Item Activity Specs Item Unit Qty Rate (TSHS) Amount (TSHS)
Item Activity Specs Item Unit Qty Rate (TSHS) Amount (TSHS)
Bills of Quantities for Spot Improvement, and Culverts Construction along Somanga Health Centre (0.6km), Miteja-
Mtoni (5km) roads
Bill 1. Preliminary and general cost
item Activity Specs Unit Qty Rate Amount
item (Tshs) (Tshs)
Drainage Works
3.01d Excavate for new Mitre drains 3.03 m3 384 4,500.00 1,728,000.00
3.02a Excavation for drainage structures 3.03 m3 6 6,000.00 36,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 45 15,000.00 675,000.00
4.27c Concrete pipe culvert - 900mm 3.07c m 8 550,000.00 4,400,000.00
3.09b Concrete in drainage structure bedding - class 15 3.08 m3 2
280,000.00
560,000.00
3.09c Concrete in drainage structure -class 20 3.08 m3 6 350,000.00 2,100,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 40 50,000.00 2,000,000.00
2.07a Overhaul gravel 2.1 M Km
3
1,600 15,000.00 24,000,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 45 4,000.00 180,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 15 9,000.00 135,000.00
Sub Total Drainage works 35,814,000.00
Total for Bill No. 2 222,429,000.00
Drainage Works
3.01d Excavate for new Mitre drains 3.03 m3 1200 4,500.00 5,400,000.00
3.02a Excavation for drainage structures 3.03 m3 24 6,000.00 144,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 432 15,000.00 6,480,000.00
4.27c Concrete pipe culvert - 900mm 3.07c m 32 550,000.00 17,600,000.00
3.09b Concrete in drainage structure bedding - class 3.08 m3 8
15
280,000.00
2,240,000.00
3.09c Concrete in drainage structure -class 20 3.08 m3 24 350,000.00 8,400,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 80 50,000.00 4,000,000.00
2.07a Overhaul gravel 2.1 M Km
3
1,280 20,000.00 25,600,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 180 4,000.00 720,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 60 15,000.00 900,000.00
Sub Total Drainage works 71,484,000.00
1
Total for Bill No. 3 216,384,000.00
SUMMARY
BILL NO. ROAD NAME AMOUNT (TSHS)
BILL NO. 1 Preliminary and General
43,500,000.00
cost
BILL NO. 2 Somanga Health Centre
222,429,000.00
(0.6km)
BILL NO.3 Miteja-Mtoni (5km) 216,384,000.00
TOTAL 482,313,000.00
GRAND TOTAL +VAT 569,129,340.00
2
Kilwa District Council
Bills of Quantities for Routine Maintanance, Spot Improvement, and Culverts Construction along Namayuni-Namakolo
(5.5km), Chumo-Ingirito (5km) roads
Bill 1. Preliminary and general cost
item Activity Specs Unit Qty Rate Amount
item (Tshs) (Tshs)
Drainage Works
3.01d Excavate for new Mitre drains 3.03 m3 450 4,500.00 2,025,000.00
3.02a Excavation for drainage structures 3.03 m3 24 6,000.00 144,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 450 15,000.00 6,750,000.00
4.27c Concrete pipe culvert - 900mm 3.07c m 24 550,000.00 13,200,000.00
3.09b Concrete in drainage structure bedding - class 15 3.08 m3 6
280,000.00
1,680,000.00
3.09c Concrete in drainage structure -class 20 3.08 m3 22 350,000.00 7,700,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 60 50,000.00 3,000,000.00
2.07a Overhaul gravel 2.1 M Km
3
450 15,000.00 6,750,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 135 4,000.00 540,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 45 9,000.00 405,000.00
Sub Total Drainage works 42,194,000.00
Total for Bill No. 2 186,424,000.00
Drainage Works
3.01d Excavate for new Mitre drains 3.03 m3 500 12000 6,000,000.00
Sub Total Drainage works 6,000,000.00
3
Total for Bill No. 3 80,940,000.00
SUMMARY
BILL NO. ROAD NAME AMOUNT (TSHS)
BILL NO. 1 Preliminary and General cost
43,000,000.00
Drainage Works
3.01d Excavate for new Mitre drains 3.03 m3 150 4,500.00 675,000.00
3.02a Excavation for drainage structures 3.03 m3 6 6,000.00 36,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 45 15,000.00 675,000.00
4.27c Concrete pipe culvert - 900mm 3.07c m 8 550,000.00 4,400,000.00
3.09b Concrete in drainage structure bedding - class 3.08 m3 2
280,000.00 560,000.00
15
3.09c Concrete in drainage structure -class 20 3.08 m3 6 350,000.00 2,100,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 40 50,000.00 2,000,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 50 4,000.00 200,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 15 9,000.00 135,000.00
Sub Total Drainage works 10,781,000.00
Total for Bill No. 3 211,556,000.00
Drainage Works
3.01d Excavate for new catch water drains 3.03 m3 600 4,500.00 2,700,000.00
3.02a Excavation for drainage structures 3.03 m3 6 6,000.00 36,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 45 15,000.00 675,000.00
4.27c Concrete pipe culvert - 900mm 3.07c m 8 550,000.00 4,400,000.00
3.09b Concrete in drainage structure bedding - class 3.08 m3 2
280,000.00 560,000.00
15
3.09c Concrete in drainage structure -class 20 3.08 m3 6 350,000.00 2,100,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 40 50,000.00 2,000,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 50 4,000.00 200,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 15 9,000.00 135,000.00
Sub Total Drainage works 12,806,000.00
Total for Bill No. 4 44,216,000.00
Drainage Works
3.01d Excavate for new catch water drains 3.03 m3 600 4500 2,700,000.00
3.02a Excavation for drainage structures 3.03 m3 6 6000 36,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 45 15000 675,000.00
4.27c Concrete pipe culvert - 600mm 3.07c m 8 550000 4,400,000.00
3.09b Concrete in drainage structure bedding - class 3.08 m3 2 280000 560,000.00
3.09c Concrete in drainage structure -class 20 3.08 m3 6 350000 2,100,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 40 50000 2,000,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 50 4000 200,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 15 9000 135,000.00
Sub Total Drainage works 12,806,000.00
Total for Bill No. 5 73,945,000.00
BILL 6: 81022: Biaza (0.36km) road Spot Improvement
Road Works
2.05a Heavy Grading 2.4 Km 0.36 6,000,000.00 2,160,000.00
2.06 Gravelling within FHD 150 mm thick gravel wearing 2.90 m3 351
course
150,000.00 52,650,000.00
Sub Total for Spot Improvement 54,810,000.00
Drainage Works
3.01d Excavate for new catch water drains 3.03 m3 600 4,500.00 2,700,000.00
3.02a Excavation for drainage structures 3.03 m3 6 6,000.00 36,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 45 15,000.00 675,000.00
4.27c Concrete pipe culvert - 900mm 3.07c m 8 550,000.00 4,400,000.00
3.09b Concrete in drainage structure bedding - class 15 3.08 2 280,000.00
m3 560,000.00
3.09c Concrete in drainage structure -class 20 3.08 m3 6 350,000.00 2,100,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 40 50,000.00 2,000,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 50 4,000.00 200,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 15 9,000.00 135,000.00
Sub Total Drainage works 12,806,000.00
Total for Bill No. 6 67,616,000.00
SUMMARY
BILL NO. ROAD NAME AMOUNT (TSHS)
BILL NO. 1 Preliminary and General cost
18,500,000.00
BILL NO. 2 Mapinduzi (260m LD) 29,544,000.00
BILL NO. 3 Nangurukuru-Zahanati (1km)
211,556,000.00
BILL NO. 4 Manzese (0.2km) 44,216,000.00
BILL NO. 5 Bibi Catherin (0.82km)
73,945,000.00
BILL NO. 6 Biaza (0.36km) 67,616,000.00
TOTAL 445,377,000.00
GRAND TOTAL +VAT 525,544,860.00