Professional Documents
Culture Documents
In
Mechanical Engineering
Of
Aurangabad.
i
CERTIFICATE
Submitted by
Aurangabad.
in partial fulfillment of
In
Mechanical Engineering
For the academic year 2017-2018
ii
ACKNOWLEDGEMENT
I take this opportunity to thank the number of individuals whose guidance and encouragement
were of enormous help to me during my In- Plant Training Period.
I would like to express my sincere gratitude to Mr. Manoj Lakde, Plant Head and Jayram
Gund, Human Resources Executive for providing me an opportunity to pursue my In- Plant
Training at Varroc Engineering Ltd. Plant- VII (valve).
I owe my gratitude to Mr. Makarand Pujari, Asst. Manager and Mr. Kiran Nunna, Senior
Engineer for being my constant source of inspiration and for their continuous support,
guidance and motivation throughout the tenure of my training.
Lastly but certainly not the least, I also thank other staff members of Varroc and our
colleagues who helped me with this In-plant training and appreciate their kind co-operation,
without which this would not have been successful.
Ashish Balsurkar.
iii
ABSTRACT
In-plant training is one of the requirements for the award of the Degree in Bachelor of
Technology in Mechanical Engineering of Maharashtra Institute of Technology. As
such, students are required to write and submit reports at the end of their training.
This report is the record of the work I personally did and experience I gained during
my in-plant training at Varroc Engineering Ltd. Plant- VII (valve) from 4th Jan to 16th
May 2018.
It consists of six chapters which altogether explain the background of training, entail
background information about Varroc Engineering Ltd., Manufacturing processes,
Inspection and Testing, the hands-on activities which I took part in and about the
project I did on tooling cost reduction by optimizing the design of bottom die holder.
iv
LIST OF FIGURES
v
LIST OF TABLES
vi
ABBREVIATIONS
vii
INDEX
ACKNOWLEDGEMENT iii
ABSTRACT iv
LIST OF FIGURES v
LIST OF TABLES vi
ABBREVATIONS vii
1 GENERAL INTRODUCTION 1
1.1 Background 1
1.2 In-plant Training Objectives 1
1.3 Project Introduction 1
2 LITERATURE REVIEW 3
3 COMPANY BACKGROUND 5
3.1 Operations 5
3.2 Vision, Mission & Core values of Varroc 8
3.3 Varroc Engineering Ltd. Plant- VII (Valve) 9
3.3.1 Engine valve manufacturing capabilities 9
3.3.2 Product of VEL-VII 9
3.3.3 Clientele of VEL-VII 10
3.3.4 Departments in VEL- VII 10
4 METHODOLOGY 18
4.1 Observing & Understanding Design and 18
Manufacturing process of Engine Valve.
4.2 Experience in Final Inspection Department 24
(FID)
4.3 Major Project- Project on Cost Reduction 33
4.3.1 Introduction 33
4.3.2 Necessity of project 36
4.3.3 Objective of present work 37
viii
4.3.4 Technique used 37
4.3.5 Cost reduction idea generation 39
4.3.6 Problem statement & its solution 41
4.3.7 Before-after comparison 45
5 RESULTS 47
6 CONCLUSIONS 48
REFRENCES 49
ix
1
1.1 Background
In-plant training (IPT) means a course of training in any industry or establishment
undergone in pursuance of memorandum of understanding between industry and institute
and under the prescribed terms and conditions of the University. It is a practical training
experience that prepares students for the tasks they are expected to perform on completion
of their training.
i. The minor project I have worked on during my in-plant training can be broken
down into two topics, which are related to each other. The first topic is about
understanding the design and manufacturing process of the engine valve,
manufacturing processes includes treating (such as heat treating or coating),
machining, or reshaping the material and manufacturing process also includes
tests and checks for quality assurance during these processes, which is called as
in-process inspection. The second topic is about the hands-on experience in the
final inspection department (FID) for the valve inspection and testing, inspection
prior to dispatch is very important as all the Dimensional & Significant
characteristics are checked at this stage, this is done in the FID. In FID I was
exposed to a well-defined quality system, in which I got the basic knowledge of
Advanced measuring equipment and machines.
ii. The major project I worked on during my training period was on tooling cost
reduction in the forging zone. To reduce the production cost, reducing the
tooling cost is an important aspect. Tooling which refers to- working or
manufacturing aids such as cutting tools, dies, fixtures, gauges, jigs, etc. which
(unless substantially altered or modified) are limited in use to a specific
production line or the performance of a specific contract or job and tooling cost
which refers to- Expenses incurred by a contractor or manufacturer in
acquisition and/or fabrication of the tooling requirements for the performance
of a contract or of a production line. The tooling cost was reduced by optimizing
the design of the bottom die holder of power press machine. The technique used
in this project was Kobetsu Kaizen, which is a Japanese word for focused
improvement, which means prioritising the most important losses and
eliminating them.
3
(i) Petrol engine exhaust valve design, analysis and manufacturing process- Seshagiri
Rao1 and D Gopi Chandul
The aim of this paper is to design an exhaust valve for a four wheeler petrol engine using
theoretical calculations. Manufacturing process that is 2D drawings is drafted from the
calculations and 3D model and transient thermal analysis is to be done on the exhaust valve
when valve is open and closed. Analysis is done in ANSYS. Analysis will be conduct when
the study state condition is attained. Study state condition is attained at 5000 cycles at the
time of when valve is closed is 127.651 sec valve is opened 127.659 sec.The material used
for exhaust valve is EN52 steel. We are doing material optimization bydoing analysis on
both materials EN52 and EN59.Static Modal analysis the exhaust valve to determine mode
shapes of the valve for number of modes.
(ii) Study and Analysis of Cost Reduction Techniques in Press Part Production-
Anuroop Athalye, Pankaj Gera, Dr. A.R. Madan- Department of Mechanical
Engineering. MITS, Ujjain (M.P.), India
In this paper, industrial engineering and management tools like TQM, TPM, JIT, Value
Analysis & Value Engineering, Lean manufacturing, Kaizen etc. have been studied and
analyzed for cost reduction in a specific production process of an auto ancillary industrial
firm. For this a case study was performed on sheet metal stamping process of LCV/HCV
body parts at XYZ Company at Pithampur (Indore)M.P.. A survey in interview form was
conducted among managerial and engineering professionals from various similar type
industries. The survey is based on cost reduction techniques, related challenges, market role
etc. Attempts have been made to investigate the role of vendors in cost reduction and the
problems faced from their side. Application of job plan in investigating the problems in
productivity improvement has also been studied. The outcomes have been analyzed and
discussed in details.
an important pillar of Total Productive Maintenance which had a major task of unifying the
kaizen effort across the division. KK Pillar looks into all the losses, analyses the losses
using various QC tools and comes up with suggestions that need to be implemented to
reduce recurring losses. This research is into the implementation of the KK Pillar activities
in a manufacturing company that is in project business and does not have repetitive
products. The main aim of this dissertation work is to reduce the losses of the machine. In
this research work a case study of machine had been undertaken for the analysis for certain
duration.
(iv) Design and Analysis of a Forging Die for Manufacturing of Multiple Connecting
Rods, C E Megharaj, P M Nagaraj, and K Jeelan Pasha Department of Industrial
Engineering and Management, Siddaganga Institute of Technology, Tumakuru.
This paper demonstrates to utilize the hammer capacity by modifying the die design such
that forging hammer can manufacture more than one connecting rod in a given forging cycle
time. To modify the die design study is carried out to understand the parameters that are
required for forging die design. By considering these parameters, forging die is designed
using design modelling tool solid edge. This new design now can produce two connecting
rods in same capacity hammer. The new design is required to validate by verifying complete
filing of metal in die cavities without any defects in it. To verify this, analysis tool
DEFORM 3D is used in this project. Before start of validation process it is require to
convert 3D generated models in to .STL file format to import the models into the analysis
tool DEFORM 3D. After importing these designs they are analysed for material flow into
the cavities and energy required to produce two connecting rods in new forging die design.
It is found that the forging die design is proper without any defects and also energy graph
shows that the forging energy required to produce two connecting rods is within the limit
of that hammer capacity. Implementation of this project increases the production of
connecting rods by 200% in less than previous cycle time.
5
Founded in 1988, Varroc group is a global tier-1 automotive component manufacturer and
supplier of exterior lighting systems, plastic and polymer components, electricals-
electronics components, and precision metallic components to passenger car, commercial
vehicle, two-wheeler, three-wheeler and off highway vehicle ("OHV") OEMs directly
worldwide. With 36 world-class manufacturing facilities and 16 R&D centers in
10 countries, Varroc group is on an exponential growth trajectory clocking a sale of
1.5 billion USD in 2016-17. The company is one of the leading global passenger car lighting
suppliers and amongst the top 2-wheeler automotive component supplier in India. Varroc
offers best design solutions that give customers a competitive edge in their markets.
3.1 Operations
The company has five business verticals under its umbrella:
i. Varroc Lighting Systems
Varroc Lighting Systems (VLS), headquartered out of Plymouth, Michigan, is a supplier of
exterior lighting for passenger cars and commercial vehicles. The division has six
manufacturing plants across North American, European, and Asian countries and six
Engineering centers in the Czech Republic, France, China, Germany, Mexico, and India.
ii. Triom Lighting
Triom Two-Wheeler Lighting, the lighting system arm of Varroc for the two-wheeler
industry, develops electronics and lighting solutions for the automotive market in India and
Europe. The division produces high quality two-wheeler lighting systems. It has four
manufacturing plants – two in Europe, one in Vietnam, and one in Mexico – as well as an
engineering center in Italy.
iii. Electrical
Varroc’s Electrical division offers complete solutions in electrical components and
assemblies for the two, three, four-wheeler, off-road as well as commercial vehicles
segments. The division has five manufacturing facilities located in the states of Maharashtra
and Uttarakhand.
iv. Metallic
Metallic division is a supplier of essential machined forgings and engine valves. The
manufacturing capabilities of forging include hot, warm and cold forging, heat treatment,
post heat treatment machining and soft machining. The forging plant based in Italy supplies
large forgings to caterpillars in Europe for construction equipment.
6
v. Polymer
Varroc polymer provides solutions to the automotive segments. The division produces a
wide range of injection and compression molded automotive and allied rubber components.
Varroc is the largest polymer solution provider to the two-wheeler industry in India.
VARROC GROUP
VPL- II
VEL- I VEL- V Finance
VPL- III
VEL- II VEL- VII
HRM
VTL Varroc
Elastomers
IMES IMES
Poland Italy
x. Quality Control
xi. BSR (Bonded Store Room)
Marketing Department
Marketing department fulfill the marketing needs and work to ensure the progress.
Major functions-
i. Market research
ii. Product development
iii. Sales support
iv. Communications
Store
The basic responsibilities of stores are to act as custodian and controlling agent for parts,
supplies, and materials, and to provide service to users of those goods. Stores has a process
and a space within, to receive the incoming materials (Receiving Bay), keep them for as
long as they are not required for use (Custody) and then to move them out of stores for use
(Issue). In a manufacturing firm this process forms a cycle to maintain and run the activities
of Stores.
Major Functions-
i. Receipt of incoming goods
ii. Inspection of all receipts
iii. Storage & preservation
iv. Identification of material stored
v. Material handling
vi. Issue & dispatch
vii. Inventory control/ management
viii. Maintenance of stock records
ix. Stores accounting, etc.
Purchase Department
Purchasing is the function of buying Goods & Services from external source to an
organization. The purchasing management department ensures that all goods, supplies and
inventory needed to operate the business are ordered and kept in stock. It is also responsible
for controlling the cost of the goods ordered, controlling inventory levels and building
strong relationships with suppliers.
Major functions-
12
Engineering Department
The Engineering Department is responsible for planning, analyzing and implementing
system extension projects; planning, design, and construction of major facility
replacements; capital improvement projects; continuing improvements in system standards;
and technical assistance to other departments.
Apart from this following are the functions of Engineering Department-
i. Ensure the safe use of equipment and schedule regular maintenance.
13
Production Department
The production department is responsible for converting raw materials and other inputs into
finished goods or services. In between the processes of production, the department works
to improve the efficiency of the production or assembly line so that it can meet the output
targets set by company management and ensure finished products offer consumers the best
value and quality.
Functions of Production Department-
Identifying Inputs- The PPC Department determines the quantity or volume of goods that
should be produced within a certain time frame and passes the information to the production
department. To meet production targets, the department establishes the quantity of raw
materials and types of machinery and equipment required to achieve the desired output level
and may collaborate with the purchasing department to source the inputs.
Scheduling Production- With the inputs ready, the production department schedules
production processes. This involves planning the tasks to be completed along the production
line and allocating the tasks to various production workers.
Minimizing Production Costs- The production department is tasked with finding effective
ways to lower production costs. One simple way to do this is to keep the production
machinery and equipment well-maintained so the firm does not regularly incur repair costs.
Along with advising the business to adopt newer technologies, the department can also
assess the production line to identify opportunities for cost reduction.
Ensuring Product Quality- A production department must ensure finished goods meet
minimum quality standards. Apart from checking all products for faults as they move
through the production process, the department must perform rigorous tests on prototypes
for new products to ensure they meet quality benchmarks before undergoing mass
production. From time to time, the production department will furnish the research and
development department with information it can use to improve existing products.
14
iii. It ensures better service to customers by delivering quality goods within the
specified time period.
iv. Reduces production costs through orderly scheduling of work activities and
reducing wastages.
v. Reduces employee idle time.
vi. Ensures a better control of material and contributes to efficient buying.
Maintenance Department
The technical meaning of maintenance involves operational and functional checks,
servicing, repairing or replacing of necessary devices, equipment, machinery, building
infrastructure, and supporting utilities in plant. The ultimate goal of maintenance is to
provide optimal reliability which meets the business needs of the company and this is done
by Maintenance Department.
Types of maintenance carried out
i. Breakdown maintenance (BM) is maintenance performed on equipment that has
broken down and is unusable. It is based on a breakdown maintenance trigger. It
may be either planned or it can be unplanned.
ii. Preventative maintenance (PM or preventive maintenance) is maintenance that
is regularly performed on a piece of equipment to lessen the likelihood of it failing.
Preventative maintenance is performed while the equipment is still working, so that
it does not break down unexpectedly.
iii. Predictive maintenance (PdM) techniques are designed to help determine the
condition of in-service equipment in order to predict when maintenance should be
performed. This approach promises cost savings over routine or time-based
preventive maintenance, because tasks are performed only when warranted.
iv. Time-based maintenance (TBM) is maintenance performed on equipment based
on a calendar schedule. This means that time is the maintenance trigger for this type
of maintenance. Time-based maintenance is planned maintenance, as it must be
scheduled in advance. This means that it can be used with both preventive
maintenance and predictive maintenance strategies.
v. Condition-based maintenance (CBM) is a maintenance strategy that monitors the
actual condition of the asset to decide what maintenance needs to be done. CBM
dictates that maintenance should only be performed when certain indicators show
signs of decreasing performance or upcoming failure.
benchmarks and that any errors encountered are either eliminated or reduced. The focus of
quality control is to ensure that the product and product manufacturing are not only
consistent but also in line with customer requirements.
Quality control specialists ensure that the department or process they work with meets
minimum quality standards.
Functions of QC department-
Testing- The most basic function of quality control involves testing. Quality control
specialists test the manufacturing process at the beginning, middle and end to ensure that
the production quality remains the same throughout. If the specialist discovers an issue at
any point in the process, they works with the production team to remedy the issue. Quality
control specialists perform quality control tests for services provided as well, evaluating the
quality of a specific service at specified intervals throughout the time of service. Testing
provides quality results as of the date of testing.
Monitoring- Monitoring consists of ongoing testing that the quality control specialist
performs on a regular basis. The specialist repeats the testing and records the results of each
test. After the specialist has performed several tests, they review the results and look for
any trends in quality. If the quality declines, they increases the amount of testing performed
in that areaThe quality control specialist continues to monitor the trending of the results.
Auditing- Quality control specialists also spend time auditing the quality of a process which
the specialist doesn’t work with. The quality control specialist may be auditing the work of
the regular quality control work performed or auditing the quality of a process without any
current quality control work. When performing the audit, the quality control specialist
reviews the results reported by the regular quality control workers to determine if they
performed the original tests correctly.
Reporting- Periodically, the quality control specialist reports the quality results to
management. A high number of quality problems mean something is wrong with the
process and there may be many unhappy customers for the company. Management reviews
the number of quality problems and where they occur in the process and take action to
address the issue.
CHAPTER 4: METHODOLOGY
4.1. Observing & Understanding Design & Manufacturing Process of Engine Valve-
The manufacturing process begins with the creation of the materials from which the design
is made. These materials are then modified through manufacturing processes to become the
required part ie. Engine Valve. Manufacturing processes includes treating (such as heat
treating or coating), machining, or reshaping the material. The manufacturing process also
includes tests and checks for quality assurance during or after the manufacturing and
planning the production process prior to manufacturing.
There is hardly any difference in the manufacturing process of a Inlet valve & a Exhaust
valve. The general process is the same, rather depending on the design the Exhaust valve is
of bimetal, where two different metals are friction welded (Stem has different material &
Head has different material).
General design specifications of engine valve-
• Stem Dia Range- 4.00mm to 12.00 mm
• Head Dia Range- 12.00mm to 55.00mm
• Material- Austenitic steel, Martensitic steel, Bimetal, Super Alloys
• Finish- Natural, Soft nitriding, Chrome plated
• Special Features- Stellite Seat & end, Induction hardened tappet end & seat, Die
finished under head & face.
some of the excess hardness, and is done by heating the metal to some temperature
below the critical point for a certain period of time, then allowing it to cool in still
air. The reduction in hardness is usually accompanied by an increase in ductility,
thereby decreasing the brittleness of the metal.
iv. Shot Blasting (Stem)- Shot blasting is a method used to clean the metal, it is also
used for removing burrs, scale and rust that may interfere with the part's integrity,
appearance or definition. Shot blasting also prepares the surface of a part for coating
by removing surface contaminants and provide a surface profile for increased
coating adhesion.
v. Inspect for Bar dia (Stem)- The Stem dia is inspected with the help of Dial gauge.
The inspection is done at this stage to eliminate the rejection due to stem dia in the
further stages.
vi. Bar cut off (Head)- Same process as for the Stem.
vii. Deburr (Head)- A burr is a raised edge or small piece of material remaining
attached to a workpiece after a process. It is usually an unwanted piece of material
and is removed with a deburring tool in a process called 'deburring'. The deburring
is done manually, Manual deburring is the most common deburring process because
it is the most flexible process. It also only requires low cost tools and allows for
instant inspection. Manual deburring is done on a grinding wheel.
viii. Inspect for bar dia (Head)- Same process as for Stem dia.
ix. Friction welding & deflash- Friction welding (FRW) is a solid-state welding
process that generates heat through mechanical friction between workpieces in
relative motion to one another, with the addition of a lateral force called "upset" to
plastically displace and fuse the materials. Because no melting occurs, friction
welding is not a fusion welding process in the traditional sense, but more of a forge
welding technique. The combination of fast joining times (on the order of a few
seconds), and direct heat input at the weld interface, yields relatively small heat-
affected zones. By this process two dissimilar metals of Stem & head are joined.
After FRW Deflashing is done- The process of removing flash by cutting the excess
metal.
xvii. Straightening II
xviii. Pre-Machining Final Inspection- Before the valve go for the machining processes
the valve are inspected to eliminate the rejection at the machining stage. Valve bend
test is also done to check the ductility.
xix. Rough centerless II
xx. CNC Facing (Head)- Facing is the process of removing metal from the end of a
workpiece to produce a flat surface. It is done on a CNC Lathe machine.
xxi. Copy Turn (Neck & Rad)- (Turning is a form of machining, a material removal
process, which is used to create rotational parts by cutting away unwanted material).
Copy turning is carried out on special lathes that control the cutting tool in some
manner to produce identical items. They are capable of producing work quickly and
to a good quality finish.
xxii. End Buffing- Buffing is process using abrasives or abrasive compounds that adhere
loosely to a flexible backing, such as a cloth wheel. Buffing is used to generate
extremely fine surfaces that match those associated with honing and lapping. A
buffed surface is smooth, highly reflective and mirror-like.
xxiii. Harden End (Induction)- Induction hardening is a form of surface hardening
(surface hardening is the process of hardening the surface of a metal object while
allowing the metal deeper underneath to remain soft, thus forming a thin layer of
harder metal (called the "case") at the surface) in which a metal part is induction-
heated and then quenched. The quenched metal undergoes a martensitic
transformation, increasing the hardness and brittleness of the part. Induction
hardening is used to selectively harden areas of a part or assembly without affecting
the properties of the part as a whole. Induction heating is a non-contact heating
process which uses the principle of electromagnetic induction to produce heat inside
the surface layer of a work-piece. Stress Relieve is followed after Induction
hardening.
xxiv. Groove & End Chamfer- Groove is provided on the stem of the valve by CNC
machine & then Chamfer is provided at the end of the stem.
xxv. Crack Detect (Zyglo)- Fluorescent penetrant inspection (FPI) is a type of dye
penetrant inspection in which a fluorescent dye is applied to the surface of metal in
order to detect defects that may compromise the integrity or quality of the part. It is
a quick and accurate process for locating surface flaws such as shrinkage cracks,
porosity, cold shuts, fatigue cracks, grinding cracks, heat treat cracks, seams,
forging laps, forging bursts, through leaks, and lack of bond.
xxvi. Chrome Flashing- Flash hard chrome plating is an electrolytic process utilizing a
chromic acid-based electrolyte. The component requiring plating becomes the
24
cathode and, with the passage of a DC current via anodes, chromium metal builds
on the component surface. Etching is carried in accordance with the guidance
relevant to the base material being plated. All components are etched before Hard
Chrome plating to provide a good key for the hard chrome deposit to be applied.
of workmanship. It is the cost art of controlling the production quality after comparison
with the established standards and specifications. It is the function of quality control. If the
said item does not fall within the zone of acceptability it will be rejected and corrective
measure will be applied to see that the items in future conform to specified standards.
Objectives of Inspection
i. To detect the faulty products in production whenever it is detected.
ii. To bring facts to the notice of managers before they become serous to enable them
discover weaknesses and over the problem.
iii. To prevent the substandard reaching the customer and reducing complaints.
iv. To promote reputation for quality and reliability of product.
Purpose of Inspection
i. To distinguish good lots from bad lots.
ii. To distinguish good pieces from bad pieces.
iii. To determine if the process is changing.
iv. To determine if the process is approaching the specification limits.
v. To rate quality of product.
vi. To rate accuracy of inspectors.
vii. To measure the precision of the measuring instrument.
viii. To secure products-design information.
ix. To measure process capability.
Inspection in the Plant is conducted during the production process. This approach of
inspection helps to control the quality of products by helping to fix the sources of defects
immediately after they are detected, and it is useful to improve productivity, reduce defect
rates, and reduce re-work and waste. This is called as In-process inspection, but Inspection
prior to dispatch is very important as all the Dimensional & Significant characteristics are
checked at this stage, this is done in the Final inspection department (FID). Inspecting the
Engine valve before it leaves the plant is an effective way of preventing quality problems
and supply chain disruptions further down the line. It is also a better way of preventing
customer’s complaints.
During my In-plant training period I was exposed to a well-defined quality system,
consisting of In-process & Final inspection which ensure 100% inspection for all the Engine
valves and also sampling inspection for Valves to meet the customer requirements.
In the Final Inspection Department (FID) which was a temperature-controlled environment,
I got the basic knowledge of Advanced measuring equipment like Dial gauges, GO gauge,
NO-GO Gauges, VICI Inspection machine, Homel Inspection machine, Leak test machine,
Hardness test machine, Equipment calibration, etc. In this department I also had hands-on
experience on these equipment and machines.
26
ii. Datum to end- The overall height of the valve is checked on the Dial gauge as
shown in the picture.
27
iii. Seat Roundness- The seat roundness or the seat angularity is checked on a dial
gauge as shown in the picture. It is a important parameter on the assembly point of
view of the valve in the engine as if roundness is not according to the standards can
cause leakage.
iv. Groove Diameter- The groove diameter is checked on GO gauge & NO GO gauge
for the groove diameter be in the desirable limits. The below picture illustrate the
same.
vii. Groove position- Groove position is checked on a dial gauge as shown below.
viii. Seat diameter- The head diameter is checked by GO gauge & NO GO gauge to be
in the required limits, It should not exceed 15 microns limit.
ix. Visual- Important parameters are checked visually like Valve free from damage,
free from crack, Polish, End rework, free from Acid mark, Head unclear, Seat, etc.
Some of the valves are dimensionally inspected with the help of Testing machines like VICI
Testing machine & Homel Testing machine according to the customer requirements.
VICI Testing Machine- The VICI valve testing machine is a static testing machine which
uses a Digital camera for the dimensional inspection of the valve. Through the technology
of ‘photogrammetry’, it is now possible to use a standard digital camera as a coordinate
measuring device comparable to a CMM. Working principle- Photogrammetry, which
refers to using photographs to obtain 3D position information, through software that
compares multiple photographs at different angles. Photogrammetry is what surveyors use
to create 3D topographical maps. At much closer range, the same technique can determine
XYZ coordinates of workpiece features to accuracies as tight as 0.001 or 0.002 inch across
a 10-foot object. Usually the product is illuminated using back light (bright field)
illumination making the edges of the product clearly visible.
Homel Testing Machine- The Homel valve testing machine is a dynamic testing machine
which uses a 3D Laser scanning system for the dimensional inspection of the valve. With
this type of 3D scanning system, a laser is projected onto the surface of the valve and a
camera captures the reflection. The laser is in the form of a single point. When the reflection
is captured, each point is triangulated, measured, and recorded, resulting in a 3D rendering
of the shape and surface measurements of the object. The laser is projected on the Valve
from the four directions & the laser point is moved throughout the length of the valve & all
the dimensional characteristics are recorded.
This is the procedure for the dimensional inspection of the Engine Valve. However some
important tests like Leak Test & Hardness Test are also conducted.
II) Valve Leak Test
All valves are inspected and tested to ensure that they conform to the required valve leakage
standards. It is one of most important test as a valve leakage can cause a safety issue. The
valve is mounted on the test cavity, and valve shall be completely closed. One side shall be
subjected to the hydrostatic pressure ie. Pressure is applied on the head of the valve and
amount of leak shall be measured from the seat.
Valve testing procedure-
i. The engine valve seat area is cleaned by cotton cloth to be free from dust, metal
particles, burr, etc.(If the valve seat is not free from particles the machine will show
leakage in the valve)
ii. The valve is kept in the cavity of the machine & button is pressed.
iii. The pressure is applied on the head of the valve by the machine.
iv. The valve body is surrounded with the testing fluid at the specified temperature.
v. The specified pressure is applied for the specified length of time.
vi. Leakage is measured across the valve element of interest (e.g., stem, seat) by the
machine. The valve standards specify that no detectable leakage is allowed.
31
Pressure
applied
Engine
valve
Cavity
CRO
Engine
valve
After the Engine valve inspection & testing is done the final process is the Laser marking
on the valve. After laser marking the valves are shifted for the packing. Once the packing
is done, the Boxes are shifted to the BSR (Bonded Store Room) where the boxes are
securely stored.
vii. Guide, back gauge, or finger stop – These parts are all used to make sure that the
material being worked on always goes in the same position, within the die, as the
last one.
viii. Setting (stop) block – This part is used to control the depth that the punch goes into
the die.
ix. Blanking dies – See blanking punch
x. Pierce die – See pierce punch.
xi. Shank – used to hold in the presses. it should be aligned and situated at the center
of gravity of the plate.
Power press machine- Power presses are driven by mechanical mechanism with the power
source of this mechanism is Electric motor. These presses have large frame openings, ie.
There is a wide space between its base and ram to accommodate large work-piece.
The Main Parts of Mechanical Power Press are-
i. Base- It is main supporting member of power press. Which is use for holding the
dies and supports different controlling mechanism.
ii. Ram- It is the main operating member, which reciprocates to and fro inside suitable
guide. It carries the punch at the bottom end.
iii. Pitman- Pitman is also called as connecting rod. It connects the ram and crankshaft.
As per the requirement the stroke length and power transferred can be adjusted.
iv. Frame- It forms the main body of power press which carries the ram and driving
mechanism. C frame type power presses are most widely used.
v. Driving mechanism- In different types of presses different type of driving
mechanisms are used, like crankshaft and eccentric mechanism in mechanical power
press. It is used to drive the ram by transferring power from motor to ram.
vi. Controlling mechanism- The power transmitted through the transmission system
can be disengaged with the help of clutch provided with driving mechanism as per
the need.
vii. Flywheel and clutch- Flywheel stores the energy required for maintaining constant
speed of ram when the punch is pressed into the workpiece. Clutch is used for
engaging and disengaging the drive shaft with the flywheel. The function of clutch
is to transmit the torque from flywheel to the eccentric shaft or crankshaft.
viii. Brakes- Brakes are used to bring the driving shaft to the rest when it disengaged
from flywheel.
ix. Bolster plate- It is fastened to the bed of the power press which supports sand hold
the die assembly over it.
Hot Forging- Forging is a manufacturing process involving the shaping of metal using
localized compressive forces. The blows are delivered with a hammer (often a power
hammer) or a die. Forging is often classified according to the temperature at which it is
performed: cold forging (a type of cold working), warm forging, or hot forging. Hot forging
is a type of hot working- Hot working process metals are plastically deformed above their
recrystallization temperature.
35
11) Line organization losses Idle time losses when waiting for multiple processes or
multiple platforms.
12) Distribution losses Distribution man-hour losses due to transport of materials,
products (processed products) and dollies.
13) Measurement and adjustment losses Work losses from frequent measurement and
adjustment in order to prevent the occurrence and outflow of quality defects.
D- Three major losses that impede efficient use of production subsidiary resources
14) Energy losses- Losses due to ineffective utilization of input energy (electric, gas,
fuel oil, etc.) in processing.
15) Die, jig and tool losses- Financial losses (expenses incurred in production.) which
occur with production or repairs of dies, jigs and tolls due to aging beyond services life
or breakage.
16) Yield losses Material losses due to differences in the weight of the input materials
and the weight of the quality products.
Kobetsu Kaizen focuses on elimination of these 16 major losses.
Looking at the 15th definition of loss & how we can eliminate it we came with a solution to
modify the Die set, hence eliminating this loss and also reducing the overall tooling cost.
In the tooling cost reduction research it was found that the huge tooling cost was required
in the Common forging zone than any zone in the plant. In the common forging zone tooling
was required on the Power press machines for the consumable items of the forging die set.
The major consumable items of the forging zone with their cost are as follows-
Major Consumable Item List of Forging Zone
Sr.No. Item Cost in Rs (Approx)
1. Bottom die holder 65000/-
2. Top die holder 48000/-
3. Bottom die 26000/-
4. Top die 25000/-
The bottom die holder which is a metal block which holds the Bottom die in the process of
forging is a consumable item of the die set and has a life of 6 months (approx) per machine
ie. 1 qty of bottom die holder of Rs- 65000/- required per 6 months per machine in the
forging zone. From this we understand that a huge tooling cost is required in the die set
mostly because of the replacement of the bottom die holder every 6 months.The bottom die
set assembly is as shown below.
BOTTOM
DIE
BOTTOM
DIE HOLDER
CLAMPING
BOLT
Providing the T- nut slot at the bottom of the bottom die holder and removing the threads
of the bottom die holder, so that the T-slot nut slides along the T-slot track of the bottom
die holder and bolt is fastened to the bottom die holder to hold the bottom die with the help
of the T-slot nut. So that when the die set-up is changed by the operator every time, the
threads of the T-slot nut gets wear instead of the bottom die holder’s internal threads. The
42
cost of T-slot nut is about 80 Rs per piece, ie. Replacing the whole bottom die holder of
65000/- or every time enlarging the hole of bottom die holder and providing threads to it
which will add machining cost, Replacing the T-slot nut every time when its threads get
wear is cost saving.
For this Standard T- slot nut of M20×2.5 is selected according to the Design requirement.
Nominal T- Width of Width of head space B1 Depth of head space C1
bolt size Throat (mm) (mm)
(mm) A1(mm)
20 22 37 (min) 40 (max) 16 (mm) 18 (mm)
i) Computer aided design of the bottom die holder- Computer-aided design (CAD) is the
use of computer systems (or workstations) to aid in the creation, modification, analysis, or
optimization of a design. In design modification of the bottom die holder we are using the
PTC Creo 3.0 software. Creo is a family or suite of design software supporting product
design for discrete manufacturers and is developed by PTC.
The modification in the design of the bottom die holder is done on CAD software prior to
the actual modification and for the demonstration purpose. This CAD design was also
useful in providing to the Tool & die maker vendor for the modification in the design of the
bottom die holder.
43
As shown in the above figure, the design of the bottom die holder is modified by providing
the T-slot at the bottom.
ii) Computer aided assembly of the bottom die set- For the demonstration purpose & to
understand how the bottom die is clamped to the bottom die holder with the help of T-slot
nut & bolt we use this tool computer aided assembly (CAA). The CAA is done on the same
software- ie. Creo 3.0.
44
T-slot with
Bottom
T-slot nut
Die
Exploded View
BEFORE AFTER
Bolts Clamped on Bottom die holder T- Slot & T-Nut provided & Threads of
bottom die holder removed.
BEFORE PICTURE AFTER PICTURE
i. Clamping bolts clamped on the i. T-slot & T-nut provided on the
bottom die holder to hold the bottom bottom die holder to clamp the die
die. set.
ii. Life of bottom die holder- 06 months ii. Life of the bottom die holder
(approx.). increased (approximately by 1
iii. Fatigue to the operator every time year).
when the Die set is repaired or iii. Fatigue to the operator minimized
changed. as only T-nut need to be replaced
iv. Bottom Die holder replacing process instead of heavy holder.
is time consuming. iv. Replacing process of T-nut
v. Tooling cost is huge as every time consumes less time.
repair or bottom die holder is replaced. v. Tooling cost is reduced as no need
vi. to replace the bottom die holder
CHANGE IN BOTTOM DIE
every time.
HOLDER vi. Team morale improved as fatigue
reduced.
Series 1 vii.
2 CHANGE IN BOTTOM DIE
1 1 1 1 1 HOLDER (FORECAST)
0
MONTH MONTH MONTH MONTH
Series 1
1 6 12 18
2
1
0
MONTH MONTH MONTH MONTH
1 6 12 18
CHAPTER 5: RESULTS
i. This present work summarizes the experience I acquired during my in-plant training
period. From this training, I acquired a number of skills and knowledge through the
application of the theoretical knowledge learnt in class into the practical operations
which led to an improvement and widening of my engineering knowledge. This
report gives an overview of the projects that I worked on during my in-plant training.
ii. I came to know the design and manufacturing process of engine valve.
iii. I had hands on experience in the final inspection department (FID), where I was
exposed to a well-defined quality system, consisting of inspection and testing which
ensure 100% inspection for all the Engine valves. I got the basic knowledge of
Advanced measuring equipment and machines like Dial gauges, GO gauge, NO-GO
Gauges, VICI Inspection machine, Homel Inspection machine, Leak test machine,
Hardness test machine, Equipment calibration, etc.
iv. By the end of my In-plant training I successfully did a major project on tooling cost
reduction by modifying the design of bottom die holder to increase its life to 12
months. Bottom die holder’s previous design life was only 6 months and after the
modification the life is now 18 months approximately. If there are ‘n’ number of
power press machines & ‘n’ number of bottom die holders on it and if this new
design is implemented on them then the tooling cost will decrease significantly. The
below graph shows the before and after the new bottom die holder design
implementation on a power press machine of 250 tonnes.
QUANTITY
QUANTITY
CHAPTER 6: CONCLUSIONS
The In-plant training was a fruitful experience. Through the application of the theoretical
knowledge into real-life problem solving situations, I gained a lot of experience. I also got
insight into professional practice and in almost every aspect of plant. The friendly welcome
from all the employees is appreciating, sharing their experience and giving their piece of
wisdom which they have gained in long journey of work. I am very thankful for the
wonderful facility from Varroc engineering plant- VII.
I am very thankful that I got opportunity to do a project on tooling cost reduction. Through
the application of the theoretical knowledge learnt in class into the practical operations
which led to successful accomplishment of the project.
It was also a great opportunity for developing personal networking activities and making
contacts with influential people; which is of great value to me as far as my career is
concerned. The training also enabled me to discover my strengths and weaknesses. This
further helped me to identify areas to improve on.
49
REFRENCES
i. www.varrocgroup.com/
ii. www.varrocgroup.com/metallic
iii. www.dieselnet.com , Valves and Ports in Four-Stroke Engines.
iv. Engine Valve Designs- By Ted Tunnecliffe, Engine Builder magazine.
v. Kobetsu Kaizen Manual- CII
vi. Handbook of Die Design- David A. Smith
vii. Jig and Fixture Design- Edward Hoffman, Yeshiva University, 2003 by Cengage
Learning US.