Professional Documents
Culture Documents
ISSN 0960-3182
Volume 32
Number 3
1 23
Your article is protected by copyright and
all rights are held exclusively by Springer
International Publishing Switzerland. This e-
offprint is for personal use only and shall not
be self-archived in electronic repositories. If
you wish to self-archive your article, please
use the accepted manuscript version for
posting on your own website. You may
further deposit the accepted manuscript
version in any repository, provided it is only
made publicly available 12 months after
official publication or later and provided
acknowledgement is given to the original
source of publication and a link is inserted
to the published article on Springer's
website. The link must be accompanied by
the following text: "The final publication is
available at link.springer.com”.
1 23
Author's personal copy
Geotech Geol Eng (2014) 32:713–724
DOI 10.1007/s10706-014-9747-6
TECHNICAL NOTE
Leonhard Weixler
Received: 23 December 2013 / Accepted: 15 March 2014 / Published online: 1 April 2014
Springer International Publishing Switzerland 2014
Abstract As of 30th June 2013, according to the data for future projects in similar geological condi-
European Wind Energy Association, there are 1,939 tions. The findings of this paper want to show how the
offshore wind turbines, with a combined capacity of trench cutter technology might be a suitable technol-
6,040 MW. They are fully grid connected in European ogy for supporting monopile installation in difficult
waters in 58 wind farms across 10 countries. About sea beds. Besides, the information contained in this
70 % of the foundations used for wind energy are manuscript wants to be an aid for contractors involved
monopiles with a diameter up to 6 m. The monopiles in offshore pile installation.
are installed by using hammers. However, there are
situations where the piles cannot be installed without Keywords Offshore wind Monopiles
the ‘‘driving and drilling technique’’, above all in the Trench cutter Performance Uniaxial
glacial areas, where glacial tills, boulders or cobbles compressive strength
can be encountered. A new technology for supporting
the installation of monopiles is the monopile-trench
cutter. The following paper describes four onshore
trench cutter case histories in hard geology. Based on 1 Introduction
several projects, a correlation between net cut perfor-
mance and uniaxial compressive strength (UCS) According to EWEA (2013a), in the first 6 months of
values of the in situ rock is briefly described. The 2013, Europe fully grid connected 277 offshore wind
variation of the cut performance decreases logarith- turbines—up 145 from the same period last year
mically with increasing UCS values. However, the (Spagnoli and Weixler 2013a)—with a combined
data showed are only based on projects already capacity totalling over 1 GW in seven wind farms, i.e.
performed, and it is not possible to extrapolate the Thornton Bank (Belgium), Gunfleet Sands 3, Lincs,
London Array, Teesside (UK), Anholt (Denmark),
BARD offshore 1 (Germany). 268 foundations were
G. Spagnoli (&) L. Weixler
installed in ten wind farms: i.e., NorthWind (Bel-
Department of Maritime Technologies, BAUER
Maschinen GmbH, BAUER-Str. 1, gium), Gwynt y Môr, West of Duddon Sands (UK),
86529 Schrobenhausen, Germany BARD offshore 1, Dan Tysk, MeerWind, Nordsee
e-mail: giovanni.spagnoli@bauer.de Ost, Global Tech 1, Trianel (Germany), Arinaga Quay
(Spain). As of 30th June 2013, there are in total 1,939
A. Bi
BAUER Technologies Far East Pte. Ltd., 30, Tuas offshore wind turbines with a combined capacity of
Avenue 11, Singapore 639108, Singapore 6,040 MW fully grid connected in European waters in
123
Author's personal copy
714 Geotech Geol Eng (2014) 32:713–724
58 wind farms across 10 countries. According to sequence are relatively long—for example, the con-
EWEA (2013b), monopile substructures remained the struction of monopiles as part of the North Hoyle wind
most popular substructure type with 355 installations farm in the United Kingdom in 2003 required
(73 %) in 2012. 1,376 monopiles foundations were approximately 70–90 h on average (Malhotra
fully installed at the end of 2012 as a cumulative value 2011)—sometimes the ‘‘drilling-and-driving’’ is the
(74 % of all installed foundations). Monopiles are only solution. For instance, the North and Baltic Sea
large diameter, thick walled, steel tubulars that are are regions where glacial till, boulders and cobbles are
driven (hammered) or drilled (or both) into the seabed. found, due to the several advances and retreats of
Outer diameters usually range from 4 to 6 m, and continental ice sheets during the Pleistocene. Subsea
typically 40–50 % of the pile is inserted into the soils in the North Sea to a depth of 150 m often consist
seabed. The thickness and the depth the piling is entirely of glacial deposits. Glacial tills are character-
driven depend on the design load, soil conditions (for ized for having cu values up to 350 kPa, which may be
instance, in soft soil regions deeper piles and thicker considerably greater at depth in, for instance, North
steel are required), water depth, environmental condi- Sea deposits. In fact, Strandgaard and Vandenbulcke
tions, and design codes. Monopiles are currently the (2002) assumed for the Samsø Wind Farm cu values
most common foundation in shallow water (up to for the clay till in the order of 700 kPa. Glacial tills are
25 m) development (DNV 2013) due to their lower also characterized by low plasticity and deformation
cost and simplicity. However, since they are limited by modulus between 10 (loose state) and 1,440 (dense
depth and subsurface conditions, they are likely to state) MPa (Weltman and Healy 1978; Bowles 2001).
decline in popularity in deeper water. However, in When the pile is driven to great penetration or when it
nascent markets such as the U.S., and for the near-term encounters a stronger material such glacial till, the pile
future, monopiles are expected to be heavily employed may plug, so that the soil inside the pile moves with the
(Kaiser and Snyder 2012). Pile driving is more pile as it moves downward. The soil plug needs to be
efficient and less expensive than drilling. If possible, removed down to within a diameter of the pile tip,
piles should be driven to their full design penetration balancing this against the danger of upheaval failure of
without the need to clean out the soil plug or drill the remaining soil plug (Randolph et al. 2005).
below the initial refusal level of an open-ended tubular The main objective of the geotechnical design for
pile. Such delays cause increased driving resistance driven monopile foundations is to select a foundation
due to setup (i.e. the increase of shaft friction). As part size that can develop the required axial capacity,
of a 280 million Euro EPC contract (Engineering, perform adequately under lateral loads without exces-
Procurement and Construction) to provide balance of sive deflection and rotation at mudline, and withstand
plant on the Belwind project (North Sea), Van Oord the installation stresses needed to penetrate the pile
sourced and installed 56 monopiles and transition without buckling the walls. A typical driven pile
pieces. The monopiles weighing between 300 and 500 design will require the prediction of: (1) Penetration
tons were installed from a floating crane. The mono- resistance with depth, (2) Depth to fixity under lateral
piles were driven around 35 m into the seabed, an loads, (3) Minimum required penetration depth for
operation which took approximately 3 h. The final fixity and axial capacity considerations, (4) Driveabil-
blows were around 12 times the force of the first ones. ity evaluation (Malhotra 2011). Driveability evalua-
Installation of the 56 monopiles was completed tions are a crucial part of the design process.
between September 2009 and February 2010 (Doug- Commercial computer programs based on wave
las-Westwood 2011). equation models enable the piling engineer to predict
driveability, optimize the selection of hammer, select
energy level which will not damage the pile, and
2 Pile Refusal ensure that the correct dolly and adapters are used.
However, according to McClelland and Reifel (1986),
There are many situations where piles cannot be it is difficult to predict when a pile will plug. During
driven to their full penetration without the need for continuous driving in clay, plugs can form due to soil
‘‘drilling-and-driving’’ techniques. Although installa- setup if driving ceases for several hours. Strandgaard
tion times for monopiles using this composite and Vandenbulcke (2002) also report for the Samsø
123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 715
123
Author's personal copy
716 Geotech Geol Eng (2014) 32:713–724
123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 717
123
Author's personal copy
718 Geotech Geol Eng (2014) 32:713–724
Fig. 5 Different cutter teeth. a Standard teeth; b round shank chisel-cutter wheel; c roller bit-cutter wheel
Table 1 Panel excavation rate for the Laojie station job site
Description Primary panel Successive panel
123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 719
123
Author's personal copy
720 Geotech Geol Eng (2014) 32:713–724
Fig. 8 a, b Performance
analysis of a panel
excavated during the
Dhauliganga project
The first 15 m were excavated by grabs because and is mounted on an 80 tons hydraulic crane and
bentonite losses in high permeable soil could be solved powered by a hydraulic unit with 630 kW. The trench
using a grab and adding just sand or using thick cutter was chosen because the creation of joints at
bentonite slurry into the trench during the excavation 60 m deep diaphragm wall panels could be resolved
process. For the lower part of the Puclaro Project a BC very well both technically and economically by
30 cutter was selected. It has a weight of about 40 tons cutting into the already concreted adjacent primary
123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 721
Fig. 10 Longitudinal section of cut-off system at Yeleh lower portion; 4 right bank curtain grouting; 5 river bed cut-off
hydropower plant axis. 1 Right bank cut-off wall upper portion wall; 6 left bank cut-off wall; 7 left bank curtain grouting; 8
with grouting joint to tunnel; 2 tunnel for construction of right tunnel for construction of left bank curtain grouting; 9
bank cut-off wall at lower portion; 3 right bank cut-off wall compacted asphalt concrete (after Brunner et al. 2011)
123
Author's personal copy
722 Geotech Geol Eng (2014) 32:713–724
123
Author's personal copy
Geotech Geol Eng (2014) 32:713–724 723
123
Author's personal copy
724 Geotech Geol Eng (2014) 32:713–724
drilling technique might be used when the monopiles Cardu M, Oreste P (2013) Productivity and working costs of
are installed in glacial areas such as the North and modern trench-cutters for the construction of concrete
diaphragms in an urban environment. Int J Min Reclam
Baltic Sea, where boulders can be encountered. Environ. doi:10.1080/17480930.2013.795340
Twenty-eight projects were analyzed based on the Der Norske Veritas AS (2013) Design of offshore wind turbine
net trench cutter performance based on the UCS structures. Standard DNV-OS-J101
values. The relation shows that the cutter net perfor- Douglas-Westwood (2011) The world offshore wind market
forecast 2012–2016. DW report
mance decreases logarithmically for increasing UCS EWEA (2013a) The European offshore wind industry—key
of the cut rocks. The results are not universal and they trends and statistics 1st half 2013. European Wind Energy
cannot in any form be used for interpreting future job Association
site projects in similar geological conditions. EWEA (2013b) The European offshore wind industry—key
trends and statistics 2012. European Wind Energy
In the typical offshore wind projects, the water Association
depths for monopile installation are between 10 and Folk PG (2008) Report on the Lianlong Project. http://www.
30 m, which means that the hydrostatic pressure is tririver-venture.com/images/43-101ReportTriRiverVer4_
around 1–3 bar. Since the UCS of the rock is in the clean.pdf. Accessed 20 Feb 2014
Kaiser MJ, Snyder BF (2012) Offshore wind energy cost mod-
range of 100–300 MPa, the hydrostatic pressure will eling, green energy and technology. Springer, London
not have a significant influence on the cutting force. Malhotra S (2011) Selection, design and construction of off-
Therefore, the standard trench cutter could be used. shore wind turbine foundations. In: Al-Bahadly I (ed) Wind
Based on the results shown in the manuscript it is turbines. InTech, Vienna, pp 231–264
McClelland B, Reifel MD (1986) Planning and design of fixed
possible to state that offshore trench cutter technology offshore platforms. Van Nostrand Reinhold Company,
might be suitable for supporting monopile installa- New York
tions without any modification on the cutting wheels in Randolph M, Cassidy M, Gourvenec S, Erbrich C (2005)
the case where the piles are hammered in glacial Challenges of offshore geotechnical engineering. In: Pro-
ceedings of the international conference on soil mechanics
geology, and relieve drilling might be necessary. and geotechnical engineering, Osaka, Japan, A. A. Balk-
ema Publishers, vol 1, pp. 123–176
Acknowledgments The authors wish to thank BAUER Spagnoli G, Weixler L (2013a) Alternative offshore foundation
Maschinen GmbH for the permission to publish the data and installation methods. In: Proceedings of the offshore tech-
Ms. Englert-Dougherty for the legal revision of the text. Thanks nology conference, OTC 23962. doi:10.4043/23962-MS
also to the anonymous reviewers, who considerably improved Spagnoli G, Weixler L (2013b) Support for offshore monopile
the quality of the manuscript. installation through the trench cutter technology. Trans R
Inst Nav Archit Part A 155:131–140
Spagnoli G, Weixler L, Finkenzeller S (2013) Drilling tools for
installation of offshore wind foundations. Sea Technol
References 54:47–49
Stevens RS, Edward A, Turton TH (1982) Evaluating pile
Beckhaus K, Schmitz S, Schwarz W (2009) Deep cut-off walls drivability for hard clay, very dense sand, and rock. In:
constructed under dams with trench cutters. In: Bauer Proceedings of the offshore technology conference, OTC
E,Semprich S, Zenz G (eds) Long term behaviour of dams, 4205
LTBD09: Proceedings of the 2nd international confer- Strandgaard T, Vandenbulcke L (2002) Driving mono-piles into
ence,Technischen Universität Graz, pp. 294–299 glacial till. IBC’s Wind Power Europe
Bowles JE (2001) Foundation analysis and design. McGraw- Tomlinson M, Woodward J (2007) Pile design and construction
Hill, New York practice, 5th edn. CRC Press, Boca Raton
Brunner W, Bi A, Chang W, Zong DF (2011) Construction of Weltman AJ, Healy PR (1978) Piling in boulder clay and other
the first cut-off wall by a low headroom trench cutter inside glacial tills. Construction Industry Research & Information
a tunnel in China. In: Proceedings of the 31st annual USSD Association (CIRIA), London
conference San Diego, California, pp 663–674
123