NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

Client: QATARGAS

LOSS PREVENTION & TECHNICAL HSE

1
Doha, 05 Jul 2022 Saipem. Engineering Energy
Saipem Classification - General Use
NFPS PROJECT
Meeting Agenda
Description
• Safety Moment

• Recap of last weekly meeting/open points

• Status update: Activities/deliverables ongoing & submitted - Loss prevention

• Status update: Activities/deliverables ongoing & submitted -Technical HSE

• Status Update: Action tracking Status update

• Focus areas & Criticalities

• AOB

Saipem Classification - General Use


Safety Moment

Saipem Classification - General Use


NFPS PROJECT
Line of fire: Pinched finger between door and frame

Saipem Classification - General Use


NFPS PROJECT
Field Schematic

28” CRA PL12S (5.7km) 28” CRA PL13S (10.4km) 28” CRA PL14S (7.8km) 28” CRA PL10S (6.8km) 28” CRA PL12N (11.6km)
28” CRA PL10LS (6.8km)

Awarded under
separate contract
6.6 kV SC12S (3.2km)

11 kV SC13S (19.7km)
6.6 kV SC13S (13.2km)
28” PL10 decom.

6.6 kV SC14S (21.2km)


28” CRA PL11S (6.5km)
28” CRA PL11LS (6.5km)

Removed from SoW (TB043) 28” PL11 decom.

38” CS PL610L (97.9+5.1 km)


32" PL1L (91.4+6.3 km) (Spools+onshore sect. CRA)
32" PL1NL (79.2+1.6 km)

Saipem Classification - General Use


NFPS PROJECT
Recap of Last weekly meeting- Actions/updates
 EPCOL-M-SPM-QG-00729_2022-07-29

Saipem Classification - General Use


NFPS PROJECT
Status update: Activities/deliverables submitted
LOSS PREVENTION
Documents issued last week
IFR:
• Helideck Wind Turbulence and Temperature Rise Study Report for RP11S
• Explosion Risk Assessment Report for RT-2 – Re-IFR
• RAM Analysis Report for RP4N – Re-IFR

IFA:
• Noise Study Report for RP8S
• Noise Study Report for RP11S
• Noise Study Report for RT-2
• Dropped Object Study Report for RP11S
• Fire and Gas Detection Layout for RP8S
• Onshore Plant North Firefighting & Safety equipment layout plans (Slug catcher #1)

AFC WITHHOLD:

• CAP 437 and Helideck Design ReportS for WHP12N, WHP14S, WHP13S, WHP12S, RP8S and RP11S
• Onshore plant south Firefighting & safety equipment layout plans (Slug Catcher #3)
• Onshore Plant North safety sign layouts plans (Slug catcher#1)

Saipem Classification - General Use


NFPS PROJECT
Status update: Activities/deliverables submitted (cont.)

LOSS PREVENTION
Documents issued last week

AFC:
• Safety Equipment List for RP11S
• Safety Equipment List for RT-2
• Firewater Hydraulic Analysis for WHP12N
• Hazardous Area Classification Layouts for RP10S
• Hazardous Area Classification Layouts for RT-2
• Safety Sign Layouts for RP10S
• Fire and Gas Detection Layouts for RT-2
• Temporary Refuge Impairment Analysis Report for RT-2
• Temporary Refuge Impairment Analysis Report for RP8S
• Temporary Refuge Impairment Analysis Report for RP11S
• Temporary Refuge Impairment Analysis Report for WHP14S
• Smoke and Gas Ingress Analysis Report for RP8S
• Smoke and Gas Ingress Analysis Report for RP11S
• POB Study – Re-AFC

Saipem Classification - General Use


NFPS PROJECT
Status update: Activities/deliverables ongoing
LOSS PREVENTION
IFR:
• Noise Study Report for WHP12S
• Noise Study Report for WHP13S

IFA:
• Hazardous Area Classification Layouts for RP11S
• Fire and Gas Detection Layouts for RP11S
• PID DIFFS for WHP14S and WHP12N – IFH
• Fire Risk Assessment Report for RP8S
• Fire Risk Assessment Report for RP11S

AFC:
• Safety Sign Layouts for RT-2
• Safety Sign Layouts for RP11S
• Firewater Demand Calculation for RT-2
• Helideck Wind Turbulence and Temperature Rise Study Report for WHP12S

Saipem Classification - General Use


NFPS PROJECT
Status update: Activities/deliverables ongoing
TECHNICAL HSE
Documents issued waiting for CPY comment
• HAZOP for Vendor Report (IFR)
• SCE-PS Report

Documents under Issue/preparation


• TIV Plan
• Design HSE Case (including Bow Tie Report) (IFR)
• SRS Group 1, Group 2, Onshore (waiting for vendor data response Time)
• Various HAZOP/HAZID/SIL Close Out Report

10

Saipem Classification - General Use


NFPS Project
LOSPE Study recommendation action tracking follow up - GF
Safety Study Actions Summary Table – GF
Status Actions Total Status Notes

Owner Discipline Closed  with sufficient


Open    
reference

Action #1, #11, #13, #18, #19, #72, #74, #75, #76, #80 are closed
CONTRACTOR INSTRUMENTATION 15 10 25 PFP Requirement on Valves have been communicated with INS team
Acoustic insulation will be indicated in PIDs
CONTRACTOR STRUCTURAL 2 6 8 Action #24, #25, #28, #29, #30, #49 are closed
Action #2, #4, #5, #8 are closed as PFP Markup at Framing Plan have been sent to
CONTRACTOR STRUCTURAL / SITE 20 4 24 YARD.
Requirement (Markup at Plot Plan) have been shared to SITE / FABRICATION YARD
Action #3, #6, #21, #61, #66, #71, #86, #90 are closed
CONTRACTOR STRUCTURAL / ARCHITECTURAL / 6 8 14
SITE
Requirement have been shared to SITE / FABRICATION YARD
CONTRACTOR PIPING / SITE 7   7 Requirement have been shared to SITE / FABRICATION YARD

CONTRACTOR OPERATION / PIPING 0 1 1 Action #23 is closed

CONTRACTOR PIPING (HANDLING) 0 2 2 Action #26 and #27 are closed


6 Recommendation on LPE's side have been incorporated
CONTRACTOR /
LOSS PREVENTION / OPERATION 12   12 Recommendation related to Operation Procedure has been shared to PCS
COMPANY
Operating manual
CONTRACTOR LOSS PREVENTION 2 6 8 Action #38, #39, #40, #41, #50, #51 are closed

STRUCTURAL
MECHANICAL
Action #33, #44 are closed
PIPING
CONTRACTOR ARCHITECTURAL 6 2 8 STR has obtained blast value in their report
MEC has conveyed blast value to vendor packages
INSTRUMENTATION
LOSS PREVENTION

MECHANICAL
CONTRACTOR INSTRUMENTATION 1 1 2 Action #47 is closed
LOSS PREVENTION (safety sign)
Action #36, #37, #52, #53, #54, #55 are closed
COMPANY LOSS PREVENTION 0 6 6 CPY has shared CAP437 Verification checklist, to be included in next revision of the
report
ERM   4 1 5 Action #35 is closed
  Total Action 75 47 122  
11

Saipem Classification - General Use


NFPS Project
LOSPE Study recommendation action tracking follow up - BF

Safety Study Actions Summary Table - BF


Status Actions

Owner Discipline Closed  Pending Total Status Notes


Total action (agreed
with CPY)

CONTRACTOR INSTRUMENTATION 5 2 3  

CONTRACTOR STRUCTURAL 5 5 0  
CONTRACTOR PIPING / STRUCTURAL 1   1  
CONTRACTOR PROCESS 29  12 17  
CONTRACTOR PROCESS/ STRUCTURAL 1   1  
MECHANICAL /
CONTRACTOR 7   7 .
INSTRUMENTATION
CONTRACTOR LOSS PREVENTION 25 20 5  
CONTRACTOR PIPING 1   1  

  Total Action 74 41 33  

12

Saipem Classification - General Use


NFPS Project
HAZID HAZOP SIL DRA follow up (Including Group 2 & Vendor)
HAZID Actions
Area Total Under Sign by CTR or CPY Closed action
GF 57 15 26
BF 29 10 4
ONS 22 6 10

HAZOP Actions
Area Total Under Sign by CTR or CPY Closed action
GF 286 62 128
BF 121 7 53
ONS 99 22 36

SIL Actions
Area Total Under Sign by CTR or CPY Closed action
GF 9 0 5
BF 9 0 5
ONS 4 3 0

DRA Actions
Area Total Under CTR Sign Closed action
Overall Actions from 1st 33 17 1
DRA

13

Saipem Classification - General Use


NFPS PROJECT
Focus areas & Criticalities
 MACP deletion from jacket level
 NOVEC & Lifesaving equipment package SDR discussion
 FRA PFP update discussion
 Technical Safety BoD discussion

14

Saipem Classification - General Use


THANK YOU

15

Saipem Classification - General Use