Operation Management: Tutor - Prof. Sriram Ramshankar
Operation Management: Tutor - Prof. Sriram Ramshankar
MANAGEMENT
Tutor – Prof. Sriram Ramshankar
Reception 120 Drug allergy consultation Fill out form & sign Administer vaccination
people/hour 60 people/hour waiver 80 people/hour 40 people/hour
There are a smaller number of people being processed in the step Administer vaccination. So, it is the
Bottleneck activity.
So, the number of people processed is calculated as 3600seconds/90 seconds = 40
people/hour.
(b)
Administer
vaccination
40people/hour
Reception 120 Drug allergy consultation Fill out form & sign
people/hour 60 people/hour waiver 80 people/hour
Administer
vaccination
40people/hour
Since two volunteers are allocated for the step Administer vaccination, a greater number of
people could be processed
Less number of people are processed in the step Drug allergy consultation. So, it is the
Bottleneck activity.
So, the time for completion depends only on the activity Drug allergy consultation. So,
the number of people processed is 60 people.
This arrangement increased the capacity of the system by increasing number of people
processed in an hour from 40 to 60 people.
(c) By combining Reception & Drug allergy consultation. The capacity of the improved system is
80 people per hour.
The process flow diagram is:
Doctors Consultation 12 1P 5
a. Here, as shown in table longest time is taken by Activity 2. So, Bottleneck activity is Medical
History. Maximum number of patients who can be seen is 3 patients/hour.
b.
Blood pressure
10
people/hour
Medical history & lab Doctor checkup & Doctor
work 2 people /hour Consultation 2 people/hour
a. Here, as shown in table longest time is taken by Type Labels. So, Bottleneck activity is Type Labels =
30people / hour
So, combining,
Receive Prescriptions & Type Labels handled by 2 technicians =2*3600/144 = 50 people/hour.
Check Prescriptions & Dispense Prescriptions handled by 1 pharmacist = 3600/70 = 51.42 people/hour
So, the capacity increases to 50 people.
Receive Prescriptions & Type
Labels 25people in 1 hour
b. In previous arrangement total time consumed was 5 hours and as per new arrangement total time
consumed is 3 hours.