ID TaskTask Name Duration Start Finish Predecessors

Resource SUB system Comments Cost % Complete


Mode Names 01 March 01 April 01 May 01 June 01 July 01 August 01 September01 October
25/0308/0422/0406/0520/0503/0617/0601/0715/0729/0712/0826/0809/0923/0907/1021/10
1 START UP NAPHTHA PLANT RIO LORO 88 days Wed 01/05/19 Fri 30/08/19 US$108,100.00 91%
2 GENERAL ACTIVITIES 74 days Wed 01/05/19 Mon 12/08/19 HSE RL;Integrity;Metalpar;OFM
General Fac;OFM US$59,500.00
Ope 97%
3 Define scope to start up Naphtha plant 4 days Wed 01/05/19 Mon 06/05/19 OFM Fac General Review in field theUS$1,000.00
scope to start up 100% OFM Fac
4 Integrity test to lines and tanks 30 days Tue 07/05/19 Mon 17/06/19 3 Integrity General REALIZAR PRUEBAUS$1,500.00
DE INTEGRIDAD DE LA100% Integrity
LINEA DE DESCARGA A LOS TANQUES Y AL SISTEMA DE MEZCLA
5 Mechanical works to repair findings for integrity 20 days Tue 18/06/19 Mon 15/07/19 4 Metalpar General US$25,000.00 100% Metalpar
6 Ask for quotes to comply scope to start up Naphtha plant 14 days Mon 13/05/19 Thu 30/05/19 3 OFM Fac General Ask and US$0.00 100% OFM Fac
receive
7 Issue service request for works to start up Naphtha plant 2 days Fri 31/05/19 Mon 03/06/19 6 OFM Fac General quotes
preparetoSR US$0.00 100% OFM Fac
and issue it
8 Socialize electromechanical works and hire personnel to do 8 days Tue 04/06/19 Thu 13/06/19 7 Metalpar General to
Hiring local US$0.00 100% Metalpar
works personnel
9 Start up of the control system from Control room and locally 12 days Fri 31/05/19 Mon 17/06/19 6 OFM Fac General VERIFICAR US$5,000.00 95% OFM Fac
FUNCIONAMIENTO
10 Maintenance and calibration of instrumentation 15 days Tue 02/07/19 Mon 22/07/19 8 OFM Ope General DE SEÑALES
( TI,PI,TIT,PIT,LIT, FIT) 95% (PSV ,PVV), PLC Y Supervision desdeOFM
Y SISTEMAS DE SEGURIDAD
US$8,000.00 OpeDE CONTROL.
CUARTO
11 Control loops Naphtha plant control system 10 days Tue 23/07/19 Mon 05/08/19 9;10 OFM Fac General Pruebas de lazo desde cada instrumento hasta
US$4,000.00 OFM Fac
90% PLC, REALIZAR PROCEDIMIENTOS DE OPERACIÓN,FILOSOFIA INSTRUMENT
12 Signaling installation in process zone 18 days Fri 14/06/19 Tue 09/07/19 8 OFM Fac General INSTALACION DE SEÑALIZACION
US$5,000.00 (NO CELULAR OFM Fac
95% AREAS DE PROCESO ZONA DE DESCARGUE , LINEAS DE FLUJO ETC) ZONA D
13 Contigence equipments inspection, like fire extingishers, 4 days Fri 31/05/19 Wed 05/06/19 6 HSE RL General VERIFICAR US$8,000.00 90% HSE RL
fighting suits EQUIPOS (SE
14 Development Procedures and operative manuals 10 days Tue 30/07/19 Mon 12/08/19 44SS OFM Fac General REALIZAN
ELABORACION Y ACTUALIZACION
US$0.00 LOS PROCEDIMIENTOS
95% PARA LA PLANTA OFM Fac
15 To do a What IF to the design 5 days Tue 18/06/19 Mon 24/06/19 9 OFM Fac General Evaluate the risk level of the plant
US$2,000.00 100% OFM Fac
16 ACTIVITIES IN LOADING BAY 45 days Tue 04/06/19 Mon 05/08/19 Metalpar;OFMLoading
Fac;OFM bay
Ope US$9,500.00 99%
17 Test continuity, status and quality of grounding system in 1 day Fri 14/06/19 Fri 14/06/19 8 OFM Ope Loading bay Test the US$100.00 100% OFM Ope
loading bay grounding
18 Maintenance of structure like paint 3 days Mon 17/06/19 Wed 19/06/19 17 Metalpar Loading bay system
Paint forinmaintenance of civil structure of
US$500.00 loading bay
100% Metalpar
19 Change of chains for support of platforms in loading bay 2 days Thu 20/06/19 Fri 21/06/19 18 Metalpar Loading bay The chains US$400.00 100% Metalpar
used to
20 Buy and Install slide cars for both life line of bays 45 days Tue 04/06/19 Mon 05/08/19 6 OFM Fac;PSCMLoading bay support
The slide cars for support of harness system
US$3,000.00 100% OFM Fac;PSCM
are in our storage house, and must be installed
21 Install grounding indicator switches for both bays 1 day Mon 17/06/19 Mon 17/06/19 17 Metalpar Loading bay The grounding switches were acquired in
US$500.00 100% Metalpar
2015 and shall be re located, because actually are used in others loading bays
22 To buy and Install unloading hoses for Naphtha and for cooling 45 days Tue 04/06/19 Mon 05/08/19 6 OFM Loading bay It is needed US$2,500.00 100% OFM Fac;PSCM
water Fac;PSCM 4 hoses to
23 Turn and install again suction filter of loading pumps actually 2 days Mon 17/06/19 Tue 18/06/19 8;17 Metalpar Loading bay unloading
The actual of US$300.00 100% Metalpar
in wrong direction suction
24 Install PIT in suction of loading pumps 5 days
Wed 19/06/19 Tue 25/06/19 23 Metalpar Loading bay basket type
The PIT's are in storage house
US$100.00 100% Metalpar
25 Install PSVs in discharge of loading pumps 3 days Tue 23/07/19 Thu 25/07/19 24;10Metalpar Loading bay The PSV's are in storage house
US$100.00 100% Metalpar
26 To buy brake arrester of vertical life lines of two tanks 45 days Tue 04/06/19 Mon 05/08/19 6 OFM Loading bay Remain two US$1,500.00 100% OFM Fac;PSCM
Fac;PSCM brakes for
27 Install and connect naphtha loading pumps which is in Capella 10 days Tue 23/07/19 Mon 05/08/19 10 Metalpar Loading bay life
Thelines of
actual US$500.00 100% Metalpar
R. pump which
28 ACTIVITIES FOR COOLING WATER SYSTEM 45 days Fri 31/05/19 Thu 01/08/19 Metalpar;OFMCooling
Fac;OFM is in Capella
System
Ope US$23,500.00 77%

Task Project Summary Manual Task Start-only Deadline

Project: Naphtha plan start up r Split Inactive Task Duration-only Finish-only Progress

Date: Tue 20/08/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID TaskTask Name Duration Start Finish Predecessors
Resource SUB system Comments Cost % Complete
Mode Names 01 March 01 April 01 May 01 June 01 July 01 August 01 September01 October
25/0308/0422/0406/0520/0503/0617/0601/0715/0729/0712/0826/0809/0923/0907/1021/10
29 Inspection and maintenance of Cooling system (Chiller) 40 days Fri 31/05/19 Thu 25/07/19 6 OFM Cooling CHILLER,BOMBAS US$5,000.00 30% OFM Fac;PSCM
Fac;PSCM System DE AGUA DE
30 Install mesh (chiller evaporator) 20 days Wed 19/06/19 Tue 16/07/19 8;23 Metalpar INFRIAMIENTO,
Cooling System
Protect chiller evaporator from bugs and100%
US$2,000.00 people Metalpar
31 Buy and Installation of globe valves and check valves at outlet 20 days Fri 14/06/19 Thu 11/07/19 8 OFM Cooling To balance US$5,500.00 100% OFM Fac;PSCM
return pipe of each tank Fac;PSCM System pressure and
32 Buy and Installation of manometers and termometers at 35 days Fri 14/06/19 Thu 01/08/19 8 OFM Cooling temperature
To balance US$8,000.00 100% OFM Fac;PSCM
outlet return pipe of each tank Fac;PSCM System pressure and
33 Installation of thredolet in cooling water outlet from each tank 8 days Wed 26/06/19 Fri 05/07/19 24 Metalpar Cooling temperature
For US$3,000.00 100% Metalpar
for instruments System additional TI
34 ACTIVITIES IN TANKS 84 days Tue 07/05/19 Fri 30/08/19 PI at the
Metalpar;OFM Fac, PSCM;OFM Ope US$10,100.00 87%
35 Relocate and install 2 walkways over pipe racks 5 days Mon 08/07/19 Fri 12/07/19 33 Metalpar Tanks The walkways were US$100.00
removed 100% Metalpar
36 Installation of TI for tanks 5 days Mon 08/07/19 Fri 12/07/19 33 OFM Ope Tanks Already US$100.00 95% OFM Ope
installed
37 Buy and Installation of one PVV 6" #150 FF 1.5onz/0.5 Oz 84 days Tue 07/05/19 Fri 30/08/19 3 OFM Tanks thermo well
This valve US$8,000.00 85% OFM Fac;PSCM
Enardo 550 (include flame arrester) on top header over tanks Fac;PSCM works in
parallel of
38 Analisys of water conditions in actual water tanks 2 days Fri 31/05/19 Mon 03/06/19 6 OFM Ope Tanks To review US$1,500.00 100% OFM Ope
status of
39 Install hatches for level metering on top of each tank 4 days Tue 04/06/19 Fri 07/06/19 38 OFM Ope Tanks The US$400.00 100% OFM Ope
hatches are
40 ACTIVITIES IN TRANSFER NAPHTHA LINE 10 days Mon 08/07/19 Fri 19/07/19 Metalpar Transfer to blend US$1,500.00 100%
41 Install and connect naphtha transfer pump which is in Storage 10 days Mon 08/07/19 Fri 19/07/19 33 Metalpar Transfer to The pump is US$1,500.00 100% Metalpar
house Rio Loro blend new and
42 ACTIVITIES OF PRE AND COMMISSIONING 20 days Mon 22/07/19 Fri 16/08/19 Metalpar;OFM Fac available in US$4,000.00 80%
43 Hydrotest for all lines 6 days Mon 22/07/19 Mon 29/07/19 41;33;5
Metalpar General Test of all lines US$1,500.00 100% Metalpar
44 Commissioning of plant 12 days Tue 30/07/19 Wed 14/08/19 43 OFM Fac General US$1,000.00 85% OFM Fac
45 Trainning for operators 5 days Mon 12/08/19 Fri 16/08/19 44FS-3OFM
daysFac General US$1,500.00 60% OFM Fac
46 US$0.00 0%

Task Project Summary Manual Task Start-only Deadline

Project: Naphtha plan start up r Split Inactive Task Duration-only Finish-only Progress

Date: Tue 20/08/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2