Condition Remarks Nature of Improvement Material Resources Manpower Needed


FACILITIES (Check One) Needed Needed (Indicate quantity
Satisfactory Unsatisfactory If unsatisfactory, describe (e.g. repair, repainting, (Indicate kind and and nature of labor
the problem replacement, etc.) quantity) service needed)
 Roofs/gutters  Damaged Repair 80 pcs GI Sheets JTS-Korea
 Ceilings  Damaged Repair 70 pcs Plywood
 Walls 
 Blackboards  Washed out Replacement 14 pcs blackboards MOOE
 Chairs/desks/tables  Washed out Replacement 178 pcs Armchairs DepEd
 Water facilities/
Drainage System  
 Signages  Washed out Replacement 4 pcs Tarpauline MOOE
 School garden  Washed out Replant Plants, seeds Parents/Pupils
 Lighting 
 Windows  Damaged Repair 175 pcs jalousies JTS-Korea
 Doors  Damaged Repair 4 pcs plywood
 Comfort Rooms  Damaged 10 pcs GI Sheets PTA
 School grounds  Damaged PTA
 School canteen/clinic  
 School fence  Washed out Reconstruct 240 pcs coco lumber Brgy. Officials
 Others, please specify
BE Form 05
Republic of the Philippines
Department of Education
Region VIII
Division of Samar
District of Marabut
LOGERO ELEM. SCHOOL
School Year 2014-2015

BRIGADA ESKWELA
RECORD OF DONATIONS RECEIVED

DATE ASSUMED COST OF ITEMS


PER UNIT TOTAL
ITEM/S OR MATERIALS QUANTITY RECEIVED NAME OF DONOR
White latex paint 4 gallons 05-16-2014 Gov. Sharee Ann T. Tan Php 460.00 Php 1,840.00
building 2 classrooms 05-12-2014 JTS – KOREA Php 200,00.00 Php 400,000.00
Coco lumber 415 pcs 05-14-2014 PLAN Php 25.00 Php 10,375.00
4” nails 30 kilos 05-14-2014 PTA Php 80.00 Php 2,400.00
5” nails 30 kilos 05-14-2014 PTA Php 80.00 Php 2,400.00

Total Php 417,015.00

BE Form 06
Republic of the Philippines
Department of Education
Region VIII
Division of Samar
District of Marabut
LOGERO ELEM. SCHOOL
School Year 2014-2015

BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT
Day 01 – May 19, 2014 (Monday)

STATUS
Activities Completed Started but not yet Not done REMARKS/RECOMMENDATIONS
completed
School fencing  continuing
Repair of two classrooms  ongoing

Day 02 – May 20, 2014 (Tuesday)

STATUS
Activities Completed Started but not yet Not done REMARKS/RECOMMENDATIONS
completed
School fencing  continuing
Repair of two classrooms  ongoing

Day 03 – May 21, 2014 (Wednesday)

STATUS
Activities Completed Started but not yet Not done REMARKS/RECOMMENDATIONS
completed
School fencing  continuing
Repair of two classrooms  ongoing
Cleaning of Plaza and School grounds  continuing

Day 04 – May 22, 2014 (Thursday)

STATUS
Activities Completed Started but not yet Not done REMARKS/RECOMMENDATIONS
completed
School fencing  continuing
Repair of two classrooms  ongoing
Cleaning of Plaza and School grounds  continuing

Day 05 – May 23, 2014 (Friday)

STATUS
Activities Completed Started but not yet Not done REMARKS/RECOMMENDATIONS
completed
School fencing  continuing
Repair of two classrooms  ongoing
Cleaning of Plaza and School grounds  continuing

Day 06 – May 24, 2014 (Saturday)

STATUS
Activities Completed Started but not yet Not done REMARKS/RECOMMENDATIONS
completed
School fencing  finished
Repair of two classrooms  ongoing
Cleaning of Plaza and School grounds  finished

BE Form 07
Republic of the Philippines
Department of Education
Region VIII
Division of Samar
District of Marabut
LOGERO ELEM. SCHOOL
School Year 2014-2015

BRIGADA ESKWELA

C. VOLUNTEER SERVICES
Type of Volunteer Name of Individuals/Organization Number of Volunteers
Day 01 Day 02 Day 03 Day 04 Day 05 Day 06 Total
1. PTCA Members 5 4 11 7 7 8 42
2. Barangay Officials 7 9 8 24
3. Municipal
Government Officials
4. Provincial
Government Officials
5. NGO’s Civic JTS (KOREA) 4 4 4 5 5 4 26
Organizations
6. Private citizens
7. Private
Companies/Corp
8. Other Government
Offices
9. Parents 4 P’s Recipients 17 26 21 64
10. Teachers 7 7 7 7 7 7 42
11. Pupils/Students 10 13 9 8 15 10 65
12. Others (specify)
13. Prominent Volunteers
TOTAL 33 37 48 35 60 50 263

D. ESTIMATED COST OF VOLUNTEER SERVICES RENDERED. Refer to Guide for Computing Labor Cost
Type of Service Total Number of Volunteers Total Number of Hours Rendered Total Estimated Costs
Masonry
Carpentry 15 200 Php 2,250
Plumbing
Electrical/Electronic
Landscaping/Gardening 10 80 0
Painting
Ordinary Labor
Others
TOTAL 25 280 Php 2,250

E. SIGNIFICANT EVENTS/EXPERIENCES
What is/are important contribution to
What happened Who were involved When the operation of the school or to the
existing needs of the school?

Repair of 2-room building JTS-Korea May to June, 2014 2-room available for classroom use

E. ISSUES AND CONCERNS (Describe briefly problems encountered and how resolved)
none

E. LESSONS LEARNED/BEST PRACTICES

Brgy. Officials and Brgy. Tanods are requested to join Brigada Eskwela
 4 P’s recipients volunteered in replanting vegetables

Prepared by:

RUTH JENNETH T. HUGO


ESHT-III/School Head