Work Performed Deliverables No of days Month Remarks

The review on Preliminary Substation 2 April


Designs of the12 nos. Design
Substations- by consultants.
Only twos are officially from
TBEA. Others not properly.

GTP of Protection, SAS, Design of 5 April


SCADA, OLM. DFDR SCADA
communication system and system
test to be performed during
commissioning was sent to PD,
DPDC and Mr. Matti. for review

Review on Preliminary design Substation 3 April


Tejgaon 132/33kV SS was Design
sent to DPDC

2nd Partial Review report on Substation 3 April


Preliminary design of Tejgaon Design
132/33/11 Kv S/S by
consultant to PD, DPDC
Consultant Expert Review Comments Overhead 6 March
on O/H distribution network of DPDC Distribution
is submitted System
Design
Proposed Additional Substation 4 April
Requirements” for 120, 50, 35 Design
and 28 MVA transformers by
Mr. Matti sent DPDC officially
Revised Review GTP of Substation 3 April
132Kv,33Kv,11Kv XLPE Design
underground cable sent to PD,
DPDC

Cable GTPs are more Substation 3 April


commented by Mr. Petri and Design
conveyed to PD, DPDC for
further action
Preliminary Design of U/G 4 April
Underground Power Distribution
Distribution System Network
Reconstruction in Dhanmondi Design
Area was submitted to PD,
DPDC
Mr. Matti comments “GTPs which Substation 3 April
you have sent us are not Design
sufficiently filled by EPC
Contractor TBEA. They have to
fulfill all the technical parameters
into GTPs and then submit for
review” to DPDC
A bilateral meeting between Substation 1 April
DPDC and JV of Hifab Oy & Design
ECBL (the Consultant) was held
on April 28th, 2020 at 2.30 pm.
through video conferencing.
Agendas discussed in the meeting
were:
1. GTPs of Power Transformers,
Switchgear, Capacitor Bank etc.
and
2. Others.

Consultant Expert's Final Substation 3 May


Review Comments, Review Design
GTP of 132 KV, 33KV and
11KV AIS for approval.

Meeting online on Dhanmondi U/G 1 May


Undergroound Distribution Distribution
Network at 2:30 P.M. Network
Design
Consultant Expert's Revised Final Substation 3 May
Review Comments, Review GTP Design
of 132 KV, 33KV and 11KV AIS
for further action.
Review Report on GTP of U/G 3 May
11kV 3x400, 300, 185, 95 Distribution
mm2, and 1Kv 4×400 XLPE Network
Copper cable, RMU, Box Type Design
Transformer for Dhanmondi
Underground Distribution
Network sent to PD, DPDC.
Description of Box Type U/G 3 May
Transformer technical Distribution
specification by DTL to DPDC. Network
Design