Professional Documents
Culture Documents
Water Pump Modifications-Propump Services-1 PDF
Water Pump Modifications-Propump Services-1 PDF
POWER2010
July 13−15, Chicago, Illinois, USA
POWER2010−27178
Robert M. Morgenstern
ProPump Services, LLC
Bethlehem, PA USA 18020
ABSTRACT:
Westar Lawrence Energy Center Unit 5 in Contained in the paper are the details of the
Lawrence, Kansas is a 375 mW unit that utilized following:
a closed loop circulating water system with a Assessment and analysis
wooden cooling tower and three horizontal o Establish baseline performance for
circulating water pumps to provide cooling water the (3) existing pumps
to the condenser. o Determining hydraulic upgrades to
the pump
The wooden cooling tower experienced rapid o Determining mechanical upgrades
degradation over the past five years of to the pump
operation. Chlorine was added to the water o Perform a hydraulic model study of
chemistry to reduce attack of the wooden the pump intake
components, but the chlorine levels in the water Implementation
caused accelerated corrosion of the pump o Implementing upgrades to the pump
components and base plates. Circulating water concurrent during a planned one
system capacity was reduced due to worn pump month outage
components and excessive clearances. Unit o Refurbishing the motors
load was limited by the lack of adequate o Repairing and replacing pump
circulating water capacity. baseplates
o Implementing intake modifications
This paper discusses the pump and motor Pump start-up and performance verification
repairs, design changes performed in parallel
with demolition of the wooden cooling tower, and The project was completed on schedule, and the
replacement with a new fiberglass tower performance exceeded the design targets.
designed to utilize the existing concrete basin.
All of the changes were implemented during an
outage in April-May 2009.
NOMENCLATURE:
1
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
HISTORICAL BACKGROUND
2
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
The Total Developed Head (TDH) was 10.9 ft The efficiency was also low by a similar
(11.1%), low compared to the expected head at percentage as the TDH, due to excessive ring
the measured flow. This indicates that the leakage. The horsepower remained near
pumps were worn with excessive ring expected for a “healthy” pump (i.e. the pump is
clearances and/or impeller breakage. doing work to pump flow through the ring
clearances, but it is a loss since it doesn’t
increase the H-Q that the pump is producing at
the discharge nozzle).
3
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
Customer Westar Lawrence 5 Pump Size & Type 36AFV Speed (RPM) 442 Capacity (gpm) 56,666
Service Circulating Water Number of Stages 1 Specific Gravity 1 Head (ft) 75
Liquid Water Npsha Temperature (o F) Ambient Efficiency 89.5%
Date 12/2/2008 Motor 1500 bhp 1.15 s.f. BHP 1199
120 120%
Existing Design
110 93' 110%
56,666 gpm
442 rpm
100 One Pump (After Speed Change) 100%
TDH - Existing Test 12/2/08 1547 bhp
Pump Design 87.1'
90 90%
43,250 gpm
442 rpm
80 80%
Efficiency
Pump Design 64% Average 1236 bhp
50 50%
40 40%
10 10%
Test 12/2/08
1479 BHP average
0 0%
0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000
Sulzer Pumps
Curves are appro ximate. P ump is guaranteed fo r o ne set o f co nditio ns.
Flow (gpm)
As shown in Figure 6 below, in addition to the a. Design pressure drop 9.0 psi across
pumps producing low TDH, the system condenser
resistance was higher than expected. This was b. Pressure drop during testing 11.5
likely due to one closed riser (increases friction psi
loss in remaining risers), condenser pressure c. Pressure drop during last 6 months
drop design value, and basin level below ranging from 10.6 to 13.0 psi at full
design. load
4. The 501 pump appeared disproportionately
low based on:
a. Visibly lower velocity at trash racks
CONCLUSIONS b. Lower motor amps
c. Impeller pieces found in system
1. The combined pumps were approximately 5. The motors were operating near full load
10.9 ft (11.1%) low in TDH at measured amps; however, the winding temperatures
capacity of 129,762 gpm. were relatively low with adequate thermal
2. The pumps were tested with one riser margin.
valved out; the expected change with the 6. TDH design conditions of 93 ft @ 170,000
riser open would be minor. gpm total flow rate put the pumps slightly in
3. Condenser cleanliness was a factor during the motor service factor (about 3% of 15%
testing with: margin).
4
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
FIGURE 6: PUMP PERFORMANCE VS. SYSTEM CURVE
Customer Westar Lawrence 5 Pump Size & Type 36AFV Speed (RPM) 442 Capacity (gpm) 56,666
Service Circulating Water Number of Stages 1 Specific Gravity 1.00 Head (ft) 93
o
Liquid Water Npsha Temperature ( F) Ambient Efficiency
Date 11/13/2008 Motor 1500 bhp? BHP
120 6000
129,762
87.1'gpm
30
0 0
0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000 200,000
Sulzer Pumps
Curves are approximate. Pump is guaranteed for one set of conditions.
Flow (gpm)
6
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
7
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
8
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
9
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
Motor
Pedestal
10
Proceedings of ASME 2010 Power Conference
POWER2010
July 13−15, Chicago, Illinois, USA
Due to site crane limits, the pumps were shipped FIGURE 18: DISASSEMBLED PUMP
in three pieces:
o Lower half casing The replacement cooling tower did not include
o Rotor the external risers; therefore flow measurement
o Upper half casing similar to that performed 12/08 was not possible.
Table 1 chronicles data from both the control
room and data acquired at both the pumps and
Installation commenced with installation of the condensers.
motor (Figure 19) on to the remachined
soleplate and subsequent installation of the
casing. With both installed the pump rotor and
upper half casing assembly was completed.
With the primary installation complete,
peripheral work included pump to driver
alignment, packing installation, and connecting
the suction and discharge flanges.
Table 1
Pump / Motor 501 Pump / Motor 502 Pump / Motor 503 Condenser 501 Condenser 502
Condenser −P [psi] 9 8
Condenser −T [ ̊ F] 27 25
Summary
Intakes
Pump and motor refurbishment were performed
Modifications were implemented to reduce
in parallel with cooling tower replacement
vortexing.
including:
Motors
Cooling Tower
Motors had routine maintenance repairs
Wooden towers were demolished and replaced
performed.
with fiberglass utilizing the existing basin.
The project was completed on schedule in
Pumps
approximately 7 weeks, and the performance
- Hydraulics and mechanical performance
exceeded the design targets.
was restored.
- Select materials were upgraded to
stainless steel for aggressive water
- Baseplates were replaced
12