NCB-10 , Quantities and Proposed Rated for VO-2

Rate

Original Quantity After Revised % Change in Contract Revised Estimate (Rate


S.N Item Description Quantity VO-1 Quantity Quantity Original Estimate Rate proposed by contractor)
Road-1 : Mudikuwa-Lunkhu Road
3.1.3 (1) Gabion Work 8154.70 9543.82 10625.50 30.30% 4385.55 4100.00
Upto 25% Excess 10193.38 4100.00
Beyonnd 25% 432.13 6264.14
3.1.3 (4) Masonry Work 8145.85 10,182.18 11967.64 46.92% 8627.24 7500.00
Upto 25% Excess 10182.31 7500.00
Beyonnd 25% 1785.32 11487.69
Quantity
in Cum
Road-2 : Armadi-banau Road
3.2.3 (1) Gabion Work 9047.77 9047.77 10067.00 11.26% 4391.73 4200.00 4200.00

3.2.3 (4) Masonry Work 12478.64 12478.64 13782.08 10.45% 8231.84 7500.00 7500.00

Quantity Rate
New Items (Proposed in VO-2) 1 Metal Beam Crash Barrier - Both Roads 60 RM 9306.37
2 Road Marking- Both Roads 2525.50 Sqm 388.51
3 200mm HDPE Pipe for Irrigation Crossing - Road 1 135.20 Rm 2,842.58