Summary Super Structure

Sr. No. Item Quantity Rate Amount


1 Cement Ba 1275 510 650250
2 Sand (Cft) 5822 29 168835
3 Crush (cft) 3930 70 275119
4 Bricks 92708 11 1019788
5 Steel (kg) 8348 130 1085175
6 Roof Insula 1892 45 85140
7 OHWT 1 100000 100000
8 UGWT 1 100000 100000
9 Septic Tan 1 100000 100000
10 Labor Rate 4713 350 1649550
11 Electrical 1 140000 140000
12 Plumbing W 1 175000 175000
13 Tax 1 100000 100000
14 Contingenci 1 200000 200000
15 Profit 4713 194 914322
TOTAL 6763179
Rate Per Sft 1435
1435