TIME FRAME PEK

Progress Pekerjaan Dec-21


No TIME FRAME
18 19 20 21 22 23 24 25 26
D208
1 Unloading Dozer 1
100% 1
2 Clean and Repainting 1 1 1 1 1 1 1 1
47% 1 1 1 1 1 1 1
3 General Service
0%
4 Repair Engine part
33%
5 Install rotary, Back Alarm , repair AC
0%
6 Install fire suppresion
0%
7 Reseal 2x Blade Cylinder
0%
8 Reseal 2x Track adjuster
0%
9 final check
0%
Total Progress 20%
D210
1 Unloading Dozer 1
100% 1
2 Clean and Repainting
75% 1 1 1
3 General Service
0%
4 Repair Engine part
0%
5 Install rotary, Back Alarm , repair AC
0%
6 Install fire suppresion
0%
7 Reseal 2x Blade Cylinder
0%
8 Reseal 2x Track adjuster
0%
9 final check
0%
Total Progress 19%
FRAME PEKERJAAN PERBAIKAN DOZER
Dec-21 Jan-21
27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1
1 1 1
1 1 1

1 1 1

1 1

1 1 1

1 1 1 1 1 1 1
1 1 1
20 21 22 23 24 25 26 27 28 29 30

1 1 1

1 1 1

1 1 1

1 1

1 1 1

1
PICA PERBAIKAN DOZER
No Problem
Pengecetan yang terlalu lama
1

2 Pengerjaan perbaikan engine yang lama

3 Instalasi rotary, Loto, Ac


4 Instalasi fire suppresion
PICA PERBAIKAN DOZER
Corrective Action Due Date
1. Penambahan Terpal agar tidak kena hujan 28-Dec-21
2. Opsi untuk peminjaman compresor angin agar pengecetan pakai sprayer 30-Dec-21
3. Penambahan 1 Mekanik,2 helper untuk melakukan pengecetan 2 dozer 4-Jan-22
1. Pembelian Tool pendukung 30-Dec-21
2. Percepatan kedatangan spare part 1-Jan-22
3. Penambahan 1 mekanik, 2 helper untuk melakukan perbaikan 2 dozer 5-Jan-22
4. Penambahan 1 welder 5-Jan-22
1. Penambahan senior electric untuk percepatan pengerjaan electric 5-Jan-22
1. percepatan persetujuan PO untuk pengerjaan fire suppression 5-Jan-22
PIC Status
Afif Close
Wawan On Progress
Wawan/Ovi On Progress
Afif Close
HO Purchasing On Progress
HO recruitment On Progress
HO recruitment On Progress
HO recruitment On Progress
HO Purchasing On Progress