QUANTITY SHEET SHEET No.

1 of 2

Job: CIVL-1034 Final Project Date: 21-nov-20


Location: Winnipeg, Manitoba Items: Concrete Work
Estimator: Carlos Quintero

Description Qty Dimensions Concrete Formwork Rebar


L W D/H m3 m2 kg
Basement - EL. 96350
Foundation walls
Rebar Lenght +5% Wt. Factor Total Rebar Wt.
15M Vert. bars - Beam reinf 20.00 4.02 84.42 1.570 132.54
15M Vert. bars - @300 2.00 77.14 4.02 2,075.28 1.570 3,258.20
15M Horiz. bars - @200 2.00 77.14 4.10 3,316.85 1.570 5,207.45
Total Kg Foundation wall rebar: 8,598.19

L*W*H 2*L*H
Concrete 77.14 0.30 4.10 94.88 632.52

Voidform
Under foundation walls 1.00 77.14 77.14
Discounting CIP Piles 22.00 0.60 (13.20)
Total m Voidform: 63.94
Anchor Bolts
Over columns 20.00 20.00
Over wall 28.00 28.00
Total bolts: 48.00

Slab-on-grade
Rebar Lenght +5% Wt. Factor Total Rebar Wt.
10M bars @ 300 lenght way 16.62 21.35 1,259.26 0.785 988.52
10M bars @ 300 wide way 16.62 21.35 1,264.23 0.785 992.42
Total Kg Slab-on-grade rebar: 1,980.94

L*W*H
Concrete 16.62 21.35 0.13 44.35

Flexcell 2*(L+W)
Slab perimeter 16.62 21.35 75.94
C1 columns perimeter 10.00 0.30 0.30 12.00
Total m Flexcell: 87.94

Poly vapour barrier L*W


Slab-on-grade 16.62 21.35 354.80
Total m2 vapour barrier (+10% overlap): 390.28

Columns
Rebar Lenght +5% Wt. Factor Total Rebar Wt.
15M vertical bars 60.00 3.87 243.62 1.570 382.48
10M ties @ 250 10.00 1.00 3.50 157.50 0.785 123.64
Total Kg columns rebar: 506.12

L*W*H 2*L*H+2*W*H
Concrete 10.00 0.30 0.30 3.50 3.15 21.00

PROJECT ADMINISTRATION
QUANTITY SHEET SHEET No. 2 of 2

Job: CIVL-1034 Final Project Date: 21-nov-20


Location: Winnipeg, Manitoba Items: Concrete Work
Estimator: Carlos Quintero

Description Qty Dimensions Concrete Formwork Rebar


L W D/H m3 m2 kg
Main floor - EL. 100000
B3 beams
Rebar
Total B3 beams lenght:
Gridlines 2, 3, 3a 3.00 21.35 64.04
Gridline 1a 1.00 19.21 19.21
Gridline B 2.00 6.87 13.73
Stair opening - vertical 2.00 2.14 4.28
Total m B3 beams: 101.26

Lenght +5% Wt. Factor Total Rebar Wt.


20M lenght bars 7.00 101.26 744.26 2.36 1,752.73
10M stirrups 272.00 1.68 479.81 0.79 376.65
Total Kg beam rebar: 2,129.38

L*W*H L*W+2*L*H
Concrete 101.26 0.30 0.45 13.67 91.14

Structural slab
Rebar Lenght +5% Wt. Factor Total Rebar Wt.
10M dowels bars @ 300 perimeter 258.00 1.40 379.26 0.785 297.72
10M dowels bars @ 300 opening 11.00 1.40 16.17 0.785 12.69
10M bars @ 300 over 1a gridline 65.00 2.40 163.80 0.785 128.58
10M bars @ 300 over 2 and 3 gridlines 72.00 4.50 340.20 0.785 267.06
10M bars @ 300 over 3a gridline 72.00 2.40 181.44 0.785 142.43
10M bars @ 300 lenght way 57.00 21.35 1,277.68 0.785 1,002.98
10M bars @ 300 wide way 72.00 16.62 1,256.47 0.785 986.33
Total Kg Slab-on-grade rebar: 2,837.79

L*W*H L*W
Concrete 21.35 16.62 0.15 53.22 354.80