Professional Documents
Culture Documents
Prefabrication and Pipe Stacking Yard Construction PDF
Prefabrication and Pipe Stacking Yard Construction PDF
Project:Prefabrication and Pipe Stacking Yard Construction Date Revision Checked Approved
Doc. no:
Service Period" as captured in "Attachment 4: Scope of Work" 18-June-20 00:... REV 1 J.K M. J
85d 85d 0% 03-Aug-20 27-Nov-20 17:00 27-Nov-20 17:00, Prefabrication and Pipe Stacking Yard
Prefabrication and Pipe Stacking Yard Construction
08:00
Milestone Summary 85d 85d 0% 03-Aug-20 08:00
27-Nov-20 17:00 27-Nov-20 17:00, Milestone Summary
A1440 Milestone 1: Commencement of the contract 0d 0d 0% 03-Aug-20 08:00 Milestone 1: Commencement of the contract
A1450 Milestone 2: Personnel and Equipment mobilized at site. 0d 0d 0% 07-Aug-20 17:00 Milestone 2: Personnel and Equipment mobilized at site.
A1460 Milestone 3: Procurement Complete 0d 0d 0% 07-Aug-20 17:00 Milestone 3: Procurement Complete
A1470 Milestone 4: Civil Work Complete 0d 0d 0% 18-Sep-20 17:00 Milestone 4: Civil Work Complete
A1480 Milestone 5: Structure and Mechanical Work Complete 0d 0d 0% 24-Sep-20 17:00 Milestone 5: Structure and Mechanical Work Complete
A1490 Milestone 6: Electrical and Instrument Complete 0d 0d 0% 28-Sep-20 17:00 Milestone 6: Electrical and Instrument Complete
A1500 Milestone 7: Water Supply and Drainage System Complete 0d 0d 0% 30-Oct-20 17:00 Milestone 7: Water Supply and Drainage System Complete
A1510 Milestone 8: Commissioning Complete 0d 0d 0% 06-Nov-20 17:00 Milestone 8: Commissioning Complete
A1520 Milestone 9: Check and approve by CLIEN 0d 0d 0% 13-Nov-20 17:00 Milestone 9: Check and approve by CLIEN
A1530 Milestone 10: Fabrication Yard Handover 0d 0d 0% 27-Nov-20 17:00 Milestone 10: Fabrication Yard Handover
A1180 Fabricate and install support of MDB and DBs 3d 3d 0% 20-Aug-20 08:00*
24-Aug-20 17:00 Fabricate and install support of MDB and DBs
A1190 Fabricate and install support for lighting 5d 5d 0% 25-Aug-20 08:00
31-Aug-20 17:00 Fabricate and install support for lighting
A1340 Fabrication & installation of Street Lighting 5d 5d 0% 01-Sep-20 08:00
07-Sep-20 17:00 Fabrication & installation of Street Lighting
A1350 Installation of Fence Lighting 5d 5d 0% 08-Sep-20 08:00
14-Sep-20 17:00 Installation of Fence Lighting
A1360 Installation of Watch tower Lighting 5d 5d 0% 15-Sep-20 21-Sep-20 17:00 Installation of Watch tower Lighting
08:00
A1370 Installation of Courtyard Lighting 5d 5d 0% 22-Sep-20 08:00
28-Sep-20 17:00 Installation of Courtyard Lighting
A1410 Electrical and Instrument Complete 0d 0d 0% 28-Sep-20 17:00 Electrical and Instrument Complete
Water Supply and Drainage System Complete 44d 44d 0% 01-Sep-20 08:00
30-Oct-20 17:00 30-Oct-20 17:00, Water Supply and Drainage System Complete
Actual Work Critical Remaining Work Summary TASK filter: All Activities
Actual Work Critical Remaining Work Summary TASK filter: All Activities