Site activities and Implementation

SITE ACTIVITIES
1.Ornamental Plants & Cutting Tree
2. Sludge Disposal of Bored Pile Work
7. Ornament Plants and Median Plants

• Stage 1st on 27th October 2023 is complete,


• Stage 2nd on 27th November 2023 is complete
• Stage 3th on 31th October 2023 is complete and already Handed over to
D i s Ta m H u t

• There are no activities for Ornament plants and Median Plants 14 January 2024
8. Sludge Disposal of Bored Pile Work

P r o g r e s s o f Vo l u m e B o r e P i l e W o r k ( m 3) - Z o n e 1 B P 1 - P 9 B

3
Sludge disposal volume (m ) per day ( Update 14/1/24 )
Volume until December January
Work Item Total
December 23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Volume
Bore Pile 2,409.57 50.51 67.34 80.53 85.50 115.15 104.22 115.52 49.92 50.14 143.56 108.36 3,380.32
3
Work (m )
1. Bored Pile Work ZONE 1
Monitoring Bored Pile Work :1st Equipment

BORED PILE Update : 1st Equipments 14-Jan


ITEM TANGGAL RENCANA Durasi Total Dec-23 Jan-24
N0. TOTAL (M)
PEKERJAAN START END (Hari) Borepile 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Cluster 2
Plan
1 P3B 01/01/24 09/01/24 9 9 Actual 0%
Borepile
Plan
2 P4B 08/01/24 13/01/24 6 4 Actual 1 25%
Borepile
Plan
3 P5B 07/12/23 09/12/23 3 4 Actual 1 1 1 1 100%
Borepile 2 1 4 3
Plan
4 P6B 07/12/23 09/12/23 3 4 Actual 1 1 1 1 100%
Borepile 2 1 4 3
Plan
5 P7B 11/12/23 13/12/23 3 4 Actual 1 1 1 1 100%
Borepile 2 1 4 3
Plan
6 P8B 11/12/23 13/12/23 3 4 Actual 1 1 1 1 100%
Borepile 2 3 1 4
Plan
7 P9B 18/12/23 19/12/23 2 9 Actual 1 2 1 1 1 1 1 1 100%
Borepile 5 9;1 7 3 8 2 6 4
* Program by WNL-KSO 75,0%