Professional Documents
Culture Documents
The information, and, in particular, the recommendations relating to the application and end-use of Sika products, are
given in good faith based on Sika’s current knowledge and experience of the products when properly stored, handled
and applied under normal conditions. In practice, the differences in materials, substrates and actual site conditions are
such that no warranty in respect of merchantability or of fitness for a particular purpose, nor any liability arising out of
any legal relationship whatsoever, can be inferred either from this information, or from any written recommendations, or
from any other advice offered. The proprietary rights of third parties must be observed. All orders are accepted subject to
our current terms of sale and delivery. Users must always refer to the most recent issue of the Technical Data Sheet for
the product concerned, copies of which will be supplied upon request.
It is recommended that an outlet should be fitted to the lowest point in the bottom of
the pool (or as an alternative for small pools: a bore hole dia. 20 - 30mm through the
bottom slab) in order to drain away any potential condensation water under the
installed waterproof membranes. If it is connected to the drainage system and
inspection man hole outside of the pool area, then this outlet can also be used to
check the water tightness of the installed waterproofing membrane.
The surfaces of the substrate must be smooth to prevent the waterproofing membrane
from being punctured under the internal hydrostatic pressure.
An indoor pool structure often includes equipment service rooms alongside the actual
pool structure, for which the roof structure is often the floor / pool side. The installed
swimming pool lining can be continued with the Sikaplan membrane also being used
for waterproofing under the poolside walkway finishes, in order to prevent any
penetration of splash-water through the concrete roof / floor slab into the service
rooms.
2. PRODUCTS
2.1 Product characteristics of sheet membranes and liners
® ® ®
Sikaplan Sikaplan Sikaplan
WP 3150-16R* WP 3100-12H / – 15H WP 3150-16RE*
Material PVC-p membrane, PVC-p membrane, PVC-p membrane,
reinforced, unreinforced, reinforced, embossed for
UV-resistant UV-resistant anti-slip surface
UV-resistant
Use Waterproofing of Waterproofing of details Waterproofing of
swimming pools in swimming pools swimming pools on
stairs, footsteps, etc.
Colours white, light-blue, azure, beige, light - blue white, light-blue, azure,
blue-grey, green, beige blue-grey, green, beige
Thickness 1.60mm 1.20mm / 1.50mm 1.60mm
® ® ®
Sikaplan Sikaplan Sikaplan
WP 3110-08H WP 3120-07H WP 3130-06H/08H/10H
Material PVC-p liner, PVC-p liner, PVC-p liner,
unreinforced, unreinforced, unreinforced,
UV-resistant UV-resistant UV-resistant
Use Waterproofing of small Waterproofing of small Waterproofing of small
swimming pools and children pools children pools
children pools
Colours white, light-blue, azure, blue blue
blue-grey, green, beige
Thickness 0.80mm 0.70mm 0.60mm/0.80mm/1.00mm
*: Sikaplan WP 3150 series replaces Sikaplan WP 3100 series. Sikaplan WP 3100 series to be phased out within next 2 years
3. INSTALLATION
3.1 General requirements for sheet membrane installation
Representatives of the waterproofing contractors invited to tender / bid for the
waterproofing must have the possibility of site inspection beforehand, in order to obtain
sufficient understanding of the project requirements for their quotations and in
preparation for the works to be carried out.
Electricity supply (110/220V/380V), clean water and on request, compressed air
(5 -10bar/1000 - 1500l/min.) must be available on site. The access to the site must be
adequate for all of the required machinery, equipment, tools and products for the
waterproofing works (i.e. through the entrance hatch or manholes into tanks). Any
unauthorised access must be prevented to avoid puncturing the installed
waterproofing. The waterproofing contractors must be instructed, that access onto the
installed membrane is only allowed in soft shoes with no sharp edges (i.e. shoes with
soft rubber soles). Smoking and open flames must not be permitted within the
installation area.
The following installation instructions are divided into single operations, according to
the type of project. The operational sequences must finally be defined according to the
structures design and specifications.
Materials stockyard
A secure storage area to store the rolls of membrane, geotextile and all of the required
ancillary products and equipment, with access to lifting equipment able to safely
transport them from stock to the installation area, must be available close to the
installation area. The membranes must be stored protected from the sun and
weathering. Defined quantities of the waterproofing membranes, geotextile fabric,
fixings and ancillary materials must be available in and from this storage area, in order
to prevent any work interruptions due to lack of materials.
Installation equipment
Dependent on requirements, supply and install all equipment for the membrane
installation, i.e.:
• movable platforms for the waterproof lining of high walls
• movable unrolling hooks for installing the waterproof lining on slopes
• mobile pneumatic working platforms, or cranes
• lighting equipment, if works have to be performed indoors / in the dark
• power supply with 380V/220V to the installation area for the welding equipment
• lifting equipment, to lift membrane and geotextile rolls on to the working platforms,
i.e. light cranes
• ventilation equipment for any works in closed tanks
Any protruding elements, i.e. pipes, fittings, bolts, etc., must be prepared by grinding or
blast cleaning.
Finally, the entire surface must be cleaned thoroughly (i. e. using stiff bristle brushes
and rinsing with clean water through a high pressure water jet cleaner). Any ponding
water must be removed.
After drying with clean compressed air, the entire substrate must be disinfected by
application of 15%-chlorine bleach solution (local supply), diluted with clean water
(ratio 1part solution : 9 parts water), or ready to use disinfectant (i.e. Sanitized P 8103,
or Bayrol Demykosan). This can be spray applied. The disinfectant is then allowed to
dry off (i.e. without rinsing). All relevant safety measures must be observed when
applying disinfectant, following the instructions on the relevant PDS, MSDS and local
regulations.
All plumbing and electrical systems and connections must be inspected, tested and
upgraded as necessary in order to conform to the relevant standards. Alternatively they
must be removed and replaced as required.
The water treatment system must also be thoroughly inspected, tested and adjusted to
the relevant local Standards and recommendations of the pool water chemicals
supplier.
4. WELDING METHOD
4.1 Heat welding
Sikaplan® WP sheet waterproofing membranes can be welded using
suitable heat welding equipment
• Seam overlaps of the membranes in all cases must be a minimum of 80mm
• the width of the finished welded seams (single and double seams) must be at
least > 30mm
• prior to welding procedures, the membrane surfaces must be dry, clean, and
free of any dust, oil and grease etc.
• Contaminated / dirty Sikaplan® WP membrane surfaces must be cleaned prior
to the welding procedures with Sika-Sikaplan® Cleaner 2000 (please refer to
the PDS and MSDS)
• prior to any heat welding work on site, it is mandatory to conduct a welding test
with actual membrane samples from the site (This is in order to correctly adjust
and set the welding temperature and speed of the machine)
• for continuous welding quality, it is recommended to use welding equipment
with
• its own power supply or generating set (i.e. automatic welding machine: 360V,
hand held welding gun: 220V or 110V according to local regulations)
• welding machine operators must be trained and experienced in heat welding
• and to operate electrical devices in wet or humid conditions according to local
regulations
5. QUALITY CONTROL
5.1. Testing of welded seams on water-tightness
All welded seams must be tested for water-tightness.
Testing methods depend on available testing equipment and/or clients specification.
total
Total
Fixing elements:
PVC-laminated metal sheets, formed
to profiles
Stainless steel profiles (V4A)
Aluminium plates
Stainless steel fasteners with stress
distribution plate
total
total
total
total
8. Penetrations
total
10.2 Material
Total
Total
®
1 Structural concrete surface disinfected with Sikagard SB disinfectant
®
2 Geotextile levelling layer with Sikaplan W Felt 300 PES biocide white
®
3 Sikaplan WP 3150-16R colour
4 Concave moulded fillet (radius = 2 – 3 cm)
®
5 Plates made of laminated Sikaplan WP metal sheet
6 Mechanical fixings; spacing maximum 500mm centres
1 Mortar bed
2 Backing profile for sealant bead
3 Sealant bead with Sikasil®-Pool and Sika® Primer 3N
4 Maximum water level
®
5 Profiles made of laminated Sikaplan WP metal sheet
6 Mechanical fixing, spacing maximum 250 mm centres
7 Sikaplan® WP 3100-16R colour
8 Levelling layer with Sikaplan® W Felt 300 PES biocide white
9 Structural concrete disinfected with Sikagard® SB