Consultancy Services for Preparation of Feasibility Study & Detailed Project Report For 4/6 Laning of Karnataka

EIA – EMP Report


Border-Kannur Section of NH-17Approx. length 132.8 km (Package No. NHDP-III/DL5/12)) In the Kerala State
Final Detailed Project Report
under NHDP Phase III Programme

Table 8.5: Environmental Monitoring Plan for Project Road


Environmental Project Duration /
Parameter Standards Locations Implementation Supervision
Component Stage Frequency
Air Construction SPM, National Wherever the contractor decides to Continuous 24- Contractor PIU,
Phase RSPM, SO2, Ambient locate the Hot Mix Plant hourly, twice a through a Supervision
NOx and CO Quality week once during approved Consultant
Standards Construction monitoring
Phase agency
SPM, RSPM National Stretch of the road where Continuous 24- Contractor PIU,
Ambient construction in progress site hourly, twice a through a Supervision
Quality preferably at Tapapadi (Km 17.500), week once in approved Consultant
Standards Upalla town (Km 29.000), Shiriaya month during monitoring
(Km 35.000), Mogral (km 41.500), Construction agency
Kasaegod (km 49.800), Thekkil (km Phase
61.500), Poinachi (km 65.000),
Kanahangod Hospital (km 85.000),
Neeleshawaram (km 93.000),
Payannur (km 114.600), Pariyaram
(km 123.000) and Velapattanam (km
149.000)
Operation SPM, National At Tapapadi (Km 17.500), Upalla Continuous 24- PIU, NHAI NHAI
Phase RSPM, SO2, Ambient town (Km 29.000), Shiriaya (Km hourly, twice a
NOx, CO, Quality 35.000), Mogral (km 41.500), week six months
Standards Kasaegod (km 49.800), Thekkil (km for 2 years
61.500), Poinachi (km 65.000),
Kanahangod Hospital (km 85.000),
Pariyaram (km 123.000) and
Velapattanam (km 149.000)
Ground Water Construction pH, TDS, As water At Tapapadi (Km 17.500), Upalla Once in six month Contractor PIU,
Quality Stage TSS, Oil & quality town (Km 29.000), Shiriaya (Km during the through a Supervision
Grease and standards 35.000), Mogral (km 41.500), Construction approved Consultant
other (IS 10500) Kasaegod (km 49.800), Thekkil (km Phase monitoring
parameters 61.500), Poinachi (km 65.000), agency
as per IS Pariyaram (km 123.000) and
10500 Velapattanam (km 149.000) and
near construction sites

Feedback Ventures Pvt. Ltd. 152 National Highways Authority of India


Consultancy Services for Preparation of Feasibility Study & Detailed Project Report For 4/6 Laning of Karnataka
EIA – EMP Report
Border-Kannur Section of NH-17Approx. length 132.8 km (Package No. NHDP-III/DL5/12)) In the Kerala State
Final Detailed Project Report
under NHDP Phase III Programme

Environmental Project Duration /


Parameter Standards Locations Implementation Supervision
Component Stage Frequency
Operation pH, TDS, As Water At Tapapadi (Km 17.500), Upalla End of summer PIU, NHAI NHAI
Phase TSS, Oil & quality town (Km 29.000), Shiriaya (Km before the onset
Grease and standards 35.000), Mogral (km 41.500), on monsoon
other (IS 10500) Kasaegod (km 49.800), Thekkil (km every year for 2
parameters 61.500), Poinachi (km 65.000), years
as per IS Pariyaram (km 123.000) and
10500 Velapattanam (km 149.000)
Surface Water Construction turbidity, As Water Up stream and down stream of During Contractor PIU,
Quality Stage TSS, Oil & quality Shiriya river (Km 36.100), Nileshwar Construction through a Supervision
Grease standards River (Km 93.200), Tejaswini River phase at the time approved Consultant,
(IS 10500) (Km 96.750), Perumba River (Km of construction monitoring NHAI
115.400), Waingiri River (Km once in month agency
131.500), Kuttikol River (Km
137.700), Vellapatanam River (Km
147.100)
Noise Levels Construction Noise Level As per Stretch of the road where One day hourly Contractor PIU,
Phase in dB (A) National construction in progress site measurement, through a Supervision
Noise preferably at Tapapadi (Km 17.500), once in months approved Consultant,
standards Upalla town (Km 29.000), Shiriaya once during the monitoring NHAI
(Km 35.000), Mogral (km 41.500), Construction agency
Kasaegod (km 49.800), Thekkil (km Phase and active
61.500), Poinachi (km 65.000), construction sites
Kanahangod Hospital (km 85.000),
Neeleshawaram (km 93.000),
Payannur (km 114.600), Pariyaram
(km 123.000) and Velapattanam (km
149.000)
Operation Noise Level As per At Tapapadi (Km 17.500), Upalla One day hourly PIU, NHAI PIU,
Phase in dB (A) National town (Km 29.000), Shiriaya (Km measurement in Supervision
Noise 35.000), Mogral (km 41.500), three months Consultant
standards Kasaegod (km 49.800), Thekkil (km
61.500), Poinachi (km 65.000),
Kanahangod Hospital (km 85.000),
Pariyaram (km 123.000) and
Velapattanam (km 149.000)

Feedback Ventures Pvt. Ltd. 153 National Highways Authority of India


Consultancy Services for Preparation of Feasibility Study & Detailed Project Report For 4/6 Laning of Karnataka
EIA – EMP Report
Border-Kannur Section of NH-17Approx. length 132.8 km (Package No. NHDP-III/DL5/12)) In the Kerala State
Final Detailed Project Report
under NHDP Phase III Programme

Environmental Project Duration /


Parameter Standards Locations Implementation Supervision
Component Stage Frequency
Soil Erosion Construction Soil erosion -- On slops and high embankment After precipitation PIU, NHAI PIU,
Phase Supervision
Consultant
Operation Soil erosion -- On slops and high embankment After precipitation PIU, NHAI PIU,
Phase
Road Side Construction Monitoring As laid out in Entire stretch of project road During felling of Forest Dept. PIU, NHAI
Plantation Phase of trees the detailed trees
felling design for
project
Operation Survival rate The survival Entire stretch of project road Every year for 3 NHAI, Forest NHAI
Phase of trees rate should years Dept.
success of be at least
re-plantation 70% below
which re-
plantation
shall be
done.