Professional Documents
Culture Documents
voltage level.
Each level has many more pieces of equipment in it than the one above.
Both the nominal voltage level and the average capacity of equipment drops from level
to level, as one moves from generation to customer. /Transmission lines 115 kV - 765
kV and 50 MW- 2GW. Distribution feeders 2.2 kV - 34.5 kV and 2 and 35 MW/.
As a result, the net capacity of each level (number of units times average size)
increases as one moves toward the customer.
Definitions and nomenclature defining "transmission" and "distribution"
investment.
• Operating costs /continuous cost/ include labour and equipment for operation, maintenance
and service, taxes and fees, as well as the value of the power lost to electrical losses.
• Initial cost of equipment can always be traded against long-term losses
costs.
• Highly efficient transformers can be purchased to use considerably less power to
perform their function than standard designs. Larger conductors can be used in any
transmission or distribution line, which will lower impedance and thus losses for any
level of power delivery.
• But both examples here cost more money initially - the efficient transformer may
cost three times what a standard design does; the larger conductor might entail a
need for not only large wire, but heavier hardware to hold it in place and stronger
towers and poles to keep it in the air. In addition, these changes may produce
other costs - for example, use of larger conductor, have a higher fault duty (short
circuit current), which increases the required rating and cost for circuit breakers.
• The first involves deciding whether a present expense is justified because it cancels
• For planning purposes, the present worth factor should be regarded simply
as a value that sums up all the reasons why a company would prefer to
spend money tomorrow rather than today. It is a planning tool used to
evaluate and rank alternatives based on when they call for expenditures and
leads to prioritization of options.
Q.1.Suppose it has been determined
that a new substation must be built in
an area of the service territory which is
the site of much new customer growth.
Present needs can be met by
completing this new substation with
only one transformer, at a total initial
cost of $1,000,000. Alternatively, it
could be built with two transformers -
twice as much capacity - at a cost of
$1,800,000. Although not needed
immediately, this second transformer
Q.2. Suppose a new feeder is to be built along will be required within four years
because of continuing growth. If added
with the new substation. If built with 336 MCM
at that time, it will cost $1,284,000 - a
conductor at a cost of $437,000, the new
reflection of the additional start-up cost
feeder will be able to satisfy all loading, for a new project and of working at an
voltage drop, contingency, and other criteria. already-energized and in service
However, if built with 600 MCM conductor, at a substation rather than at a "cold" site.
total cost of $597,000, it will lower annual Which plan is best? Should planners
losses costs every year in the future by an recommend that the utility spend
estimated $27,000. Are the planners justified $800,000 now to save $1,284,000 four
in recommending that $160,000 be spent on years from now? Present worth factor
the larger, based on the long term continuing = 0.83, 0.9
savings? Present worth factor = 0.83, 0.9
• Adding 1% - or whatever is appropriate based on analysis of the
uncertainty and the planning method being used - to the PWF biases all
planning decisions so that they reflect this imperfection of planning.
period – for example the seven-year period during which the schedule of
transformer installations may vary - planners or budget administrators
often wish to look at a new addition to the system over the period in
which it will be in service or be financed.
Cost to deliver power varies
depending on location within a power
system. Variations are both due to
"natural" reasons - it is difficult to
deliver power to some locations like
the tops of mountains, etc., and due
to "system characteristic" reasons: no
matter how a delivery system is laid
out, some consumers will be close to
a substation and others will be
farther away from it. In some sense,
those farthest from it are most
expensive to serve, those closest to it
less expensive to serve. One must
bear in mind that traditional and
established regulatory opinion holds
that such variations do not
automatically justify proportional
pricing of electric service.
• All cost evaluation for power delivery planning should be based upon
economic evaluation that is consistent over the range of all alternatives.
Usually, this means that present and future costs must be compared.
Present worth analysis, life time levellized costing, or some similar
method of putting present and future value on a comparable basis will
be used.
• One complication in determining the most economical equipment for a
power system is that its various levels — transmission, substation, and
distribution – are interconnected, with the distribution, in turn, connected
to the customers.
• This means that the best size and equipment type at each level and
location in the system is a function not only of the local load, but of the
types of equipment selected for the other levels of the system nearby,
their locations and characteristics, as well as the loads they serve.
• Two Q method: A complication of modern, non-traditional distribution
planning is that reliability is often a key design element. Planners are
challenged to reduce overall cost while achieving designs that achieve
targets for both capacity and reliability.
• Planning methods and concepts that deal simultaneously with a
distribution system's quantity (demand and capacity) and quality
(continuity of sufficient service - reliability) are labelled as Two-Q
methods.
• Hence, the essence of Two-Q planning is to add
• This means they plan and design systems to numerical reliability targets
while another peaks at 21 kVA between 7:53 AM and 8:06 AM, while another peaks at 23
kVA between 9:54 AM and 10:02 AM. These individual peaks are not additive
because they occur at different times. The individual peaks, all quite short, do not all
occur simultaneously.
• Peak load per customer drops as more customers are added to a group. Each
household has a brief, but very high, peak load - up to 22 kW in this example for
a southern utility with heavy air-conditioning loads.
• This tendency of observed peak load per customer to drop as the size of the
Load forecasts are the starting point for the entire chain of power delivery.
Planners require a load forecast before they can set an optimal dispatch.
The load forecast must be of sufficient detail to provide necessary
information to the dispatch model.
Usually all the needed load data is not available directly and the load
factors influencing the customer’s load. The most important factors are:
Population: overall residential demand and also commercial and industrial activity
increase with increasing population.
• Weather parameters: it follows seasonal and daily patterns, which coupled with
temporal behaviour impact on residential, commercial and industrial load. This
includes temperature, humidity, sunshine and cloudiness, etc.
given time interval. There are daily, weekly, and seasonal load patterns.
• Load predictions are made over different time horizons. Based on this,
• Load can be forecasted but is uncertain over the planning horizon. Mid-
term plans must be set to meet many possible outcomes for the load, so
planners must develop more than a single load forecast depending
weather condition, population growth, etc.
• It also optimizes dispatch costs over a time horizon ranging between 1
month and 3 years. A complete description of the load and supply
outlook is necessary.
• Mid-term planning address issue related to maintenance scheduling for
both generation and transmission, use of energy-limited resources, and
capacity contracting with other utilities.
• One aspect of midterm utility planning is support of decision making for
capacity transaction. The first step is to design a data set that determines
a capacity price and an associated energy price for interutility
transactions.
• In short, midterm planning is the decision to include or exclude a
resource from a utility’s capacity base in accordance with maintenance
requirements, weather and environmental limitations, or the price and
availability of capacity with in a network of utilities.
Long-term load forecasting and utility planning: is required for planning
requirements.
also critical for contingency planning. Actual demands may vary from
baseline forecast, and planning must address this contingency.
1.4 POWER QUALITY AND RELIABILITY
• Perfect power quality is characterized by a perfect sinusoidal voltage
• On the other hand, a utility could spend as little money as possible and
cost and the level of power quality provided to customers. Concerns arise
when power quality levels do not meet equipment power quality needs.
• Distribution reliability primarily relates to equipment outages and
customer interruptions. In normal operating conditions, all equipment
(except standby) is energized and all customers are energized.
Where fv is the fixed cost at voltage V, sv is the slop of the cost in the linear range, F is the total
length of feeder routing (F=A*r), dss is the avergage distance b/n substations , A is area served, L
is load served(L=A*M), M= load density(MW/mile sq.), r = feeder route density (mile/mile sq.)
• The required reach for feeders in a distribution system will be roughly .75
times the substation spacing.
• Cost of the feeder system on a per
MW basis increases linearly up to the
maximum economical each of the prim-
ary voltage being used, then increases
exponentially. Shown here is the cost
per MW of a 12.47kV feeder system.
• Cost per MW of the combined sub-
transmission-substation-feeder system,
as a function of substation size and
spacing. Dotted line represents the cost,
assuming that planners can choose the
best sub-transmission voltage (dotted
line) appropriate to the spacing.
Solid line represents the cost with 138 kV
sub-transmission.
• The optimal spacing of 4.56 miles results because it is the best
• Each substation area consists of the part of the service territory that the
substation serves, its area covered by the feeder system emanating from
its low-side buses.
• For any existing or planned substation, there is a best location for it in the
• Occasionally, these two locations are identical, but usually they are
• The optimal location for a substation from the cost standpoint is almost
never the lowest cost site (i.e., cheapest land), but is instead the best
overall compromise between all the cost elements involved in the
substation - land cost, site preparation cost, cost of getting transmission
in and feeders out, and proximity to the loads it is intended to serve.
• The perpendicular bisector rule of identifying a substation service area
identifies the set of all points equidistant between a proposed substation
and its already existing neighbours. A line is drawn from the substation to
each of its neighbours (dotted lines) and bisected with a perpendicular
line (solid lines). Points inside this boundary are designated as served by
the proposed substation.
• While simple, this method in one form or another was used to lay out a
majority of substations currently in use worldwide.
• Modem substation sitting computer programs use accurate analytical
approaches that build upon the concept's guiding rule: serve load from
the nearest substation.
• Serving each customer from the nearest substation assures that the
while still being required to serve the hexagonal (shaded) area identified as its
service territory in that figure (i.e., that area's boundaries and territory will not
change).
• Moving this substation would have little impact on the sub-transmission costs
(the new site is along the same transmission corridor) or the substation itself
(the same exact substation would be built to serve the same load, assuming
the new site costs no more or less than the old site). The major cost impact
affected by this change in location would be on the feeder system. The new
site means the substation is closer to some loads (those to the west), and
farther from others (those on the east side of its service territory).
MW mile load density length of edge distance moved
2
its theoretical optimum location, they should make whatever adjustments they
could to the rest of the system layout in order to reduce the cost impact as
much as possible.
• One option is to change the service area of the substation and its neighbours,
rather than leave them fixed, as was the case considered above.
• The substation in the figure is moved one mile west, and its
service area boundaries are "re-optimized" to minimize overall
impact on the feeder system, slightly changing substation service
area shape (but not its area, although the areas of its neighbours
do change). All substation boundaries in this system satisfy the
perpendicular bisector rule, optimal in a situation where load
density is uniform and there are no geographic constraints.
• Readjusting substation boundaries when the site must be moved will usually
2. Small deviations (less than 1/3 mile) in the actual substation site from the
center feeder cost create insubstantial cost increases. (A 1/3 mile difference
in the previous condition carries a cost impact of $37,000, less than 1% of
the substation's cost and less than .2% of the sub-transmission-substation-
feeder cost.)
3. Large deviations in actual site location from the center of feeder cost are
very expensive - moving the substation in the previous example 1.2 miles
(6,400 feet) costs $1,000,000.
4. Whenever non-optimal sites must be accepted, planners should re-plan the
associated service area boundaries and feeder network for the substation
and its neighbours.
6. T&D systems with higher primary voltage are less sensitive to deviations in
their substation location.
7. T&D systems with higher load density are ore sensitive to deviations in their
substation locations.
2.3 Effect of Changing load density
• When density is doubled, a substation whose capacity was previously sufficient
to serve an X mile radius around It now can serve only an X/1.41 radius. The
same radius as before can
associated equipment.
density of the plan is raised, a lower one when density is reduced. When
density is doubled, optimum sub-transmission voltage will rise by 41%: Making
this increase gains the capability to serve the same number of substations per
transmission circuit.
• Increasing the load density changes the
relative economics of the various levels of
the system in favour of a slightly smaller
substation spacing with a slightly larger
substation size.
spacing diagram (at the base example system density of 3.25 MW/mile2). The
curve for a 25 kV feeder system is plotted along with that for 12.47 kV.
• The vast majority of line segments in a feeder system are very lightly loaded.
kV. Now, the curves cross at just over two miles substation spacing,
instead of at eight miles, as at 3.25 MW/mile2.
• For any substation spacing beyond two miles, the higher primary voltage
• The 25 kV voltage is now more economical than 12.47 kV for all but very
• The cost behaviour shown here is representative of all but very rare,
• Low price, short and certain delivery and low cost financing are
also major factors leading to the success of the project from both
the client’s and contractor’s point of view.
3.1 Project Evaluation
• The electricity supply company must satisfy demand for power by the
ii. Payback: to allow for the timing of returns from the project the payback method of
assessment may be used. This is a simple project financial appraisal method which
indicates how many years it will take before the original amount invested in the
project is ‘paid back’ – i.e, the time before cumulative return exceed the initial
investment with, generally the shorter the period the better.
iii. Discounted cash flow: In order to forecast and analyse better a particular project
investment more information about both the amounts of cash generated and the
timing involved is required. Having said this no method of analysis gives a precise
answer or avoids the risks involved. The timing assumed in the analysis may not be
correct, the forecasted cash quantities may be inaccurate, the opportunity cost of
capital may vary as interest rates and tax regimes change during the life of the project
and non-financial aspects (cost benefit analysis, political upheaval, etc.) all need to be
considered.
iv. Sensitivity analysis: Obviously the end result of any such financial analysis can only
be as good as the input data and original assumptions. Such items as interest rates,
cost of materials, exchange rates and inflation may all change during the life of the
project and have an effect on the viability of the project. For the more sophisticated
analysis the sensitivity of the results to such changes are considered.
chopping down trees for fuel (thereby saving the environment from soil
erosion) and allow greater productivity in the community.
• generally a three stage process. First, the scheme has to be shown to be the
resource saving, superior quality energy supplies, extra output) and the
difficulties.
3.2 Financing
• Borrowing money on the open market is expensive and so both client and
• Sources of finance for a project may be internal to the client and taken out
are important:
1. Sufficient advance payments to the contractor should be considered. The purpose of
such payments is to cover contract ‘front end’ expenditure such as mobilization, early
engineering work, payments to subcontractors, commission and insurances. Typically,
such advances will be of the order of 10% of the contract value.
2. Progress payments to the main contractor on a regular basis related to the value of
work actually achieved. These should not normally be related to payments made by
the main contractor to the subcontractors. An independent valuation by respectable,
professional and independent quantity surveyors or consulting engineers on behalf of
the client assists in reducing client/contractor disputes.
3. Progress payments linked to the timely completion of specific defined parts of the
works or milestones. These must be capable of easy definition and measurement.
4. Retentions kept by the client from interim progress payments during the course of the
contract. The purpose of these is to act as an incentive for the contractor to finish the
works.
5. Insurance bonds or bank guarantees to be provided by the contractor and held by an
independent bank as surety that the contractor will complete the works.
3.3 Project Phases
• A project is the process of creating a specific result. Infrastructure
transmission and distribution development projects all tend to follow the
same general phases as shown in figure below.
• The concept and planning stages will require the type of financial and
economic evaluation together with finance resourcing as detailed in
previous section.
• In a ‘fast track’ project, where the client requires very fast completion
the consulting engineer has specific duties and powers under the terms
and conditions of the client/contractor contract and is able to instruct the
contractor to perform during the course of the works. The arrangement is
shown in figure below.
• The consulting engineer is often brought in by the client at an early stage in
the project life cycle to carry out the technical system studies. The engineer
may advise the client on the best form of contract for the particular work to
be performed.
• The engineer may also assist or complete the financial and economic
project evaluation and prepare the project outline design. This work is then
converted into a tender document. The engineer will then supervise the
issue of tenders and produce an independent tender adjudication from
which the most appropriate contractor is selected to carry out the works.
• Typically, the engineer will check
• It is not necessary always to accept the lowest bid price since the bid may
not be technically compliant and may not have met the commercial
conditions required.
• Therefore it must be made clear at the tender stage what tender evaluation
• Each section is then broken down into criteria which are considered
and expertise necessary to complete the project and bring it on line. The
process proceeds from ordering supplies and materials through
construction, initial testing and final testing.
• Typically, a utility does not use its own personnel for actual construction
• Note that the least expensive way to supply the generation is not with all three units
running, or even any combination involving two units. Rather, the optimum commitment
is to only run unit 1, the most economic unit.
• Suppose the load follows a simple “peak-valley’’ pattern as shown in
decided that when load is above 1000 MW, run all three units; between
1000 MW and 600 MW, run units 1 and 2; below 600 MW, run only unit 1.
• So far, we have only obeyed one simple constraint: Enough units will be
committed to supply the loud. If this were all that was involved in the unit
commitment problem-that is, just meeting the load-we could stop here
and state that the problem was “solved.” Unfortunately, other constraints
and other phenomena must be taken into account in order to claim an
optimum solution. These are spinning reserve, thermal unit constraints
and hydro-constraints.
4.2 Spinning Reserve
• Spinning reserve is the term used to describe the total amount of
generation available from all present load and losses being supplied.
Spinning reserve must be carried so that the loss of one or more units
does not cause too far a drop in system frequency. Quite simply, if one
unit is lost, there must be ample reserve on the other units to make up
for the loss in a specified time period.
• Spinning reserve must be allocated to obey certain rules, usually set by
regional reliability councils (in the United States) that specify how the
reserve is to be allocated to various units.
• The priority list could be obtained in a much simpler manner by noting the
full-load average production cost of each unit, where the full-load average
production cost is simply the net heat rate at full load multiplied by the
fuel cost.
• The average production cost of the units given in the previous example is
• and the commitment scheme would (ignoring min up/down time, start-up
operate
i. At each hour when load is dropping, determine whether dropping the next unit on
the priority list will leave sufficient generation to supply the load plus spinning-reserve
requirements.
ii. Determine the number of hours, H, before the unit will be needed again. That is,
assuming that the load is dropping and will then go back up some hours later.
• If H is less than the minimum shut-down time for the unit, keep commitment as is
and go to last step; if not, go to next step.
• Calculate two costs. The first is the sum of the hourly production costs for the
next H hours with the unit up. Then recalculate the same sum for the unit down and
add in the start-up cost for either cooling the unit or banking it, whichever is less
expensive. If there is sufficient savings from shutting down the unit, it should be shut
down, otherwise keep it on.
iii. Repeat this entire procedure for the next unit on the priority list.
End
Thank You