PROJECT : Renovation of Building - KPS San Luis

LOCATION : San Luis, Batangas

ITEM DESCRIPTION ITEM COST Duration


Day 1 Day 2 Day 3 Day 4 Day 5
I. Preliminaries 97,000.00
A Mobilization 1 1
B Cleaning, Hauling and Clearing 3
II. Dismantling / Demolition works 38,000.00 0
A Demolition of Existing Electrical 3 1 1 1
B Demolition of Existing Mezzanine 2 1 1
III. Installation of Cable tray & lighting Structured Support 197,950.00 20 1 1
IV. Installation of Electrical Wiring and Lighting Structed Support 179,700.00
A Cable Pulling 22
B Tapping of Wires 21
C Installation 21
D Testing 9
V. Installation of Feeder 78,000.00 3
VI. Installation of Water Duct Grating 68,300.00 5
VII. Installation of Mezanine Floor Flooring 42,000.00 10
VIII. Plumbing: Domestic Water 32,900.00 3
Total Labor Cost 733,850.00
Contractor's Profit (10%) 73,385.00
Contingencies (5%) 36,692.50
843,927.50 Total Project Cost
DURATION
Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18 Day 19
`

1 1 1 1 1 1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1

1
1 1 1 1 1 1 1 1 1 1
1 1 1
Day 20 Day 21 Day 22 Day 23 Day 24 Day 25 Day 26 Day 27 Day 28 Day 29 Day 30

1 1 1

1 1 1 1

1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1
1 1 1
1 1 1 1