Work Performed Deliverables No of days Month Remarks
The review on Preliminary Substation 2 April
Designs of the12 nos. Design Substations- by consultants. Only twos are officially from TBEA. Others not properly.
GTP of Protection, SAS, Design of 5 April
SCADA, OLM. DFDR SCADA communication system and system test to be performed during commissioning was sent to PD, DPDC and Mr. Matti. for review
Review on Preliminary design Substation 3 April
Tejgaon 132/33kV SS was Design sent to DPDC
2nd Partial Review report on Substation 3 April
Preliminary design of Tejgaon Design 132/33/11 Kv S/S by consultant to PD, DPDC Consultant Expert Review Comments Overhead 6 March on O/H distribution network of DPDC Distribution is submitted System Design Proposed Additional Substation 4 April Requirements” for 120, 50, 35 Design and 28 MVA transformers by Mr. Matti sent DPDC officially Revised Review GTP of Substation 3 April 132Kv,33Kv,11Kv XLPE Design underground cable sent to PD, DPDC
Cable GTPs are more Substation 3 April
commented by Mr. Petri and Design conveyed to PD, DPDC for further action Preliminary Design of U/G 4 April Underground Power Distribution Distribution System Network Reconstruction in Dhanmondi Design Area was submitted to PD, DPDC Mr. Matti comments “GTPs which Substation 3 April you have sent us are not Design sufficiently filled by EPC Contractor TBEA. They have to fulfill all the technical parameters into GTPs and then submit for review” to DPDC A bilateral meeting between Substation 1 April DPDC and JV of Hifab Oy & Design ECBL (the Consultant) was held on April 28th, 2020 at 2.30 pm. through video conferencing. Agendas discussed in the meeting were: 1. GTPs of Power Transformers, Switchgear, Capacitor Bank etc. and 2. Others.
Consultant Expert's Final Substation 3 May
Review Comments, Review Design GTP of 132 KV, 33KV and 11KV AIS for approval.
Meeting online on Dhanmondi U/G 1 May
Undergroound Distribution Distribution Network at 2:30 P.M. Network Design Consultant Expert's Revised Final Substation 3 May Review Comments, Review GTP Design of 132 KV, 33KV and 11KV AIS for further action. Review Report on GTP of U/G 3 May 11kV 3x400, 300, 185, 95 Distribution mm2, and 1Kv 4×400 XLPE Network Copper cable, RMU, Box Type Design Transformer for Dhanmondi Underground Distribution Network sent to PD, DPDC. Description of Box Type U/G 3 May Transformer technical Distribution specification by DTL to DPDC. Network Design