Assumption:This schedule is base on the "Milestone Schedule" in item "1.

Project:Prefabrication and Pipe Stacking Yard Construction Date Revision Checked Approved
Doc. no:
Service Period" as captured in "Attachment 4: Scope of Work" 18-June-20 00:... REV 1 J.K M. J

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish A A A A A S S S S O O O O N N N N N D D D D J


Duration Complete

85d 85d 0% 03-Aug-20 27-Nov-20 17:00 27-Nov-20 17:00, Prefabrication and Pipe Stacking Yard
Prefabrication and Pipe Stacking Yard Construction
08:00
Milestone Summary 85d 85d 0% 03-Aug-20 08:00
27-Nov-20 17:00 27-Nov-20 17:00, Milestone Summary

A1440 Milestone 1: Commencement of the contract 0d 0d 0% 03-Aug-20 08:00 Milestone 1: Commencement of the contract
A1450 Milestone 2: Personnel and Equipment mobilized at site. 0d 0d 0% 07-Aug-20 17:00 Milestone 2: Personnel and Equipment mobilized at site.
A1460 Milestone 3: Procurement Complete 0d 0d 0% 07-Aug-20 17:00 Milestone 3: Procurement Complete
A1470 Milestone 4: Civil Work Complete 0d 0d 0% 18-Sep-20 17:00 Milestone 4: Civil Work Complete
A1480 Milestone 5: Structure and Mechanical Work Complete 0d 0d 0% 24-Sep-20 17:00 Milestone 5: Structure and Mechanical Work Complete
A1490 Milestone 6: Electrical and Instrument Complete 0d 0d 0% 28-Sep-20 17:00 Milestone 6: Electrical and Instrument Complete
A1500 Milestone 7: Water Supply and Drainage System Complete 0d 0d 0% 30-Oct-20 17:00 Milestone 7: Water Supply and Drainage System Complete
A1510 Milestone 8: Commissioning Complete 0d 0d 0% 06-Nov-20 17:00 Milestone 8: Commissioning Complete
A1520 Milestone 9: Check and approve by CLIEN 0d 0d 0% 13-Nov-20 17:00 Milestone 9: Check and approve by CLIEN
A1530 Milestone 10: Fabrication Yard Handover 0d 0d 0% 27-Nov-20 17:00 Milestone 10: Fabrication Yard Handover

Commencement of the contract 0d 0d 0% 03-Aug-20 08:00


03-Aug-20 08:00 03-Aug-20 08:00, Commencement of the contract

A1000 Commencement of the contract 0d 0d 0% 03-Aug-20 08:00 Commencement of the contract

Personnel and Equipment mobilized at site. 5d 5d 0% 03-Aug-20 08:00


07-Aug-20 17:00 07-Aug-20 17:00, Personnel and Equipment mobilized at site.

A1010 Personnel 5d 5d 0% 03-Aug-20 08:00


07-Aug-20 17:00 Personnel
A1020 Equipment 5d 5d 0% 03-Aug-20 08:00
07-Aug-20 17:00 Equipment
A1030 Mobilized at site complete 0d 0d 0% 03-Aug-20 08:00 Mobilized at site complete

Procurement 5d 5d 0% 03-Aug-20 08:00


07-Aug-20 17:00 07-Aug-20 17:00, Procurement

A1040 Procurement of material 5d 5d 0% 03-Aug-20 08:00


07-Aug-20 17:00 Procurement of material
A1050 Procurement of consumable 5d 5d 0% 03-Aug-20 08:00
07-Aug-20 17:00 Procurement of consumable
A1060 Procurement Complete 0d 0d 0% 07-Aug-20 17:00 Procurement Complete

Civil Work 30d 30d 0% 10-Aug-20 08:00


18-Sep-20 17:00 18-Sep-20 17:00, Civil Work

A1070 construction of ditch 5d 5d 0% 10-Aug-20 08:00*


14-Aug-20 17:00 construction of ditch

A1080 construction of chain link mesh 5d 5d 0% 17-Aug-20 08:00*


21-Aug-20 17:00 construction of chain link mesh
A1090 construction of block wall 8d 8d 0% 17-Aug-20 08:00*
26-Aug-20 17:00 construction of block wall
A1100 construction of Road 8d 8d 0% 21-Aug-20 08:00*
01-Sep-20 17:00 construction of Road
A1110 Construction of watch tower 8d 8d 0% 02-Sep-20 08:00*
11-Sep-20 17:00 Construction of watch tower
A1120 Construction of Septic Tank 5d 5d 0% 14-Sep-20 08:00*
18-Sep-20 17:00 Construction of Septic Tank
A1130 Civil Work Complete 0d 0d 0% 18-Sep-20 17:00 Civil Work Complete

Structure and Mechanical Work 30d 30d 0% 14-Aug-20 08:00


24-Sep-20 17:00 24-Sep-20 17:00, Structure and Mechanical Work

A1140 Construction of Warehouse-01 10d 10d 0% 14-Aug-20 08:00*


27-Aug-20 17:00 Construction of Warehouse-01
A1150 Construction Steel structural Shed 10d 10d 0% 28-Aug-20 08:00*
10-Sep-20 17:00 Construction Steel structural Shed
A1160 Construction of Training centre steel structural shelter 10d 10d 0% 11-Sep-20 08:00*
24-Sep-20 17:00 Construction of Training centre steel structural shelter
A1170 Structural & Mechanical complete 0d 0d 0% 24-Sep-20 17:00 Structural & Mechanical complete

Electrical and Instrument Complete 28d 28d 0% 20-Aug-20 08:00


28-Sep-20 17:00 28-Sep-20 17:00, Electrical and Instrument Complete

A1180 Fabricate and install support of MDB and DBs 3d 3d 0% 20-Aug-20 08:00*
24-Aug-20 17:00 Fabricate and install support of MDB and DBs
A1190 Fabricate and install support for lighting 5d 5d 0% 25-Aug-20 08:00
31-Aug-20 17:00 Fabricate and install support for lighting
A1340 Fabrication & installation of Street Lighting 5d 5d 0% 01-Sep-20 08:00
07-Sep-20 17:00 Fabrication & installation of Street Lighting
A1350 Installation of Fence Lighting 5d 5d 0% 08-Sep-20 08:00
14-Sep-20 17:00 Installation of Fence Lighting
A1360 Installation of Watch tower Lighting 5d 5d 0% 15-Sep-20 21-Sep-20 17:00 Installation of Watch tower Lighting
08:00
A1370 Installation of Courtyard Lighting 5d 5d 0% 22-Sep-20 08:00
28-Sep-20 17:00 Installation of Courtyard Lighting
A1410 Electrical and Instrument Complete 0d 0d 0% 28-Sep-20 17:00 Electrical and Instrument Complete

Water Supply and Drainage System Complete 44d 44d 0% 01-Sep-20 08:00
30-Oct-20 17:00 30-Oct-20 17:00, Water Supply and Drainage System Complete

Actual Work Critical Remaining Work Summary   TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


Assumption:This schedule is base on the "Milestone Schedule" in item "1. Project:Prefabrication and Pipe Stacking Yard Construction Date Revision Checked Approved
Doc. no:
Service Period" as captured in "Attachment 4: Scope of Work" 18-June-20 00:... REV 1 J.K M. J

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish A A A A A S S S S O O O O N N N N N D D D D J


Duration Complete

A1200 installation of Deep Well Pump 2d 2d 0% 01-Sep-20 08:00*


02-Sep-20 17:00 installation of Deep Well Pump
A1210 installation of water lift pump 2d 2d 0% 03-Sep-20 08:00
04-Sep-20 17:00 installation of water lift pump
A1220 Construction of Water Tank 10d 10d 0% 07-Sep-20 08:00
18-Sep-20 17:00 Construction of Water Tank
A1230 Installation of Water Supply inside Steel Structure Builidings 5d 5d 0% 21-Sep-20 08:00
25-Sep-20 17:00 Installation of Water Supply inside Steel Structure Builidings
A1240 Installation of Water Supply inside Foldable and Movable Containers 5d 5d 0% 28-Sep-20 08:00
02-Oct-20 17:00 Installation of Water Supply inside Foldable and Movable Containers
A1250 Installation of External Water Supply Syestem 5d 5d 0% 05-Oct-20 08:00
09-Oct-20 17:00 Installation of External Water Supply Syestem
A1260 Construction of Water Drainage inside Steel Structure Builidings 5d 5d 0% 12-Oct-20 08:00
16-Oct-20 17:00 Construction of Water Drainage inside Steel Structure Builidings
A1270 Construction of External Water Drainage Syestem 5d 5d 0% 19-Oct-20 08:00
23-Oct-20 17:00 Construction of External Water Drainage Syestem
A1280 Construction of Drainage outside building tie-in external drainage system 5d 5d 0% 26-Oct-20 08:00
30-Oct-20 17:00 Construction of Drainage outside building tie-in external drainage system
A1290 Water Supply and Drainage System Complete 0d 0d 0% 30-Oct-20 17:00 Water Supply and Drainage System Complete

Commissioning 5d 5d 0% 02-Nov-20 08:00


06-Nov-20 17:00 06-Nov-20 17:00, Commissioning

A1300 Commissioning of Mechanical system 5d 5d 0% 02-Nov-20 08:00*


06-Nov-20 17:00 Commissioning of Mechanical system
A1310 Commissioning of Electrical & instrument system 5d 5d 0% 02-Nov-20 08:00
06-Nov-20 17:00 Commissioning of Electrical & instrument system
A1320 Commissioning complete 0d 0d 0% 06-Nov-20 17:00 Commissioning complete

Check and approve by CLIEN 5d 5d 0% 09-Nov-20 08:00


13-Nov-20 17:00 13-Nov-20 17:00, Check and approve by CLIEN

A1380 Check and approve by CLIEN 5d 5d 0% 09-Nov-20 08:00


13-Nov-20 17:00 Check and approve by CLIEN
A1420 Check and approve by CLIEN complete 0d 0d 0% 09-Nov-20 08:00 Check and approve by CLIEN complete

Fabrication Yard Handover 10d 10d 0% 16-Nov-20 08:00


27-Nov-20 17:00 27-Nov-20 17:00, Fabrication Yard Handover

A1390 Fabrication Yard Handover 10d 10d 0% 16-Nov-20 08:00*


27-Nov-20 17:00 Fabrication Yard Handover
A1430 Fabrication Yard Handover complete 0d 0d 0% 27-Nov-20 08:00 Fabrication Yard Handover complete

Actual Work Critical Remaining Work Summary   TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation