Requirements List.It will display planning parameters maintained material master like MRP type, MRP
controller, Procurement Type, Strategy group, availability check and Lot size etc at header level for the
respective plant.
Examples:
Various requirements for the material like PIR, sales order, production order, planned orders etc are displayed
in MD04
MRP Element data: Defines against the MRP element relevent data.
Examples:
1. In case of PIR it displays the requirement type or requirement plan if demand is created against the
plan
2. In sales of Sales Order (CustSt) - Displays respective sales order number which is created for the
material
3. In case of production order PrdOrd - It displays the respective production order number
4. In case of planned order PldOrd - Displays planned order number which was generated after MRP run.
5. In case of purchase requsition it displays the PR number or PO number if converted to PO.
Eg:
In nut shell MD04 display all the current demand/requirements for the material along with current stock