You are on page 1of 14

Trench Cutter Case Histories and Their

Possible Application for Offshore Piles as


Relieve Drilling

Giovanni Spagnoli, Arthur Bi &


Leonhard Weixler

Geotechnical and Geological


Engineering
An International Journal

ISSN 0960-3182
Volume 32
Number 3

Geotech Geol Eng (2014) 32:713-724


DOI 10.1007/s10706-014-9747-6

1 23
Your article is protected by copyright and
all rights are held exclusively by Springer
International Publishing Switzerland. This e-
offprint is for personal use only and shall not
be self-archived in electronic repositories. If
you wish to self-archive your article, please
use the accepted manuscript version for
posting on your own website. You may
further deposit the accepted manuscript
version in any repository, provided it is only
made publicly available 12 months after
official publication or later and provided
acknowledgement is given to the original
source of publication and a link is inserted
to the published article on Springer's
website. The link must be accompanied by
the following text: "The final publication is
available at link.springer.com”.

1 23
Author's personal copy
Geotech Geol Eng (2014) 32:713–724
DOI 10.1007/s10706-014-9747-6

TECHNICAL NOTE

Trench Cutter Case Histories and Their Possible


Application for Offshore Piles as Relieve Drilling
Giovanni Spagnoli • Arthur Bi •

Leonhard Weixler

Received: 23 December 2013 / Accepted: 15 March 2014 / Published online: 1 April 2014
 Springer International Publishing Switzerland 2014

Abstract As of 30th June 2013, according to the data for future projects in similar geological condi-
European Wind Energy Association, there are 1,939 tions. The findings of this paper want to show how the
offshore wind turbines, with a combined capacity of trench cutter technology might be a suitable technol-
6,040 MW. They are fully grid connected in European ogy for supporting monopile installation in difficult
waters in 58 wind farms across 10 countries. About sea beds. Besides, the information contained in this
70 % of the foundations used for wind energy are manuscript wants to be an aid for contractors involved
monopiles with a diameter up to 6 m. The monopiles in offshore pile installation.
are installed by using hammers. However, there are
situations where the piles cannot be installed without Keywords Offshore wind  Monopiles 
the ‘‘driving and drilling technique’’, above all in the Trench cutter  Performance  Uniaxial
glacial areas, where glacial tills, boulders or cobbles compressive strength
can be encountered. A new technology for supporting
the installation of monopiles is the monopile-trench
cutter. The following paper describes four onshore
trench cutter case histories in hard geology. Based on 1 Introduction
several projects, a correlation between net cut perfor-
mance and uniaxial compressive strength (UCS) According to EWEA (2013a), in the first 6 months of
values of the in situ rock is briefly described. The 2013, Europe fully grid connected 277 offshore wind
variation of the cut performance decreases logarith- turbines—up 145 from the same period last year
mically with increasing UCS values. However, the (Spagnoli and Weixler 2013a)—with a combined
data showed are only based on projects already capacity totalling over 1 GW in seven wind farms, i.e.
performed, and it is not possible to extrapolate the Thornton Bank (Belgium), Gunfleet Sands 3, Lincs,
London Array, Teesside (UK), Anholt (Denmark),
BARD offshore 1 (Germany). 268 foundations were
G. Spagnoli (&)  L. Weixler
installed in ten wind farms: i.e., NorthWind (Bel-
Department of Maritime Technologies, BAUER
Maschinen GmbH, BAUER-Str. 1, gium), Gwynt y Môr, West of Duddon Sands (UK),
86529 Schrobenhausen, Germany BARD offshore 1, Dan Tysk, MeerWind, Nordsee
e-mail: giovanni.spagnoli@bauer.de Ost, Global Tech 1, Trianel (Germany), Arinaga Quay
(Spain). As of 30th June 2013, there are in total 1,939
A. Bi
BAUER Technologies Far East Pte. Ltd., 30, Tuas offshore wind turbines with a combined capacity of
Avenue 11, Singapore 639108, Singapore 6,040 MW fully grid connected in European waters in

123
Author's personal copy
714 Geotech Geol Eng (2014) 32:713–724

58 wind farms across 10 countries. According to sequence are relatively long—for example, the con-
EWEA (2013b), monopile substructures remained the struction of monopiles as part of the North Hoyle wind
most popular substructure type with 355 installations farm in the United Kingdom in 2003 required
(73 %) in 2012. 1,376 monopiles foundations were approximately 70–90 h on average (Malhotra
fully installed at the end of 2012 as a cumulative value 2011)—sometimes the ‘‘drilling-and-driving’’ is the
(74 % of all installed foundations). Monopiles are only solution. For instance, the North and Baltic Sea
large diameter, thick walled, steel tubulars that are are regions where glacial till, boulders and cobbles are
driven (hammered) or drilled (or both) into the seabed. found, due to the several advances and retreats of
Outer diameters usually range from 4 to 6 m, and continental ice sheets during the Pleistocene. Subsea
typically 40–50 % of the pile is inserted into the soils in the North Sea to a depth of 150 m often consist
seabed. The thickness and the depth the piling is entirely of glacial deposits. Glacial tills are character-
driven depend on the design load, soil conditions (for ized for having cu values up to 350 kPa, which may be
instance, in soft soil regions deeper piles and thicker considerably greater at depth in, for instance, North
steel are required), water depth, environmental condi- Sea deposits. In fact, Strandgaard and Vandenbulcke
tions, and design codes. Monopiles are currently the (2002) assumed for the Samsø Wind Farm cu values
most common foundation in shallow water (up to for the clay till in the order of 700 kPa. Glacial tills are
25 m) development (DNV 2013) due to their lower also characterized by low plasticity and deformation
cost and simplicity. However, since they are limited by modulus between 10 (loose state) and 1,440 (dense
depth and subsurface conditions, they are likely to state) MPa (Weltman and Healy 1978; Bowles 2001).
decline in popularity in deeper water. However, in When the pile is driven to great penetration or when it
nascent markets such as the U.S., and for the near-term encounters a stronger material such glacial till, the pile
future, monopiles are expected to be heavily employed may plug, so that the soil inside the pile moves with the
(Kaiser and Snyder 2012). Pile driving is more pile as it moves downward. The soil plug needs to be
efficient and less expensive than drilling. If possible, removed down to within a diameter of the pile tip,
piles should be driven to their full design penetration balancing this against the danger of upheaval failure of
without the need to clean out the soil plug or drill the remaining soil plug (Randolph et al. 2005).
below the initial refusal level of an open-ended tubular The main objective of the geotechnical design for
pile. Such delays cause increased driving resistance driven monopile foundations is to select a foundation
due to setup (i.e. the increase of shaft friction). As part size that can develop the required axial capacity,
of a 280 million Euro EPC contract (Engineering, perform adequately under lateral loads without exces-
Procurement and Construction) to provide balance of sive deflection and rotation at mudline, and withstand
plant on the Belwind project (North Sea), Van Oord the installation stresses needed to penetrate the pile
sourced and installed 56 monopiles and transition without buckling the walls. A typical driven pile
pieces. The monopiles weighing between 300 and 500 design will require the prediction of: (1) Penetration
tons were installed from a floating crane. The mono- resistance with depth, (2) Depth to fixity under lateral
piles were driven around 35 m into the seabed, an loads, (3) Minimum required penetration depth for
operation which took approximately 3 h. The final fixity and axial capacity considerations, (4) Driveabil-
blows were around 12 times the force of the first ones. ity evaluation (Malhotra 2011). Driveability evalua-
Installation of the 56 monopiles was completed tions are a crucial part of the design process.
between September 2009 and February 2010 (Doug- Commercial computer programs based on wave
las-Westwood 2011). equation models enable the piling engineer to predict
driveability, optimize the selection of hammer, select
energy level which will not damage the pile, and
2 Pile Refusal ensure that the correct dolly and adapters are used.
However, according to McClelland and Reifel (1986),
There are many situations where piles cannot be it is difficult to predict when a pile will plug. During
driven to their full penetration without the need for continuous driving in clay, plugs can form due to soil
‘‘drilling-and-driving’’ techniques. Although installa- setup if driving ceases for several hours. Strandgaard
tion times for monopiles using this composite and Vandenbulcke (2002) also report for the Samsø

123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 715

driven in rock. Driving piles in rock might experience


refusal. According to Stevens et al. (1982), driving in
rock is no longer possible when the RQD is[50 %, the
recovery rate of the rock is[85 % and the UCS of the
formation is [5 MPa.
Cleaning out the soil plug is an effective way of
reducing the driving resistance, thus obtaining deep
penetration, because of the elimination of base resis-
tance. It is particularly advantageous for obtaining
deep penetration into coarse soils; e.g. to develop
uplift resistance, to avoid excessive settlement due to
vibration effects, or to reach rockhead. This is because
the base resistance in a coarse soil represents the major
proportion of the total resistance to the driving of the
pile. Removal of the soil plug is not particularly
effective for piles penetrating deeply into clays where
the base resistance is only a very small proportion of
the total resistance. Drilling out the soil within the pile
does not reduce the external shaft friction of the
surrounding clay (Tomlinson and Woodward 2007). A
Fig. 1 Interpretation of pile drivability. Curve 1 is the
estimated resistance to driving based on remolded side friction
sandy-soil plug, a plug of clay or weak broken rock
in clay, static side friction in sand and end bearing on pile wall; can be removed by lowering the trench cutter down the
curve 2 is the estimated resistance to driving based on remolded tube. Trench cutter performances in hard geology
side friction in clay, static side friction in sand and end bearing based on twenty-eight onshore projects and their
on whole pile area (plug); curve 3 is the computed ultimate
compressive capacity (modified after McClelland and Reifel
possible offshore use is analyzed for supporting
1986) monopile installation where boulders or hard soil
layers impede the proper pile installation.

Wind Farm difficulties to produce a driveability


design profile due to the glacial deposits. Weltman 3 Trench Cutter Technology
and Healy (1978) report several situations where
drilled piles were installed in glacial tills (e.g. Boggart In the excavation of shallow underground works in an
Pits, Heatons Canal Bridge, Ring O’Bells Canal urban environment using the ‘cut and cover’ method,
Bridge, Finger House Railway Bridge) with max cu the choice is often made to use concrete diaphragms in
at pile base ranging from 136 up to 365 kPa. order to support the side walls, before proceeding with
McClelland and Reifel (1986) showed in Fig. 1 that the excavation of the ground. When these diaphragms
between the estimated resistance to driving after a long exceed a depth of about 20 m, trench cutters are
delay in the driving and the estimated resistance generally used to excavate the panels, using a supply
during continuous driving without estimated plugs, the of bentonite mud (Cardu and Oreste 2013).
pile driveability is less definitive because the penetra- The trench cutter (Fig. 2) is an excavating machine
tion to which the pile can be driven may depend on that operates on the principles of reverse circulation. It
factors that are not easily predictable. Besides, the is made up of a heavy steel frame with two gear boxes
Fig. 1 shows that the effect of the pile plugging on the at the bottom of the frame. Cutting wheel drums fitted
pile penetration is very significant, because this with a series of teeth are fixed to the gearboxes; they
indicates that the pile would reach refusal almost rotate in opposite directions, break up the soil and mix
immediately if it plugs after the tip enters the sand it with the bentonite suspension. As the cutter
layer found at a penetration of 72 m. penetrates, soil, rock and bentonite are conveyed
Hard driving may also be experienced if the pile towards the openings of the suction box, from where
encounters cobble layers, boulders or if the pile is they are pumped by a centrifugal pump through the

123
Author's personal copy
716 Geotech Geol Eng (2014) 32:713–724

into the trench or for storage and later reuse. The


torque output of the cutter wheels in combination with
the weight of the cutter is sufficient to cut into any type
of soil, to crush cobbles, small boulders or weak rock
and to over-cut concrete of adjacent panels as well.
The verticality of the trench cutter and thus the trench
alignment are measured on two axes by means of two
independent inclinometers. Adjustment of verticality
in the two directions is carried out by a system of
steering plates.
In order to absorb the impact caused by the crushing
of the boulders the drive gears are protected by elastic
shock absorbers, which are positioned between cutter
wheels and drive gears (Fig. 3).
The cutter wheels are equipped with long tooth
holders. They enable excavation in all types of soil,
including plastic clays. The cut produced by the teeth
covers the full width of the tooth holder. Depending on
soil type, different teeth can be deployed, ranging from
teeth for cutting soft soils to percussive teeth for
crushing boulders. In order to prevent blockages in the
mud hose pipe, the openings of the suction box are
Fig. 2 Trench cutter system reduced by half the diameter of the hose pipe. The
performance and output of a cutter is crucially
dependent on the crowd force V characterized by the
slurry pipe incorporated in the cutter’s frame, via the cutter’s weight and the torque H delivered by the cutter
mast head into the slurry conveying system to the de- wheels. Both of these components mutually influence
sanding plant. There solid soil and rock particles are each other. Although, in the case of a high H/V ratio,
separated from liquid bentonite which is pumped back the available torque may be adequate, the teeth simply

Fig. 3 Cutter head with components

123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 717

pressure required by the roller bits, the main cutter


frame is surcharged with additional ballast (Spagnoli
and Weixler 2013b) (Fig. 5).

4 Trench Cutter Case Histories

Four projects are described in detail. In addition, 28


more projects are listed below with information
regarding trench cutter performance, geology and
project country.
A project was carried out in China for the Laojie
station of the Shenzhen Metro, which is located at the
Eastern part of the Shenzhen urban area, where the
ground conditions presented soft soil on top and hard
granite at lower levels. The typical soil condition
consisted of three distinct layers of variable thickness,
comprising top soft soil, completely to highly decom-
Fig. 4 H/V ratio of the cutter teeth of a trench cutter. Sensitive posed granite and moderate decomposed granite
controls in respect of H and V forces allow excavation to be (Fig. 6).
continuously optimized The maximum uniaxial compressive strength
(UCS) of rock indicated by the site investigation was
scrape along the base of the trench without making any 138 MPa, with the ground water table at 2.5 m below
progress at all (Fig. 4). Alternatively, if the H/V ratio the ground surface. The diaphragm wall toe level was
drops too low, then the teeth bite too hard into the designed to penetrate the lower hard rock layer. For
ground and cause the cutter wheel to stop. the diaphragm walls—used as a part of permanent
The standard set of cutter wheels is equipped with structures—a special type of joint system was
tungsten carbide-tipped teeth. They are inserted into designed for this project, also in order to obtain better
long teeth holders and can easily be replaced. Ejector resistance to lateral forces induced by an earthquake.
plates, attached to the suction box, remove any spoil After the construction of a primary panel, the
between the tooth holders, particularly in cohesive reinforcement cage with the attached I-beam
soils. Standard cutter wheels are primarily used in (700 9 350 9 10 mm) was installed. The reinforcing
mixed soils. Based on the large number of available cage of the successive or secondary panel was lowered
cutter teeth with differently shaped tungsten carbide to provide an overlap at the joint. A typical full
tips, the available selection ranges from aggressive example is given in Table 1. The excavation process
cutter teeth through to impact teeth. Round shank in this specific site was the most consuming part in the
chisel-cutter wheels are equipped with special round whole process, above all in primary panels. Other
shank chisels. They are primarily deployed for cutting factors which influence the excavation time are:
in cemented sands, conglomerates, cobbles, and maintenance, bottom cleaning, recycling/desanding,
weathered rock. The gapless distribution of cutter steel cage installation, gravel backfill and concreting.
teeth across the entire cutter wheel ensures that the For the offshore use of the trench cutter inside the
whole area under the cutter wheel is cut away, making monopiles, the only time-consuming part is the
it impossible for the cutter wheel to ground. The roller excavation, as no cementing will be performed.
bit-cutter wheel has been developed for extremely Giving an exact percentage of the cutting time is
hard rock formations (UCS [120 MPa). The roller always subject to ground conditions and sometimes
bits are arranged on the wheel in such a way that the site activities/operation too. Therefore, it is hardly
entire rectangular cross section of the trench is cut. possible to give precise values. For excavating the top
The central ridge below the gear shield is removed by soft soil in the Laojie station to about 15 m a hydraulic
flipper teeth. To generate the right amount of crowd grab was adopted. A BC 25 cutter was selected due to

123
Author's personal copy
718 Geotech Geol Eng (2014) 32:713–724

Fig. 5 Different cutter teeth. a Standard teeth; b round shank chisel-cutter wheel; c roller bit-cutter wheel

Table 1 Panel excavation rate for the Laojie station job site
Description Primary panel Successive panel

Panel length (m) 5.0 4.4


Panel depth (m) 28.6 28.6
3
Excavation volume (m ) 160.2 100.7
Soil, by grab 84.0 52.8
Rock, by cutter 76.2 47.9
Excavation (h) 28.6 (69.25 %) 17.9 (61.08 %)
Soil, by grab 10.1 6.3
Rock, by cutter 18.5 11.6

supplementary soil investigation with rock strength


tests was carried out. It proved that the maximum rock
strength was up to 138 MPa, which is two times higher
than original data 67 MPa, and averaged 101.3 MPa.
To overcome this problem and also economic concern,
it was decided to use cutting wheels armored with
round shank chisel teeth and change 500 pump to 600 for
hard rock cutting. Under such modifications, the net
Fig. 6 Soil profile of the Laojie station
rock cutting performance successfully improved to an
average of 3 m3/h.
Another project with trench cutter technology was
the requirement of keying into the bedrock for about the Dhauliganga Dam. It is located in the state of
9.0 m, the demanding project program and the strict Uttarakhand at the border between India, Nepal and
requirement of verticality. Cutting wheels of 800 mm China. The dam was 56 m high. The crown length of
fitted with tungsten carbide teeth for rock up to the dam was 270 m. The dam axis was located at a
60 MPa UCS and cutting wheels 800 mm fitted with V-type valley with very steep side slopes. The bedrock
round shank chisel teeth for rock up to 120 MPa UCS is formed of biotite gneiss and gneiss with bands of
were used. mica schist with UCS values up to 60 MPa. The valley
Original soil data showed a maximum UCS of deposits were mainly fluvial deposits formed of sand
67 MPa, therefore cutting wheels armored with stan- and gravel (about 25 %) with some bands of marl type
dard tungsten carbide teeth were selected for rock layers. The main characteristic (about 75 %) however
cutting. Due to continuous equipment-/rock-related was the presence of boulders throughout the whole
problems and a very slow production (0.22–1.12 m3/h valley section. The boulders were found at any depth
in rock cutting) at the start of the project, a with a size ranging from 20 cm to 6 m with UCS

123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 719

and BC 40 rock cutter. The bite length of the


equipment was 2.8 m. The single bite solution was
selected because it had to be assumed that one panel
would have to stand open for a considerably long time.
The average net performance of the round shank chisel
wheels was 2.9 m3/h. Figure 8 shows a performance
analysis of two panels excavated with RSC and roller
bits. Figure 8a shows the use of RSC wheels from a
depth of about 30 m, reaching a cutting speed of
0.68 m/h for this panel. Figure 8b shows the use of
roller bits from a depth of about 35 m, reaching a
cutting speed of 0.64 m/h for this panel. The concern
was not only the control of trench verticality, but also
the UCS of boulder reached 120 MPa which is very
Fig. 7 Material excavated with the BC 40 for the Dhauliganga
project
difficult for RSC. When using roller bits cutter wheels,
which can handle the UCS up to 250 MPa, the
chiseling in principle is not required.
values ranging from 60 to 120 MPa (Beckhaus et al. For the Puclaro Dam (Chile) a vertical concrete
2009) (Fig. 7). barrier wall was constructed at the waterside dam foot
The diaphragm wall operations started in mid- as a diaphragm wall to a depth of 60 m with a total
January 2002, following a 2-month mobilization wall area of 16,500 m2. The top of the diaphragm was
period, and the last panel was finished in mid-March directly connected to the bottom of the inclined
2003, that is, 2 months ahead of the construction surface concrete slab. The construction of the dia-
schedule. The valley fill with gravel, sand and stones phragm wall at the Puclaro Dam project is a very good
was in reality very compact, because of glacial example which proves the technical and economic
overburden and due to seismic compaction. Therefore, feasibility of the diaphragm walling technology for
the amount of soil which had to be excavated by the forming a watertight cut-off wall even in very difficult
cutter was larger than initially planned. The key soil conditions. It also shows very clearly that such a
equipment was the trench cutter BC 40, equipped with task can only be performed when combining the merits
specially designed rock cutting wheels (round shank of various excavation technologies. The subsoil in the
chisel wheels), which can excavate into hard rock such valley was mainly consisting of alluvial sediments
as granite, basalt, gneiss. The first round shank chisel which were deposited in the eroded valley cut. The
wheels were developed for cutting in volcanic andesite first 15 m were composed by dense alluvial gravels
rocks with UCS values up to 200 MPa for the and cobbles with high permeability (k-values ranging
Shiokawa Dam Project in Japan. The main advantages from 10-2 to 10-4 m/s). Below 15 m heterogeneous
of the cutter BC 40 for the Dhauliganga Dam project strata consisting of very dense sands, gravels, cobbles
were: and boulders with lower permeability were found.
Figure 9 shows a boulder encountered in this job site.
• capacity to excavate a trench up to 70 m depth; The valley flanks consisted of hard rock (sandstone on
• forming of joints between primary and secondary one side and andesite with a compressive strength of
panels by overcutting; up to 180 MPa on the other side). They had an
• forming of rock socket in bedrock; inclination of up to 45 to a depth of 40 m towards the
• breaking of large boulders. valley center. The subsoil conditions were so complex
The cut-off wall was constructed as a series of that the use of one type of equipment only would not
primary and secondary panels with an overcutting have made it possible to construct a diaphragm wall as
ratio of 300 mm on each side. Excavation of the panels required in the specifications. The diaphragm wall was
is carried out in single bites by hydraulic diaphragm constructed with a combination of excavation
wall grabs, supported by the box chisel, cross chisel equipments.

123
Author's personal copy
720 Geotech Geol Eng (2014) 32:713–724

Fig. 8 a, b Performance
analysis of a panel
excavated during the
Dhauliganga project

The first 15 m were excavated by grabs because and is mounted on an 80 tons hydraulic crane and
bentonite losses in high permeable soil could be solved powered by a hydraulic unit with 630 kW. The trench
using a grab and adding just sand or using thick cutter was chosen because the creation of joints at
bentonite slurry into the trench during the excavation 60 m deep diaphragm wall panels could be resolved
process. For the lower part of the Puclaro Project a BC very well both technically and economically by
30 cutter was selected. It has a weight of about 40 tons cutting into the already concreted adjacent primary

123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 721

wide 9 6.5 m high tunnel. The excavated volume for


the Yeleh cut-off wall was about 19,000 m2 in very
dense sand, cobble and boulder formations.
Folk (2008) reports that the region contains glaciers
and abundant signs of glaciation. In this area the
Triassic strata are dominated by a succession of marine
clastic rocks, with subordinate carbonate rocks, and
basic to intermediate-basic volcanic rocks. Cretaceous
granite bodies of what in China is called the Yanshan
Orogeny intrude the Triassic strata. These granites
which contain anomalously high Bi and Be contents
are related to several mineral occurrences in the region
Fig. 9 Boulder encountered in the Puclaro Dam (Folk 2008). Typical geology of the area was exposed
quartz-feldspar rock face on the left bank and more
panels. Besides, the bottom of the cut-off wall had to than 200 m thick alluvium and lake deposit on the right
be keyed into the bedrock with a minimum of 50 cm at bank. Soil type consisted of sand and silt (40 %), basalt
any location. The steep dipping of the rock with 40 cobbles with dimensions ranging between 60 and
required a socket length of up to 3 m ensuring the 200 mm (ca. 35 %), gravel (20 %) and basalt boulders
minimum of 60 cm at any location. This requirement with diameters from 200 mm (5 %). The strength of
could only be fulfilled with a trench cutter which is boulders and cobbles was estimated to range between
equipped with roller bits. 100 and 160 MPa.
Brunner et al. (2011) report the use of a low The projects described above were chosen because
headroom trench cutter CBC25/MBC30 for cut-off their geologies are, in part, similar to the glacial
walls for a 240 MW Yeleh hydroelectric plant in the geologies of the North and Baltic Sea, where big
South of Sichuan province (Fig. 10). The foundation boulders and cobbles may jeopardize the pile driving
treatment included the construction of a 75 m deep process. Table 2 presents a list of projects, where rock
and 1 m thick concrete cut-off wall inside a 6 m type and UCS values are provided.

Fig. 10 Longitudinal section of cut-off system at Yeleh lower portion; 4 right bank curtain grouting; 5 river bed cut-off
hydropower plant axis. 1 Right bank cut-off wall upper portion wall; 6 left bank cut-off wall; 7 left bank curtain grouting; 8
with grouting joint to tunnel; 2 tunnel for construction of right tunnel for construction of left bank curtain grouting; 9
bank cut-off wall at lower portion; 3 right bank cut-off wall compacted asphalt concrete (after Brunner et al. 2011)

123
Author's personal copy
722 Geotech Geol Eng (2014) 32:713–724

Table 2 Project information based on job site results with


geology, UCS values and type of teeth
Country Rock UCS Teeth
(MPa)

Canada Granite 250 Roller


bits
Japan Andesite 250 Roller
bits
Japan Andesite 200 Roller
bits
Japan Andesite 150 Roller
bits
Japan Andesite 100 Roller
bits
Taiwan Quartz–sandstone 120 Roller
bits
Fig. 11 Correlation of the cutting performance with the UCS Austria Limestone 145 Roller
values of the rock in situ. The values shown in the diagram refer bits
to projects already performed. It is not expected the same exact Chile Andesite 140 Roller
performance in future projects in similar geological conditions bits
Singapore Granite 176 Roller
It is not possible to show the single performance due bits
to a contract agreement with contractors and custom- Singapore Granite 270 Roller
bits
ers. However, based on the results, it is possible to
Austria Quartz–phillite 120 Roller
observe how the trench cutter net performance
bits
decreases not linearly with UCS of the cut rocks, but
Canada Quartz–phillite 120 Roller
with a logarithmic path (coefficient of determination bits
R2 = 0.72) (Fig. 11). It is important to point out that Canada Granite/gneiss 170 RSC
the values shown are merely informative and they refer China Granite 138 RSC
to projects already carried out. For future projects, it is India Gneiss 120 RSC
not to be expected that the same performance can be China Granite 100 RSC
obtained in similar conditions. Trench cutter perfor- China Weathered tuff 30 RSC
mance depends not only on the UCS, but also on RQD India Quartz boulders 200 RSC
values, water content, state of the rock, type of rock,
Hong Kong Granite 150 RSC
presence and type of joints and type of teeth used for
Portugal Basalt 200 RSC
cutting the rock. Based on the results above, it is
South Granite/Gneiss 190 RSC
possible to state that the trench cutter technology Africa
might be suitable for being used as relieve drilling for Sudan Gneiss 110 RSC
big monopiles. Spagnoli and Weixler (2013b) describe Australia Basalt 250 RSC
the new technological development also based on the China Weathered conglomerate/ 40 Standard
use of trench cutter for offshore diamond exploration. sandstone
For the preparation for that project, cobbles of up to China Weathered mudstone 15 Standard
300 mm diameter were placed in the test pit and mixed China Weathered diorite 40 Standard
with steel bolts and nuts. The mixture was subse- Italy Limestone 100 Standard
quently excavated by a standard BC 30 cutter and Switzerland Granite 100 Standard
separated into its components by a screening plant.

123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 723

plug. The trench cutters are designed for depths (water


and soil) up to 250 m.
Current relieve drilling for offshore piles both for
oil & gas and renewable energy applications are
performed by the top drilling units. Because of the lack
of performance data and literature information is not
possible to make a direct comparison with the offshore
trench cutter technology. However, one of the pecu-
liarities of the top drilling unit is the addition of the
drilling rods which is time-consuming. The trench
cutter does not need any drill rod addition as it is a
continuos drilling method.
One possible way to use the trench cutter for
offshore projects when pile refusal is reached is:
1. Hammer is removed from the top of the pile;
2. Frame is introduced with the trench cutter in the
pile;
3. Drilling starts;
4. Spoil can be either discharged in situ as done for
the BSD3000 project for the EMEC turbine
(Spagnoli et al. 2013) or stored on the jack-up/
vessel for late disposal;
5. Once the problematic section is drilled out, the
trench cutter is removed and the hammer is put
Fig. 12 Sketch of the guide frame and trench cutter for monopile again on the top of the pile.
support; a the trench cutter with the special frame used for drilling
the plug out; b the guide frame from above within the monopile; Even though the trench cutter may be used both
c the trench cutter in the monopile for excavating boulders (mod-
from a turbine installation vessel (similar to the MPI
ified after Spagnoli and Weixler 2013b)
resolution) and from a DP vessel, which however will
increase the initial costs of installation, the crane used
The test clearly demonstrated that all types of cobbles for controlling the trench cutter must be designed for
could be broken down by the cutter wheels and even working in offshore conditions.
metal particles with a specific gravity of 7.8 g/cm3
could be lifted and conveyed by the mud pump
(Spagnoli and Weixler 2013b). 5 Conclusions
Once the problematic site inside the pile has been
reached the cutter tool is able to move in the two The paper showed four case histories of trench cutter
directions (± in the x direction) within the borehole by job sites in difficult geologies. Trench cutters are
means of a special guide frame with a weight of 30 normally used in the foundation engineering for
tons (Fig. 12). It is aimed at specifically cutting the excavating diaphragm walls in order to facilitate
erratics which impede the pile driving. Thanks to the certain construction activities, such as retaining walls,
special guide frame the trench cutter is also able to cut-off provisions to support deep excavation, final
rotate of ±90 within the borehole. The verticality of walls for basements or other underground structure
the trench cutter and thus the trench alignment are (e.g. tunnel and shaft). The excavation of diaphragm
measured on two axes by means of two independent walls depends very much on several factors such as the
inclinometers. Data provided by the inclinometers is UCS, RQD values, water content, state of the rock,
processed by a computer on-board the base carrier and type of rock and type of teeth used for cutting the rock.
displayed on-line. The trench cutter, together with the Currently offshore monopiles are installed by ham-
guide frame, might also be able to clean out the soil mering them into the sub-soils. However, driving-

123
Author's personal copy
724 Geotech Geol Eng (2014) 32:713–724

drilling technique might be used when the monopiles Cardu M, Oreste P (2013) Productivity and working costs of
are installed in glacial areas such as the North and modern trench-cutters for the construction of concrete
diaphragms in an urban environment. Int J Min Reclam
Baltic Sea, where boulders can be encountered. Environ. doi:10.1080/17480930.2013.795340
Twenty-eight projects were analyzed based on the Der Norske Veritas AS (2013) Design of offshore wind turbine
net trench cutter performance based on the UCS structures. Standard DNV-OS-J101
values. The relation shows that the cutter net perfor- Douglas-Westwood (2011) The world offshore wind market
forecast 2012–2016. DW report
mance decreases logarithmically for increasing UCS EWEA (2013a) The European offshore wind industry—key
of the cut rocks. The results are not universal and they trends and statistics 1st half 2013. European Wind Energy
cannot in any form be used for interpreting future job Association
site projects in similar geological conditions. EWEA (2013b) The European offshore wind industry—key
trends and statistics 2012. European Wind Energy
In the typical offshore wind projects, the water Association
depths for monopile installation are between 10 and Folk PG (2008) Report on the Lianlong Project. http://www.
30 m, which means that the hydrostatic pressure is tririver-venture.com/images/43-101ReportTriRiverVer4_
around 1–3 bar. Since the UCS of the rock is in the clean.pdf. Accessed 20 Feb 2014
Kaiser MJ, Snyder BF (2012) Offshore wind energy cost mod-
range of 100–300 MPa, the hydrostatic pressure will eling, green energy and technology. Springer, London
not have a significant influence on the cutting force. Malhotra S (2011) Selection, design and construction of off-
Therefore, the standard trench cutter could be used. shore wind turbine foundations. In: Al-Bahadly I (ed) Wind
Based on the results shown in the manuscript it is turbines. InTech, Vienna, pp 231–264
McClelland B, Reifel MD (1986) Planning and design of fixed
possible to state that offshore trench cutter technology offshore platforms. Van Nostrand Reinhold Company,
might be suitable for supporting monopile installa- New York
tions without any modification on the cutting wheels in Randolph M, Cassidy M, Gourvenec S, Erbrich C (2005)
the case where the piles are hammered in glacial Challenges of offshore geotechnical engineering. In: Pro-
ceedings of the international conference on soil mechanics
geology, and relieve drilling might be necessary. and geotechnical engineering, Osaka, Japan, A. A. Balk-
ema Publishers, vol 1, pp. 123–176
Acknowledgments The authors wish to thank BAUER Spagnoli G, Weixler L (2013a) Alternative offshore foundation
Maschinen GmbH for the permission to publish the data and installation methods. In: Proceedings of the offshore tech-
Ms. Englert-Dougherty for the legal revision of the text. Thanks nology conference, OTC 23962. doi:10.4043/23962-MS
also to the anonymous reviewers, who considerably improved Spagnoli G, Weixler L (2013b) Support for offshore monopile
the quality of the manuscript. installation through the trench cutter technology. Trans R
Inst Nav Archit Part A 155:131–140
Spagnoli G, Weixler L, Finkenzeller S (2013) Drilling tools for
installation of offshore wind foundations. Sea Technol
References 54:47–49
Stevens RS, Edward A, Turton TH (1982) Evaluating pile
Beckhaus K, Schmitz S, Schwarz W (2009) Deep cut-off walls drivability for hard clay, very dense sand, and rock. In:
constructed under dams with trench cutters. In: Bauer Proceedings of the offshore technology conference, OTC
E,Semprich S, Zenz G (eds) Long term behaviour of dams, 4205
LTBD09: Proceedings of the 2nd international confer- Strandgaard T, Vandenbulcke L (2002) Driving mono-piles into
ence,Technischen Universität Graz, pp. 294–299 glacial till. IBC’s Wind Power Europe
Bowles JE (2001) Foundation analysis and design. McGraw- Tomlinson M, Woodward J (2007) Pile design and construction
Hill, New York practice, 5th edn. CRC Press, Boca Raton
Brunner W, Bi A, Chang W, Zong DF (2011) Construction of Weltman AJ, Healy PR (1978) Piling in boulder clay and other
the first cut-off wall by a low headroom trench cutter inside glacial tills. Construction Industry Research & Information
a tunnel in China. In: Proceedings of the 31st annual USSD Association (CIRIA), London
conference San Diego, California, pp 663–674

123

You might also like