Professional Documents
Culture Documents
Faculty of Engineering
Department of Chemical Engineering
Project
Course: Equipment design
CHE 471
1
Table of content:
Abstract: .......................................................................................................................................... 3
Introduction: .................................................................................................................................... 4
Path Selection: ................................................................................................................................ 4
Material of construction: ................................................................................................................. 5
Crude oil properties: ....................................................................................................................... 5
Design: ............................................................................................................................................ 6
Piping design:.............................................................................................................................. 7
Friction calculations: ................................................................................................................... 9
Pipe friction:............................................................................................................................ 9
Fittings friction: ...................................................................................................................... 9
Work Calculations .................................................................................................................... 10
Number of Pumps ................................................................................................................. 11
Pump Station: ........................................................................................................................ 12
Cost ............................................................................................................................................... 13
Pipe cost: ................................................................................................................................... 13
Pump Cost: ............................................................................................................................ 13
Valve Cost ................................................................................................................................. 13
Fittings Cost .............................................................................................................................. 14
Stand by Cost ............................................................................................................................ 14
Cost of Operating: ..................................................................................................................... 15
Total Cost .................................................................................................................................. 16
References: .................................................................................................................................... 17
List of Table
Table 1: Distance and elevations for the selected path. .................................................................. 6
Table 2 Frictions Calculations ........................................................................................................ 7
Table 3 Work and Power Calculations ......................................................................................... 10
Table 4 Pump Stations Calculations ............................................................................................. 12
List of Figures
Figure 1: the selected path using Google Maps .............................................................................. 5
Figure 2 Stand By Line ................................................................................................................. 15
2
Abstract:
Total cost for this project was calculated and it equal Capital cost = $101,442,225.
In another hand, Cost of Operating = $24,541,600.57 for one year.
3
Introduction:
It is desired to pump 150000 bbl/day of light crude oil from Kirkuk, Iraq to Haifa Palestine,
while using suitable material of construction, select closest way and considering physical laws,
safety regulations, standards and codes, and economical value. Furthermore, assumptions will be
taken a place in calculations.
Path Selection:
The path was between Iraq (Kirkuk) and Palestine (Haifa). It was chosen to be near cities,
highways, and internal streets. However, it took several changes in direction to stay as much as
possible near them and this was to decrease the generators and electrical power required
subsequently decreasing the total cost. In addition, to avoid smashing streets or building.
Also, it was chosen to avoid rivers and watercourses, and this was taken a place to decreasing the
energy required and cost for it.
The distance between the two cities was 1102 km, and it passes through 3 countries which are
Iraq, Jordan, and Palestine. And the path was chosen to be the closest way, while taking the
mentioned factors in consider.
The following figure shows the path and the elevation differences starting from Kirkuk (344m)
above the sea level and ending with Haifa (0 m).
4
Figure 1: the selected path using Google Maps
Material of construction:
Choosing a suitable material of construction is the most important step in the design, and the
decision taken is based on two factors, one is the corrosion rate of the material with both the
environmental factors and the fluid it interacts with, and the other is cost per meter length of the
pipe. Carbon steel meets the latter factors so it will be the material of construction for the
pipeline designed in the project including pipes, valves and fittings
5
the pipes and valves from taking high load pressure. However, density at 20 0C is 933.1(kg/m3)
and viscosity is (9.095 cp).
Design:
The following calculations were tabled to show the Nominal Pipe Size (NPS), the friction loss in
the system, the required power for the pumps, the efficiency for the pump and the number of
pumps required in the system, these calculations will help us to select a suitable pump and pipe
size.
At first, the distance was measured by using Google Earth [1], the elevations differences along the
selected path, and the horizontal distance for each elevation change. Then, all of this is tabled in
(table1).
6
Then, after studying the properties of the crude oil, the condition that it will go through, and
choosing the suitable material of construction, it was assumed turbulent flow using equation [3] to
calculate the optimum diameter at the specific conditions, and it was found to be (0.4947 m) but
it was neglected because it does not give the desired flowrate. So, to find the optimum diameter
the calculation was repeated to find new velocity value then check whether it was suitable or not.
Finally, the value which was estimated for inner diameter at the given conditions was (23.25 in)
with nominal pipe size 24 and schedule number is 20.
After finding the optimum values, calculations were tabled in (table2):
The equations that have been used to fill the table and find the calculated values:
As it was mentioned before, it was assumed to have turbulent flow, so to ensure that the
assumption was correct, Reynolds number must be checked:
Piping design:
7
After finding the diameter the velocity must be calculated:
𝑄 0.276 𝑚
𝑣=𝐴=𝜋 = 1.4359
∗0.49472 𝑠
4
When Reynolds value calculated is higher than 2100, therefore the assumption is correct. Since
the assumption is correct, the value of nominal pipe size must be found:
Now, from table (D-13) [4], at 𝐷 = 0.4947 𝑚 = 19.476 𝑖𝑛𝑐ℎ ,then the value of nominal pipe size
is 20in, and schedule number is 20. So, optimum diameter = 20 in.
Now checking whether the optimum diameter can give the required flowrate:
𝑚3 𝑚3
ṁ𝑣 = 0.2688 , which is less than the required flowrate ṁ𝑣𝑟𝑒𝑞 = 0.276 .
𝑠 𝑠
So that, for safety the (NPS) that must be taken from table (D-13) [4], is 24 with Sch# 20, with an
𝐷𝑖,𝑜𝑝 = 23.25 𝑖𝑛 = 0.59005 𝑚.
Then, by repeating the calculation to check whether it will give the required flowrate or not:
𝑚3 𝑚3
ṁ𝑣 = 0.409 𝑠 , which is higher than the required flowrate ṁ𝑣𝑟𝑒𝑞 = 0.276 , and this must be
𝑠
suitable.
Then, velocity and Reynolds number must be calculated:
𝑄 0.276 𝑚
𝑣=𝐴=𝜋 2
= 1.0076 𝑠
∗0.59055
4
8
𝑘𝑔 𝑚
𝜌𝐷𝑣 933.1 3 ∗1.0076 ∗0.59055 𝑚
𝑚 𝑠
𝑅𝑒 = = = 56027.25 >> 2100, then the turbulent assumption is
𝜇 0.009905 𝑝𝑎.𝑠
correct.
Friction calculations:
Pipe friction:
Since it is used Carbon-Steel welded pipe, the relative roughness 𝜀 = 0.046 𝑚𝑚, so
𝜀 0.046∗10−3
= = 7.8 ∗ 10−5 , 𝑅𝑒 = 56027 , by using Moody chart [4]:
𝐷 0.59055
𝑓 = 0.02067
Fittings friction:
When calculating the fittings friction, it must be mentioned what fittings will be used along the
path, which are:
a- 14 (450) elbows.
b- 3 (900) elbows.
c- 100 Gate Valve
𝐾𝑓 .𝑣 2
𝐹𝑒𝑙𝑏𝑜𝑤 = 2
9
Table 3 Work and Power Calculations
W (N.m/Kg) Power eff 80% (W) # Pumpes Actual Pump eff 80% #Pump
2684.619805 864231.4655 1.325406741 1.656758426 2
1350.341817 434701.3626 0.666668756 0.833335946 1
13216.63832 4254693.601 6.525103291 8.156379114 9
21920.51616 7056641.602 10.82224002 13.52780002 14
414.0055976 133276.475 0.204396097 0.255495121 1
9963.93306 3207584.349 4.919230655 6.149038319 7
8395.10583 2702548.271 4.144694841 5.180868552 6
6214.649232 2000616.773 3.068195343 3.835244179 4
-60.72760944 -19549.40167 No need No need No Need
5363.547608 1726630.564 2.648003319 3.310004149 4
638.1830125 205443.5563 0.315073317 0.393841646 1
1951.327705 628170.4392 0.963377715 1.204222144 2
-243.9191849 -78522.34204 No need No need No Need
1135.31962 365481.5244 0.560511501 0.700639376 1
-5547.948971 -1785992.959 No need No need No Need
5533.931057 1781480.319 2.732122259 3.415152824 4
2019.342923 650065.864 0.99695708 1.24619635 2
Work Calculations
ASSUME:
ΔV²/2α term = 0
Because V1 = V2 in the pipe and V1 = V2 =0 in the start and end of the path so ΔV = 0
P1=P2 = atmospheric pressure so ΔP = 0 we will neglect the change of the atmospheric pressure
with elevation change because it a low values compares with other terms
𝒘 = 𝒈(𝒛𝟏 − 𝒛𝟐) + ∑𝑭
10
F long pipe = (2fV²L)/D
To calculate f :
𝜖 = 0.046 mm
D = 590.55 mm
𝜖/𝐷 = 7.7893*10-5
Re=56027.253
f from moody diagram
f= 0.02067
Power = Wtot * Q * 𝜌
P = 80801.46175*0.276*933.1
= 20809254.32 W
Power = 26011566.17 W
Number of Pumps
To calculate Ps :
Ss=94500 Kpa
Ps= 1890000 Pa
11
So we need 50 Station pump
Pump Station:
Dis = L/ #Pumps
12
Cost
Pipe cost:
Pipe Cost
• Material of construction: the carbon steel welded pipe
• Inner diameter = 23.25 in = 0.59055m
• Sch #20
Pump Cost:
Centrifugal pump was chosen; simple and inexpensive and has a low maintenance cost with
high efficiency.
Valve Cost
For each Pump stage we need 2 Gate valves, for safety and maintenance so 50*2 =100 Gate
valves.
13
Cost of gate valve at 2070 Kpa = $10000
Fittings Cost
Stand by Cost
To have a Stand by we need a pump for each pump and a tee and 2 vavles.
14
Figure 2 Stand By Line
Cost of Operating:
Assuming the system need 2 weeks for maintenance over 1 year, so the number of working is
351 day/ year
In 351 day = 26011.5662 KW*351*24 h/day = 219,121,433.7 KWh for one year
15
Total Cost
Capital cost = Cost Pipes +Cost fittings + Cost Pumps + Cost valves + Installation Cost
16
References:
1. Eduardo D. Glandt, M. T. K. F. E., 2003. Plant Design and Economics for chemical
engineers 5th eddition. New York: University of Colorado.
2. Google earth.
3. www.propertiesofmatter.si.edu/Changing_Temp.html.
4. www.petro-online.com/article/analytical-instrumentation/11/anton-paar/the-facts-
andnbspfigures-of-digitalnbspdensity-measurement-nbsp/1304
5. http://belgo.6te.net/doc/Iraqi%20Kirkuk%20Light%20Crude%20Oil.pdf?fbclid=IwAR1pYd0zgtq3l
_wExs6NTPBlYy79YEOBM6USXc4pRsAAprvGuVLbKoBTW1U
6. http://blog.dwyer-inst.com/2018/08/29/common-valves-used-in-theoil-gas-
industry/#sthash.34DPgnpU.dpbs
7. https://www.globalpetrolprices.com/Iraq/electricity_prices/
8. Viscosity of Crude Oil – viscosity table and viscosity chart :: Anton Paar Wiki (anton-
paar.com)
17