N Variances Formulas

o
I Material Variances (Standard Quantity x Standard Price) - (Actual Quantity x Actual Price) (or) =
(SQ x SP) - (AQ x AP)
(1) Material Cost Variance (MCV) Actual Quantity x (Standard Price - Actual Price) (or) = AQ (SP - AP)
(2) Material Price Variance (MPV) Standard Price (Standard Quantity - Actual Quantity) (or) = SP (SQ - AQ)
Material Usage Variance (MUV)
(3) Standard Price (Standard Quantity - Actual Quantity) (or) = SP (SQ - AQ)
(4) Material Mix Variance (MMV) Standard Unit Cost (Revised Standard Quantity - Actual Quantity)
(or) = SP (RSQ - AQ)
(a) Revised Standard Quantity Total Weight of Actual Mix
(RSQ) Total Weight of Standard Mix
(b) Revised Material Usage
Variance
(5) Materials Yield Variance (MYV)
Standar Rate Total Weight of Actual Mix
Total Weight of Standard Mix
Verification
(1) Material Cost Variance Material Price Variance + Material Usage Variance
(2) Material Usage Variance Material Mix Variance + Material Yield Variance
(3) Material Cost Variance Material Mix Variance + Material Price Variance + Material Yield Variance
II Labour Variances
(1) Labour Cost Variance (LCV) (Standard Cost of Labour - Actual Cost of Labour) (or)
(Standard Rate x Standard Time for Actual Output) - (Actual Rate x Actual Time)
(2) Labour Rate Variance (LRV) Actual Time Standard Rate - Actual Rate
(3) Labour Efficiency Variance Standard Rate Standard Time - Actual Time
(4) Labour Idle Time Variance Idle Hours x Standard Rate
(5) Labour Mix Variance (LMV)
(a) When Standard & Actual Standard Cost of Standard Labour Mix - Standard Cost of Actunl Labour Mix
Time of the Labour Mix are
same
(b) When Standard & Actual Standard Rate Revised Standard Time - Actual Time
Time of Labour Mix are
different
Revised Standard Time Total Actual Time
x ActualTim e
Total Standard Time
Verification
Total Labour Cost Variance Labour Rate Variance + Labour Efficiency Variance
Total Labour Efficiency Labour Efficiency Variance + Labour Idle Time Variance
Variance
III Overhead Variances
Essentials of Certain Terms:
(1) Standard Overhead Rate per unit Budgeted Overheads
Budgeted Output
(2) Standard Overhead Rate per hour Budgeted Overheads
Budgeted Hours
(3) Standard Output for Actual Time Budgeted Output
x Actual Hours
Budgeted Hours
(4) When Output is measured in Standard Rate Per Hour x Standard Hours for Actual Output
Stantard Hours:
Recorded Overheads
When Output is measured in Standard Rate Per Unit x Actual Output in Units
units:
Absorbed Overhead
N Variances Formulas
o
(5) Budgeted Overhead Standard Rate Per Unit x Budgeted Output in Units (or)
= Standard Rate Per Hour x Budgeted Hours
(6) Actual Overhead Actual Rate Per Unit x Actual Output in Units (or)
= Actual Rate Per Hour x Actual Hours
(7) Standard Overhead Standard Rate Per Unit x Standard Output for Actual Time (or)
= Standard Rate Per Hour x Actual Hours
Overhead Variances (Actual Output x Standard Overhead Rate per Unit)-Actual Overhead Cost '"
Overhead Cost Variance (or) = Standard hours for Actual Output x [Standard Overhead Rate Per Hour-
Actual Overhead Cost]
(A) Variable Overhead Variances:
(1) Variabe Overhead Cost Variance Standard Variable Overhead for Actual Output-Actual Variable Overhead
(2) Variable Overhead Expenditure Actual Time (Standard Variable Overhead Rate per Hour Actual Variable
Variance Overhead Rate per Hour) a (or)
= Standard Variable Overheads - Actual Variable Overheads
(3) Variable Overhead Efficiency Standard Rate per Hour x (Standard Hours for Actual Production - Actual
Variance Hours)
(B) Fixed Overhead Variances
(1) Fixed Overhead Cost Variance Actual Fixed Overhead - Standard Fixed Overhead for Actual Production
(or) = Actual Output Standard Fixed Overhead Rate per Hour - Actual Fixed
Overheads
(2) Fixed Overhead Expenditure (Budgeted Fixed Overheads) - (Actual Fixed Overheads)
Variance (or) Budget Variance
(3) Fixed Overhead Volume Budgeted Fixed Overheads - Standard Fixed Overheads on Actual Production
Variance
(4) Fixed Overhead Capacity Standard Fixed Overheads - Budgeted Fixed Overheads
Variance (or) = Standard Fixed Overhead Rate per Hour x (Actual Hours Worked -
Budgeted Hours)
(5) Fixed Overhead Efficiency Standard Fixed Overhead Rate per Hour x (Standard Quantity - Actual
Variance Quantity)
(6) Fixed Overhead Calendar Standard Rate per Hour / per Day x Excess or Deficit Hours or Days Worked
Variance
IV Sales Variances
(A) Sales Value Method Variances
(1) Sales Value Variance Actual Value of Sales - Budgeted Value of Sales
(2) Sales Price Variance Actual Quantity x (Standard Price - Actual Price)
(3) Sales Volume Variance Standard Price Actual Quantity of Sales - Budgeted Quantity of Sales
(4) Sales Mix Variance (Standard Value of Actual Mix) - (Standard Vaue of Revised Standard Mix)
(5) Sales Quantity Variance Standard Selling Price Revised Standard Sales Ql,lantity - Budgeted Sales
Quantity
(B) Sales Margin or profit Methad of Variances
(1) Sales Margin Value Variance Budgeted Profit - Actual Profit (or)
(Budgeted Sales Quantity x Budgeted Profit Per Unit) - (Actual Quantity Sold
x Actual Profit per Unit)
(2) Sales Margin Volume Variance Standard Profit x (Standard Quantity - Actual Quantity)
(3) Sales Margin Price Variance Standard Profit - Actual Profit (Or)
Actual Quantity Sold Budgeted per Unit - Actual Profit per Unit
(4) Sales Margin Mix Variance Standard Profit per Unit Revised standard Quantity - Actual Quantity)