Project Name:-A068-City University College

Monthly Supervision fees calculations With Detail Breakdown.

Substantial % percentage of Period


completion / deployment in a Total Contract
Sub Structure + Fit out work + External work + amount
completion months
S.N. Professionals Monthly Salary Super Structure MEP Services (supervision)
certificate /
Handing over
Months Total Month
10 6 1 1 18

Project Manager/Residence
1 50% 50% 50% 50% 50% -
Engineer

2 Civil Engineer-Structure 100% 50% 100% 50% 81% -

3 Senior Architectural Engineer 25% 100% 25% 25% 50% -

4 Senior Mechanical Engineer 25% 100% 50% 100% 56% -

4 Senior Electrical Engineer 25% 100% 50% 100% 56% -

5 QA/QC 25% 33% 33% 50% 30% -

6 Quantity Surveyor 25% 25% 25% 50% 26% -

7 Planning Engineer 20% 20% 20% 10% 19% -

8 Safety manager 100% 100% 100% 100% 100% -

9 Document Control 100% 100% 100% 100% 100% -

Total Amount (Monthly) ( QAR) -

Total Amount for 18 month (QAR) -