WATER SUPPLY SYSTEM AT IBADAN HOUSING ESTATE

1. The overall total demand for this project is 330,000 Gallon/day.


2. The breakdown demand for each phase is like below:

3. In Phase 1&2 B.Q, the constructions at the utility area are consist of:
a. Tube well and treatment plant: this treatment plant will only cater demand
for Phase 1 and 2.
b. Suction Tank with capacity of 110,000 Gallon/day: this suction tank will
cater for all phase.
c. Pump House: the pump house will be build with three separate compartments
for three separate modular pumping systems, one for each elevated water tank.
However only one pumping system will be install