Waktu Pelaksanaan

Periode
No Description Skor (%) Aug Sep Okt KETERANGAN
%
IV I II III IV I II III IV
II III IV V VI VII VIII IX X
1 Material Preparation 10 2.5 2.5 2.5 2.5 100
2 Machine placement 4 4
3 Pilot hole drilling 14" 4 4
4 Pipe installation 10" (antikolep) 5 2.5 2.5 80
5 Pilot hole drilling 6" 6 6
6 Logging test 5 2.5 2.5
7 Reaming 9" 5 5
8 Cassing pipe installation 6" + screening 8 1.6 6.4 60
9 Cleaning wells with jetting 4 4
10 Gravel charging 5 5
11 Flushing well 4 4 40
12 Bore hole camera 5 5
13 Submersible pump & suction pipe installation 8 8
14 Panel control installation 4 4
15 Pumping Test 8 5.3 2.7 20
16 Water analysis 5 4.3 0.7
17 SIPA 5 1.67 1.67 1.67
18 Distibution pipe installation 5 0.4 2.5 2.1 0
Progres % 100 13 13.5 11.6 18.3 28.8 9.1 2.37 1.67 1.67
Rencana
Kumulatif % - 13 26.5 38.1 56.4 85.2 94.3 96.67 98.34 100
Progres % -
Realisasi
Kumulatif % -
Waktu Pelaksanaan
Periode
KETERANGAN
No Description Skor (%) Aug Sep Okt
%
IV I II III IV I II III IV
I II III IV V VI VII VIII IX
1 Material Preparation 10 0.1 100
2 Machine placement 4 1
3 Pilot hole drilling 14" 4
4 Pipe installation 10" (antikolep) 5 80
5 Pilot hole drilling 6" 6
6 Logging test 5
7 Reaming 9" 5
8 Cassing pipe installation 6" + screening 8 60
9 Cleaning wells with jetting 4
10 Gravel charging 5
11 Flushing well 4 40
12 Bore hole camera 5
13 Submersible pump & suction pipe installation 8
14 Panel control installation 4
15 Pumping Test 8 20
16 Water analysis 5
17 SIPA 5
18 Distibution pipe installation 5 0
Progres % 100 13 13.5 11.6 18.3 28.8 9.1 2.37 1.67 1.67
Rencana
Kumulatif % - 13 26.5 38.1 56.4 85.2 94.3 96.67 98.34 100
Progres % - 1.1
Realisasi
Kumulatif % - 1.1
Devisiasi Kumulatif % - 11.9