: D19-07
Project Name : GAS Dev. FOR THE Project JTB Field.
PROJECT SCHEDULE FOR PRE- P.O. Delivery Date: June 15, 2020
PO. NO. : JTB-RJJ000-M0-XEP-900-00134 SCRUBBER ( 2 SETS ) Del. Condition : Ex-Work DIHI-Shop- Cilegon Banten.
3 Preparation
100%
Strength
6 Preparation
100%
Drawing
Detail
100%
10 Submission 100% 12/7 12/23
100%
11 Return and Approval 100% 12/24 1/8
100%
12 Preparation 100% 7/10 9/17
procedure
100%
Work
WPS
100%
for
100%
19 Receiving material 100% 2/20
100%
20 Purchase Order issued 100% 7/20
100%
Material for
100% 3/9
Nozzles
100%
Gasket/
100%
28 Receiving material 100% 1/7
100%
29 Purchase Order issued 100% 11/5
bolts
100%
30 Receiving material 100%
100% 2/20
31 Fabrication of Template for Air Receiver ( 241-D9018) 100% 9/15
100%
32 Marking / Cutting plate 100% 9/1
100%
33 Fabrication 100% 10/5
100%
34 Inspection 100% 10/5
100%
33 Painting & Packing 100% 10/9
100%
34 Ready for delivery 100% 10/10
100%
35 pre- Inspection Meeting 100% 2/21
100%
36 Overall Fabrication progress 28%
28%
28%
37 Fabrication of 232-T1002 ( PRE-SCRUBBER ) - RECOVERY SCHEDULE 2/22 6/15
28%
28%
55 Fabrication of 232-T2001 ( PRE-SCRUBBER )-RECOVERY SCHEDULE 2/22 6/15
28%
PLANNING ( %) 79,4%
ACTUAL ( %) 79,0%
DEVIATION ( %)/ (-) Delay / =( ) on schedule/ A-head -0,5% 19-May
Customer : PT. REAKAYASA INDUSTRI
Project Name : GAS Dev. FOR THE Project JTB Field.
PO. NO. : JTB-RJJ000-M0-XEP-900-00134 PROJECT SCHEDULE FOR PRE-SCRUBBER ( 2 SETS )
:Old Scheduled :Actual (Finished) :Overall :New-Scheduled :Old Scheduled :Actual (Finished) :Overall :New-Scheduled :Old Scheduled :Actual (Finished) :Overall :New-Scheduled :Old Scheduled :Actual (Finished) :Overall :New-Scheduled
DATE Mar-20 Apr-20 May-20 Jun-20 Jul-20
RECOVERY SCHEDULE
PROGRESS 1 6 10 14 18 22 26 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
PLAN ACTUAL
DESCRIPTION WORK
(%) (%)
12 Finishing
14 Hydrotest
12 Finishing
14 Hydrotest