Documentation Screen Designing

3 24 days 5 30 days
09/24/12 10/20/12 10/01/12 11/01/12
Data Gathering Review Data
2 12 Days 4 6 Days
09/17/12 09/29/12 10/15/12 10/20/12
Testing and
Revision and Final Implementation
8 150 Days 7 8 Days
10/15/12 03/14/13 03/14/13 03/21/13
Initial Planning Programming and
Presentation Debugging
1 6 Days 6 115 Days
09/17/12 09/22/12 9 1 Day
11/19/12 03/13/13
03/14/13 03/14/13

Gantt Chart

Sept. Oct. Nov. Dec. Jan. Feb. March


3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1. Initial
Planning
2. Data
Gathering
3. Review
Data
4. Documentati
on
5. Screen
Designing
6. Programming
and
Debugging
7. Testing and
Implementati
on
8. Revision
and Final
9. Presentation

LEGEND :
CRITICAL
NON-CRITICAL