You are on page 1of 25

Specification List from “MASTER FORMAT” of the Construction Specifications Institute (CSI)

1979

Division 1. General requirements


Division 2. Site work
Division 3. Concrete
Division 4. Masonry
Division 5. Metals
Division 6. Wood and plastics
Division 7. Thermal and moisture protection
Division 8. Doors and windows
Division 9 Finishes
Division 10. Specialties
Division 11. Equipments
Division 12. Furnishings
Division 13. Special construction
Division 14. Conveying systems
Division 15. Mechanical
Division 16. Electrical

Depending on the particular requirement of the works each of the above sections will have
divisions reflecting particular requirements as shown below.
DIVISION 1 GENERAL REQUIREMENTS

01010 Summary of Work


01020 Allowances
01030 Special Project Procedures
01040 Coordination
01050 Field Engineering
01060 Regulatory Requirements
01070 Abbreviations and Symbols
01080 Identification Systems
01100 Alternates/ Alternatives
01150 Measurement and Payment
01200 Project Meetings
01300 Submittals
01400 Quality Control
01500 Construction Facilities and Temporary Controls
01600 Material and Equipment
01650 Starting of Systems
01660 Testing, Adjusting, and Balancing of Systems
1700 Contract Closeout
01800 Maintenance Materials

DIVISION 2-SITE WORK

02010 Subsurface Investigation


02050 Demolition
02100 Site Preparation
02150 Underpinning
02200 Earthwork
02300 Tunneling
02350 Piles, Caissons and Cofferdams
02400 Drainage
02440 Site Improvements,
02480 Landscaping
02500 Paving and Surfacing,
02580 Bridges
02590 Ponds and Reservoirs
02600 Piped Utility Materials and Methods
02700 Piped Utilities
02800 Power and Communication Utilities
02850 Railroad Work
02880 Marine Work
DIVISION 3-CONCRETE

03010 Concrete Materials


03050 Concreting Procedures
03100 Concrete Formwork
03150 Forms
03180 Form Ties and Accessories
03200 Concrete Reinforcement
03250 Concrete Accessories
03300 Cast-In-Place Concrete
03350 Special Concrete Finishes
03360 Specially Placed Concrete
03370 Concrete Curing
03400 Pre-cast Concrete
03500 Cementitious Decks
03600 Grout
03700 Concrete Restoration and Cleaning

DIVISION 4-MASONRY

04050 Masonry Procedures


04100 Mortar
04150 Masonry Accessories
04200 Unit Masonry
04400 Stone
04500 Masonry Restoration and Cleaning
04550 Refractories
04600 Corrosion Resistant Masonry

DIVISION 5-METALS

05010 Metal Materials and Methods


05050 Metal Fastening
05100 Structural Metal Framing
05200 Metal Joists
05300 Metal Decking
05400 Cold-Formed Metal Framing
05500 Metal Fabrications
05700 Ornamental Metal
05800 Expansion Control
05900 Metal Finishes

DIVISION 6-WOOD AND PLASTICS

06050 Fasteners and Supports


06100 Rough Carpentry
06130 Heavy Timber Construction
06150 Wood-Metal Systems
06170 Prefabricated Structural Wood
06200 Finish Carpentry
06300 Wood Treatment
06400 Architectural Woodwork
06500 Prefabricated Structural Plastics
06600 Plastic Fabrications

DIVISION 7-THERMAL AND MOISTURE PROTECTION

07100 Waterproofing
07150 Damp proofing
07200 Insulation
07250 Fireproofing
07300 Shingles and Roofing Tiles
03370 Concrete Curing
07400 Preformed Roofing and Siding
07500 Membrane Roofing
07570 Traffic Topping
07600 Flashing and Sheet Metal
07800 Roof Accessories
07900 Sealants

DIVISION 8-DOORS AND WINDOW'S

08100 Metal Doors and Frames


08200 Wood and Plastic Doors
08250 Door Opening Assemblies
08300 Special Doors
08400 Entrances and Storefronts
08500 Metal Windows
08600 Wood and Plastic Windows
08650 Special Windows
08700 Hardware
08800 Glazing
08900 Glazed Curtain Walls

DIVISION 9-FINISHES

09100 Metal Support Systems


09200 Lath and Plaster
09230 Aggregate Coatings
09250 Gypsum Wallboard
09300 Tile
09400 Terrazzo
09500 Acoustical Treatment
09 550 Wood Flooring
09600 Stone and Brick Flooring
09650 Resilient Flooring Carpeting
09680 Special Flooring
09760 Floor Treatment
09800 Special Coatings
09900 Painting
09950 Wall Covering

DIVISION 10-SPECIALTIES

10100 Chalkboards and Tackboards


10150 Compartments and Cubicles
10200 Louvers and Vents
10240 Grilles and Screens
10250 Service Wall Systems
10260 Wall and Corner Guards
10270 Access Flooring
10280 Special Modules
10290 pest control
10300 Fireplaces and stoves
10340 Prefabricated Steeples, Spires and Cupolas 10350 Flagpoles
10400 Identifying Devices
10450 Pedestrian Control Devices
10500 Lockers
10520 Fire Extinguishers, Cabinets, and Accessories
10530 Protective Covers
10550 Postal Specialties
10600 partitions
10650 Scales
10670 Storage Shelving
10700 Exterior Sun Control Devices
10750 Telephone Enclosures
10800 Toilet and Bath Accessories
10900 Wardrobe Specialties

DIVISION 11-EQUIPMENT

11010 Maintenance Equipment


11020 Security and Vault Equipment
11030 Checkroom Equipment
11040 Ecclesiastical Equipment
11050 Library Equipment
11060 Theater and Stage Equipment
11070 Musical Equipment
11080 Registration Equipment
11100 Mercantile Equipment
11110 Commercial Laundry and Dry Cleaning Equipment
11120 Vending Equipment
11130 Audio-Visual Equipment
11140 Service Station Equipment
11150 Parking Equipment
11160 Loading Dock Equipment
11170 Waste Handling Equipment
11190 Detention Equipment
11200 Water Supply and Treatment Equipment
11300 Fluid Waste Disposal and Treatment Equipment
11400 Food Service Equipment
11450 Residential Equipment
11460 Unit Kitchens
11470 Darkroom Equipment
11480 Athletic, Recreational, and Therapeutic Equipment
11500 Industrial and Process Equipment
11600 Laboratory Equipment
11650 Planetarium and Observatory Equipment
11700 Medical equipment
11780 Mortuary equipment
11800 Telecommunications equipment
11850 Navigation Equipment

DIVISION 12 FURNISHINGS

12100 Artwork
12300 Manufactured Cabinet and Casework
12500 Window Treatment
12550 Fabrics
12600 Furniture and Accessories
12670 Rugs and Mats,
12700 Multiple Seatings
12800 Interior Plants, and Plantings

DIVISION 13- SPECIAL CONSTRUCTION

13010 Air supported structures


13020 Integrated Assemblies,
13030 Audiometric Rooms
13040 Clean Rooms
13050 Hyperbaric Rooms
13060 Insulated Rooms
13070 Integrated Ceilings
13080 Sound, Vibration, and Seismic Control
13090 Radiation Protection
13100 Nuclear Reactors
13110 Observatories
13120 Pre-Engineered Structures
13130 Special Purpose Rooms and Buildings
13140 Vaults
13150 Pools
13160 Ice Rinks
13170 Kennels and Animal Shelters
13200 Seismographic Instrumentation
13210 Stress Recording Instrumentation
13220 Solar and Wind Instrumentation
13410 Liquid and Gas Storage Tanks
13510 Restoration of Underground Pipelines
13520 Filter Underdrains and Media
13530 Digestion Tank Covers and Appurtenances
13540 Oxygenation Systems
13550 Thermal Sludge Conditioning Systems
13560 Site Constructed Incinerators
13600 Utility Control Systems
13700 Industrial and Process Control Systems
13800 Oil and Gas Refining Installations and Control Systems
13900 Transportation Instrumentation
13940 Building Automation systems
13970 Fire Suppression and Supervisory Systems
13980 solar Energy Systems
13990 Wind energy systems

DIVISION 14 CONVEYING SYSTEMS

14100 Dumbwaiters
14200 Elevators
14300 Hoists and Cranes
14400 lifts
14500 Material Handling systems
14600 Turntables
14700 Moving Stairs and Walks
14800 Powered Scaffolding
14900 Transportation Systems

DIVISION 15-MECHANICAL
15050 Basic Materials and Method,
15200 Noise, Vibration, and Seismic Control
15250 Insulation
15300 Special Piping Systems
15400 Plumbing Systems
15450 Plumbing Fixtures and Trim
15500 Fire Protection
15600 Power or Heat Generation
15650 Refrigeration
15700 Liquid Heat Transfer
15800 Air Distribution
15900 Controls and Instrumentation

DIVISION 16-ELECTRICAL

16050 Basic Materials and Methods


16200 Power Generation
16300 Power Transmission
16400 Service and Distribution
16500 Lighting
16600 Special Systems
16700 Communications
16850 Heating and Cooling
16900 Controls and Instrumentation
RECOMMENDED ORGANIZATION OF GENERAL REQUIREMENTS (from CSI MASTER-FORMAT)

DIVISION 1: GENERAL REQUIREMENTS

NUMBER TITLE

01010 SUMMARY OF WORK

Work Covered by Contract Documents

-11 Contracts
-12 Work by Others
-13 Future Work
-14 Work Sequence
-15 Contractor Use of Premises
-16 Occupancy
Owner Occupancy
Partial Occupancy
Continued Occupancy
Maintenance of Operation

-17 Pre-Ordered Products


-18 Owner-furnished Items

01020 ALLOWANCES

-21 Cash Allowances


-22 Inspection Testing Allowances
-23 Contingency Allowance

01030 SPECIAL PROJECT PROCEDURES

-31 Alterations Project Procedures


-32 Hospital Project Procedures
-33 Industrial Project Procedures
-34 Nuclear Project Procedures
01040 COORDINATION

-41 Project Coordination


-42 Mechanical and Electrical Coordination
-45 Cutting and Patching

01050 FIELD ENGINEERING

-51 Grades, Lines, and Levels

01060 REGULATORY REQUIREMENTS


-61 Building Codes
-65 Mechanical Codes, Fees, and Lateral Costs
-66 Electrical Codes, and Fees

01070 ABBREVIATIONS AND SYMBOLS

-71 Architectural Abbreviations and Symbols


-75 Mechanical Reference Symbols
-76 Electrical Reference Symbols

01080 IDENTIFICATION SYSTEMS

-85 Control Identification Systems


-86 Piping Identification Systems
-87 Electrical Identification Systems

01100 ALTERNATES/ ALTERNATIVES

01150 MEASUREMENT AND PAYMENT

-51 Unit Prices


-52 Applications for Payment
-53 Change Order Procedures

01160-01199 (Reserved)

01200 PROJECT MEETINGS

-01 Preconstruction Conferences


-02 Progress Meetings
-03 Job Site Administration

01210-01299 (Reserved)

01300 SUBMITTALS

-10 Construction Schedules


-11 Network Analysis Schedules
-20 Progress Reports
-30 Survey Data
-40 Shop Drawings, Product Data, and Samples
-50 Mock-ups
-60 Layout Data
-70 Schedule of Values
-80 Construction Photographs

01390-01399 (Reserved)

01400 QUALITY CONTROL

-10 Testing Laboratory Services


-20 Inspection Services

01500 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

-510 TEMPORARY UTILITIES

-11 Temporary Electricity


-12 Temporary Lighting
-13 Temporary Heating, Cooling, and Ventilating
-14 Temporary Telephone Service
-15 Temporary Water
-16 Temporary Sanitary Facilities
-17 Temporary First Aid Facilities
-18 Temporary Fire Protection
-19 Temporary Construction

Interim Bridges
Interim Overpasses
Interim Runarounds
Interim Decking

-520 CONSTRUCTION AIDS (Data Filing Only)

-21 Construction Elevators and Hoists


-22 Temporary Enclosures
-23 Swing Staging
-24 Scaffolding and Platforms

-530 BARRIERS

-31 Fences
-32 Tree and Plant Protection
-33 Barricades
-540 SECURITY

-45 Protection of Work and Property

-550 ACCESS ROADS AND PARKING AREAS

-51 Access Roads


-52 Parking Areas

-560 TEMPORARY CONTROLS

-61 Noise Control


-62 Dust Control
-63 Water Control
-64 Pest Control
-65 Rodent Control
-66 Debris Control
-67 Pollution Control
-68 Erosion Control

01570 TRAFFIC REGULATION

-71 Traffic Signals


-72 Flagmen
-73 Flares and Lights
-74 Construction Parking Control
-75 Haul Routes

01580 PROJECT IDENTIFICATION AND SIGNS

01590 FIELD OFFICES AND SHEDS

01600 MATERIAL AND EQUIPMENT

-10 Transportation and Handling


-20 Storage and Protection
-30 Substitutions and Product Options
01650 STARTING OF SYSTEMS

-55 Starting Piping Systems


-56 Disinfection of Domestic Water Lines
-57 Starting Process Systems

01660 TESTING, ADJUSTING, AND BALANCING OF SYSTEMS

-65 Testing Mechanical Systems


-66 Testing Piping Systems
-67 Balancing Air Systems
-68 Testing Electrical Systems
-69 Testing Process Systems

01700 CONTRACT CLOSEOUT

-10 Cleaning
-20 Project Record Documents
-30 Operating and Maintenance Data
-35 Equipment Systems Demonstrations
-36 Mechanical Systems Demonstrations
-37 Electrical Systems Demonstrations
-38 Process Systems Demonstrations
-39 Conveying Systems Demonstrations
-40 Warranties and Bonds
-50 Spare Parts and Maintenance Materials

01800 MAINTENANCE (Data Filing Only)

01850-01999 (Reserved)
Site work may be further divided as follows.

NUMBER TITLE

02010 SUBSURFACE INVESTIGATION

-11 Borings
-12 Core Drilling
-13 Standard Penetration Tests
-14 Seismic Exploration

02050 DEMOLITION

-60 Building Demolition


-70 Selective Demolition
-71 Selective Structural Demolition
-72 Minor Demolition for Remodeling
02080-02099 (Reserved)

02100 SITE PREPARATION


-10 Clearing
-11 Tree and Shrub Removal
-12 Tree Pruning
-13 Sod Stripping
-14 Large Tract Tree Clearing
-20 Structure Moving
02130-02149 (Reserved)

02150 UNDERPINNING
-51 Shores
-52 Needle Beams
-53 Grillage
-54 Pit Underpinning
-55 Pile Underpinning
-60 Slab-jacking
-65 Pressure Injected Footings
02170-02199 (Reserved)
Once a list of the work analysis is prepared each section of the specification may then be
prepared based on the following general format.

General, Requirements
 Description and Scope of works
 Related documents
 Summary of the specific works
 References and standards etc

 Specific Requirements,
 Any requirements to be adhered to in the specific work area

 Types and Quality of Materials that must be used


 Description of materials, Standards
 Testing
 Workmanship, Technical procedure of carrying out works, (ex
concrete, mixing and placing etc )

 Level and Quality of Workmanship,


The quality of workmanship required in the work, and methods of assessing this
requirement.
 Method of Measurement of Completed Work
 Units to be used in the measurement of the works, as well as how
the completed work is to be measured, such as in m2 Linear meter
(LM) etc
 Method of Payment
 Method of payments, unit rates etc.

These sub divisions are in fact applicable and form a general guideline to all forms of
construction activities. In general therefore planning specifications follows the sequence of the
works, further divided into specific requirements described above.
A sample specification taken form an actual construction project in Ethiopia is shown below.

1. General items

1.1 Project Description: - what the nature of the project is or an introduction to the
project. Describing the scope of works with a detailed account of the extent of the
work.
1.2 Scope:
“This section covers matters which relate to the construction work as a whole.
Definitions, phrases or wording which would otherwise require repetition in
other sections of the Specifications are also covered by clauses in this section.
Matters covered by the General Conditions of Contract are not repeated in this
section, except where necessary in order to provide more detailed information.”

1.3 Works executed by the employer or other contractors: The Employer reserves
the right to execute, on the Site, works not included in the Contract and to
employ for his purpose either his own employees or other contractors. The
Contractor shall ensure that neither his own operations nor the actions of his
employees shall interfere with the operations of the Employer or his contractors
employed on such work and the same obligations shall be imposed on the
Employer or contractors in respect of work being executed under the Contract

1.4 Location and access Where the project is or the geographical location or the
access options to the site as well as the general description of the surrounding
areas. The Access description usually contains the type of the access roads that
exist, whether it is Gravel or, Bitumen surfaced, all weather or Dry weather road
or if there is no access hence instructing the contractor to build an access road.
“The contractor shall use the temporary roads to and within the site as agreed
with the Engineer. The Contractor will not be allowed to use any other routes
except with the express permission of the Engineer. The contractor shall
provide, maintain and clear away on completion all necessary temporary roads,
access, hard standings culverts and the like There shall be no unnecessary
obstruction to existing roads and rights of way and any damaged caused shall
in any case be made good as it occurs by the contractor at his expense.”
1.5 Special precaution during construction: instruction on issues such as protection
of adjacent property, protection or relocation of public utilities, should be
included. When writing such parts of the specification it is prudent to keep in
mind the cost implication on the project. The specifications may state “This
Contract may include certain work involved in moving and reinstating existing
services that may be affected by the construction of the Works. The Employer
will provide information regarding the location of existing utility service, in the
works area but the Employer does not accept responsibility for the accuracy of
the information….the contractor shall take all the necessary precautions to
protect existing services during construction and during relocation of such
services. ….. any pipe , cable, conduit, or other known service of any nature
whatsoever, which has been damaged as a result of the constructor’s operation
shall be repaired and reinstated forthwith by the contractor or by the
authority concerned , all at the expense of the contractor and to the
satisfaction of the engineer”

1.6 Maintenance and protection of traffic: when existing traffic is heavy at a


construction site, the contractor should be required; to maintain and protect traffic
with a minimum of interference to the traveling public, the provision of detours,
maintaining minimum traffic etc need to be included in this section.

1.7 Climate: - gives a general description of the weather, describing any seasons of
rain etc. As this affects the timing of the construction as well as the time, it will
take to complete the project. Generally, such information will help the contractor
to have his construction schedule, such as when to do a specific job.

1.8 Soil conditions: - the specifications will give a general description of what the
soil profile looks like. Such sub soil information is also issued at the time of the
tendering, which may be supplemented by further investigation as the work is
started. This information helps the contractor to mobilize what type of machines
he needs:-Whether he has to use temporary roads or whether he can use the soil as
it is (with up grading or not). In issuing such information, one should be careful
to project the soil profile form the borehole data. The typical specification may
read “the subsurface information and data furnished herein are not intended as
representations or warranties but are furnished for information only. It is
expressly understood that the owner and the engineer will not be responsible,
for the accuracy thereof or for any deduction, interpretation or conclusion
drawn there from by the contractor. The information is made available in order
that the contractor may have ready access to the same information available to
the owner and the engineer and is not part of this contract.”

1.9 Units of Measurement:- specifies the type of measurement of standards


applicable to the contract, say international method of measurement (SI) or other
applicable types

MEASUREMENT
a) Units of measurements
All work shall be measured in metric units
b) Bills of Quantities

The quantities set out in the Bill of Quantities are estimated quantities and are
used for the comparison of Tenders and awarding the Contract. It must be
clearly understood that only the actual quantities of work done or materials
supplied shall be measured for payment, and that the billed quantities may be
increased or decreased as provided in the General Conditions of Contract.
Measurement of completed work

Except otherwise noted all distances shown on the Drawings are horizontal
distances and these distances will be used in Calculating the
quantities of fill, sub base, bases, shoulder ,surfacing and paving for
payment purposes. All cross-sections shall be taken in a vertical plane.

1.10 WORKMANSHIP AND QUALITY CONTROL

The onus rests with the Contractor to produce work which conforms in quality
and accuracy of detail to the requirements of the Specifications and Drawings,
and the Contractor must, at his own expense, institute a quality control system
and provide experienced engineers, foreman, surveyors, materials technicians,
other technicians and other technical staff, together with all transport,
instruments and equipment, to ensure adequate supervision and positive control
of the Works at all times. The cost of all supervision and process control
including testing, so carried out by the Contractor shall be, deemed to be
included in the rates tendered for the related items of work, except that the cost
of certain tests and the provision separately as provided for in those of certain
items of testing and sampling equipment shall be paid for sections of the
Specifications where this applies

1.11 STANDARDS AND CODES:

The contract is based on the standards of quality established in the contract


documents and to this end certain acceptable manufacturers have been
indicated in the Specifications. Substitutions will be considered only when listed
at the time of bidding, together with documentation on establishing that the
item is, in fact, equal or better than that specified. In this Specification Subject
to the approval of the Engineer and the employer, any other national or
internationally accepted standard or manufacturer which maintains or
improves the specified quality may be used

The standard referred to shall be latest editions published at the time of Tender.
All the conditions and particulars as to standard of materials workmanship and
tests contained in such Standards shall be complied with for various Items
unless otherwise agreed by the Engineer. Copies, in the English language, of
any Standards used in connection with the Works shall be supplied to the
Engineer within ……. days of the Engineer's written request stipulating the
required standards. The contractor shall maintain on site one set of all specified
standards and will provide an extra set for the Engineer's office. The latter set
will revert to the Employer.

Where such standards and codes are national in character, or relate to a


particular country or region, other authoritative standards which ensure an
equal or higher quality than the standards and codes specified will be accepted
subject to the Engineer's prior review and written approval. Differences
between the standards specified and the proposed alternative standards must be
fully described in writing by the Contractor and submitted to the Engineer at
least …………days prior to the date when the Contractor desires the Engineer's
approval. In the event the Engineer determines that such proposed deviations
do not ensure equal or higher quality, the Contractor shall comply with the
standards set forth in the documents.

1.12 Materials:-the type of materials and the specific requirements are stated with
reference to applicable standards.

1.13 Office and site facilities Has two sections that are
i. Facilities for the engineer
ii. Facilities for the contractor
Normally the contractor provides for the needs of the engineer on site, so that he is able
to carry out his tasks. These facilities may include items such as offices, sanitary units,
stores, parking areas etc. In most instances, these facilities are temporary but the client
may include provisions in the contract to keep the items at the end of the contract. The
specifications state the minimum usable space, and may include a sketch of the over-all
dimensions and layout of the building. The contractor may also provide for his own staff,
temporary site offices, living and accommodation facilities etc. If the site has little or no
storage area, the contractor may be required to provide such facilities at his own expense.

B. Site offices/Living accommodation: includes facilities for the Engineer, his staff,
contractor and his staff, workers etc.
Site office
“The office shall have a net floor area and consist of rooms and offices as
detailed in Figure -- Section --- all rooms shall be provided with through
ventilation and electric lighting of a minimum of 100 watts per room. A total of
eight power points shall be provided.”
C. Laboratories, the contract documents may specify the provision and set up as
well as staffing of laboratory facilities for the project. In areas where there may
be other independent laboratories nearby, this item may be omitted, but for remote
areas, it is usually necessary. The specifications state the types of testing
equipment, instruments, and type of building etc. Usually the usable area (area
not including walls, corridors, stairs, terraces etc). Sampling and testing of
materials is to be done under the direction of the engineer. “The Contractor shall
provide, furnish, equip and maintain for the duration of the Contract a site
office, and laboratory for the sole use of the Engineer's resident site staff. The
office and laboratory shall be located adjacent to the Contractor's main site
office and at a location approved by the Engineer. The Contractor shall make
available to the Engineer all services provide for his own offices including road
access, fencing, hard standing, water, power, telephone, tele-fax, and
sewerage..”
D. Survey equipments: documents specify the provision, the type and number of
survey equipments needed for use by the engineer and contractor. It is usually
written, as “the contractor shall provide…”

power water and telephone (communication) such as power required for the
temporary facilities and for the construction, Water for human consumption and
for the construction work such as concrete, washing sand etc use of potable water
for concrete if available, if not specify the source and quality of water to be used
for concreting etc. Telephones, communication for office uses and radios for site
communication, the need to obtain the necessary communication permit from the
relevant authorities. The availability source, and who should pay (whether the
contractor or the client) for these installations need to be included in the
specifications.

“The Contractor shall provide a constant supply of clean potable water suitable
for human consumption, as well as the necessary electric power at 220/250 V to
the offices and laboratory. Electric power shall be supplied to the offices and
laboratories 24 hours per day.”

1.14 Sewage and refuse disposal: specify the standards of treatment, “treated and
disposed of in a hygienic way to satisfy…”
1.15 Engineer’s transport: the contractor provides at all times (24 hrs.) for the sole
use of the engineer, a car… the vehicle is exclusively fro the use of the engineer
and the contractor has no right over it. It should also have full insurance
coverage,

“Motor vehicles of the make and type detailed below shall be supplied, serviced
and maintained in good running order by the Contractor for the full period of
the Contract. The specified vehicles shall, during the contract period, be made
available to the Engineer his representatives and those persons authorized by
him at all times (including at weekends) during breakdown and servicing
periods, equivalent alternative vehicles shall be provided at no extra cost.

Vehicle Type A

Passenger Station Wagon, long wheelbase, four-wheel drive, 9 seater


(minimum}, with 6-cylinder Diesel Engine. Fitted with air conditioning, car
audio system and roof rack”

1.16 The programme of work required in, terms of the General Conditions of
Contract shall be submitted to the Engineer not later than one month after the
Contractor has been given access to the Site The programme shall not be in the
form of a bar chart only, but shall clearly show the anticipated quantities of
work to be, performed each month, as well as the anticipated earnings for the
various sections of work.
1.17 Drawings during the tendering period, drawings are issued so that the contractor
is able to price his tenders. These drawings normally contain sufficient detail, to
define the scope of the works. Frequently however, they require development and
elaboration before the various components can be fabricated. Drawings that
contain such details for fabrication and erection are called shop drawings. For
instance for reinforced concrete construction Shop drawings detail bar schedules,
bar bending details, formworks etc. When the works are, finished then, as built
drawings are prepared to show the work exactly as it is done and after the work is
finished. The specification should normally contain information o these aspects
of the construction

“The Contract Drawings show the general arrangement and details necessary
to perform the Work. The Contractor shall prepare Shop and Working
Drawings, for permanent and temporary Work, and for the proposed methods
of construction, complete with all relevant calculations, descriptions, technical
and performance data Shop Drawings shall consist of fabrication and erection
drawings, schedule drawings, manufacturer's scale drawings, wirings and
control diagrams, and other drawings as required by the specifications
Working Drawings are Contractor prepared plans for temporary structures
such as decking, temporary bulkheads, support of excavation, support of
utilities, ground water Control systems and forming and false work; for
underpinning and for such other Work as may be required for construction but
which does not become an integral part of the completed Work. They should be
accompanied by calculations or other sufficient information to completely
explain the structure or system described and its intended manner of use.”

1.18 Photographs: Taken at certain stages for follow-up of the work they are as useful
and important as drawings. The Engineer and client receive copies of the photos
of works in progress / completed at specified times

“Colored photograph showing the progress of the Works shall be taken every
month. Photographs shall not be less than 150 mm x 100 mm and shall be
inscribed with the location, and when taken and a brief description or title.
Each set shall comprise six prints of each of up to twenty negatives. All
Negatives shall be numbered and retained on the site. completion of the works,
the negatives shall become the property of the Employer Two prints of each
photograph shall be signed and dated on the back by the Engineer and the
Contractor and the Contractor shall insert them in albums in a systematic
manner. One print each shall be retained by the Employer and the Engineer as
an agreed record”
.
1.19 Insurance: - issues related to Insurance of works etc..

1.20 Mobilization and Demobilization: - all the preparatory work required to start the
work transport of temporary materials office set up etc and removal at the end of
the project.
Contractor's Establishment on Site

Scope

This section covers all work and costs involved in the establishment of the
Contractor's organization camps and plant on the Site, and the removal thereof
after completion. It also covers the cost of general obligations, liabilities and
risks which is not covered elsewhere

General Requirements

Camps, Plant and Testing Facilities

It is the Contractor's responsibility to acquire land for the siting of all his
offices, accommodation, stores, testing facilities, plant yards and workshops and
for all temporary works and for the reinstatement of such land on the
completion of the Contract to the satisfaction of the owners. The Contractor
shall obtain the approval of the Engineer to the siting of offices,
accommodation, stores, testing facilities, plant yards and workshops before
such land is acquired and he shall indemnify the Employer against all claims
and charges in respect of the occupation, use and reinstatement of the land.

The Contractor is solely responsible for the satisfactory housing of all his
employees and for complying with all Local District and Government
regulations and requirements in this respect. The Contractor will be required to
provide and maintain and remove on completion of the contract at his own costs
all camps and housing he thinks necessary, properly to accommodate his
personnel and labor together with shelters for his labor including all necessary
water supply for drinking and other purposes, electrical light, sanitation,
Cooking houses, fencing fire prevention equipment etc. and all such buildings
and all sheds and temporary structures which the contractor may erect for his
own purposes shall in respect of design, situation layout, water supply washing
and cooking facilities, lighting, sanitary and health arrangements and welfare
be such as will conform with the statutes regulations and Bylaws in force in the
district. On completion of the contract the camps or housing provided by the
contractor shall be demolished and the site thereof properly cleaned and all
temporary rubbish pits or sewage pits filled in all to the satisfaction of the
Engineer.

PAY ITEM NO DESCRIPTION UNIT

1. 1 Contractor's establishment on Site LS

Payment shall be a lump sum to provide for the Contractor's expenses in


connection with:
a) Setting up and maintaining his organization, camps and plant on the Site,
the supply and erection of contract signboards and for the removal of all on
completion;
b) Effecting the insurance and indemnities required in terms of the General
Conditions of Contract;
c) meeting all other general obligations and liabilities which are not
specifically measured for payment elsewhere in these Contract Documents

The lump sum shall not exceed 10% of the total Tender amount, excluding any
amounts allowed for day works and escalation. It the Tenderer should tender a higher
amount for this item, it shall be reduced to the amount allowed above and all other
tendered prices increased in the proportion required to retain the same Tender amount.

1.21 Environment and natural resources protection: the contractor has to take
adequate care of the environment, such that any activity should not cause damage
to the surrounding area. Toxic materials must not be released into the
environment.

Environmental Protection

This section specifies the environmental protection requirements for all work of
the contract.

a) Submittals

The Contractor shall submit Material Safety Data Sheets (MSDS) to the
Engineer for any chemical or material containing toxic substances or
hazardous materials

b) Environmental Requirements

The Contractor shall comply with all applicable ordinances, regulations, and
health codes pertaining to environmental protection. Equipment from which
factory-installed anti-pollution and noise control devices have been removed or
are ineffective shall not be used. Excessive idling and unnecessary operation of
equipment is prohibited

c) Protection of Natural Resources

Oil or other hazardous substances shall not be allowed to enter the ground,
drainage areas and piping systems

d) Toxic Substances Control


All solid waste from the Work shall be removed promptly from the Worksite and
disposed of by the Contractor. Solid waste removed by the Contractor shall not
be disposed of on or near the construction site, and shall be disposed of only in
legal landfills. All solid waste shall be removed on a daily basis. All solid waste
shall be accumulated in covered refuse Containers.

d) Toxic Substances and Hazardous Materials Control

No chemical substance, mixture, equipment, container, sealant, coating, or


dust-control agent shall be used except where permitted or approved by the
Engineer. Chemical waste shall be stored in appropriate corrosion-resistant
containers, removed from the Worksite, and disposed of as necessary, but not
less frequently than monthly. Fueling and lubricating of equipment and motor
vehicles on the Worksite shall be conducted in a manner that affords the
maximum protection against spills and evaporation. Lubricants to be discarded,
including burned oil, shall be disposed of in accordance with approved
procedures

1.22 Site reinstatement the site should be kept clean during and after the completion of
the contract. The requirements for such type of work should be clearly stated in
the documents.

“Upon completion of each section of the Works, the Contractor shall clean up
the Site; remove all temporary, equipment and debris. He shall level off and
fine grade all excavated material, which is surplus to requirements. The whole
of the Site shall be left in a clean and workmanlike condition to the satisfaction
of the Engineer. No separate payment shall be made for final clearance of the
Site and the cost shall be deemed to be included in the rates entered in the
Schedule of Quantities”

1.23 Omissions and conflicts: in the event that discrepancies occur in contract
documents such as a discrepancy between the plans and the specifications, the
specifications are usually given precedence. , details on large scale drawings are
given precedence over drawings with small scale drawings. Other requirements
also need to be addressed in the specifications.

1.24 Measurement and payment

MEASUREMENT
A. Measurement of Quantities - the determination of Quantities of Work
acceptably completed under the terms of the Contract, will be made by the
Engineer, based on measurements made by the Engineer. These measurements
will be taken, according to the acceptable standards of metric measurements
and units of measure, measurements used in common practice at the place of
the work and will be the actual length, area, solid contents, numbers, and
weights.
B. Unit Price - Where in the Contract Documents a "Unit Price" is set
forth, the "Unit Price" includes the furnishing by the Contractor of
all supervision, labor, tools, materials, machinery , appliances, plant and
equipment appurtenant to and necessary for the construction in every detail and
the completion in a first-class, workmanlike manner of all the Work to be done
under the Contract Documents. The "Unit Price" also includes all permanent
protection of overhead, surface and underground structures, training of
personnel, safeguards, cleaning up, finish, overhead expense,
bond, insurance, patent fees, royalties, risk due to the elements, delay, profit,
injuries, damages, claims, and all other items not specifically mentioned that
may be required to construct fully each item of the Work, complete in place.

C. Over-run and Under-run Payments -

“The Contractor and the Owner recognize that, in the performance of the
Contract, there may be either over-runs or under-runs in the estimated
quantities of Work and materials. The Owner agrees to make payment to the
Contractor for the actual quantities of Work performed and the material
furnished at the unit prices set forth herein”

PAYMENT

The Contractor shall receive and accept the compensation, as herein provided,
in full payment at the proposed unit prices and/or lump sum price for
furnishing all labor, tools, material, equipment and incidentals; for performing
all Work contemplated and embraced under the Contract”

You might also like