MTN Rwanda

Manual of Procedure

MOP for Link Packet Congestion troubleshoot

Prepared by Abdul Mvunabandi


November 2020
1. Introduction
This document describes general Method of procedure for Link spacing channel, modulation
change.
1.1 Scope.

Link Congestion and Packet capacity upgrade on KABEZA-BUSANZA

2. Activity Details

 Health check performance


 Save TN report and print screen data
 Change spacing channel, modulation according to new Link Budget Plan
 Confirm Packet Capacity Upgrade improvement

3. Overview of procedures
Step Action Detail Content Responsibility
Site Login Call MTN NOC before start of activity. MTN NOC to
1 Lambert
verify services status before start of the activity.
Save backup configuration file, TN report and print
2 Login to the node screen before start of activity. Lambert

Step-1 Change spacing channel, modulation according to


3 new Link Budget Plan Lambert

Step-2
5 Confirm packet capacity upgrade improvement Lambert

Site Logout
6 Call MTN NOC after completion of activity. Lambert
4. Schedule and timeline

 This activity scheduled Thursday 12th November 2020 from 00:00am to 3:00am
 Maximum expected outage: 3 hours

5. Service Impact during implementation


5.1 Downtime

1. K057 BUSANZA, K250 NYARUGUNGA, K438 URUKUNDO 2G and 3G Going down


during activity

6. Post activity requisites

o MTN Engineer to support in Monitoring the nodes during the day

o MTN Engineer to support in case of any issues or emergencies caused by post activity

7. Roll back Procedure


 Roll back to initial set up.

 Check the status of the link and all alarms if cleared/OK.

 Confirm with NOC if all the services are restored.