Professional Documents
Culture Documents
Basis of Schedule
Contents
1.0 INTRODUCTION.......................................................................................................... 7
Project Background ...................................................................................................... 7
2.0 DEFINITIONS .............................................................................................................. 9
3.0 DOCUMENT PURPOSE ............................................................................................ 10
4.0 EPIC CONTRACT ...................................................................................................... 11
5.0 LONG LEAD ITEMS ................................................................................................... 12
6.0 PIPELINE INITIATING PLATFORM ........................................................................... 13
7.0 SUBSEA PIPELINES ................................................................................................. 14
8.0 ONSHORE GAS PLANT ............................................................................................ 15
Page 2 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
Tables
Page 3 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
ABBREVIATIONS
Page 4 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
HOLDS LIST
HOLD SECTION DESCRIPTION
01
02
03
04
05
Page 5 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
REVISION HISTORY
REV SECTION DESCRIPTION
Page 6 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
1.0 INTRODUCTION
Project Background
The East-West Offshore Gas Gathering System (EWOGGS) Project is intended to transform
Nigeria’s Energy landscape by transporting a nominal 3 Bscf/d processed dry gas from Offshore
Bonny Island to Lekki. This is the single largest gas infrastructure investment in Nigeria’s history
for the benefit of domestic gas demand. Dangote Industries Limited in Joint Venture with FIRST
E&P is embarking on the EWOGGS Project. This infrastructure will allow stranded assets along
its trajectory to be developed as a gas monetization route becomes available.
The EWOGGS Infrastructure comprises two lean processed gas pipelines each initiating from
the Pipeline Initiating Platform (PIP) in OML 72. Gas will be gathered along the approximately
535 km route and delivered to the Onshore Gas Plant at the Dangote Industrial Complex,
Lekki, Nigeria. This is illustrated above in Figure 1-1.
New build PIP in OML 72 gathering gas from OML 52, 70, 71, 72 and 117;
Dual pipelines commencing at the new build platform in OML 72;
Five (05) proposed gas receiving tie-ins based on potential gas export from neighbouring
OMLs;
Two (02) proposed subsea gas draw offs tie-ins to supply gas to other locations;
Page 7 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
The installation of a new build PIP, 1 x 535km pipelines and 1 x 1.5 Bscf/d. Onshore Gas
Trains and associated Utilities.
The Installation of the 2nd pipeline and 2nd 1.5 Bscf/d. Onshore Gas Train, to be installed
in line with future development demands and schedule.
Page 8 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
2.0 DEFINITIONS
Page 9 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
Page 10 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
Page 11 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
Page 12 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
6.1 Calendars
Two calendars have been used in the PIP section of the schedule:
5 (five) day working week for design office activities;
6 (six) day working week for fabrication activities;
7 (seven) day working week for all other activities.
The schedule is based on a detail design start date of 29th October 2018
6.2 Fabrication
The schedule is based on topsides and jacket being fabricated in a Nigerian yard.
6.3 Installation
Page 13 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
Page 14 of 15
East West Offshore Gas Gathering System
Document & Rev No: J08937A-A-RT-00045 Rev A1
Document Title: Basis of Schedule
Page 15 of 15