RM-03
Project Name: Sun Shine Complex
Risk ID: EP10 Date Raised: 14-07-2020
Type: Risk Risk Timeline: Medium Term
Assessment Date: 29-06-2020 RBS Code: 1.3.1
RISK Details
Risk Description: Economical Policy
Changing government changes economic policies that have an impact on ongoing projects in terms of budgets
and costs
Impact
Probability Score Comments
Scope Schedule Cost Quality
4 2 2 4 4
RISK MITIGATION
APPROVAL
RISK Details
Risk Description: Availability
Due to current pandemic, there is less engagement of labor as many projects have stopped. So availability can
be an opportunity at this time
Impact
Probability Score Comments
Scope Schedule Cost Quality
3 2 3 1 3
RISK MITIGATION
APPROVAL
RISK Details
Risk Description: Seasonal Work
Due to wheat crop harvesting and during Islamic eves unskilled labor is rarely available for construction
projects
Impact
Probability Score Comments
Scope Schedule Cost Quality
5 4 4.5
RISK MITIGATION
APPROVAL
RISK Details
Risk Description: Funding
Due to changing economic conditions, funding can be risk to the project
Impact
Probability Score Comments
Scope Schedule Cost Quality
4 3 3 3.5
RISK MITIGATION
APPROVAL
RISK Details
Risk Description: Inflation
Inflation can greatly impact the costs associated to the project thus happening as a risk
Impact
Probability Score Comments
Scope Schedule Cost Quality
5 3 5 5
RISK MITIGATION
APPROVAL
RISK Details
Risk Description: Extreme Weather
Monsoons are a major risk to a construction project specially during starting phase
Impact
Probability Score Comments
Scope Schedule Cost Quality
5 3 3 4
RISK MITIGATION
APPROVAL
RISK Details
Risk Description: Time Frame
Time frame is always a constraint hence risk for a construction project
Impact
Probability Score Comments
Scope Schedule Cost Quality
5 2 4 3 4.5
RISK MITIGATION
APPROVAL
RISK Details
Risk Description: Conflicts
At big projects, conflicts occur among different working parties which is a risk for the project
Impact
Probability Score Comments
Scope Schedule Cost Quality
4 1 2 3 3.5
RISK MITIGATION
APPROVAL