Professional Documents
Culture Documents
Spring 2017
[MECH-498]
Group Members:
Supervisors:
Dr. Bashar El Khasawneh
Dr. Anas Alazzam
1. Summary
During this semester, we are expected to do more of hands-on work instead of research to
assemble the machine. Up to this point, we can say that the project progress is heading
towards the final stage as most of the machine parts are ready.
The report gives an overview of the work progress during this semester, starting with
machine parts that we have purchased and manufactured along with a financial analysis.
It also emphasizes on the issues and challenges that we have faced while building the
machine, and how we were able to deal with it.
2. Activities and Progress
2.1 Hydraulic System
We are using a hydraulic system to compress the soil mixture and produce a brick. The
final decision of choosing the suitable hydraulic system has been taken after several
changes in terms of hydraulic capacity and supplier. So far, we have decided on the main
components needed to operate the hydraulic cylinder, and they all will be purchased from
Power Hydraulics. At the beginning of the semester, we have met with engineers from
that company and discussed our requirements, and they suggested to have the following:
● Hydraulic Power Pack: which includes oil tank, motor, pump and all other
hydraulic components. The recommended hydraulic cylinder has a pressing speed
of 30cm/7s.
● Hydraulic Cylinder: which has a rear end flange with rod eye. It has a capacity of
15 ton and a stroke of 30 cm.
● Electric Control Panel: direct online with related switches. The main purpose of
using this control panel is to monitor the hydraulic movement up or down, and
adjust the pressing time.
As stated in the quotation that is mentioned in the appendix, all the parts are expected to
finish within 6-8 working days upon receiving first down payment. On March 6, 2017,
the first payment has been transferred to the company’s bank account, and the parts will
be delivered hopefully by March 15.
All the parts that should be manufactured in the university are included in the appendix.
Product Quantity
High-Load Metal Gear - 20 Degree 3
Pressure Angle, Steel, 20 Pitch, 30 Teeth
The major tasks of setting up the Arduino are presented in the figure above. Breaking
down the major task into minor tasks simplifies the problem and makes the solution
effective. A discussion of the tasks is presented below.
2.4.1 Power Source
Choosing a power source for the Arduino is crucial for making it autonomous.
There are four different ports for supplying power to the board:
1. USB port: USB connection coming from a computer or any power source
with a USB port such as a mobile battery bank,
2. Japan Jack port: AA or PP3 batteries providing or any power adaptor
providing a voltage of 7 to 12V is suitable,
3. Vin socket: applying 6 to 12V across the Vin socket, and
4. 5V socket: applying 5V across the 5V socket.
The use of batteries, whether rechargeable or nonrechargeable, is not efficient
since they require recharging or replacing periodically. The USB port is
appropriate but not practical, because powering the Arduino with a USB
connection from a computer does not provide autonomy. The Vin and 5V socket
are preferable for drawing power for Arduino-dependent devices rather than
inputting power. The last choice is the power adaptor, which provides an effective
and practical solution.
a) USB Port b) Japan Jack port
5. Dissemination
When doing a project it is important to split the work based on the strength points of each team
member. Therefore, the team has discussed the strengths of each team member and split the work
accordingly. Below is a table that clarifies the work distribution along the team.
Throughout the course of the project, we tried to keep the major tasks to the same people, but for
the small ones the tasks were interchangeable between the members. This was done to ensure
that all the tasks, big and small, were always progressing, and that nothing got stuck.
Another internal issue is the lack of technical knowledge about certain fields in the project.
Things like the programming of an arduino, or the basic components of a hydraulic cylinder
cycle were some of the things the group members lacked. This resulted in some work being
delayed due to the lack of knowledge to make it. Of course, we have overcome these issues, and
are progressing steadily.
To begin, one of the biggest issues the project faced was budget. We started the project with the
hopes that the given budget from the university will be sufficient. However, with time, we
discovered that the parts needed to complete the project will cost a lot of money, so we sought
some companies to support us, and found a candidate in Aljaber Group, where they offered to
make the parts we asked for for free. That turned out in a bad way, however, as the company
decided to cancel its sponsorship a mere two weeks from the delivery deadline. This threw a
wrench in our plan, as we now had to find a source of money to pay the amount of money
Aljaber asked for. We did so by paying the down payment from our own pockets (9850 AED),
and we are expected to pay the next amount by the middle of the month. We tried to resolve the
issue by making the university reallocate some of an old project that the SDP project leader
worked on, but the university claims that the transfer will take at least a month to complete, so in
the meantime we will have to pay the rest of the money from our own pockets.
Another external issue we faced is the delay from the manufacturer. The parts we needed from
Aljaber were given to them as drawings and explained since the middle of January. However,
with all the delays, and the slow progress due to the long chains of authority any decision has to
go through, the companies were very slow to respond to anything we propose to them. This issue
was made worse by the university, where it has the same attitude of long chains of authority for
any decision especially if it is related to money. We got assurances that we will get the money
we spent on the project, but that will take some time.
Another challenge we had to go through is the manufacturing itself. Making parts in the
computer is easy, but designing and building them for the real world is a different issue. That
became evident when we decided to manufacture the parts of the project in the university. While
most of the parts have had no major issues to them, some parts were very difficult to
manufacture, and required precision, fittings and tests to ensure that the perfectly fit to our liking.
Another issue is our access to the manufacturing lab in the university. Of course, to work in the
lab, the lab engineer has to be present. However, the lab engineer is only available from Sunday
till Thursday until 5 pm. This means that we can only work on manufacturing the parts on these
times, and that we cannot work in the weekend or late each day. This makes producing the parts
slow.
Financial Statement:
For any project to become a reality, purchasing parts, equipment and material are vital. As such,
each project has a financial statement that should list the things, from where we got them, and
how much did it cost. Of course, the details of the purchases are listed in the appendix.
8. Next Steps:
In the next stages, since we are reaching the final weeks of the project, the machine should be
assembled, tested, and checked. The steps can be summarised in the following points:
● Finishing the parts that we are supposed to finish in the university
● Sort out all the financial issues with all the locations
● Building the machine: the parts should arrive from the manufacturers by next week. We
need to check all the parts and make sure that they fit perfectly.
● Finishing the programming: the arduino programming is almost finished. The next step
would to make it work with the components that we have in the machine (relay and the
motor). This could be done once we have the components delivered to us.
● Testing the soil: while not important for the operation, the soil could be tested to
determine the optimal pressure for the machine to press on. However, this is not
important, as the pressure designated for the bricks is rated at 9-10 tons from the
literature. Therefore, applying said pressure on the soil for 10 seconds will be sufficient
to form the brick.
● Buying the oil for the hydraulic: while Power Hydraulics has agreed to provide us with
the hydraulic system, it will not provide us with hydraulic oil for operation. We need to
buy our own supply of oil.
● Buying the columns for the machine: this is the only component left where we haven’t
decided from where it will be from. Most probably, we will buy such columns from the
local market, as we have all the dimensions and numbers to support our dimensions.
9. Appendix
void loop() {
switchState1 = digitalRead(switch1);
switchState2 = digitalRead(switch2);
switchState3 = digitalRead(switch3);
if(switchState1 == LOW) {
digitalWrite(LED1 , LOW);
}
else {
digitalWrite(LED1 , HIGH);
}
if(switchState2 == LOW) {
digitalWrite(LED2, LOW);
}
else {
digitalWrite(LED2, HIGH);
}
if(switchState3 == LOW) {
digitalWrite(LED3, LOW);
}
else {
digitalWrite(LED3, HIGH);
}
}
10. References
[1] E.A.Adam, "Compressed Stabilised Earth Block Manufacture in Sudan," United Nations
Educational, Scientific and Cultural Organization, Paris, 2001.
[7]J. Nussey, Arduino for dummies. Chichester, U.K.: J. Wiley & Sons, 2013.