Project: Naphtha plan start up r Split Inactive Task Duration-only Finish-only Progress
Date: Tue 20/08/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 1
ID TaskTask Name Duration Start Finish Predecessors
Resource SUB system Comments Cost % Complete
Mode Names 01 March 01 April 01 May 01 June 01 July 01 August 01 September01 October
25/0308/0422/0406/0520/0503/0617/0601/0715/0729/0712/0826/0809/0923/0907/1021/10
29 Inspection and maintenance of Cooling system (Chiller) 40 days Fri 31/05/19 Thu 25/07/19 6 OFM Cooling CHILLER,BOMBAS US$5,000.00 30% OFM Fac;PSCM
Fac;PSCM System DE AGUA DE
30 Install mesh (chiller evaporator) 20 days Wed 19/06/19 Tue 16/07/19 8;23 Metalpar INFRIAMIENTO,
Cooling System
Protect chiller evaporator from bugs and100%
US$2,000.00 people Metalpar
31 Buy and Installation of globe valves and check valves at outlet 20 days Fri 14/06/19 Thu 11/07/19 8 OFM Cooling To balance US$5,500.00 100% OFM Fac;PSCM
return pipe of each tank Fac;PSCM System pressure and
32 Buy and Installation of manometers and termometers at 35 days Fri 14/06/19 Thu 01/08/19 8 OFM Cooling temperature
To balance US$8,000.00 100% OFM Fac;PSCM
outlet return pipe of each tank Fac;PSCM System pressure and
33 Installation of thredolet in cooling water outlet from each tank 8 days Wed 26/06/19 Fri 05/07/19 24 Metalpar Cooling temperature
For US$3,000.00 100% Metalpar
for instruments System additional TI
34 ACTIVITIES IN TANKS 84 days Tue 07/05/19 Fri 30/08/19 PI at the
Metalpar;OFM Fac, PSCM;OFM Ope US$10,100.00 87%
35 Relocate and install 2 walkways over pipe racks 5 days Mon 08/07/19 Fri 12/07/19 33 Metalpar Tanks The walkways were US$100.00
removed 100% Metalpar
36 Installation of TI for tanks 5 days Mon 08/07/19 Fri 12/07/19 33 OFM Ope Tanks Already US$100.00 95% OFM Ope
installed
37 Buy and Installation of one PVV 6" #150 FF 1.5onz/0.5 Oz 84 days Tue 07/05/19 Fri 30/08/19 3 OFM Tanks thermo well
This valve US$8,000.00 85% OFM Fac;PSCM
Enardo 550 (include flame arrester) on top header over tanks Fac;PSCM works in
parallel of
38 Analisys of water conditions in actual water tanks 2 days Fri 31/05/19 Mon 03/06/19 6 OFM Ope Tanks To review US$1,500.00 100% OFM Ope
status of
39 Install hatches for level metering on top of each tank 4 days Tue 04/06/19 Fri 07/06/19 38 OFM Ope Tanks The US$400.00 100% OFM Ope
hatches are
40 ACTIVITIES IN TRANSFER NAPHTHA LINE 10 days Mon 08/07/19 Fri 19/07/19 Metalpar Transfer to blend US$1,500.00 100%
41 Install and connect naphtha transfer pump which is in Storage 10 days Mon 08/07/19 Fri 19/07/19 33 Metalpar Transfer to The pump is US$1,500.00 100% Metalpar
house Rio Loro blend new and
42 ACTIVITIES OF PRE AND COMMISSIONING 20 days Mon 22/07/19 Fri 16/08/19 Metalpar;OFM Fac available in US$4,000.00 80%
43 Hydrotest for all lines 6 days Mon 22/07/19 Mon 29/07/19 41;33;5
Metalpar General Test of all lines US$1,500.00 100% Metalpar
44 Commissioning of plant 12 days Tue 30/07/19 Wed 14/08/19 43 OFM Fac General US$1,000.00 85% OFM Fac
45 Trainning for operators 5 days Mon 12/08/19 Fri 16/08/19 44FS-3OFM
daysFac General US$1,500.00 60% OFM Fac
46 US$0.00 0%
Project: Naphtha plan start up r Split Inactive Task Duration-only Finish-only Progress
Date: Tue 20/08/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 2