Summary Basement

Sr. No. Item Quantity Rate Amount


1 Cement Bags 1292 510 658920
2 Sand (Cft) 3754 29 108857
3 Crush (cft) 6108 70 427566
4 Bricks 23283 11 256113
5 Steel (kg) 9975 130 1296750
6 Bitumen (Sft) 2943 25 73563
7 Polythene Sheet 2943 6 17655
8 WaterProofing Membrane (sft) 2500 45 112500
9 Septic Tank 1 75000 75000
10 Labor Rate 2646 400 1058400
11 Electrical Works including Labor 1 100000 100000
12 Plumbing Works including Labor 1 175000 175000
13 Termite Proofing 1 20000 20000
14 Tax 1 100000 100000
15 Contingencies/ Petrol/ Supervisor 1 200000 200000
16 Profit 2646 116 306936
TOTAL 4987260
Rate Per Sft 1885