Site Safety Supervisor


Competency Course

Part V(A) - Site Management


Planning, Program & Budgeting
1
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Course Learning Objectives


Assist the Employer to:
Conduct Preliminary Conduct Table-Top
Appraisal Prior Exercise for Site
Execution of Project Planning

Identify Administrative Determine OSH


Requirements & Programs Budget for the
Project
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
2
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Topics to be Covered

 Introduction

 Phases of Construction Work

 Site Planning

 Site Layout

 OSH Budgeting

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
3
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Introduction
Early Planning is Vital

Workers get Minimise Short Cuts,


Convenient Work Delays, Unsafe Acts &
Progressing Other Problems

Won’t Cost More & Won’t Slow Down Progress


© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
4
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Introduction

Cost

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
5
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Phases of Construction Work

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
6
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Pre-Tender
Preparation of Tender Document

Designs Specifications

Drawings Conditions of
Contract

Incorporate OSH requirements


© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
7
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Tender

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
8
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Contract Management
Execution of Work as per Contract
All Parties have to Implement
Fulfill Contractual OSH Requirements
Obligations

Implementation Monitor
Contractual Implementation of
Obligations OSH Requirements
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
9
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Contract Management
Typical Activities & Flows

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
10
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Contract Management
 Typical plant, machinery, equipment and tools:

- Excavators.

- Piling rigs.

- Bar bending machines.

- Carpentry tools and machinery.

- Scaffoldings and ladders.


© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
11
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Contract Management
 Typical plant, machinery, equipment and tools:
- Power elevated working platforms.
- Cranes – trucked mounted, towers and
derricks.
- Batching plant, concrete mixers and
vibrators.
- Etc.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
12
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Completion
Typical Activities & Flows

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
13
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Planning
Preliminary Appraisal
 Conduct preliminary hazard analysis for the
project.

 Examine contract document – drawings,


designs, specification and conditions of
contract
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
14
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Planning
Preliminary Appraisal

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
15
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Planning
Safety Provisions

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
16
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Planning
Safety Provisions

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
17
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Planning
Safety Provisions

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
18
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Planning
Health & Welfare Provisions

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
19
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
Statutory Notifications

 Department of Occupational Safety & Health.

 Department of Environment.

 Construction Industry Development Board.

 Local Authorities, etc.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
20
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
Statutory Notifications - DOSH

 Notification of Factory (JKJ 101) –


batching plant, fabrication yard, etc.

 Site Registration (JKJ 103).

 Installation of Machinery Requires


Certificate of Fitness (JKJ 105).

 First Use of Any Other Machinery


(JKJ 106).
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
21
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
Kick-Off Meeting
Prior to Discuss Issues
Commencement Related to
of Work Work

Clarify Duties & Roles of All Parties


© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
22
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
Appointment of Safety Personnel

 Safety & Health Officer/Site Safety


Supervisor.

 Designated Persons.

 Establishment of Safety & Health Committee.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
23
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
Arrangements with Sub-Contractors

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
24
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
Arrangements with Sub-Contractors

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
25
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
General Site Rules

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
26
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Administrative Arrangements
Documentation

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
27
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Site Security
 To protect the public from site hazards .
 To prevent children straying on the site.

Restricted Guard Post &


Access – Security
Lockable Gate Guard

Suitable Project Sign


Hoarding – Min. Board & General
1.8M Site Rules
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
28
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Access & Egress

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
29
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Storage Facilities
 Determines by:

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
30
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Lifting Appliances
 Position determines by:

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
31
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Temporary Services

 The positioning and marking of temporary


services should be carefully undertaken to
avoid possibility of accidental damage.
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
32
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Temporary Structures

 Adequate space must


be allowed for lighting
towers, scaffolding &
other support work.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
33
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Site Waste Management

 Designated dumping area.


 Arrangements for regular disposal
particularly for scheduled waste.
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
34
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Temporary Traffic Management and Vehicles
Parking

 Designated routes

 Adequate and appropriate directional and


warning signs.

 Parking facilities – on/off site does not


constitute any hazards and risks.
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
35
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Table-Top Exercise
 Based on preliminary appraisal conduct table-top
exercise.

 Sketch on the site layout plan all the necessary


physical requirements and arrangements.

 Give due considerations for workplace safety and


effective execution of the work.

 Assess the suitably and convenience of proposed


layout.
© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
36
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Site Layout
Table-Top Exercise

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
37
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

OSH Budgeting

 Assist estimator in identifying safety and


health requirements.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
38
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

OSH Budgeting
Considerations
 Appointment of safety and health personnel.

 Special Hazards – applicable Acts, Codes of


Practice, Standards and Guidelines.

 Statutory notification and other


requirements.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
39
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

OSH Budgeting
Considerations

 Induction other training requirements.

 Means of communication.

 Control and monitoring activities.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
40
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

OSH Budgeting
Considerations

 Provision of means of access and egress.

 Provision of temporary lighting.

 Provision of health and welfare amenities.

 PPE, signs, etc.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
41
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my

Summary
 Comprehensive planning is vital in ensuring
workplace safety and health.

 Preliminary hazard analysis is to be conducted


to identify the project’s safety and health needs
and requirements.

 Includes preliminary appraisals, administrative


arrangements, budgeting and site layout.

© 2014 NIOSH Malaysia. All rights reserved. No part of this document shall be reproduced
42
without written consent of NIOSH Malaysia.
INSTITUT KESELAMATAN & KESIHATAN PEKERJAAN NEGARA
NATIONAL INSTITUTE OF OCCUPATIONAL SAFETY & HEALTH

www.niosh.com.my