3C 1.00 0.60 0.15 0.09
Grid 3D 1.00 0.60 0.15 0.09
Grid 3E 1.00 1.05 0.15 0.16

Ground Floor
Along grid 1
Grid 1A,1E 2.00 1.10 2.33 5.12
Grid 1B,1C,1D 3.00 0.65 2.33 4.53
Along grid 2
Grid 2A,2E 2.00 0.65 2.33 3.02
Along grid 3
Grid 3A,3E 2.00 1.05 3.00 6.30

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
2.00 0.75 2.88 4.31
Grid 3B,3C,3D 3.00 1.20 2.88 10.35
3.00 0.60 3.00 5.40

First Floor
Along grid 1
Grid 1A,1E 2.00 1.10 3.00 6.60
Grid 1B,1C,1D 3.00 0.65 3.00 5.85
Along grid 2
Grid 2A,2E 2.00 0.65 3.00 3.90
Along grid 3
Grid 3A,3E 2.00 1.05 3.00 6.30
2.00 0.75 2.88 4.31
Grid 3B,3C,3D 3.00 1.20 2.88 10.35
3.00 0.60 3.00 5.40

For Drain 1.00 41.15 0.85 34.98


External Steps Side Wall
Grid 2A,2E 2.00 1.03 0.45 0.92
Grid 3A 1.00 0.93 0.45 0.42
Steps Edge 3.00 0.60 0.45 0.81
For Ramp
Top-3B 1.00 1.33 0.25 0.33
Top 3AB 1.00 6.47 0.13 0.81
Front 3-AB 1.00 1.60 0.60 0.96
1.00 5.10 0.38 1.91
Inner 1.00 7.52 0.15 1.13
Side-3B 1.00 1.33 0.60 0.80
For Bench
Top 1.00 2.40 0.50 1.20
Edge 1.00 5.80 0.13 0.73
Side 1.00 5.40 0.53 2.84

Plaster on Outer Walls


Ground floor
Along grid 1 1 16.65 2.33 38.71
1 3.05 2.02 6.16
Along grid 2 1 16.28 2.33 37.84
Along grid A and E 2 6.55 2.33 30.46

First floor level


Along grid 1 1 16.65 2.45 40.79
1 3.05 2.53 7.70
Along grid 2 1 16.35 2.45 40.06
Along grid A and E 2 6.55 2.45 32.10

Deduction for doors and windows


Ground floor plan
W1 -14 1.10 1.13 -17.33
V1 -14 1.10 0.53 -8.09
W3 -1 1.50 0.37 -0.56
D1 -4 1.10 2.33 -10.23
First floor plan
W1 -14 1.10 1.13 -17.33
V2 -14 1.10 0.65 -10.01
W2 -1 1.50 1.00 -1.50

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Breadth Height
S. No. Description No. Length (m) Quantity Unit Remarks
(m) (m)
D2 -4 1.10 2.45 -10.78
Total 343.47 sq.m

7.2 Painting Works


7.2.1 Distemper Paint
As per Internal Plaster on Wall 1.00 599.03 599.03
As per Internal Plaster on Ceiling 1.00 291.97 291.97
On False Ceiling 1.00 289.83 289.83
Total 1,180.83 sq.m

7.2.2 Exterior Weather Coat Paint


As per External Plaster 1.00 343.47 343.47
Total 343.47 sq.m

7.2.4 Enamel Paint Factor


Collapsable Gate 1.00 3.05 2.48 2.00 15.10
Door D1 4 1.10 2.44 2.00 21.43
D2 4 1.10 2.56 2.00 22.53
D3 2 1.00 2.10 2.00 8.40
D4 2 1.00 1.55 2.00 6.20
Window W1 28 1.10 1.13 2.00 69.30
W2 1 1.50 1.00 2.00 3.00
V1 14 1.10 0.53 2.00 16.17
V2 14 1.10 0.65 2.00 20.02
Window Grill
W1 19 1.10 1.13 2.00 47.03
W2 1 1.50 1.00 2.00 3.00
W3 1 1.50 0.37 2.00 1.11
V1 14 1.10 0.53 2.00 16.17
V2 5 1.10 0.65 2.00 7.15
Total 256.60 sq.m

8 MISCELLANEOUS
8.2 Cement Board Wall
8.2.1 For partition
Gable Walls 4.00 7.26 Area 29.04
Total 29.04 sq.m

8.3 Railing
Staircase Railing
Horizontal ISNB 40M 1 8.43 8.43 3.56 30.01
Vertical 38mm Square Pipe 2 0.989 1.98 2.82 5.58
Vertical 38mm Square Pipe 6 0.969 5.81 2.82 16.40
Horizontal 25mm Square Pipe 4 8.34 33.37 0.85 28.37
Balcony Railing
First Floor
Horizontal ISNB 40M 1 23.80 23.80 3.56 84.73
Horizontal ISNB 32M 2 23.80 47.60 3.10 147.56
Vertical ISNB 32M 19 1.02 19.38 3.10 60.08
Inclined ISNB 32M 19 0.134 2.55 3.10 7.89
Vertical 25mm Square Pipe 163 0.82 133.66 0.85 113.61

Pedestal
ISNB 40M Pedestal Bars 8 1.91 15.28 3.56 54.40
8 1.49 11.92 3.56 42.44
16 0.40 6.40 3.56 22.78

Base plate 60 0.00009375 0.01 7850 44.16


12 mm dia. Anchor Bolt, Nut 240 0.13 31.20
Total 689.19 Kg

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Block : 2-LaLiEC
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

Truss Calculation Details-2-LaLiEC


Total Total Wt.
S.N Description Notation Nos Length Breadth Thickness Wt/m Wt/m3
Length (Kg)
1 Top Chord TP dia 50 M 16 6.167 98.672 5.03 496.33
2 Bottom Chord BC dia 40 M 16 4.903 78.448 3.56 279.28
3 Vertical Strut VS dia 40 M 16 3.917 62.672 3.56 223.12
4 Cross bracing CB dia 40 M 32 1.7 54.4 3.56 193.67
5 Diagonal Strut DS dia 32 M 16 4.223 67.568 3.1 209.47
6 Purlin P dia 65 12 23.75 285 6.61 1883.85
7 Bottom Center Connection Plate T1 BCCP 10 mm 6 0.175 1.05 0.175 0.01 7850 14.43
8 Bottom Center Connection Plate T2 BCCP 10 mm 10 0.175 1.75 0.15 0.01 7850 20.61
9 Top Center Connection Plate (T1 & T2) CCP 10 mm 16 0.175 2.8 0.175 0.01 7850 38.47
10 Truss Base Plate TBP 10 mm 48 0.3 14.4 0.3 0.01 7850 339.12
11 Truss Cleat for Purlin TCP 10 mm 264 0.2 52.8 0.09 0.01 7850 373.04
12 Purlin Eves Plate PEP 3 mm 24 0.125 3 0.075 0.003 7850 5.30
13 Truss Eves Plate TEP 3 mm 16 0.125 2 0.06 0.003 7850 2.83
14 Cross Bracing Center Plate CBP 6 mm 16 0.38 6.08 0.08 0.006 7850 22.91
15 Cross Bracing Truss Cleat CBTC 6 mm 32 0.165 5.28 0.08 0.006 7850 19.90
16 Cross Bracing Truss Cleat-Wind Tie CTC 6 mm 32 0.1 3.2 0.1 0.006 7850 15.08
17 Wind Bracing Center Cleat DBCC 6 mm 32 0.17 5.44 0.08 0.006 7850 20.50
18 Anchor Bolt AB 16 dia 96 0.45 43.2 1.58 68.26
19 Stiffner Cleat Base Plate SC 10 mm 48 0.05 2.4 0.075 0.01 7850 14.13
20 Base Plate Truss Guide Cleat BPRGC 48 0.3 14.4 0.14 0.01 7850 158.26
21 Center Joint Cleat-T1 CJC 10 mm 78 0.062 4.836 0.13 0.01 7850 49.36
22 Center Joint Cleat-T2 CJC 10 mm 50 0.062 3.1 0.13 0.01 7850 31.64
23 Truss Runner Support Plate (C-Section) TRSP 10 mm 56 0.055 3.08 0.07 0.01 7850 16.93
24 Runner Purlin Cleat RPC 10 mm 56 0.175 9.8 0.07 0.01 7850 53.86
25 Runner Pipe NB 40 2 21.5 43 3.56 7850 153.08
26 Center Row Column (truss Support) CRC 10 mm 16 0.25 4 0.03 0.01 7850 9.42
Total of Truss Work 4712.85

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Block : 2-LaLiEC
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
Detailed measurement Sheet : 2-LaLiEC
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

Footing (5 Nos): 1500*1500mm, Bars 1.40


1 12 150 0.89 5.00 10 1.60 82.67 73.48
(X direction) 0.10

1.40
Bars (Y - direction) 12 150 0.89 5.00 10 1.60 82.67 73.48
0.10

2.10
Footing (2 Nos): 2200*2200mm, Bars
12 150 0.89 2.00 15 2.30 69.00 61.33
(X direction) 0.10

2.10
Bars (Y - direction) 12 150 0.89 2.00 15 2.30 69.00 61.33
0.10

2.30
Footing (3 Nos): 2400*2400mm, Bars
12 150 0.89 3.00 16 2.50 122.50 108.89
(X direction) 0.10

2.30
Bars (Y - direction) 12 150 0.89 3.00 16 2.50 122.50 108.89
0.10

2.40
Footing (1 Nos): 2500*2500mm, Bars
12 150 0.89 1.00 17 2.60 44.20 39.29
(X direction) 0.10

2.40
Bars (Y - direction) 12 150 0.89 1.00 17 2.60 44.20 39.29
0.10

2.70
Footing (1 Nos): 2800*2800mm, Bars
12 150 0.89 1.00 19 2.90 55.10 48.98
(X direction) 0.10

2.70
Bars (Y - direction) 12 150 0.89 1.00 19 2.90 55.10 48.98
0.10

2.90
Footing (2 Nos): 3000*3000mm, Bars
12 150 0.89 2.00 20 3.10 126.07 112.06
(X direction) 0.10

2.90
Bars (Y - direction) 12 150 0.89 2.00 20 3.10 126.07 112.06
0.10

3.00
Footing (1 Nos): 3100*3100mm, Bars
12 150 0.89 1.00 21 3.20 67.20 59.73
(X direction) 0.10

3.00
Bars (Y - direction) 12 150 0.89 1.00 21 3.20 67.20 59.73
0.10

3 Foundation Beams, 250*300


Main Bars (Long side beams); Along 21.5+0.45-2(0.05)
0.44 12 0.888 3 6 24.41 439.38 390.17
Grid 1-1, 2-2, 3-3

0.20 0.08
100 &
Stirrups (for 250*300) 8 0.395 3 171 0.81 416.56 164.54
150
0.15

Main Bars (Short side beams); Along


9.5+0.45-2(0.05) 12 0.888 5 6 10.73 321.90 285.85
Grid A,B,C,D,E 0.44

0.20 0.08
100 &
Stirrups (for 250*300) 8 0.395 5 75 0.81 304.50 120.28
150
0.15
Columns(450*450) upto plinth level

At Grid 1- A,B,C,D,E 16 1.58 5.00 12 2.16 129.60 204.80


0.08+0.51 0.37+0.75+0.45

At Grid 2- A,B,C,D,E 16 1.58 5.00 8 2.16 86.40 136.53


0.08+0.51 0.37+0.75+0.45

20 2.47 5.00 4 2.40 48.00 118.52


0.08+0.75 0.37+0.75+0.45

At Grid 3- A,B,E 16 1.58 3.00 8 2.16 51.84 81.92


0.08+0.51 0.37+0.75+0.4
5

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

20 2.47 3.00 4 2.40 28.80 71.11


0.08+0.75 0.37+0.75+0.45

At Grid 3- C,D 20 2.47 2.00 12 2.40 57.60 142.22


0.08+0.75 0.37+0.75+0.45

0.37 0.08
Stirrups for 15 columns 8 100 0.395 15.00 14 1.59 334.32 132.06
0.37
0.08
0.14
8 100 0.395 15.00 17 1.13 288.66 114.02
0.37
4 Plinth Tie Beams, 300*525mm
Main Bars (Long side beams); Along Grid 1-1, 2-2, 3-3

Top (T/O) 0.72 16 1.58 3 3 24.41 219.69 347.11


21.5+0.45-2(0.05)

Bottom (T/O) 21.5+0.45-2(0.07) 20 2.47 3 4 25.25 303.00 747.50


1.0

Extra Bars (at 2 ends) 1.37 25 3.86 3 4 3.45 41.40 159.60


0.38+1.70

Extra Bars above Grid B-B 0.45+1.7*2 25 3.86 3 2 3.85 23.10 89.05

Extra Bars above Grid C-C, D-D 1.05+0.45+1.7 25 3.86 3 4 3.20 38.40 148.03

Torsion Bar 16 1.58 3 2 22.30 133.80 211.40

0.475 0.1`2
Stirrups (for 300*525) 12 100&150 0.89 3 201 1.64 990.13 879.23
0.25
Main Bars (Short side beams); Along Grid A,B,C,D,E 0.00 0.00

Top (T/O) 0.72


9.5+0.45-2(0.05) 16 1.58 5 3 11.29 169.35 267.57

Bottom (T/O) 9.5+0.45-2(0.05) 20 2.467 5 4 11.85 237.00 584.68


1.0

Extra Bars (at 2 ends) 1.12


0.38+2.5+1.75 25 3.855 5 2 6.00 60.00 231.30

1.12 25 3.855 5 2 3.50 35.00 134.93


0.38+1.75

Torsion Bar 16 1.58 5 2 10.40 104.00 164.32

0.475 0.12

Stirrups (for 300*525) 12 100&150 0.888 5 79 1.62 639.11 567.53


0.25

G.F. Columns

FFL

Grid-1 (A,B,C,D,E) 3000 16 1.58 5 6 3.00 90.00 142.22

GFL

FFL

3000 16 1.58 5 6 3.96 118.80 187.73

GFL

FFL

Grid-2(A,B,C,D,E) 3000 16 1.58 5 6 3.00 90.00 142.22

GFL

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

FFL

3000 16 1.58 5 2 3.96 39.60 62.58

GFL

FFL

3000 20 2.47 5 4 4.20 84.00 207.41

GFL

FFL

Grid-3(A,B,E) 3000 16 1.58 3 6 3.00 54.00 85.33

GFL

FFL

3000 16 1.58 3 2 3.96 23.76 37.55

GFL

FFL

20 2.47 3 4 4.20 50.40 124.44


3000

GFL

FFL

Grid-3(C,D) 3000 20 2.47 2 6 3.00 36.00 88.89

GFL

FFL

3000 20 2.47 2 6 4.20 50.40 124.44

GFL

0.37 0.08
100 &
Stirrups for 15 columns 8 0.40 15 29 1.59 686.55 271.23
0.37 150

0.08
0.14 100 &
4 8 0.40 15 52 1.13 874.47 345.47
150
0.37
Main Beams at F.F. Level
Main Bars (Long side beams); Along Grid 1-1, 2-2, 3-3

Top (T/O) 0.72 16 1.58 3 3 24.41 219.69 347.16


21.5+0.45-2(0.05)

21.5+0.45-2(0.07)
Bottom (T/O) 1.0 20 2.47 3 4 25.25 303.00 748.15

Extra Bars (at 2 ends) 1.37


0.38+1.70
25 3.86 3 4 3.45 41.40 159.72

Extra Bars above Grid B-B 0.45+1.7*2 25 3.86 3 2 3.85 23.10 89.12

Extra Bars above Grid C-C, D-D 1.05+0.45+1.7 25 3.86 3 4 3.20 38.40 148.15

Torsion bar 16 1.58 3 2 21.90 131.40 207.64

0.475 0.12
100 &
Stirrups (for 300*525) 10 0.62 3 232 1.64 1142.83 705.45
150
0.25

Main Bars (Short side beams); Along Grid A,B,C,D,E

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

Top (T/O) 0.72


9.5+0.45-2(0.05) 16 1.58 5 3 11.29 169.35 267.61

Bottom (T/O) 9.5+0.45-2(0.05) 20 2.47 5 4 11.85 237.00 585.19


1.0

Extra Bars (at 2 ends) 1.35 25 3.86 5 2 6.00 60.00 231.48


4.65

1.35 25 3.86 5 2 3.50 35.00 135.03


0.38+1.75

Along grid B,C,D 16 1.58 2 3 5.25 31.50 49.78

Torsion bar 16 1.58 5 2 9.90 99.00 156.44

0.47 0.12
100 &
Stirrups (for 300*525) 10 0.62 5 78 1.58 616.20 382.04
150
0.25
Secondary Beam -

Along Grid A1,B1,D1 0.4


9.8-2(0.05) 16 1.58 3 3 102.96 162.70
11.44

0.4 9.8-2(0.05) 16 1.58 3 3 102.96 162.70


11.44
0.375 0.10
100 &
Stirrups (for 425*250) 8 0.40 3 1.30 313.78 123.96
150
0.20 80

Along Grid 1b 0.4 16 1.58 1 3 5.44 16.32 25.79


3.8-2(0.05)

0.4 3.8-2(0.05)
16 1.58 1 3 5.44 16.32 25.79

0.4 0.10
100 &
Stirrups (for 425*250) 8 0.40 1 1.30 35.37 13.97
150
0.20 27

Along Grid 1a 0.4


11.7+.3*2-.05*2+.96 16 1.58 1 3 14.90 44.70 70.64

0.4
16 1.58 1 3 14.90 44.70 70.64
11.7+.3*2-.05*2+.96

0.375 0.10
100 &
Stirrups (for 425*250) 8 0.40 1 147 1.30 191.39 75.61
150
0.20

0.4
5.7+.5
16 1.58 1 3 7.94 23.82 37.64

0.4 5.7+.5 16 1.58 1 3 7.94 23.82 37.64

0.375 0.10
100 &
Stirrups (for 425*250) 8 0.40 1 49 1.30 63.80 25.20
150
0.20

960 960
Hunge bar(at secondary beam
420 16 1.58 2 16 3.01 96.32 152.21
intersection) 420
250
First floor slab (First floor level) - -
Along Y-axis - -
600
GRID 1-3: between A-C 75 8 300 0.40 1 37 10.96 409.17 161.65
9800-40
450 600
75 8 300 0.40 1 37 11.12 415.15 164.01
9800-40

2350 8 150 0.40 1 47 2.50 117.50 46.42


75 75

2100 8 150 0.40 1 45 2.25 102.00 40.30


75 75

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

450
GRID 2-3: between C-D 75 8 300 0.40 1 12 5.49 63.99 25.28
4925-40

450
75 8 300 0.40 1 12 5.57 64.93 25.65
4925-40

3080 8 150 0.40 1 13 3.23 43.07 17.01


75 75

450 600
GRID 1-3: between D-E 75 8 300 0.40 1 19 10.96 210.07 82.99
9800-40

600
75 8 300 0.40 1 19 11.12 213.13 84.20
9800-40

2350 8 150 0.40 1 26 2.50 64.17 25.35


75 75

2100 8 150 0.40 1 24 2.25 54.00 21.33


75 75
Along X-axis - - -
525
GRID A-C: between 1-1a 75 75 8 300 0.40 1 15 13.94 214.91 84.90
12300-40

525
75 75 8 300 0.40 1 15 14.18 218.61 86.36
12300-40

2050 8 300 0.40 1 14 2.20 30.43 12.02


75 75

2100 8 300 0.40 1 14 2.25 31.13 12.30


75 75

2050 8 300 0.40 1 14 2.20 30.43 12.02


75 75

525
GRID A-E: between 1a-3 75 75 8 300 0.40 1 16 23.44 365.27 144.31
21800-40
525
75 75 8 300 0.40 1 16 23.92 372.75 147.26
21800-40

2050 8 150 0.40 3 11 2.20 74.80 29.55


75 75

2100 8 150 0.40 1 11 2.25 25.50 10.07


75 75

2250 8 150 0.40 2 11 2.40 54.40 21.49


75 75

525
GRID D-E: between 1-1a 75 75 8 300 0.40 3 15 7.46 345.03 136.31
6300-40
525
75 75 8 300 0.40 3 15 7.54 348.73 137.77
6300-40

2050 8 150 0.40 2 15 2.20 67.47 26.65


75 75
Dstribution Bars - -

Along Short Span on A-C/1-1a 75 75 8 150 0.40 1 19 12.89 247.06 97.60


12300-40

Along Short Span on A-E/1a-3 75 75 8 150 0.40 1 17 22.39 369.44 145.95


21800-40

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

Along Short Span on D-E/1-1a 75 75 8 150 0.40 1 19 6.41 122.86 48.54


6300-40

Along Long Span on 1-3/A-C 75 8 150 0.40 1 46 9.91 459.16 181.40


9800-40

Along Long Span on 1b-3/C-D 75 8 150 0.40 1 15 5.04 75.53 29.84


4925-40

Along Long Span on 1-3/D-E 75 8 150 0.40 1 19 9.91 184.99 73.08


9800-40
Staircase on G.F. - - -

1200
First Flight 12 125 0.89 1 13 3.80 49.34 43.85
2260
335
1450

3354 270
12 125 0.89 1 13 8.20 106.65 94.80
2700
430

1000
12 125 0.89 1 13 2.00 26.00 23.11
1000

1000
1000 12 125 0.89 1 13 2.00 26.00 23.11

1870
780 180 12 125 0.89 1 13 2.83 36.79 32.70

855
75
Second Flight 3354 12 125 0.89 1 13 8.05 104.64 93.01
2315
145
2260
240 780 12 125 0.89 1 13 3.28 42.64 37.90

2035
330 1000
12 125 0.89 1 13 3.37 43.75 38.88

1000
1880 12 125 0.89 1 13 4.68 60.84 54.08

180

1000
12 125 0.89 1 13 2.00 26.00 23.11
1000

450
Nosing ties 122 8 300 0.40 1 120 2.20 264.00 104.30
150

Nosing Bar 10 0.62 1 20 1.63 32.50 20.06


75 1475 75

First flight distribution bar 10 150 0.62 1 91 1.63 147.88 91.28


75 1475 75

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

Second Flight distribution bar 75 1475 10 150 0.62 1 56 1.63 91.00 56.17
75

F.F. Columns

SFL

Grid-1 (A,B,C,D,E) 3000 16 1.58 5 6 3.60 107.85 170.43

FFL

SFL

3000 16 1.58 5 6 4.56 136.65 215.94

FFL

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

SFL

Grid-2(A,B,C,D,E) 3000 20 2.47 5 4 3.88 77.50 191.36

FFL

SFL

3000
16 1.58 5 2 3.60 35.95 56.81

FFL

SFL

3000 16 1.58 5 6 4.56 136.65 215.94

FFL

SFL

Grid-3(A,B,E) 3000 16 1.58 3 6 3.60 64.71 102.26

FFL

SFL

3000 16 1.58 3 6 4.56 81.99 129.56

FFL

SFL

Grid-3(C,D) 3000 16 1.58 2 6 3.60 43.14 68.17

FFL

SFL

3000 20 2.47 2 6 5.08 60.90 150.37

FFL

0.37 0.08
100 &
Stirrups for 15 columns 8 0.40 15 29 1.59 692.52 273.59
150
0.37

0.08
0.14 100 &
8 0.40 15 52 1.13 882.96 348.82
150
0.37
Main Beams at Truss Level
Main Bars (Long side beams); Along Grid 1-1, 2-2, 3-3

0.72
Top (T/O) 21.5+0.45-2(0.05) 16 1.58 3 3 24.41 219.69 347.16

Bottom (T/O) 0.72


21.5+0.45-2(0.05)
16 1.58 3 2 24.41 146.46 231.44

21.5+0.45-2(0.07)
0.42 12 0.889 3 2 23.57 141.42 125.71

0.35 0.12
100 &
Stirrups (for 300*400) 8 0.395 3 232 1.39 968.83 382.75
150
0.25
Main Bars (Short side beams); Along Grid A,B,C,D,E 0.00 0.00

Top (T/O) 0.72


9.5+0.45-2(0.05) 16 1.58 5 3 11.29 169.35 267.61

Bottom (T/O) 0.72


9.5+0.45-2(0.05) 16 1.58 5 2 11.29 112.90 178.41

0.42
9.5+0.45-2(0.05) 12 0.889 5 2 10.73 107.30 95.38

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

0.35 0.12
100 &
Stirrups (for 300*525) 8 0.395 5 79 1.39 549.84 217.22
150
0.25
G.F Sill band
600 600
At grid 1 10 0.62 3 2 7.29 43.74 27.00
5550

8 150 0.40 3 38 0.26 29.64 11.71

600 600
10 0.62 1 2 4.55 9.10 5.62
3050

8 150 0.40 1 21 0.26 5.55 2.19

600 600
At grid 2 10 0.62 2 2 5.95 23.80 14.69
5550
8 150 0.40 2 33 0.26 17.25 6.81

600 600
10 0.62 1 2 4.61 9.22 5.69
5550
8 150 0.40 1 25 0.26 6.59 2.60

600 600
At grid A,C,D,E 10 0.62 4 2 8.05 64.40 39.75
6550

8 150 0.40 4 45 0.26 46.45 18.35

At store partition wall


10 0.62 1 2 1.88 3.75 2.31
10 0.62 1 2 4.13 8.25 5.09

Lintel Band
600 600
At grid 1 10 0.62 3 2 7.05 42.30 26.11
5550
8 150 0.40 3 38 0.26 29.64 11.71

600 600
10 0.62 1 2 4.55 9.10 5.62
3050

8 150 0.40 1 21 0.26 5.55 2.19

600 600
At grid 2 10 0.62 2 2 5.95 23.80 14.69
5550
8 150 0.40 2 31 0.26 15.95 6.30

600 600
10 0.62 1 2 4.85 9.70 5.99
5550
8 150 0.40 1 0.26 6.59 2.60
25
600 600
At grid A,C,D,E 10 0.62 4 2 8.05 64.40 39.75
6550

8 150 0.40 4 45 0.26 46.45 18.35

Vertical Band 10 0.62 4 2 2.48 19.80 12.22


2475

8 150 0.40 4 18 0.26 18.20 7.19

At store partition wall


10 0.62 1 2 1.88 3.75 2.31
10 0.62 1 2 4.13 8.25 5.09
F.F. Sill Band
600 600
At grid 1 10 0.62 3 2 7.05 42.30 26.11
5550

8 150 0.40 3 38 0.26 29.64 11.71

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)

600 600
At grid 2 10 0.62 2 2 5.95 23.80 14.69
5550

8 150 0.40 2 31 0.26 15.95 6.30

600 600
10 0.62 1 2 4.85 9.70 5.99
5550

8 150 0.40 1 25 0.26 6.59 2.60

600 600
At grid A,C,D,E 10 0.62 4 2 8.05 64.40 39.75
6550
8 150 0.40 4 45 0.26 46.45 18.35

At store partition wall


10 0.62 1 2 1.88 3.75 2.31
10 0.62 1 2 4.13 8.25 5.09
Lintel Band
600 600
At grid 1 10 0.62 3 2 7.05 42.30 26.11
5550

8 150 0.40 3 38 0.26 29.64 11.71

600 600
10 0.62 1 2 4.55 9.10 5.62
3050

8 150 0.40 1 21 0.26 5.55 2.19

600 600
At grid 2 10 0.62 2 2 5.95 23.80 14.69
5550

8 150 0.40 2 33 0.26 17.16 6.78

600 600
10 0.62 1 2 4.85 9.70 5.99
5550

8 150 0.40 1 25 0.26 6.50 2.57

600 600
At grid A,C,D,E 10 0.62 4 2 8.05 64.40 39.75
6550

8 150 0.40 4 44 0.26 45.76 18.08

Vertical Band 10 0.62 4 2 2.60 20.80 12.84


2600

8 150 0.40 4 18 0.26 19.07 7.53

At store partition wall


10 0.62 1 2 1.88 3.75 2.31

10 0.62 1 2 4.13 8.25 5.09

Soak Pit 8 200 0.40 1 1 3.77 3.77 1.49


8 200 0.40 1 1 2.51 2.51 0.99
8 200 0.40 1 1 1.26 1.26 0.50
Main Bar 8 200 0.40 1 1 1.15 1.15 0.45
8 200 0.40 1 1 1.08 1.08 0.43
8 200 0.40 1 1 0.84 0.84 0.33
Distribution Bar 8 200 0.40 1 1 1.15 1.15 0.45
8 200 0.40 1 1 1.08 1.08 0.43
8 200 0.40 1 1 0.84 0.84 0.33
Negative Bar 8 200 0.40 1 1 0.45 0.45 0.18
Distribution Bar 8 200 0.40 1 21 1.08 22.70 8.97
8 200 0.40 1 8 0.84 6.75 2.67
built in furniture
At store room
6700 X 600 built in furniture(2 nos) - -
long bar 8 0.40 2.00 5 7.00 35.00 13.83
short bar 8 0.40 2.00 46 0.73 33.11 13.08
Practical room - -
3600 X 900 built in furniture(1nos) - -
long bar 8 0.40 1.00 7 3.25 22.75 8.99
short bar 8 0.40 1.00 22 1.00 22.00 8.69

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Piece
Dia. Spacing Wt./m Total Total Wt.
SN Description Bar Shape Lot Nos. Length Remarks
(mm) (mm) (Kg) Length (Kg)
(m)
around basin 8 0.40 1.00 2 2.75 5.50 2.17
8 0.40 1.00 19 0.22 4.18 1.65
1800 X 900 built in furniture(4nos) - -
long bar 8 0.40 4.00 7 1.90 53.20 21.02
short bar 8 0.40 4.00 13 1.00 52.00 20.54
at grid 2 - -
long bar 8 0.40 1.00 4 0.93 4.01 1.58
8 0.40 1.00 4 1.38 5.96 2.35
8 0.40 1.00 4 2.35 10.18 4.02
short bar 8 0.40 1.00 32 0.60 19.20 7.59
at grid 1 - - -
long bar 8 0.40 1.00 4 4.38 18.96 7.49
8 0.40 1.00 4 3.30 14.30 5.65
8 0.40 1.00 4 0.65 2.82 1.11
short bar 8 0.40 1.00 57 0.60 33.90 13.39
at corridor - -
long bar 8 0.40 2.00 5 2.65 26.50 10.47
short bar 8 0.40 2.00 17 0.50 17.00 6.72
TOTAL 21,919.44 KG
21.92 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU, Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: 2-LaLiEC
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

2-LaLiEC Total
S. No. Description Unit Remarks
GF FF Quantity
A Common Installation
1.1 Stand Alone 40 A DP MCB with Enclosure 1 1.00 No

2 Cables and Wires


2 Nos 10 Sq mm Multistranded Cu Wire + 1 No 6 Sq mm
2.1 Multistranded Cu wire 45 45.00 Rm
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.2 45 45.00 Rm
Multistranded Cu wire

B SCHOOL BLOCKS
1 DISTRIBUTION BOARDS
DB (DB-1) Incoming: 1 x 40A DP MCB Outgoing: 2 x 25
1.1 A DP MCB 7 x 6 A SP MCB 3 x 16 A SP MCB 1 1.00 No
DB ( DB-2) & DB ( DB-3) Incoming:
1.3 1 x 25A DP MCB 1 1.00 No

2 CABLES & WIRES


2 Nos 6 Sq mm Multistranded Cu Wire + 1 No 4 Sq mm
2.1 Multistranded Cu wire 2 2 4.00 Rm
2 Nos 4 Sq mm Multistranded Cu Wire + 1 No 2.5 Sq mm
2.2 Multistranded Cu wire 2 2 4.00 Rm
2 Nos 2.5 Sq mm Multistranded Cu Wire + 1 No 1.5 Sq mm
2.3 12 12 24.00 Rm
Multistranded Cu wire

3 General service light point wiring


3.1 One way light point 20 17 37.00 Pts
3.2 Two Way Light Point 1 1.00 Pts
4 6A Universal pin Light power point wiring 17 32 49.00 Pts
5 Switch Socket Outlets
5.1 6A Universal power Switch Socket 17 32 49.00 No

7 Light Fixtures/Luminaires & Accessories


7.1 24 W LED Surface Mounted Square type 6 6.00 Nos.
7.2 24 W LED Reccesed Mounted Square type 6 6.00 Nos.
7.3 18 W LED Surface Mounted Square type 4 4.00 Nos.
7.4 18 W LED Recessed Mounted Square type 4 4.00 Nos.
7.5 12 W LED Surface Mounted Cylindrical type 7 7.00 Nos.
7.6 12 W LED Recessed Mounted Cylindrical type 8 8.00 Nos.
7.7 LED Wall Light made 1 1.00 Nos.
8 Pull Box 3 3.00 No
9 External post top light pole 3 3.00 No
10 Post Top External Light Fixtures 3 3.00 No

11 Earthing and Lightning protection


11.1 11.1. Chemical Earhting 3 3.00 Nos.
11.2 Earthing Bar 3 3.00 Nos.
GI Strip/Cu wire Earthing
12.1 12.1. 25 x 3 mm GI Strip 64.00 Mtr.
12.2 12 SWG Cu wire 14.00 Mtr.
13 Earth Test link 1.00 No

FIRE EXTINGUISHER
D a) Supplying Fire extinguisher ABC stored Pressure 5.0kg size 1 3 4.00 Nos.
ABC stored pressure type Fire extinguisher.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
S. No. Description No. Length Breadth Height Qty Unit Remarks
1 Earthworks
1.1 Site Clearance
Toilet Block 1 14.30 12.30 175.89
Septic Tank 1 8.75 3.95 34.56
Soak Pit 1 8.55 Area 8.55
Sewer Manhole (Rectangular) 4 2.00 2.00 16.00
Total 235.00 sq.m

1.2 Earthwork in excavation


Footing
F1 9 1.30 1.30 1.20 18.25
Excavation for lower tie beam
Grid 1 2 3.70 0.60 0.7 3.11
Grid 2 2 3.70 0.50 0.7 2.59
Grid 3 2 3.70 0.60 0.7 3.11
Between grid 2 and 3 2 4.45 0.60 0.7 3.74
Grid A-12 , B-12 and C-12 3 2.20 0.60 0.7 2.77
Along grid A-23 and C-23 2 1.20 0.50 0.7 0.84
Along grid B-23 1 1.20 0.60 0.7 0.50
Ramp
For Slope 2 1.58 1.03 0.28 0.89
Drain 1 11.45 0.63 0.23 1.61
1 11.45 0.58 0.38 2.52
Outside Steps 2 1.20 0.68 0.15 0.24

Septic Tank 1 6.75 1.95 2.72 35.78


Soak Pit 1 4.15 Area 1.55 6.44
For Sewer Manhole (Rectangular) 4 1.00 1.00 0.50 2.00
Total 84.39 cum

1.3 Earth Back filling


Total earthwork 84.39
Deduction
Boulder soling -1 19.26 Vol. -19.26
PCC work -1 2.03 Vol. -2.03
RCC work -1 5.16 Vol. -5.16

Inside the room(Compacted) 2 4.70 3.20 0.18 5.41


Along lobby(Compacted) 2 4.70 2.20 0.18 3.72
Total 67.07 cum

1.4 Boulder soling


For Footing
F1 9 1.00 1.00 0.20 1.80
For Lower Tie Beam
Grid 1 and Grid 3 2 9.40 0.45 0.10 0.85

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Grid 2 2 4.70 0.35 0.10 0.33
Between grid 2 and 3 2 4.45 0.45 0.10 0.40
Along grid A-12,B-12 & C-12 3 3.20 0.45 0.10 0.43
Along grid A-23 & C-23 2 2.20 0.35 0.10 0.15
Along grid B-23 1 2.20 0.45 0.10 0.10
Toilet Floors 2 4.75 3.25 0.20 6.18
Corridor Floors 2 4.75 0.88 0.20 1.66
Ramp
below ramp 2 6.77 1.03 0.20 2.78
For Outer Steps 2 1.20 0.60 0.1 0.14
Drain 1 11.45 1.20 0.10 1.37
Septic tank 1 6.75 1.95 0.1 1.32
For Sewer Manhole (Rectangular) 4 1.00 1.00 0.1 0.40
Soak pit ( Boulder packing) 1 1.13 Area 1.20 1.36
Total 19.26 cum

2 Concrete Works
2.1 PCC
2.1.1 PCC work (1:3:6)
For Footing
F1 9 1.00 1.00 0.10 0.90
For Lower Tie Beam
Grid 1 and Grid 3 2 9.40 0.45 0.05 0.42
Grid 2 2 4.70 0.35 0.05 0.16
Between grid 2 and 3 2 4.45 0.45 0.05 0.20
Along grid A-12,B-12 & C-12 3 3.20 0.45 0.05 0.22
Along grid A-23 & C-23 2 2.20 0.35 0.05 0.08
Along grid B-23 1 2.20 0.45 0.05 0.05
Septic Tank 1 0.83 1.45 0.08 0.09
Sewer Manhole (Rectangular)
Bottom 4 1.00 1.00 0.10 0.40
PCC Benching 4 0.07 Area 1.00 0.30
Total 2.82 cum

Sand Filling
Periphery of Soak pit 1 1.88 Area 1.55 2.92
Total 2.93 cu.m

2.1.2 P.C.C.(1:2:4) Works


Toilet 2 3.20 4.75 0.20 6.08
Corridor 2 1.20 4.75 0.20 2.28
Ramp
Below Ramp 2 6.77 1.03 0.08 1.04
For Outer Steps 2 1.20 0.60 0.05 0.07
2 1.20 0.30 0.05 0.04
Drain 1 11.45 0.58 0.075 0.49

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Total 10.01 cu.m

2.2 RCC Work 1:1.5:3


For Footing
F1 9
Square portion 1.00 1.00 0.20 1.80
Trapazoid portion Area 0.63 0.15 0.84
Lower Tie Beam
Grid 1,2,3 3 9.40 0.25 0.25 1.76
Grid A-12,C-12 2 3.20 0.25 0.25 0.40
Grid B-13 1 5.70 0.25 0.25 0.36
Plinth Tie Beam
Grid 1,2,3 3 9.40 0.25 0.30 2.12
Grid A-12,C-12 2 3.20 0.25 0.30 0.48
Grid A-23,C-23 2 2.20 0.25 0.59 0.65
Grid B-13 1 5.70 0.25 0.30 0.43
Column
From lower to plinth tie beam 9 0.30 0.30 1.00 0.81
Ground Floor Column 9 0.30 0.30 3.00 2.43
Truss Beam
Grid 1 1 9.40 0.25 0.40 0.94
Grid 2-3 2 9.40 0.25 0.45 2.12
Grid A-12,B-12,C-12 3 3.20 0.25 0.40 0.96
Grid A-23,B-23,C-23 3 2.20 0.25 0.45 0.74
Slab
Corridor Slab 2 4.75 2.25 0.150 3.21
Lintel Bands,
Ground floor level
Grid 1,2,3 3 9.40 0.23 0.13 0.81
Grid A& C 2 3.20 0.23 0.13 0.18
Grid B 1 5.40 0.23 0.13 0.16
Partition Wall
Partition Wall for disable toilet 2 3.27 0.23 0.13 0.19
Partition wall for toilet short wall 2 1.32 0.13 0.13 0.04
Partition wall for toilet long wall 2 2.50 0.13 0.13 0.08
Sill Bands
Ground floor level
Grid 1,2,3 3 9.40 0.23 0.08 0.49
Grid A& C 2 3.20 0.23 0.08 0.11
Grid B 1 5.40 0.23 0.08 0.09
Partition Wall
Partition Wall for disable toilet 2 3.27 0.23 0.08 0.11
Partition wall for toilet short wall 2 1.32 0.13 0.08 0.02
Partition wall for toilet long wall 2 2.50 0.13 0.08 0.05
Along the incinerator 3 1.95 0.13 0.08 0.05
Deduction of Doors For Sill
Ground floor level
D1 -2 1.00 0.23 0.08 -0.03
D2 -2 0.90 0.23 0.08 -0.03
D3 -4 0.75 0.13 0.08 -0.03

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Along the water trough 2 3.75 0.60 0.10 0.45
Water trough edge 2 5.40 0.20 0.10 0.22
at both end 2 0.48 0.20 0.10 0.02
at Center 1 0.50 0.20 0.10 0.01
Incinerators Slab 1 0.83 1.05 0.08 0.06
Septic Tank
At Bottom 1 6.30 2.25 0.15 2.13
Concealed Beam CB1 1 1.95 0.25 0.12 0.06
Concealed Beam CB 1 2.25 0.15 0.12 0.04
Top Cover 1 5.75 1.95 0.12 1.35
Deduction of Manhole -2 0.60 0.60 0.12 -0.09
Manhole Cover Slab 2 0.60 0.60 0.15 0.11
Manhole Cover Slab 1 0.75 0.75 0.15 0.08
Soak Pit
RCC slab 1 4.15 Area 0.13 0.52
Manhole/Waste Chamber
Top Cover 4 1.00 1.00 0.15 0.60
Total 27.89 cu.m

2.3 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10 27.89 278.90
Total 278.90 Kg

2.5 Form Work


For Footing
F1 9 4.00 0.20 7.20
Lower Tie Beam
Grid 1,2,3 3 9.40 0.50 14.10
Grid A-12,C-12 2 3.20 0.50 3.20
Grid B-13 1 5.70 0.50 2.85
Pedestal column 9 1.00 1.20 10.80
Deduction1 at beam and column junction at LTB -24 0.25 0.25 -1.50
Deduction1 at beam and column junction at UTB -24 0.25 0.30 -1.80
Plinth Tie Beam
Grid 1,2,3 3 9.40 0.60 16.92
Grid A-12,C-12 2 3.20 0.60 3.84
Grid A-23,C-23 2 2.20 1.18 5.18
Grid B-13 1 5.70 0.60 3.42
Ground Floor Column 9 1.20 3.00 32.40
Deduction for Beam opening part -24 0.25 0.40 -2.40
Truss Beam
Grid 1-2-3 3 9.40 1.15 32.43
Grid A-12,B-12,C-12 3 3.20 1.05 10.08
Grid A-23,B-23,C-23 3 2.20 1.15 7.59
G.F. Slab
Corridor Slab 2 4.75 2.25 21.38
Lintel Bands,
Ground floor level
Grid 1,2,3 3 9.40 0.25 7.05
Grid A & C 2 3.20 0.25 1.60

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Grid B 1 5.40 0.25 1.35
Partition Wall
Partition Wall for disable toilet 2 3.27 0.25 1.64
Partition wall for toilet short wall 2 1.32 0.25 0.66
Partition wall for toilet long wall 2 2.50 0.25 1.25
Sill Bands
Ground floor level
Grid 1,2,3 3 9.40 0.15 4.23
Grid A & C 2 3.20 0.15 0.96
Grid B 1 5.40 0.15 0.81
Partition Wall
Partition Wall for disable toilet 2 3.27 0.15 0.98
Partition wall for toilet short wall 2 1.32 0.15 0.40
Partition wall for toilet long wall 2 2.50 0.15 0.75
Along the incinerator 3 1.95 0.08 0.44
Deduction of Doors For Sill
Ground floor level
D1 -2 1.00 0.08 -0.15
D2 -2 0.90 0.08 -0.14
D3 -4 0.75 0.08 -0.23
Along the water trough
Along the water trough 2 3.75 0.60 4.50
Water trough edge 2 3.75 0.50 3.75
at both end 2 0.48 0.50 0.48
at Center 1 0.50 0.50 0.25
Incinerators Slab 1 0.53 0.90 0.47
1 2.70 0.08 0.20
Septic Tank
At Bottom 1 17.10 0.15 2.57
Concealed Beam CB1 1 1.95 0.49 0.96
Concealed Beam CB 1 2.25 0.24 0.54
Top Cover 1 5.75 1.95 11.21
1 15.40 0.12 1.85
Deduction of Manhole -2 2.40 0.12 -0.58
Manhole Cover Slab 2 2.40 0.15 0.72
Manhole Cover Slab 1 3.00 0.15 0.45
Side Formwork for void 2 2.40 0.15 0.72
Soak Pit
RCC slab 1 4.15 Area 4.15
1 7.22 0.13 0.90
Manhole/Waste Chamber 0.00
Top Cover 4 4.00 0.15 2.40
Total 222.83 cu.m

3 Brickworks

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
3.2 Brick Masonary Works (1:4 c/s)
Below Plinth tie beam
Grid 1,2,3 3 9.40 0.35 0.40 3.95
9.40 0.10 0.55 1.55
Grid A-12, B-12 & C-12 3 3.20 0.35 0.40 1.34
3.20 0.10 0.55 0.53
Grid B-23 1 2.20 0.35 0.40 0.31
2.20 0.10 0.55 0.12
Along the ramp 2 4.70 0.35 0.68 2.22

Brick Work above Tie Beam


Ground floor
Grid A-12, B-12& C-12 3 3.20 0.23 2.40 5.30
Grid B-23 1 2.20 0.23 2.35 1.19
Grid 1&2 2 9.40 0.23 2.40 10.38
Grid 3 1 9.40 0.23 1.30 2.81
Partition Wall for disable toilet 2 3.27 0.23 2.80 4.21
Cross wall at Water trough 2 0.58 0.23 0.30 0.08
2 0.58 0.23 0.45 0.12
Drain 1 11.45 0.25 0.20 0.57
Outer Steps 2 1.20 0.60 0.15 0.22
2 1.20 0.30 0.15 0.11
Deduction for doors and windows
Ground floor
D1 -2 1.00 0.23 2.10 -0.97
D2 -2 0.90 0.23 2.10 -0.87
V1 -2 3.48 0.23 0.38 -0.60
V2 -2 3.48 0.23 0.33 -0.52
V3 -2 1.98 0.23 0.38 -0.34
V4 -2 1.98 0.23 0.33 -0.30
Incinerators 2 0.65 0.23 0.30 0.09
1 0.65 0.23 0.30 0.04
Septic Tank
Outer Wall 2 6.00 0.38 2.72 12.23
1 1.20 0.38 2.72 1.24
1 1.20 0.38 1.70 0.78
1 1.20 0.25 1.02 0.31
2 0.50 0.25 1.02 0.26
Baffle wall 1 1.20 0.25 2.72 0.82
Deduct openings -1 1.20 0.25 0.57 -0.17
Soak Pit 1 1.14 Area 0.55 0.63
Total 47.63 Cu.m.

3.3 Half Brick Work (1:4 c/s)


Toilet Room
Partition wall for toilet short wall 2 1.32 2.80 3.70
Partition wall for toilet long wall 2 2.50 2.80 14.00
Low wall Beside Urinal 2 0.60 1.20 1.44
Cross wall at Water trough 2 0.30 0.60 0.36
Incinerators 1 1.95 1.20 2.34

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Drain 1 11.45 0.20 2.29
Deduction for doors and windows
D3 -4 0.75 2.10 -6.30
Septic Tank
Inlet wall 1 0.70 1.17 0.82
Manhole Cover wall 2 1.20 0.35 0.84
Manhole/Waste Chamber
Rectangular 4 4.00 0.60 9.60
Total 29.08 Sq.m.

3.4 Honey Comb Brick (350 mm) Works (1:3c/s)


Soak pit 1 1.14 Area 1.40 1.59
Total 1.59 Cu.m.

4 DOORS & WINDOWS WORKS


4.4 UPVC Door
UPVC Door Shutter
D1 2 1.0 2.05 4.10
D2 2 0.9 2.05 3.69
D3 4 0.70 2.05 5.74
Total 13.53 sq.m

4.5 Window Grill


Ventilation
Ventilation V1 2 2.48 0.38 1.86
Ventilation V2 2 2.48 0.33 1.61
Ventilation V3 2 1.98 0.38 1.48
Ventilation V4 2 1.98 0.33 1.28
Total 6.23 sq.m

5 FLOORING WORKS
5.1 Hard Concrete Flooring (40mm) With Neat Cement Punning
Toilet Floors 2 4.75 3.25 30.88
Corridor Floors 2 4.75 1.27 12.07
Outside Staircase 2 1.20 1.05 2.52
Ramp
Slanted Portion 1 5.45 1.03 5.59
Horizontal Portion 1 1.20 1.03 1.23
Drain 1 11.45 1.48 16.95
Along the terrace 2 4.75 2.25 21.38
Water Trough 2 0.60 3.75 4.50
Total 95.10 sq.m

5.2 Cement Finishing Skirting works


Along the corridor and ramp 2 13.97 27.94
Deduction -2 1.90 -3.80
Total 24.14 r.m

5.3 Terrazo cast in Situ Dado (Tile works)


Along grid 1 2 4.84 1.20 11.62

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Along grid 2 2 4.84 1.20 11.62
Deduction
D1 -2 0.98 1.20 -2.35
D2 -2 0.86 1.20 -2.06
Along grid A 1 3.34 1.20 4.01
Along grid B 2 3.34 1.20 8.02
Along grid C 1 3.34 1.20 4.01
Partition Wall for disable toilet 2 3.30 1.20 7.92
Partition wall for toilet short wall 4 1.35 1.20 6.48
Partition wall for toilet long wall 2 2.50 1.20 6.00
Urinal 4 1.30 1.35 7.02
Deduction
D3 -4 0.73 1.20 -3.50
Water trough 2 1.85 0.90 3.33
2 1.85 0.75 2.78
Total 64.87 sq.m

6 ROOFING/TERRACING WORKS
6.1 Metal Works
Truss 1 999.81
Total 999.81 kgs

6.2 CGI Sheet Roofing


Sheet Area 1 12.10 2.13 25.77
Sheet Area 1 12.10 2.74 33.15
Total 58.93 sq.m

6.3 CGI Sheet Roofing Ridge


Top Ridge cover 1 12.10 12.10
Total 12.10 r.m

6.4 GI facia (Eaves) Volume Density


Front and back sides 2 0.006 7850 98.78
Sides 4 0.001 7850 44.74
Total 143.52 k.g

6.5 False Ceiling


Inside portion 1 9.40 3.20 30.08
Outside portion 1 12.10 0.79 9.55
2 4.87 0.90 8.77
Total 48.40 sq.m

7 PLASTERING WALL FINISHING WORKS


7.1 Plaster Works
7.1.1 CEMENT PLASTER WORKS ON INNER WALL (1:6)
Grid 1 & Grid 2 2 9.40 1.20 22.56
Grid 2 1 9.40 2.40 22.56
Grid 3 1 9.40 1.50 14.10
Grid A-12, B-12& C-12 4 3.20 1.40 17.92
Grid B-23 2 2.20 2.55 11.22

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Partition Wall for disable toilet 4 3.27 1.80 23.54
Partition wall for toilet short wall 4 1.32 1.80 9.50
Partition wall for toilet long wall 4 2.50 1.80 18.00
Cross wall at Water trough 4 0.58 0.30 0.69
4 0.58 0.45 1.04
4 0.30 0.58 0.69
Deduction
D1 -2 1.00 2.10 -2.10
D2 -2 0.90 2.10 -1.89
V1 -2 3.48 0.38 -1.30
V2 -2 3.48 0.33 -1.13
V3 -2 1.98 0.38 -0.74
V4 -2 1.98 0.33 -0.64
Total 134.02 sq.m

7.1.2 CEMENT PLASTER WORKS ON CEILING (1:4)


Main Beam
Grid 1 & Grid 2 2 9.50 0.45 8.55
Grid A-12, B-12& C-12 3 3.25 0.40 3.90
Slab
Corridor Slab 1 9.50 2.25 21.38
Column Copla 8 0.05 3.00 1.20
Total 35.03 Sq.m.

7.1.3 External Plaster


Grid 1 1 9.40 2.60 24.44
Grid 3 1 9.40 1.50 14.10
Grid A-12 & C-12 2 3.20 1.85 11.84
Plinth Beam
Grid 1 & Grid 3 2 9.40 0.45 8.46
Grid A-12 & C-12 2 3.20 0.45 2.88

Main Beam Outer


Grid 1 1 9.40 0.40 3.76
Grid 2 1 9.40 0.55 5.17
Grid 3 1 9.40 1.00 9.40
Grid A-12 & C-12 2 3.20 0.40 2.56
Grid A-23 & C-23 2 2.20 1.00 4.40
Grid B-23 1 2.20 0.85 1.87
Column Outer
Grid 1 2 0.60 3.00 3.60
1 0.30 3.00 0.90
Grid 2 3 0.60 3.00 5.40
Grid 3 2 0.90 3.00 5.40
1 0.30 3.00 0.90
Column Copla 12 0.07 3.00 1.26
Total 106.34 Sq.m.

7.1.4 Internal Plaster on Wall (1:4) with Cement Punning


Inside Septic Tank Wall 1.00 11.30 2.25 25.43

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
S. No. Description No. Length Breadth Height Qty Unit Remarks
Inner Wall of manhole 2.00 2.40 0.25 1.20
Inner Wall of Inlet 1.00 2.25 0.70 1.58
1.00 0.75 1.00 0.75
Baffle wall 2.00 1.20 1.45 3.48

Sewer Manhole (Rectangular)


Inside Sewer Manhole 2.00 3.00 0.30 1.80
Sewer Manhole (Circular)
Inside Sewer Manhole 2.00 2.36 0.30 1.41
Total 35.65 sq.m

7.2 Painting Works


7.2.1 Distemper Paint
Total of Interior Wall Plaster 1 134.02 Area 134.02
Total of Ceiling Plaster 1 35.03 Area 35.03
False Ceiling 1 48.40 Area 48.40
Total 217.44 sq.m

7.2.2 Exterior Weather Coat Paint


Total of External Wall Beam and Column Plain Plaster 1 106.34 Area 106.34
Total 106.34 sq.m

7.2.4 Enamel Painting


ForVentilation Coefficient
V1 2 2.48 0.38 2.00 3.71
V2 2 2.48 0.33 2.00 3.22
V3 2 1.98 0.38 2.00 2.96
V4 2 1.98 0.33 2.00 2.57
Total 12.46 sq.m

8 Miscellaneous
8.2 Cement Board Wall
For Partition
Gabel wall 2 1.09 Area 2.17
Total 2.18 sq.m

8.4 Pump Shed


1 1.00 1.00
Total 1.00 Nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
Length Breadth Height Quantity
S.N Material Description Nos. Quantity Units kg/unit
(m) (m) (m) (kg)
1 Truss
10mm thick plate Base Plate 12 0.3 0.3 0.01 0.011 cu.m. 7,850.00 84.78
10mm thick plate Truss stiffener 12 0.3 0.05 0.01 0.002 cu.m. 7,850.00 14.13
10mm thick plate 12 0.3 0.0865 0.01 0.003 cu.m. 7,850.00 24.44
10mm thick plate 12 0.05 0.085 0.01 0.001 cu.m. 7,850.00 4.00

16mm dia rod Anchor bolt 24 0.45 10.800 r.m. 1.58 17.07
16mm dia nut nut 24 24.000 no. 0.03 0.75

NB 40(M) Bottom Chord 5 3.9 19.500 r.m. 3.61 70.40


NB 40(M) Verticle Struts 5 0.561 2.805 r.m. 3.61 10.13
NB 40(M) Runner 1 10 10.000 r.m. 3.61 36.10

NB 50(M) Top Chord 5 2.036 10.180 r.m. 5.10 51.92


NB 50(M) 5 2.629 13.145 r.m. 5.10 67.04

NB 32(M) Inclined Struts 10 0.912 9.120 r.m. 3.15 28.73

NB65 (M) Purlins 6 10.1 60.600 r.m. 6.53 395.72

10mm thick plate Top chord cleat 30 0.2 0.09 0.01 0.005 cu.m. 7,850.00 42.39
10mm thick plate Purlin Cleat 60 0.2 0.09 0.01 0.011 cu.m. 7,850.00 84.78

10mm dia nut bolt (50mm) nut bolt 60 60.000 no. 0.05 2.91

10mm thick plate Runner plate 16 0.175 0.07 0.01 0.002 cu.m. 7,850.00 15.39
10mm thick plate Runner box 32 0.175 0.07 0.01 0.004 cu.m. 7,850.00 30.77
10mm thick plate 32 0.08 0.07 0.01 0.002 cu.m. 7,850.00 14.07

16mm dia nut bolt (50mm) Runner box 32 32.000 no. 0.13 4.30

Total Truss 999.81

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
BAR BENDING SCHEDULE
Piece
Dia. Spacing Wt./m Total Wt.
SN Description Bar Shape Nos. Length Weight (Kg) Remarks
(mm) (mm) (Kg) (Kg)
(m)

0.9
1 F1 Footing: Main bars 12 150 0.888 7 1.06 6.59
0.08

0.9
Distribution bars 12 150 0.888 7 1.06 6.59
0.08

for One footing = 13.18


for Nine footings = 118.60
2 Column C1, (300*300mm) (9 Columns)
0.42
Ld= d*60, Top= (Ld+10
Main Bars 12 0.888 8 5.12 36.34 327.03
(0.27+0.55+0.45+2.975) dia.)
0.06+0.39

0.22 0.08
100 &
Stirrups 8 0.395 30 1.04 12.32 110.92 Total height
150
0.22 for Stirrups= 3.25
0.15 0.08 & Ht. for 150 1.65
100 & spacing=
8 0.395 30 0.76 9.01 81.05
150
0.15
0.08 3 Nos. in
U shaped Stirrups & ties (total) 8 each 0.395 9 1.20 4.27 38.39
0.22
member
for One Column = 61.93
for Nine Columns = 557.40
3 Foundation Beams, 250*250

Main Bars (Long side beams); Along 10.0+0.3-2(0.06)


0.6 12 0.888 6 12.10 64.47 193.41 3 beams 1 Lap
Grid 1-1, 2-2, 3-3

0.15 0.08
100 &
Stirrups (for 250*250) 8 0.395 203 0.76 61.04 61.04 5 Stretches
150
0.15

0.15 0.08
8 150 0.395 32 0.76 9.71 9.71 1 Stretch (Section 2)
0.15

Main Bars (Short side beam); Along


0.6 6.0+0.3-2(0.06) 12 0.888 6 7.38 39.32 39.32 1 beam
Grid B-B

0.15 0.08
100 &
Stirrups (for 250*250) 8 0.395 48 0.76 14.41 14.41
150
0.15

Main Bars (Short side beams); Along


0.6 3.5+0.3-2(0.06) 12 0.888 6 4.88 26.00 52.00 2 beams
Grid A-A, C-C [Stretch 1-2]

0.15 0.08
100 &
Stirrups (for 250*250) 8 0.395 28 0.76 8.46 16.91
150
0.15

Main Bars (Short side beam); Along


2.5+0.3-2(0.06) 16 1.580 4 4.44 28.06 56.12 2 beams
Grid A-A, C-C [Stretch 2-3] 0.88

0.6 2.5+0.3-2(0.06) 12 0.888 2 3.88 6.89 13.78 2 beams

0.40 0.08
100 &
Stirrups (for 250*501) 8 0.395 20 1.26 9.87 19.74
150
0.15

4 Tie Beams, 250*300mm

Main Bars (Long side beams); Along 10.0+0.3-2(0.06)


0.6 12 0.888 6 12.10 64.47 193.41 3 beams 1 Lap
Grid 1-1, 2-2, 3-3

0.25 0.08
100 &
Stirrups (for 250*300) 8 0.395 203 1.06 85.14 85.14 5 Stretches
150
0.20

0.25 0.08
8 150 0.395 32 1.06 13.54 13.54 1 Stretch (Section 2)
0.20

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Main Bars (Short side beam); Along
0.6 6.0+0.3-2(0.06) 12 0.888 6 7.38 39.32 39.32 1 beam
Grid B-B

0.25 0.08
100 &
Stirrups (for 250*300) 8 0.395 48 1.06 20.10 20.10
150
0.20

Main Bars (Short side beams); Along


0.6 3.5+0.3-2(0.062) 12 0.888 6 4.88 25.98 51.96 2 beams
Grid A-A, C-C [Stretch 1-2]

0.25 0.08
100 &
Stirrups (for 250*300) 8 0.395 28 1.06 11.79 23.59
150
0.20

Main Beams:
5 Long Beams: 250*450

Bottom Bars (Long side); Along 10.0+0.3-2(0.06)


0.4+0.2 12 0.888 2 12.10 21.49 64.47 3 beams 1 Lap
Grid 1-1, 2-2, 3-3

10.0+0.3-2(0.06)
0.4+0.48 16 1.580 2 12.90 40.76 122.29 1 Lap

0.88
Top Bars 10.0+0.3-2(0.06) 16 1.580 3 12.90 61.15 183.44 1 Lap

0.40 0.08
100 &
Stirrups (for 250*450) 8 0.395 244 1.36 131.08 131.08 6 Stretches
150
0.20
Short side beams:

6.0+0.3-2(0.06)
Bottom Bars 0.4+0.2 12 0.888 4 7.38 26.21 78.64 3 beams

0.6
Top Bars 6.0+0.3-2(0.062) 12 0.888 3 7.38 19.66 58.98

0.40 0.08
Stirrups (for 250*450) 8 100 0.395 23 1.36 12.36 37.07
0.20

0.35 0.08
100 &
Stirrups (for 250*400) 8 0.395 28 1.26 14.02 42.06
150
0.20

0.86
6 SLAB: Short Span 0.11 2.71 10 150 0.617 65 4.65 186.49 186.49 65

1.48
Long Span 10.21 10 300 0.617 9 13.95 77.46 77.46 1 Lapping 9
0.09

1.48
1 Lapping, & Cranked
10.21 10 300 0.617 9 14.17 78.69 78.69
0.09 over middle beam

3.25
Top Extra (Negative) Bar 8 300 0.395 9 3.25 11.55 11.55

10.21
Distribution Bar, Long Span 8 150 0.395 10 10.21 41.40 41.40

2.71
Distribution Bar, Short Span 8 150 0.395 41 2.71 43.53 43.53

Grand Total 2736.63 Kg


Grand Total 2.74 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
Reinforcement of Septic and Soak pit tank
Total Total
S. No Item Description Dia Lot No length m wt/m Remarks
length Quantity
1 Septic tank
Beam
Long span

16 2 2 8.34 33.36 1.58 52.71


695 6950 695

12 2 1 7.78 15.56 0.89 13.82


415 6950 415

85 85 16 2 2 7.12 28.48 1.58 45.00


6950

85 85 12 2 1 7.12 14.24 0.89 12.65


6950
200

8 2 70 1.06 148.40 0.40 58.62


80
250

short span

16 1 2 5.79 11.58 1.58 18.30


695 4400 695

12 1 1 5.23 5.23 0.89 4.64


415 4400 415

85 85 16 2 2 4.57 18.28 1.58 28.88


4400

85 85 12 2 1 4.57 9.14 0.89 8.12

4400
200

8 1 45 1.06 47.70 0.40 18.84


80
250

slab
Along Y axis

110 8 1 45 5.12 230.40 0.40 91.01 Main Bar


5010

distribution bar 8 2 13 4.91 127.66 0.40 50.43


negetive bar 8 1 47 5.06 237.82 0.40 93.94
along X axis

1915
110 8 1 34 9.03 306.85 0.40 121.21 Main Bar
7000

distribution bar 8 2 10 7.00 140.00 0.40 55.30


Corner bars 10 12 3 0.60 21.60 0.62 13.33
Concealed beam

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
main bars 10 2 4 6.60 52.80 0.62 32.58
stirrups 8 2 41 0.56 45.92 0.40 18.14
Steps at septic tank 16 2 5 0.60 6.00 1.58 9.48
2 Soak pit
Beam 16 1 4 12.74 50.94 1.58 80.49
12 1 2 12.50 24.99 0.89 22.19
Slab 8 1 2 1.17 2.33 0.40 0.92
8 1 2 1.80 3.60 0.40 1.42
8 1 2 2.23 4.45 0.40 1.76
8 1 2 2.55 5.09 0.40 2.01
8 1 2 2.80 5.60 0.40 2.21
8 1 2 3.00 6.00 0.40 2.37
8 1 2 3.16 6.32 0.40 2.50
8 1 2 3.28 6.56 0.40 2.59
8 1 2 3.38 6.76 0.40 2.67
8 1 4 1.35 5.40 0.40 2.13
8 1 4 1.37 5.47 0.40 2.16
8 1 4 1.38 5.50 0.40 2.17
negetive bar 8 1 23 0.60 13.80 0.40 5.45
distribution bar 8 1 4 10.99 43.96 0.40 17.36
Total 897.38 Kg
Grand Total 0.90 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Tc(S)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

Total
S. No. Description Tc(S) Unit Remarks
Quantity
A. Common Installation
1.2 Stand Alone 6 A DP MCB with Enclosure 2 2.00 nos.
B School Blocks
1 DISTRIBUTION BOARDS
1.5 6A DP MCB with Enclosure 2.00 2.00 nos.
3 General Service Light Point Wiring
3.1 One Way Light Point 12 12.00 pts.
3.3 Ceiling and Exhaust Fan Point Wiring 4 4.00 pts.
6 Sweep Ceiling/ Exhaust Fan/Wall Fan
6.2 225mm dia M/D exhaust Fan 4 4.00 nos.
7 Light Fixtures/Luminaires & Accessories
7.6 LED Wall Light 2 2.00 nos.
7.7 9 W LED Surface Mounted Cylindrical type 2 2.00 nos.
7.8 6 W LED Recessed Circular type 6 6.00 nos.
7.9 7 W LED T5 Slim Mirror Light 2 2.00 nos.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Building: Toilet Block,Tc(S)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
Length
S. No. Description No. Quantity Unit Remarks
(m)
A Piping Works
1 WATER SUPPLY INSTALLATION
a CPVC pipes SDR-11
40 mm 1 150 150.00 r.m
20mm 1 22 22.00 r.m
15mm 1 7 7.00 r.m
c CPVC Ball Valve
40 mm 5 5.00 nos.
25 mm 2 2.00 nos.
d Electrical Centrifugal Water Pump 1 1.00 nos.
e 2000 litres Capacity Water Storage Tank 1 1.00 nos.
2 Sewer, Rain and Waste Water Installation
110 mm 1 40 40.00 r.m
75mm 1 50 50.00 r.m
50mm 1 21 21.00 r.m

B School Blocks
1 Sanitary Installation
a Lab Sink 5 5.00 set
b PVC Multi Floor Trap 10 10.00 nos.

2 Sanitary Installation
a Water Closet Set 2 2.00 set
b Orissa Pan 4 4.00 set
c Hand Wash Basin 2 2.00 set
d Ladies Urinal 2 2.00 set
e Self Closing Bib Cock 12 12.00 nos.
f CP Spreader in Urinal 4 4.00 set
g Toilet Paper Holder 2 2.00 nos.
h Commode Spray 2 2.00 nos.
i PVC Multi Floor Trap 10 10.00 nos.
j Waste Coupling and PVC Bottle Trap 4 4.00 nos.
k 40mm SS Grab Bar-Side 2 2.00 nos.
l 40mm SS Grab Bar-Rear 2 2.00 nos.
m CP Foldable Hinge 4 4.00 nos.

Prepared By: Checked By: Approved By:


Sharma AM JV Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

Building: 2-LaLiEC
S.N Furniture Description Symbol Qty Unit Remarks
Classroom
1 ECD Student Desk (6 Seater) D-03 3 nos.
4 Soft Board F-01 1 nos.
5 Book Shelf F-02 3 nos.
6 Teacher's Table T-01 3 nos.
7 Teacher's Chair C-01 3 nos.
8 White Board F-03 3 nos.
Library
6 Student Bench G6-12 (3 Seater) B-02C 14 nos.
4 Library Table T-02 7 nos.
5 Library Shelf F-04 5 nos.
Computer nos.
7 Computer Table T-04 12 nos.
8 Computer Shelf C-02 24 nos.
9 White Board with Stand F-05 1 nos.
Laboratory
10 Equipment Shelf F-07 3 nos.
11 Lab Stool F-08 31 nos.
Miscellaneous
12 Equipment Cabinet F-09 4 nos.
13 Cusions F-16 18 nos.
14 Carpet 27.43 sq.m
Total 135 nos.

Building: Academic Block,3-12(MsF)


S.N Furniture Description Symbol Qty Unit Remarks
1 Student Desk G1-2 (3 Seater) D-02A 22 nos.
2 Student Desk G3-5 (3 Seater) D-02B 33 nos.
3 Student Desk G6-12 (3 Seater) D-02C 55 nos.
4 Student Bench G1-2 (3 Seater) B-02A 22 nos.
5 Student Bench G3-5 (3 Seater) B-02B 33 nos.
6 Student Bench G6-12 (3 Seater) B-02C 55 nos.
7 Teacher's Table T-01 10 nos.
8 Teacher's Chair C-01 10 nos.
9 White Board F-03 10 nos.

Office
10 Cabinet F-06 7 nos.
11 Office Table (2 Sides Drawer) T-05 1 nos.
12 Office Table (1 Side Drawer) T-06 2 nos.
13 Office Table T-07 12 nos.
14 Office Chair C-03 16 nos.
15 Office Chair-Headmaster C-04 1 nos.
16 Office Visitors Chair C-05 7 nos.
17 File Cabinet F-10 2 nos.

Miscellaneous

Prepared By: Checked By: Approved By:


Sharma AM JV Consultant Engineer DLPIU Engineer
18 Notice Board F-14 1 nos.
Total 299 nos.

Prepared By: Checked By: Approved By:


Sharma AM JV Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job: Site Development
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
1 Site Clearance
For Pavement
Infront of 3-12C(MsF)-D 1 29.25 2.70 78.98
Infront of 2-LaLi EC 1 24.15 2.70 65.21

From Gate to Infront of 3-12C(MsF)D 1 38.00 2.00 76.00


Total 220.18 sq.m

2 Earth Work Excavation


For Concrete Pavements
Infront of 3-12C(MsF)-D 1 22.55 2.70 0.25 15.22
1 6.70 1.50 0.25 2.51
1 10.00 1.50 0.25 3.75
Infront of 2-LaLi EC 1 17.45 2.70 0.25 11.78
1 6.70 1.50 0.25 2.51
1 2.90 1.50 0.25 1.09
Side of Toilet Block 1 2.95 1.80 0.25 1.33
1 Area 2.27 0.25 0.57
1 7.00 1.50 0.25 2.63
Between 3-12C(MsF)-D and Tc(S) 1 14.20 3.30 0.25 11.72
At Gate 1 4.00 2.00 0.25 2.00
From Gate to Infront of 3-12C(MsF)D 1 38.00 2.00 0.25 19.00
Gate Column 2 1.20 1.20 1.50 4.32
Excavation For Retaining Wall
Retaining wall 3m height 1 13.52 2.60 0.85 29.88
Protection Wall Infront of 2LaLiEC 1 15.00 0.55 0.30 2.48
1 2.25 0.55 0.30 0.37
Protection wall Infront of 3-12C(MsF)-D 1 14.20 0.55 0.23 1.80
Protection Wall Between 2 LaLiEC and 3 1 15.60 0.55 0.23 1.97
Retaining wall 1m height 1 8.40 1.25 0.40 4.20
Excavation For Boundary Wall
Chain Link Fence 128 0.15 0.15 0.60 1.73
Excavation For Gate Column
Column 2 1.20 1.20 1.50 4.32
Excavation For Flag Pole
Flag Pole 2 0.60 0.60 1.00 0.72
2 1.10 0.50 0.15 0.17
2 1.60 0.25 0.15 0.12
1 0.60 0.40 0.15 0.04
Total 126.16 cu.m

3 Earth Back Filling


Total Excavation Work 1 38.40 38.40
Deduction
Soling -1 6.87 -6.87
PCC -1 7.54 -7.54
RCC -2 0.29 -0.58
Stone Masonary 1 16.04 16.04
Additional Backfill of 3 m Retaining Wall 1 Area 1.18 13.52 15.94
Additional Backfill of 1 m Retaining Wall 1 Area 0.09 8.40 0.76
Total 56.15 cu.m

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
4 Boulder Soling
For Concrete Pavements
Infront of 3-12C(MsF)-D 1 22.55 2.70 0.15 9.13
1 6.70 1.50 0.15 1.51
Infront of 2-LaLi EC 1 17.45 2.70 0.15 7.07
1 6.70 1.50 0.15 1.51
1 2.90 1.50 0.15 0.65
Side of Toilet Block 1 2.95 1.80 0.15 0.80
1 Area 2.27 0.15 0.34
1 7.00 0.90 0.15 0.95
Between 3-12C(MsF)-D and Tc(S) 1 5.83 3.30 0.15 2.89
1 8.50 1.50 0.15 1.91
Gate Column 2 0.90 0.90 0.20 0.32
From Gate to Infront of 3-12C(MsF)D 1 38.00 2.00 0.15 11.40
Infront Of Gate 1 4.00 2.00 0.15 1.20
For Retaining Wall 0.00
Retaining wall 3m height 1 13.52 2.30 0.10 3.11
Protection Wall Infront of 2LaLiEC 1 21.75 0.55 0.10 1.20
1 2.25 0.55 0.10 0.12
Retaining wall 1m height 1 8.40 0.95 0.10 0.80
Protection wall Infront of 3-12C(MsF)-D 1 14.20 0.55 0.10 0.78
Protection Wall Between 2 LaLiEC and 3-
1 15.60 0.55 0.10
12C(MsF)-D 0.86
Total 46.54 cu.m

5 P.C.C.(1:3:6) Works
PCC For Gate Column
Column 2 0.90 0.90 0.08 0.12
PCC For Flag Pole
Flag Pole 2 0.30 0.30 1.20 0.22
1 2.40 0.80 0.10 0.19
2 0.30 0.30 0.08 0.01

For Retaining Wall


Retaining wall 3m height 1 13.52 2.30 0.10 3.11
Retaining wall 1m height 1 8.40 0.95 0.10 0.80
Protection Wall Infront of 2LaLiEC 1 21.75 0.60 0.10 1.31
Protection wall Infront of 3-12C(MsF)-D 1 14.20 0.60 0.10 0.85
Protection Wall Between 2 LaLiEC and 3 1 15.60 0.60 0.10 0.94
Total 7.54 cu.m

6 P.C.C.(1:2:4) Works
For Concrete Pavements
Infront of 3-12C(MsF)-D 1 22.55 2.70 0.08 4.57
1 6.70 1.50 0.08 0.75
Infront of 2-LaLi EC 1 17.45 2.70 0.08 3.53
1 6.70 1.50 0.08 0.75
1 2.90 1.50 0.08 0.33
Side of Toilet Block 1 2.95 1.80 0.08 0.40
1 7.00 0.90 0.08 0.47
1 Area 2.27 0.08 0.17
Retaining wall 3m height 1 13.52 0.50 0.10 0.68
Retaining wall 1m height 1 8.40 0.50 0.10 0.42
Protection Wall Infront of 2LaLiEC 1 21.75 0.45 0.08 0.73
Protection wall Infront of 3-12C(MsF)-D 1 14.20 0.45 0.08 0.48
Protection Wall Between 2 LaLiEC and 3 1 15.60 0.45 0.08 0.53

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)

Between 3-12C(MsF)-D and Tc(S) 1 5.83 3.30 0.08 1.44


2 8.50 1.50 0.08 1.91
Infront Of Gate 1 4.00 2.00 0.75 6.00
From Gate to Infront of 3-12C(MsF)D 1 38.00 2.00 0.08 5.70
Total 28.87 cu.m

7 P.C.C For R.C.C. Works


R.C.C. Works M20
A Foundation
Gate Column Footing
Footing 2 0.90 0.90 0.25 0.41

B Column
Gate Column 2 0.30 0.30 2.95 0.53
Top RCC Coping 2 0.59 0.59 0.05 0.03
2 0.175 0.05 0.02
Total 0.99 cu.m

8 Silica Cement Admixture


10 Kg per cu.m. of R.C.C. M20 10.00 0.99 9.88
Total 9.88 Kg
9 Steel Reinforcement
For gate
Total
At base of the footing kg per m
length
Main bar(10mm) 12 0.90 10.80 0.62 6.70
Distribution bar(10mm) 12 0.90 10.80 0.62 6.70
For column Ld (12mm) 16 0.48 7.68 0.89 6.84
For column (12mm) 16 2.80 44.80 0.89 39.87
For stirrups (external) 8mm 54 1.30 70.20 0.39 27.38
For stirrups (Internal)) 8mm 54 0.72 38.88 0.39 15.16
Total 102.64 Kg
0.10 Tons

10 Formworks
A Entrance Gate-Foundation 2 3.60 0.35 2.52
Gate Column 2 1.20 3.15 7.56
Flag Pole Steps 2 0.25 0.80 0.4
Flag Pole Masonry Top Surface 1 1.70 0.50 0.85
Infront of 3-12C(MsF)-D Through The Face 1 29.25 0.23 6.59
Infront of 2-LaLiEC Through The Face Of 1 24.15 0.23 5.44
Between 3-12C(MsF)-D and Toilet 2 5.89 0.23 2.71
1 8.50 0.23 1.96
Side of Tc(S) 1 7.00 0.23 1.61
1 2.95 0.23 0.68
Total 30.32 sq.m

11 Stone Masonry Works (1:6c/s)


Retaining Wall
Retaining wall 3m height 1 Area 2.20 13.52 29.79
1 Area 1.19 13.52 16.04
Retaining wall 1m height 1 Area 0.66 8.4 5.54
Protection Wall Infront of 2LaLiEC 1 Area 41.325 0.45 18.60
Protection wall Infront of 3-12C(MsF)-D 1 14.2 1.4 0.45 8.95
Protection Wall Between 2 LaLiEC and 3-
1 15.6 0.45 0.82 5.76
12C(MsF)-D

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
Total 84.68 cu.m

13 Full Brick (230 mm) Works (1:4c/s)


Gate Column 2 0.54 0.23 1.85 0.46
2 0.30 0.23 0.45 0.06
Flag Pole Base 2 0.80 0.23 0.55 0.20
Total 0.72 cu.m

14.0 Neat Cement Skirting works


Gate Column 2 2.20 4.40
Total 4.40 r.m

15 Metal Works (Fence)


Total
Description Nos length Kg/m Total
Length
Chain Link Fence
ISA 40x40x4mm 2 317 634.00 2.40 1,521.60
ISA 50x50x5mm 128 1.90 242.82 3.80 922.72
ISA 50x50x5mm (Bracings) 29 2.00 58.00 3.80 220.40
Incinerator Vent Pipe 1 2.416 17.5 42.28 M=17.5 Kg/m
Total 2,707.00 k.g

16 Metal work (Entrance Gate)


Metal Gate
50mm Dia MS Pipe 2 7.13 14.26 3.61 51.48
25mm Dia MS Pipe 56 0.7 39.2 1.58 61.94
Middle sheet 1 0.74 0.0012 7850 6.97
Hole Fast 4 0.45 1.8 3.61 2.92
Total 123.31 k.g

19 Chain Link Fence(50x50 Mesh)


Fencing 1.00 317 1.20 380.40
Total 380.40 sq.m

17 External Plaster
Column Inside face 4 0.54 1.64 3.54
Column Outside face 2 1.2 0.20 0.48
4 0.54 1.70 3.67
Deduct -2 0.3 1.40 -0.84
Top Coping 2 2.36 0.05 0.24
4 0.59 0.30 0.71
Total 7.80 sq.m

18 Exterior Weather Coat Paint


As per Outside Plaster 1 7.8 7.80
Gate Column Skirting 2 2.36 0.10 0.47
Total 8.27 sq.m

20 Flag Pole
75 Dia GI Pipe 2.00 1 2.00
Total 2.00 nos

21 50 dia PVCweep pipe


Retaining wall 3 m height 10 1.32 13.20
Total 13.20 r.m
22 Geotextile Fabric
Retaining wall 1 m height 1 8.40 0.67 5.63

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Length Breadth
S.No Description No. Height (m) Qty. Unit Remarks
(m) (m)
Retaining wall 3 m height 1 13.52 2.27 30.69
Total 36.32 sq.m

Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant SE DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha

Description Length Breadth Height


S. No. No. Quantity Unit Remarks
(m) (m) (m)
1 Earthworks
1.1 Site Clearance & Mobilization
For Water Tank 1 4.85 4.6 22.31
Total 22.31 sq.m

1.2 Earthwork in excavation


For Water Tank 1 3.65 3.40 1.98 24.57
Total 24.57 Cu.m.

1.3 Earthback Filling


Total Earthwork Excavated 24.57
Water Tank Volume -1 3.35 3.1 1.98 -20.56
Total 4.01 Cu.m.

1.4 Boulder soling


Below Water Tank 1 3.35 3.1 0.2 2.077
Total 2.08 Cu.m.

2 Concrete Works
2.1 PCC
2.1.1 PCC Work (1:3:6)
Below Water Tank 1 3.35 3.1 0.075 0.78
Total 0.78 Cu.m.

2.2 PCC for RCC Work 1:1.5:3


For Base Slab 1 3.35 3.10 0.18 1.82
For Water Tank Wall
Long Wall 2 3.35 0.18 1.68 1.96
Short Wall 2 2.75 0.18 1.68 1.61
Trianagle Portion
Long Wall 2 3.00 0.05 Area 0.27
Short Wall 2 2.75 0.05 Area 0.25
Slab 1 3.35 3.1 0.15 1.56
Manhole openings -1 0.6 0.6 0.15 -0.05
Total 7.41 Cu.m.

2.3 Silica Admixture


10 Kg per cu.m. of R.C.C. M20 10 7.41 74.15
Total 74.15 kg

2.5 Form works


For Base Slab 1 12.9 0.18 2.26
For Water Tank Wall
Outer Side
Long Wall 2 3.35 1.83 12.23 23.18
Short Wall 2 3.00 1.83 10.95
Inside wall
Long Wall 2 3.00 1.53 9.15
Short Wall 2 2.75 1.53 8.39
Trianagle Portion

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Description Length Breadth Height
S. No. No. Quantity Unit Remarks
(m) (m) (m)
Long Wall 2 3.00 0.30 1.80
Short Wall 2 2.75 0.30 1.65
Slab 1 3 2.75 8.25
Side for Manhole openings 1 2.4 0.15 0.36
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 54.67 Sq.m.

3 PLASTERING WALL FINISHING WORKS


3.1.1 CEMENT PLASTER WORKS WITH PUNNING
Base Slab 1 2.30 2.13 4.90
For Water Tank Wall
Long Wall 2 3.05 1.37 8.36
Short Wall 2 2.78 1.37 7.62
Triangle Portion
Long Wall 2 3.00 0.42 2.54
Short Wall 2 2.78 0.42 2.36
Top Slab 1 3.00 2.75 8.25
Deduct Manhole openings -1 0.6 0.60 -0.36
Total 33.66 Sq.m.

4 Water Proof Coating


Inside Water tank 1 33.66
Total 33.66 sq.m

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Project Name : Emergency School Reconstruction Project (ESRP)
Job : Reservoir Water Tank
School Name : Shree Jhimrek Secondary School
Location : Thalajung, Gorkha
Bar Bending Schedule
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)
A Outer Vertical Bars 1
1 Shorter Span 10 33 7.01 231.33 0.62 143.42 0.083 0.083

1.915 1.915

3.02

2 Longer span 10 28 7.286 204.008 0.62 126.48


0.083 0.083

1.915 1.915

3.29

B Inner Vertical Bars 2


1 Shorter Span 10 33 2.503 165.198 0.62 102.4228 0.079 0.079

1.884 1.884

0.05
0.49 0.49

2 Longer Span 10 28 2.503 170.204 0.62 105.5265 0.079 0.079

1.884 1.884

0.05
0.49 0.49

C. Extra Bars 2 10 62 1.79 221.96 0.62 137.62 0.6 0.6

0.592
0.592 0.6 0.6

D. Horizontal Bars(outer 4
0.3 0.3
1 Shorter Span 10 20 3.62 289.6 0.62 179.552

3.02 3.02

0.3 0.3

2 Longer Span 10 20 3.87 309.6 0.62 191.952 0.3 0.3

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer
Cut Total
Dia. of No. of Wt/m Weight
S. No. Description No. Length Length Bar Shape
Bar (mm) Bars (Kg) (Kg)
(m) (m)

3.27 3.27

0.3 0.3
E. Base Slab bar 4
1 Shorter Span 10 32 3.14 401.92 0.62 249.19 3.045
0.05 0.05

2 Longer Span 10 28 3.42 383.04 0.62 237.48 3.32


0.05 0.05
1473.65 Kg
1.47 Mt.

Prepared and Submitted By: Checked By: Approved By:


Sharma-AM J/V Consultant Engineer DLPIU Engineer