UNOPS

UNITED NATIONS OFFICE FOR PROJECT SERVICES

BILL OF QUANTITIES

Ai Khanem Border Crossing Point Facilities


Takhar, Afghanistan

Customs and Police Office Buildings

NOTICE TO ALL BIDDERS - COMPLETE PROJECT PRICE:

1. All bidders MUST examine the complete project documents. These


documents include the Drawings, BOQ, Schedules and Specifications.
Any discrepancies between these documents are to be brought to the
immediate attention of UNOPS Engineer.

2. Quotation given by the contractor on this BOQ are to cover any and all
additional materials, labor or associated costs to complete the works as
documented on the complete project documents.

3. Eventual claims for extra works are covered by project general


documentation of contract.

Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Tender Title: Customs and Police Office Buildings
Original Issue: February 25, 2010
Ai Khanem Border Crossing Point Facilities
Takhar, Afghanistan
Customs Office Building
UNOPS
Vertical Structures Unit
DETAILS OF COMPONENT
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
1. General
1.1 Preliminaries 1.1 Occupied Areas, 1.1 Existing
Services Schedule and 1.1 Items
to be supplied schedules

1 Pre-construction work, mobilisation activities


including paper/ documentation tasks. LS 1.00 -
2 Post construction works and clean up.
LS 1.00 -
1.2 General Requirements 1.2 Inspection notification
schedule and 1.2 Warranty
schedules
1 Testing and Operation/Maintenance Manuals.
LS 1.00 -
Subtotal General
-

2. Site
2.3 Earthwork 2.1 Identified hazardous materials
and 2.3 Earthwork schedules

1 Excavation (any soil type) for foundation.


This item includes all excavations, disposal and
temporary support or shoring if needed. See
drawing and schedule for details.
CU.M 246.00 -
2 Ground improvement under foundations.
This includes supplying of filling materials and
compacting the layers according to schedule
and drawings. CU.M 110.00 -
3 Soil backfilling on RCC math foundation up to
ground level. This includes supplying of needed
materials. See drawings and schedules for
levels/dimensions and details. CU.M 190.00 -
4 Gravel compaction, Class 2, at any places
under the PCC/RCC shown inside the building
or at sidewalk/ramp. This includes supplying of
needed materials. See drawing and project
schedules for dimensions and details.
CU.M 75.00 -
Subtotal Site
-

3. Structure
3.1 Concrete-General 3.1 Non reinforced concrete, 3.1
Reinforced concrete and 3.2
Concrete- Integral Finishes
schedules
NOTE: Cost for concrete items in this section
includes reinforcement, steel anchorage embedded
in concrete, shuttering, concrete, concrete curing
and all to the complete job.
1 PCC lean concrete (10 Mpa) under the RCC
foundations. CU.M 13.00 -
2 RCC (20 Mpa) foundations, rectangular and
trapezoidal foundation beams. CU.M 140.00 -
3 PCC, 40mm thick, lean concrete (10 Mpa) at
the floor over the gravel compaction. CU.M 19.00 -

3/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
4 PCC concrete, 100mm thick, (20 Mpa) at the
floor over the water-proofing layer. This item
includes the stairs steps at the entrances and
the ramps. CU.M 47.00 -
5 RCC Columns, includes all columns (from -1.65
to +3.55) and supporting columns/ring beams
for trusses on the roof. CU.M 82.00 -
6 RCC (20 Mpa) slabs and beams. The items
covers all slabs, beams and RCC floor for the
bank. CU.M 86.00 -
7 RCC Pavement (20 Mpa), for 1000mm-wide
side walks. This includes entrances and ramps.
The cost includes expansion joint on side walk
surface as shown and as well as the broom
finish to the side walk/ ramp surfaces.
CU.M 15.00 -
3.3 Pre-cast RC Concrete 3.3 Precast Concrete Prototypes
Schedule
1 Precast RCC (20 Mpa) exterior window sill for
all windows as per drawings. This includes all
work need for complete installation.
Lin M 29.00 -
3.5 Brickwork 3.5 Brickwork construction
schedule
1 Second Class Brick masonry with mortar. This
includes all brick walls/ brick masonry in the
entire building. The cost includes steel bars
shown in the walls and their connection to the
perimeter RCC elements. CU.M 60.00 -
3.9 Light Timberwork 3.9 Light Timberwork schedule,
6.6 Interior painting and 6.6
Exterior painting schedules
1 Roof timber structure on the trusses. The cost
includes 30mm thick wooden planks as shown
on the drawing. This also cover all auxiliary and
needed materials and supplying and installation
of members including painting to make the
surface ready for folded metal sheet roofing
according to the drawing, schedule and
specifications. SQ.M 680.00 -
3.10 Concrete Unit Masonry 3.10 Concrete Unit Masonry

1 CMU masonry with mortar. This item covers all


CMU works shown on the drawings for the
building. The cost includes all needed
materials, steel bars, anchors etc and works. CU.M 60.00 -
3.11 Structural Steel 3.11 Structural Steel Schedules

NOTE: Cost for steel related items in this section


includes supplying materials and installation to the
complete condition for all members, gussets,
fasteners, connections, welding and other
accessories and works needed to complete the job.
The cost also includes painting according to the
schedules and specifications for steel member
painting, which is at least on coat of anti-rust
followed by 2 other coats of oil-based painting for all
surfaces and sides of the steel members.
1 Steel support, purlin, at the metal sheet roof as
(C-shape 140x65mm + L-shape 50x50mm).
See drawing for details. Lin M 560.00 -
2 Steel truss (TRUSS 1) at the roof. See drawing
for details. No 6.00 -
3 Steel truss (TRUSS 2) at the roof. See drawing
for details. No 4.00 -
4 Steel truss (TRUSS 3) at the roof. See drawing
for details. No 2.00 -

4/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
5 Steel truss (TRUSS 4) at the roof. See drawing
for details. No 8.00 -
6 Steel truss (TRUSS 5) at the roof. See drawing
for details. No 2.00 -
7 Steel truss (TRUSS 6) at the roof. See drawing
for details. No 2.00 -
8 Steel truss (TRUSS 7) at the roof. See drawing
for details. No 8.00 -
9 Steel truss (TRUSS 8) at the roof. See drawing
for details. No 2.00 -
10 Steel truss (TRUSS 9) at the roof. See drawing
for details. No 4.00 -
11 Steel truss (TRUSS 10) at the roof. See
drawing for details. No 4.00 -
12 Steel truss (TRUSS 11) at the roof. See
drawing for details. No 1.00 -
13 Steel frame fixed ladder inside the toilet as the
access way to the roof. The work and the cost
includes construction of fixed later to the wall
and the opening pane, its hardware and other
accessories to complete the installation as per
drawing and schedule. This also includes
painting according to the schedules and
specifications for steel surfaces painting.
LS 1.00 -
Subtotal Structure
-

4. Enclosure
4.1 Waterproofing 4.1 Waterproofing system
schedule
1 Bitumen water-proofing coat. This is a 3-5mm
thick hot bitumen painting coats on dried PCC
surface. The item applies on 40mm PCC at the
floor beneath the 20 Mpa, 100mm thick PCC
layer. This cost includes supplying and applying
the coats with all needed accessories and work
to do the job as per manufacturer's data and to
the full satisfaction of UNOPS engineer.
SQ.M 470.00 -
2 Single layer bitumen membrane at the floor and
walls of toilets/kitchen. This includes
preparation of base layers shown on the
drawings. Refer to schedule/drawing for details.
SQ.M 55.00 -
4.2 Roofing 4.2 Roofing materials, and 4.2
Gutter and Down pipe Schedules
1 Standing seam metal roofing (using GI sheet
gauge 24). This includes all accessories
required for installation of roof on the prepared
timber plank (see item 3.9.1 for the cost of
timber plank on roof). The cost also includes all
flashings, capping etc needed on the metal roof.
SQ.M 680.00 -
2 Metallic gutter around the roof (using GI sheet
gauge 20). The cost includes all accessories
required for complete installation of gutter such
as supplying, fixing and others as per drawing
and schedules.
Lin M 116.00 -
3 Down pipes, PVC pipe class-B. This includes
all accessories required for complete installation
such as supplying, fixing and others as per
drawing and schedules.
Lin M 45.00 -

5/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
4.3 Windows and Window Hardware 4.3 Window, 4.3 Window
Hardware, 4.5 Annealed Glasses,
and 4.6 Glassblock work
schedules
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
1 Wooden frame windows. The work includes
making, transportation, installation, hardware,
glazing, glass-block work around window,
insect screen, 3 coats of oil-based painting, and
other accessories required for complete
installation as per drawings and schedule.
SQ.M 63.00 -
4.4 Doors and Door Hardware 4.4 Joinery doors 4.4 PVC doors,
4.4 Steel doors and 4.5 Annealed
Glasses schedules
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
1 Wooden frame doors. The work includes
making, transportation, installation, hardware,
glazing, and other accessories required for
complete installation as per drawings and
schedule. SQ.M 76.00 -
2 PVC frame doors. The work includes making,
transportation, installation, hardware, glazing,
and other accessories required for complete
installation as per drawings and schedule.
SQ.M 6.00 -
3 Steel frame doors. The work includes making,
transportation, installation, hardware, glazing, 1
coat of anti-rust followed by 2 other coats of oil-
based painting, and other accessories required
for complete installation as per drawings and
schedule.
SQ.M 2.00 -
4.5 Glazing 4.5 Mirrors schedules

1 Mirrors (40x60cm) at toilets. This includes


complete installation. No 5.00 -
4.7 Insulation and Vapour Barriers 4.7 Insulation Schedules

1 Glasswool thermal insulation on RCC roof,


beneath roof structure. See drawings and
schedules for details. SQ.M 640.00 -
4.8 Exterior Insulation and Finish System 4.8 EFIS Schedules

NOTE: Prior to work, samples must be approved by


UNOPS Engineer.
1 External wall insulation system, STOTHERM
CLASSIC, (expanded polystyrene foam and
organically bound render) "or equivalent ". See
drawing and schedule for location and detail.
The cost includes one preparation layer of
cement render and all other process required for
a complete job as per product's manufacturer
data and UNOPS engineer satisfaction.
SQ.M 310.00 -
Subtotal enclosure
-

5. Interior
5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule

6/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
1 Lasani wooden board, 16mmm, fixed ceiling for
all soffits around the building. The cost includes
all framing, fixing, oil based painting and
needed work for a complete job to the full
satisfaction of Engineer. SQ M 152.00 -
2 Gypsum board, 16mmm, reflected ceiling for
the side entrances of the building. The cost
includes all framing, fixing, and needed work for
complete job. SQ M 4.00 -
5.5 Joinery 5.5 Joinery fixtures schedule

1 Wooden frame, MDF finish, wall mounted


cabinet at the kitchen. See drawings for details.
The cost includes making, installation, framing,
hardware, finish, 3 coats oil-based painting and
all to the complete job.
LS 1.00 -
2 Wooden frame, MDF finish, floor mounted
cupboard at the kitchen. See drawings for
details. The cost includes making, installation,
framing, finish, hardware, stone table top,
splash back, 3 coats oil-based painting and all
to the complete job. LS 1.00 -
5.6 Metalwork 5.6 Metal Fixtures Schedule

1 Metallic plaster beads for outer corners at the


corridors only, including edge of walls. This
includes any needed work for complete
installation. See schedules and drawings for
details. Lin M 70.00 -
2 Toilet roll holders. This also includes installation.
No 3.00 -
3 Grab rail for handicap toilet. One complete set.
This includes supplying and complete
installation. LS 1.00 -
4 Soap dishes. This also includes installation.
No 4.00 -
5.8 Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule
1 Extinguishers, wall mounted, powder-type (9kg).
No 4.00 -
Subtotal Interior
-

6. Finish
6.1 Plastering 6.1 Plastering Schedule

NOTE: Prior to work, samples must be approved by


UNOPS Engineer.
Internal surfaces

1 Cement render medium CRM followed by


cement render fine CRF on all internal surfaces
of walls/ ceilings/ beams/ columns/ reveals. See
schedule for detail. SQ.M 1,100.00 -
External surfaces

2 Gypsum board, decorative finish, at both main


entrances foreheads. The cost includes
supplying, making, installation and all to the
complete condition as per Engineer's approval.
SQ.M 40.00 -
6.2 Cementitious Toppings 6.2 Cementitious Toppings
Schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.

7/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
1 In situ colored chips, colored mortar terrazzo,
including marble trims for joints, for all floors as
shown on the drawing. See schedule for details.
The cost also includes stainless steel nosing at
the outer edges of the stair steps at the
entrances. SQ.M 510.00 -
6.3 Tiling 6.3 Wall tiling and 6.3 Floor tiling
schedules
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
1 Ceramic wall tiles for toilets, kitchen, around the
drinking water fountain and any place shown.
The cost includes bed preparation, bedding and
grout. SQ.M 70.00 -
2 Ceramic floor tiles for toilets including bed
preparation, bedding and grout. SQ.M 35.00 -
3 Marble skirting for all rooms and halls where did
not receive ceramic tiles. The cost includes
bedding and grout. Lin M 450.00 -
6.6 Painting 6.6 Interior/Exterior painting
schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
Internal surfaces

1 Flat water based: Interior, on all surfaces that


receive cement plaster. The cost includes wall
putty (gypsum filling) layer before painting and
all needed preparation of the surfaces for
painting. See schedule for detail on this paint
system SQ.M 1,100.00 -
Subtotal Finishes
-

8. Water Services
8.1 Water Services 8.1 Water services samples, 8.1
Water system piping, 8.1 Sanitary
fixtures, 8.1 Water heater
schedules and 8.1 Water
Services Testing schedules

NOTE: The cost for all pipes exposed to


weather includes glass wool thermal insulation
cover. The cost given for all GI and PVC pipes
with diameter less than 60mm includes all
required fittings, accessories and work for
complete system installation.
Water supply piping

1 GI water supply pipe D=32mm, including


fittings and installation. Lin M 30.00 -
2 GI water supply pipe D=25mm, including
fittings and installation. Lin M 22.00 -
3 GI water supply pipe D=20mm, including
fittings and installation. Lin M 25.00 -
4 GI water supply pipe D=15mm, including
fittings and installation. Lin M 50.00 -
5 Water supply bronze Valve D=32mm, including
fittings and installation. No 2.00 -
6 Water supply bronze Valve D=20mm, including
fittings and installation. No 1.00 -
7 Damp proof Insulation rubber tape for all GI
Piping. Lin M 150.00 -
8 Water supply inspection manhole less than
1200mm deep. This includes excavation and
any needed work to make the manhole as per
drawings and schedule. No 3.00 -

8/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
Sanitation Piping

9 PVC pipe D=100mm, including supply and


installation. This also includes supply and
installation of PVC pipe from GI sheet
downpipes to the open channel collector at the
side walks. Lin M 34.00 -
10 PVC pipe D=50mm, including fittings and
installation. Lin M 50.00 -
11 Ventilation PVC pipes D=100mm (from toilets
to roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule for
details. Lin M 15.00 -
12 Ventilation PVC pipes D=50mm (from toilets to
roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule for
details. Lin M 10.00 -
13 PVC Elbow D=100x100,45ْ, including supply
and installation. No 4.00 -
14 PVC Tee D=100x100, 45ْ, including supply and
installation. No 8.00 -
15 Sanitation Grease Trap less than 1200mm
deep. This includes excavation and any needed
work to make the manhole according to the
drawings and schedules. No 1.00 -
Sanitary and other fixtures

16 Western toilet, including supply, installation and


accessories. No 3.00 -
17 Water fountain , including supply, installation
and accessories. No 2.00 -
18 Ceramic sink at toilets and labs, including mixer
and all accessories, supplying and installation.
No 4.00 -
19 Floor trap D=50mm, including supply and
installation. No 6.00 -
20 Stainless steel sink, including supply and
installation. No 1.00 -
21 Ventilation cap D=100mm, including supply
and installation. No 2.00 -
22 Ventilation cap D=50mm, including supply and
installation. No 1.00 -
23 Service Sink, including supply and installation.
No 1.00 -
24 Electrical water boiler with capacity of 50 Liter,
including supply and installation. No 2.00 -
25 Electrical water boiler with capacity of 30 Liter,
including supply and installation. No 1.00 -
26 Sewer Manholes More than 1200mm deep.
This includes excavation and any needed work
to make the manhole according to the drawings
and schedules. No 2.00 -
Subtotal Water Services
-

9. Electrical Services
9.1 Electrical Services 9.1 Electrical systems, 9.1
Electrical supply mains, 9.1
Electrical switchboard design, 9.1
Main 380VAC Distribution
System, 9.1 Panel Construction,
9.1 Power accessories, 9.1
Lighting control and fittings, 9.1
Fire Detection Equipment
Schedule Schedules and the
Attachments

9/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
Note: for all items below the cost includes
complete/installations with all needed
accessories and works.
Switchboard and sub boards
1 Sub distribution panel, 750x500x250 mm,
powder coated, weatherproof, outdoor mounted
metal. With Digital Measurement equipments.
No. 1.00 -
2 Main circuit breaker, MCCB, 3x160Amps, Type-
C. No. 1.00 -
3 Circuit breaker, MCB, 1x32Amps, Type-C
No. 16.00 -
4 Circuit breaker, MCB, 1x20Amps, Type-C
No. 38.00 -
Distribution wiring

5 3 (1X6mm2) wires pulled in 24mm PVC


Conduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 600.00 -
6 3 (1X4mm2) wires pulled in 24mm PVC
Conduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 1,500.00 -
Fittings/Fixtures

7 Single pole/double pole or two way light switch.


No 42.00 -
8 32W circular surface ceiling mount, IP54
fluorescent light fixture. No 35.00 -
9 60W circular Pendant ceiling mount, IP54
fluorescent light fixture with all accessories. No 21.00 -
10 60W Circular Surface ceiling mount, IP54
fluorescent light fixture with all accessories. No 7.00 -
11 2x36W pendant ceiling mounted fluorescent
light fixture, IP-44.with all accessories. No 25.00 -
12 1x36W pendant ceiling mounted fluorescent
light fixture, IP-56. with all accessories. No 2.00 -
13 16 Amp Duplex power receptacle.
No 98.00 -
14 16 Amp single water proof power receptacle.
No 9.00 -
15 25 Amp single water proof power receptacle for
electrical water heater and kitchen. No 9.00 -
AC/Split Units and Exhaust fans

16 12000 BTU AC/ Split unit 220 V, 50 HZ


Samsung made in Italy with all accessories. No 15.00 -
17 Roof mounted exhaust fans .
No 3.00 -
18 25 Amp single electrical non-fuse disconnecting
switch for AC/ Split unit. No 15.00 -
Emergency evacuation lighting

19 2x10 watt IP-65 wall mounted Emergency Light


Fixture. No 7.00 -
20 1X10W surface mounted IP-40 Exit light.
No 4.00 -
Fire alarm system (including all associated
cabling, wiring, mounting, etc)

21 Addressable fire alarm panel, with all


accessories, to the complete and functioning
job. LS 1.00 -
22 Fire alarm push button, double action type, UL
Listed No 4.00 -
23 Fire alarm
No 4.00 -
24 Photoelectric type smoke detectors, UL Listed
No 22.00 -
Electrical Grounding and Lightning
Protection.

10/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
25 Lightening protection as mentioned in lightening
protection drawing with air terminal, electrodes,
tape, connectors, clamp and grounding cable
Set 1.00 -
26 Grounding system as mentioned in grounding
drawing with electrodes, tape, connectors,
clamp and grounding cable Set 1.00 -
Labeling

27 Proper and correct all circuits numbering, cable


circuit drawings, cable and switchboard labeling
to the full satisfaction of UNOPS engineer.
LS 1.00 -
Subtotal Electrical Services -

11/24
UNOPS
Vertical Structures Unit

SUMMARY OF COMPONENT

Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010

Work Type
Total for General 0.00
Total for Site 0.00
Total for Structure 0.00
Total for Enclosure 0.00
Total for Interior 0.00
Total for Finish 0.00
Total for Water Supply Services 0.00
Total for Electrical Services 0.00

Total for Customs Office Building 0.00


Ai Khanem Border Crossing Point Facilities
Takhar, Afghanistan
Police Office Building
UNOPS
Vertical Structures Unit
DETAILS OF COMPONENT
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


1. General
1.1 Preliminaries 1.1 Occupied Areas, 1.1 Existing
Services Schedule and 1.1 Items to be
supplied schedules
1 Pre-construction work, mobilisation activities
including paper/ documentation tasks.
LS 1.00 -
2 Post construction works and clean up.
LS 1.00 -
1.2 General Requirements 1.2 Inspection notification schedule and
1.2 Warranty schedules
1 Testing and Operation/Maintenance Manuals.
LS 1.00 -
Subtotal General
-

2. Site
2.3 Earthwork 2.1 Identified hazardous materials and
2.3 Earthwork schedules
1 Excavation (any soil type) for foundation.
This item includes all excavations, disposal
and temporary support or shoring if needed.
See drawing and schedule for details.
CU.M 190.00 -
2 Ground improvement under foundations.
This includes supplying of filling materials and
compacting the layers according to schedule
and drawings. CU.M 85.00 -
3 Soil backfilling on RCC math foundation up
to ground level. This includes supplying of
needed materials. See drawings and
schedules for levels/dimensions and details.
CU.M 147.00 -
4 Gravel compaction, Class 2, at any places
under the PCC/RCC shown inside the building
or at sidewalk/ramp. This includes supplying
of needed materials. See drawing and project
schedules for dimensions and details.
CU.M 60.00 -
Subtotal Site
-

3. Structure
3.1 Concrete-General 3.1 Non reinforced concrete, 3.1
Reinforced concrete and 3.2 Concrete-
Integral Finishes schedules
NOTE: Cost for concrete items in this section
includes reinforcement, steel anchorage embedded
in concrete, shuttering, concrete, concrete curing
and all to the complete job.
1 PCC lean concrete (10 Mpa) under the RCC
foundations. CU.M 10.00 -
2 RCC (20 Mpa) foundations, rectangular and
trapezoidal foundation beams. CU.M 108.00 -
3 PCC, 40mm thick, lean concrete (10 Mpa) at
the floor over the gravel compaction. CU.M 15.00 -

14/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


4 PCC concrete, 100mm thick, (20 Mpa) at the
floor over the water-proofing layer. This item
includes the stairs steps at the entrances and
the ramps. CU.M 36.00 -
5 RCC Columns, includes all columns (from -
1.65 to +3.55) and supporting columns/ring
beams for trusses on the roof. CU.M 66.00 -
6 RCC (20 Mpa) slabs and beams. The items
covers all slabs, beams and RCC floor for the
bank. CU.M 66.00 -
7 RCC Pavement (20 Mpa), for 1000mm-wide
side walks. This includes entrances and
ramps. The cost includes expansion joint on
side walk surface as shown and as well as the
broom finish to the side walk/ ramp surfaces.
CU.M 12.00 -
3.3 Pre-cast RC Concrete 3.3 Precast Concrete Prototypes
Schedule
1 Precast RCC (20 Mpa) exterior window sill for
all windows as per drawings. This includes all
work need for complete installation.
Lin M 23.00 -
3.5 Brickwork 3.5 Brickwork construction schedule
1 Second Class Brick masonry with mortar. This
includes all brick walls/ brick masonry in the
entire building. The cost includes steel bars
shown in the walls and their connection to the
perimeter RCC elements. CU.M 46.00 -
3.7 Light Steelwork 3.7 Light Steelwork, 6.6 Interior painting
and 6.6 Exterior painting schedules

NOTE: The following steel items include


painting according to the schedules and
specifications for steel member painting for
complete installation. See drawing for details.

1 Steel frame cabinet for First-Aid-Kits at the


hall of Police Office Building. The item and its
cost include making, transportation,
installation, hardware, finishes and all other
accessories and work required for a complete
cabinet to the full satisfaction of the Engineer.
LS 1.00 -
2 Steel frame cabinets for Weapon Storages at
the hall of Police Office Building. The item and
its cost include making, transportation,
installation, hardware, finishes and all other
accessories and work required for a complete
cabinet to the full satisfaction of the Engineer.
LS 1.00 -
3.9 Light Timberwork 3.9 Light Timberwork schedule, 6.6
Interior painting and 6.6 Exterior
painting schedules
1 Roof timber structure on the trusses. The cost
includes 30mm thick wooden planks as
shown on the drawing. This also cover all
auxiliary and needed materials and supplying
and installation of members including painting
to make the surface ready for folded metal
sheet roofing according to the drawing,
schedule and specifications.
SQ.M 495.00 -
3.10 Concrete Unit Masonry 3.10 Concrete Unit Masonry

15/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


1 CMU masonry with mortar. This item covers
all CMU works shown on the drawings for the
building. The cost includes all needed
materials, steel bars, anchors etc and works.
CU.M 46.00 -
3.11 Structural Steel 3.11 Structural Steel Schedules

NOTE: Cost for steel related items in this section 3.7 Light Steelwork Schedule
includes supplying materials and installation to the
complete condition for all members, gussets,
fasteners, connections, welding and other
accessories and works needed to complete the
job. The cost also includes painting according to
the schedules and specifications for steel member
painting, which is at least on coat of anti-rust
followed by 2 other coats of oil-based painting for
all surfaces and sides of the steel members.

1 Steel support, purlin, at the metal sheet roof


as (C-shape 140x65mm + L-shape
50x50mm). See drawing for details. Lin M 440.00 -
2 Steel truss (TRUSS 1) at the roof. See
drawing for details. No 3.00 -
3 Steel truss (TRUSS 2) at the roof. See
drawing for details. No 4.00 -
4 Steel truss (TRUSS 3) at the roof. See
drawing for details. No 2.00 -
5 Steel truss (TRUSS 4) at the roof. See
drawing for details. No 8.00 -
6 Steel truss (TRUSS 5) at the roof. See
drawing for details. No 2.00 -
7 Steel truss (TRUSS 6) at the roof. See
drawing for details. No 2.00 -
8 Steel truss (TRUSS 7) at the roof. See
drawing for details. No 8.00 -
9 Steel truss (TRUSS 8) at the roof. See
drawing for details. No 2.00 -
10 Steel truss (TRUSS 9) at the roof. See
drawing for details. No 4.00 -
11 Steel truss (TRUSS 10) at the roof. See
drawing for details. No 4.00 -
12 Steel truss (TRUSS 11) at the roof. See
drawing for details. No 1.00 -
13 Steel frame fixed ladder inside the toilet as the
access way to the roof. The work and the cost
includes construction of fixed later to the wall
and the opening pane, its hardware and other
accessories to complete the installation as per
drawing and schedule. This also includes
painting according to the schedules and
specifications for steel surfaces painting.
LS 1.00 -
Subtotal Structure
-

4. Enclosure
4.1 Waterproofing 4.1 Waterproofing system schedule
1 Bitumen water-proofing coat. This is a 3-5mm
thick hot bitumen painting coats on dried PCC
surface. The item applies on 40mm PCC at
the floor beneath the 20 Mpa, 100mm thick
PCC layer. This cost includes supplying and
applying the coats with all needed accessories
and work to do the job as per manufacturer's
data and to the full satisfaction of UNOPS
engineer. SQ.M 360.00 -

16/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


2 Single layer bitumen membrane at the floor
and walls of toilets/kitchen. This includes
preparation of base layers shown on the
drawings. Refer to schedule/drawing for
details. SQ.M 55.00 -
4.2 Roofing 4.2 Roofing materials, and 4.2 Gutter
and Down pipe Schedules
1 Standing seam metal roofing (using GI sheet
gauge 24). This includes all accessories
required for installation of roof on the prepared
timber plank (see item 3.9.1 for the cost of
timber plank on roof). The cost also includes
all flashings, capping etc needed on the metal
roof. SQ.M 495.00 -
2 Metallic gutter around the roof (using GI sheet
gauge 20). The cost includes all accessories
required for complete installation of gutter
such as supplying, fixing and others as per
drawing and schedules.
Lin M 98.00 -
3 Down pipes, PVC pipe class-B. This includes
all accessories required for complete
installation such as supplying, fixing and
others as per drawing and schedules.
Lin M 38.00 -
4.3 Windows and Window Hardware 4.3 Window, 4.3 Window Hardware, 4.5
Annealed Glasses, and 4.6 Glassblock
work schedules
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
1 Wooden frame windows. The work includes
making, transportation, installation, hardware,
glazing, glass-block work around window,
insect screen, 3 coats of oil-based painting,
and other accessories required for complete
installation as per drawings and schedule.
SQ.M 50.00 -
4.4 Doors and Door Hardware 4.4 Joinery doors 4.4 PVC doors, 4.4
Steel doors and 4.5 Annealed Glasses
schedules
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
1 Wooden frame doors. The work includes
making, transportation, installation, hardware,
glazing, and other accessories required for
complete installation as per drawings and
schedule. SQ.M 60.00 -
2 PVC frame doors. The work includes making,
transportation, installation, hardware, glazing,
and other accessories required for complete
installation as per drawings and schedule.
SQ.M 6.00 -
3 Steel frame doors. The work includes making,
transportation, installation, hardware, glazing,
1 coat of anti-rust followed by 2 other coats of
oil-based painting, and other accessories
required for complete installation as per
drawings and schedule.
SQ.M 2.00 -
4.5 Glazing 4.5 Mirrors schedules

1 Mirrors (40x60cm) at toilets. This includes


complete installation. No 5.00 -
4.7 Insulation and Vapour Barriers 4.7 Insulation Schedules

1 Glasswool thermal insulation on RCC roof,


beneath roof structure. See drawings and
schedules for details. SQ.M 495.00 -

17/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


4.8 Exterior Insulation and Finish System 4.8 EFIS Schedules

NOTE: Prior to work, samples must be approved by


UNOPS Engineer.
1 External wall insulation system,
STOTHERM CLASSIC, (expanded
polystyrene foam and organically bound
render) "or equivalent ". See drawing and
schedule for location and detail. The cost
includes one preparation layer of cement
render and all other process required for a
complete job as per product's manufacturer
data and UNOPS engineer satisfaction. SQ.M 250.00 -
Subtotal enclosure
-

5. Interior
5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule

1 Lasani wooden board, 16mmm, fixed ceiling


for all soffits around the building. The cost
includes all framing, fixing, oil based painting
and needed work for a complete job to the full
satisfaction of Engineer.
SQ M 117.00 -
2 Gypsum board, 16mmm, reflected ceiling for
the side entrances of the building. The cost
includes all framing, fixing, and needed work
for complete job. SQ M 4.00 -
5.5 Joinery 5.5 Joinery fixtures schedule

1 Wooden frame, MDF finish, wall mounted


cabinet at the kitchen. See drawings for
details. The cost includes making, installation,
framing, hardware, finish, 3 coats oil-based
painting and all to the complete job.
LS 1.00 -
2 Wooden frame, MDF finish, floor mounted
cupboard at the kitchen. See drawings for
details. The cost includes making, installation,
framing, finish, hardware, stone table top,
splash back, 3 coats oil-based painting and all
to the complete job. LS 1.00 -
5.6 Metalwork 5.6 Metal Fixtures Schedule

1 Metallic plaster beads for outer corners at the


corridors only, including edge of walls. This
includes any needed work for complete
installation. See schedules and drawings for
details. Lin M 54.00 -
2 Toilet roll holders. This also includes
installation. No 3.00 -
3 Grab rail for handicap toilet. One complete
set. This includes supplying and complete
installation. LS 1.00 -
4 Soap dishes. This also includes installation.
No 4.00 -
5.8 Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule
1 Extinguishers, wall mounted, powder-type
(9kg). No 4.00 -
Subtotal Interior
-

6. Finish
6.1 Plastering 6.1 Plastering Schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.

18/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


Internal surfaces

1 Cement render medium CRM followed by


cement render fine CRF on all internal
surfaces of walls/ ceilings/ beams/ columns/
reveals. See schedule for detail. SQ.M 880.00 -
External surfaces

2 Gypsum board, decorative finish, at both main


entrances foreheads. The cost includes
supplying, making, installation and all to the
complete condition as per Engineer's approval.
SQ.M 40.00 -
6.2 Cementitious Toppings 6.2 Cementitious Toppings Schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
1 In situ colored chips, colored mortar terrazzo,
including marble trims for joints, for all floors
as shown on the drawing. See schedule for
details. The cost also includes stainless steel
nosing at the outer edges of the stair steps at
the entrances. SQ.M 390.00 -
6.3 Tiling 6.3 Wall tiling and 6.3 Floor tiling
schedules
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
1 Ceramic wall tiles for toilets, kitchen, around
the drinking water fountain and any place
shown. The cost includes bed preparation,
bedding and grout. SQ.M 70.00 -
2 Ceramic floor tiles for toilets including bed
preparation, bedding and grout. SQ.M 35.00 -
3 Marble skirting for all rooms and halls where
did not receive ceramic tiles. The cost
includes bedding and grout. Lin M 360.00 -
6.6 Painting 6.6 Interior/Exterior painting schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
Internal surfaces

1 Flat water based: Interior, on all surfaces that


receive cement plaster. The cost includes wall
putty (gypsum filling) layer before painting and
all needed preparation of the surfaces for
painting. See schedule for detail on this paint
system SQ.M 880.00 -
Subtotal Finishes
-

8. Water Services
8.1 Water Services 8.1 Water services samples, 8.1 Water
system piping, 8.1 Sanitary fixtures, 8.1
Water heater schedules and 8.1 Water
Services Testing schedules

NOTE: The cost for all pipes exposed to


weather includes glass wool thermal insulation
cover. The cost given for all GI and PVC pipes
with diameter less than 60mm includes all
required fittings, accessories and work for
complete system installation.

Water supply piping

1 GI water supply pipe D=32mm, including


fittings and installation. Lin M 30.00 -

19/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


2 GI water supply pipe D=25mm, including
fittings and installation. Lin M 22.00 -
3 GI water supply pipe D=20mm, including
fittings and installation. Lin M 59.00 -
4 GI water supply pipe D=15mm, including
fittings and installation. Lin M 78.00 -
5 Water supply bronze Valve D=32mm,
including fittings and installation. No 2.00 -
6 Water supply bronze Valve D=20mm,
including fittings and installation. No 2.00 -
7 Damp proof Insulation rubber tape for all GI
Piping. Lin M 200.00 -
8 Water supply inspection manhole less than
1200mm deep. This includes excavation and
any needed work to make the manhole as per
drawings and schedule. No 4.00 -
Sanitation Piping

9 PVC pipe D=100mm, including supply and


installation. This also includes supply and
installation of PVC pipe from GI sheet
downpipes to the open channel collector at the
side walks. Lin M 50.00 -
10 PVC pipe D=50mm, including fittings and
installation. Lin M 45.00 -
11 Ventilation PVC pipes D=100mm (from toilets
to roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule
for details. Lin M 23.00 -
12 Ventilation PVC pipes D=50mm (from toilets
to roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule
for details. Lin M 8.00 -
13 PVC Elbow D=100x100,45ْ, including supply
and installation. No 10.00 -
14 PVC Tee D=100x100, 45ْ, including supply
and installation. No 15.00 -
15 Sanitation Grease Trap less than 1200mm
deep. This includes excavation and any
needed work to make the manhole according
to the drawings and schedules. No 1.00 -
Sanitary and other fixtures

16 Western toilet, including supply, installation


and accessories. No 5.00 -
17 Water fountain , including supply, installation
and accessories. No 2.00 -
18 Ceramic sink at toilets and labs, including
mixer and all accessories, supplying and
installation. No 6.00 -
19 Floor trap D=50mm, including supply and
installation. No 7.00 -
20 Stainless steel sink, including supply and
installation. No 1.00 -
21 Ventilation cap D=100mm, including supply
and installation. No 3.00 -
22 Ventilation cap D=50mm, including supply
and installation. No 1.00 -
23 Service Sink, including supply and installation.
No 1.00 -
24 Electrical water boiler with capacity of 50
Liter, including supply and installation. No 2.00 -
25 Electrical water boiler with capacity of 30
Liter, including supply and installation. No 2.00 -

20/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


26 Sewer Manholes More than 1200mm deep.
This includes excavation and any needed work
to make the manhole according to the
drawings and schedules. No 3.00 -
Subtotal Water Services
-

9. Electrical Services
9.1 Electrical Services 9.1 Electrical systems, 9.1 Electrical
supply mains, 9.1 Electrical switchboard
design, 9.1 Main 380VAC Distribution
System, 9.1 Panel Construction, 9.1
Power accessories, 9.1 Lighting control
and fittings, 9.1 Fire Detection
Equipment Schedule Schedules and the
Attachments

Note: for all items below the cost includes


complete/installations with all needed
accessories and works.
Switchboard and sub boards
1 Sub distribution panel, 750x500x250 mm,
powder coated, weatherproof, outdoor
mounted metal. With Digital Measurement
equipments. No. 1.00 -
2 Main circuit breaker, MCCB, 3x160Amps,
Type-C. No. 1.00 -
3 Circuit breaker, MCB, 1x32Amps, Type-C
No. 12.00 -
4 Circuit breaker, MCB, 1x20Amps, Type-C
No. 30.00 -
Distribution wiring

5 3 (1X6mm2) wires pulled in 24mm PVC


Conduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 400.00 -
6 3 (1X4mm2) wires pulled in 24mm PVC
Conduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 900.00 -
Fittings/Fixtures

7 Single pole/double pole or two way light


switch. No 38.00 -
8 32W circular surface ceiling mount, IP54
fluorescent light fixture. No 26.00 -
9 60W circular Pendant ceiling mount, IP54
fluorescent light fixture with all accessories. No 16.00 -
10 60W Circular Surface ceiling mount, IP54
fluorescent light fixture with all accessories. No 2.00 -
11 2x36W pendant ceiling mounted fluorescent
light fixture, IP-44.with all accessories.
No 16.00 -
12 1x36W pendant ceiling mounted fluorescent
light fixture, IP-56. with all accessories.
No 3.00 -
13 16 Amp Duplex power receptacle.
No 54.00 -
14 16 Amp single water proof power receptacle.
No 16.00 -
15 25 Amp single water proof power receptacle
for electrical water heater and kitchen.
No 12.00 -
AC/Split Units and Exhaust fans

16 12000 BTU AC/ Split unit 220 V, 50 HZ


Samsung made in Italy with all accessories.
No 8.00 -

21/24
Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Pos. Description of Work/Items Unit Quantity Unit Cost Total Cost


17 Roof mounted exhaust fans .
No 5.00 -
18 25 Amp single electrical non-fuse
disconnecting switch for AC/ Split unit. No 8.00 -
Emergency evacuation lighting

19 2x10 watt IP-65 wall mounted Emergency


Light Fixture. No 5.00 -
20 1X10W surface mounted IP-40 Exit light.
No 4.00 -
Fire alarm system (including all associated
cabling, wiring, mounting, etc)

21 Addressable fire alarm panel, with all


accessories, to the complete and functioning
job. LS 1.00 -
22 Fire alarm push button, double action type, UL
Listed No 4.00 -
23 Fire alarm
No 4.00 -
24 Photoelectric type smoke detectors, UL Listed
No 16.00 -
Electrical Grounding and Lightning
Protection.
25 Lightening protection as mentioned in
lightening protection drawing with air terminal,
electrodes, tape, connectors, clamp and
grounding cable Set 1.00 -
26 Grounding system as mentioned in grounding
drawing with electrodes, tape, connectors,
clamp and grounding cable Set 1.00 -
Labeling

27 Proper and correct all circuits numbering,


cable circuit drawings, cable and switchboard
labeling to the full satisfaction of UNOPS
engineer. LS 1.00 -
Subtotal Electrical Services -

22/24
UNOPS
Vertical Structures Unit

SUMMARY OF COMPONENT

Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010

Work Type
Total for General 0.00
Total for Site 0.00
Total for Structure 0.00
Total for Enclosure 0.00
Total for Interior 0.00
Total for Finish 0.00
Total for Water Supply Services 0.00
Total for Electrical Services 0.00

Total for Police Office Building 0.00


UNOPS
Vertical Structures Unit
SUMMARY BILL OF QUANTITIES

Currency: US Dollars

Project No: 810


Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan

Tender No: 04
Tender Title: Customs and Police Office Buildings
Original Issue: February 25, 2010

CONTRACT COMPONENTS
Total for Customs Office Building
Total for Police Office Building

BOQ Value for whole tender in words:


Zero

Agreed on behalf of Contractor UNOPS


Name Name

Position Position

Signature Signature

Address and
Mobile Number