Professional Documents
Culture Documents
Oman India Fertiliser Company was commissioned in April-2005. The performance in the first five
commercial years of operation has been very good and all the envisaged project targets have been
accomplished. Meticulous Root Cause Analysis of the problems surfaced at various stages have been
analysed by the OMIFCO engineers in close association with the vendors and the consultants and
implementation of the identified corrective measures in the shortest possible time has been the key to
the achieved success of the company.
The paper highlights about a critical Ammonia leak incident that occurred in the Urea 21 plant and
how the situation was analysed to prevent re-occurrence of similar incidents. In chemical Industry,
Careful Root Cause Analysis of the problems is very important and complacency cannot be ensured
unless the remedies identified are convincing and consistent with the findings of the Root Cause
Analysis made.
S G Gedigeri
Oman India Fertiliser Company
O
MAN INDIA FERTILIZER 75000 MT) and Ammonia (2X30000 MT) as
COMPANY S.A.O.C. (OMIFCO) was well as jetty with ship loaders are part of the
set up as a joint venture project under project.
the initiative of Government of Sultanate of
Oman and Government of India. OMIFCO is
owned 50% by Oman Oil Company, 25% by
Indian Farmers Fertilizer Co-Operative Ltd
(IFFCO) and 25% by Krishak Bharati Co-
Operative Ltd (KRIBHCO). OMIFCO was
registered in the Sultanate of Oman as a closed
joint stock company in the year 2000.
21-HV-1021
CO2
High Pressure Ammonia
Ammonia Pump P-101 Ammonia Booster Receiver-V-105
Recycle Ammonium
Carbamate solution Pump P-105
OMIFCO’S HSE (Health, Safety & Photo-02: Weld joint with Sealing Clamp.
Environment) team and the Production staff
controlled and confined the leakage to within
the plant battery limits by using their own fire
tender and the personnel protection appliances.
Causes of Failure:
• The pipe is exposed to sea water atmosphere
and the paint had peeled off at some places
near welding and corrosion has taken place.
• The failure had taken place on account of Photo-08: Low magnification (33X) shows multiple
fatigue cracking assisted by mild corrosion origins in the form of ratchet marks.
initiated at weld and HAZ both from OD and
ID. Fatigue was due to cyclic load caused by
unexpected shutdowns, start-ups, pump
change overs and vibrations on the pipe.
• The prevailing marine atmosphere, the
vibration stresses from the pipe line while in
operation and the surface corrosion that acted
as stress concentration site, had resulted in
corrosion fatigue.
• Low Magnification Examination confirmed
multiple origins of the cracks all over the
circumference starting from both OD as well Photo-09: Presence of corrosion products observed
as ID. (Photo: 07) at the cracked surface.
Percentage Percentage
Elements Elements
Present Present
Oxygen 37.22 Chlorine 1.07
Sodium 1.31 Calcium 0.87
Magnesium 0.87 Iron 57.74
Silicon 0.93
• The prevailing vibrations on the pipe line Micro Hardness Profile did not indicate any
induced the fluctuating stresses. severe abnormality. Values at HAZ and Weld
were slightly on higher side (Refer Figure-03).
Most Probable Cause of failure: forces and moments are noticed at the
restrained points.
• This failure might be due to corrosion,
material defect and internal stresses owing to • Reports also indicated that stresses are
welding joint. within the allowable limits and the failure
of pipe weld joint is not due to
• The stresses might have developed on overstressing.
welding due to injection of sealing compound
and clamping • WFMPI (Wet Fluorescent Magnetic
Particle Inspection), testing and Insitu
metallography of all other weld joints on
Corrective Measures taken: the affected pipe line were examined and
those weld joints which did not pass all the
• Flexibility and stress analysis of the pipe tests were repaired. Radiography was
line from Ammonia receiver (V-105) to the carried out for checking the ID cracking.
Ammonia Booster pumps (P-105-A/B) and
from the discharge of the Ammonia booster • One new On-Off type control valve HV-
pumps to the suction of the HP Ammonia 1013 has been installed on C-101 MP
Pumps (P-101A/B) was carried out Absorber outlet Ammonia vapours line in
separately by a reputed local consultant and both the Urea plants. This will facilitate
a foreign consultant of International repute. quick isolation of C-101 in the event of any
leakage (Figure-04).
• The reports indicated no over stressing at
any point in the pipe line and no alarming
V-105
P-105
C-101
MP Absorber
P-101
H.P Ammonia feed Pump To MP Decomposer
or Flare
LP Steam
P-102
Carbamate Recycle Pump V-101
Carbamate Separator
Condenate Carbamate
HP Stripper Over head Vapors
Condenser
• New on line Breathing Air sets with • Much lower failure stresses and much
extendable hose of 50 meters length have shorter failure times can occur in a corrosive
been provided inside the plant field area to environment compared to the situation
facilitate quick isolation in the event of where the alternating stress is in a non-
Ammonia leaks. corrosive environment.
• Care is being taken for the quality of the • OMIFCO has decided not to do online
painting on the pipe surface particularly sealing for any developed leakages of
near weld joints to avert peeling of paint Ammonia pipe lines.
and subsequent underneath corrosion
damage.
Conclusion:
• Corrosion-fatigue is the result of the
combined action of an alternating or cycling
stresses and a corrosive environment.
• On line sealing of leakages either from pipes
or weld joints should be avoided which
otherwise might cause inadvertent additional
stresses, to the component which has been
already under the influence of some parental
residual stresses.
• Contrary to a pure mechanical fatigue, there
is no fatigue limit load in corrosion-assisted
fatigue.