ID: COM 2210 - Introduction to Mass Media: Project Timeline

Design Team
Dr. LaMetrius Daniels: Project Manager
Dr. Jeffery Wells: Content Expert
Samantha Longanecker: Instructional Designer

Stage I: ID Consult and Design Logistics


Task Date (2020) Outcome Resources - clickable
Initial Design Meeting: ID & PM 8-Jun On June 8, 2020 - I met with the project manager, Dr. LaMetrius Meeting Notes
Daniels to discuss the proposed plan for the development of COM
2210 via Blackboard LMS for August 2020 deployment for Trevecca
Nazarene University.
9-Jun Purpose - The ID, Samantha Longanecker, will email to introduce Initial Email
Introductory Email to Dr. Wells
herself to the CE for the COM 2210 development.
(CE)
ID will email CE and Project 10-Jun ID will setup and communicate the date and time of the initial Email with Meeting Link
Manager with info on first design design meeting to the team.
meeting for June 16th
Project Manager and ID Meeting 11-Jun Project Manager meets with ID to discuss updates from CE and Notes
next steps with Course Outline file
ID to Complete Course Outline 14-Jun ID completes Course Outline file and sends to project manager for Course Outline File
review
16-Jun ID leads design meeting with Dr. Wells (CE) and Dr. Daniels (PM) Notes
Initial Design Meeting: PM, CE, ID
17-Jun ID communicates notes and additional information shared at the Follow-up Email
June 16th initial meeting
ID Email Follow-up with CE, PM
All course content to ID by: July 25th (Video content by July 25th)
Stage II: Course Content Development and ID Assistance
Task Date (2020) Outcome Resources - clickable
ID communicates to PM 29-Jun ID will reach out to Dr. Wells with a resource recommendation and Email to PM
check-in

CE communicates to ID 30-Jun ID receives an update from CE Email from CE


CE communicates to ID 7-Jul CE updates ID with info on Course Outline updates Email from CE
Phone Call to CE from ID 8-Jul Phone call to troubleshoot shared file access Follow-up Email to CE
Email from CE to ID 8-Jul Dr. Wells has almost finished the 3 major projects of the course Email
design
Phone Call from CE to ID 15-Jul CE update: Textbook publisher offers online resources & Exam n/a
Test banks need uploading to Blackboard - ID will upload

ID Test Bank Upload Complete 16-Jul ID successfully uploads course test banks in BB
Test Banks Email
CE Check-in 20-Jul CE will work on tests and weekly intro vidoes - after weekly Check-in Email
folders are complete with course resources. ID will begin
reworking the Course Syllabus for the CE.

Stage III: Course Development within LMS, Blackboard


Task Date (2020) Outcome Resources - clickable
PM shares Blackboard development 23-Jul ID begins developing course content from CE developed weekly Course Resource for BB
video resource for ID files Development from PM

ID Course Design in LMS 23-Jul ID continues to upload and organize Course content files into BB *Ongoing during Stage III
ID emails PM 23-Jul LMS
ID sends email to PM with questions gathered during BB Email to PM
Update on Project Format 27-Jul development
CE and ID discuss formatting of projects (Panopto) Email communication
ID Updates CE on Progress 28-Jul ID communicates progress and questions to CE Email to CE
ID Phone Call with CE 28-Jul Discuss questions sent via email with CE: Text you may omit n/a
sections added to One Drive File
PM email to ID 31-Jul PM emails ID with Quality Matters review and standards Quality Matters
Course Syllabus Update ID to CE 1-Aug Email update with course syllabus and generated "To Do.." list Email with To-Do list
ID adds video content to LMS 3-Aug Link sharing access is updated and content videos added to n/a
Blackboard, LMS
ID communicates progress to CE 4-Aug CE receives a progress update via email Email

Exams Complete in BB 8-Aug CE emails to let ID know Exams are complete in BB n/a

Adjust point totals to equal 1,000 8-Aug Discovery of point total requirement. Course point totals 930 - but adjustments were made based
must equal 1,000. ID will communciate this to CE on CE recommendations

ID communicates completion of 10-Aug PM will start the review process for COM 2210 development n/a
design to PM
Stage IV: Course Review & Approval
Task Date (2020) Outcome Resources - clickable
Course Review Begins 10-Aug Course is approved for August 13th deployment n/a
Email CE - Course Completion 15-Aug ID emails CE to notifiy of course completion and next steps Email