Professional Documents
Culture Documents
net/publication/328278472
CITATIONS READS
0 1,390
1 author:
Gilberto Mejia
Los Andes University (Colombia)
2 PUBLICATIONS 0 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Gilberto Mejia on 11 September 2019.
CONTENTS
1 INTRODUCTION...................................................................................................................... 1
2 OBJECTIVES ............................................................................................................................ 1
4 BACKGROUND INFORMATION................................................................................................ 1
4.1 Light Rail Metro Environment................................................................................................................... 1
| Page I of vii
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page II of vii |
Insulation Coordination Study - Analysis of Lightning Overvoltages
LIST OF FIGURES
Page IV of vii |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page V of vii
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 109. Transient overvoltage at substation zone A, due a 20 kA lightning impulse impacts on first mast at
OCW and Surge arrester earth resistance is 0 Ω .................................................................................................80
Page VI of vii |
Insulation Coordination Study - Analysis of Lightning Overvoltages
LIST OF TABLES
1 INTRODUCTION
The present document shows the application of the “EN 50214 Railway applications – Insulation coordination
– Clearances and creepage distances for all electrical and electronic equipment” standard, for a metro station.
“Insulation coordination” implies the selection of the equipments with an electrical insulation characteristic
with regard to its application in relation to its anticipated lifespan. Insulation coordination can only be achieved
with the design of the equipment in regard to its application and in relation to its surroundings.
The term “insulation co-ordination” explains the process for co-ordinating the constituent of an electrical
insulation, i.e. solid/liquid insulation, clearances and creepage distances. The use of standard EN 5014 is to
take into account the insulations in railway systems and their expected reliability and long lifespan.
2 OBJECTIVES
Activity: Analysis of Lightning overvoltages.
• Investigate the behaviour of the system against lightning overvoltages.
• Ensure protection of the system equipment through the appropriate positioning of surge arresters.
3 APPLICABLE DOCUMENTS
The insulation co-ordination shall be based upon the requirements established in “EN 5014 Railway
applications – Insulation coordination – Clearances and creepage distances for all electrical and electronic
equipment” and related documents and standards”.
4 BACKGROUND INFORMATION
4.1 Light Rail Metro Environment
| Page 1 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 2 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 3 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 4 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
In terms of insulation coordination, although the system is designed for 1500 Vdc, the lightning overvoltage
study will be performed for the lowest operation voltage, 750 Vdc, according to the employer’s requirements.
5.5 Determination of the rated impulse voltage for this equipment UNI and the minimum clearance in air
Method 1 described at section 2.2.2.1 of EN 50124-1 was taking into account to determine the rated impulse
voltage. Overvoltage category is OV3, refer to section 5.1 from this document.
| Page 5 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Table 3. Rated impulse voltage UNi for circuits not powered by the contact line
Table 3 and Table 4 from standard is used to determine the rated impulse voltage; only for this case, Table 4 is
applicable.
• Uni = 10 kV
According to section 5.4, Table 5; for 10 kV Uni the value of the minimum clearance distance is 11 mm for basic
insulation and a PD3 category.
We have to check with Table 6, if the value from this table is lower than the previous value selected value from
minimum clearance distance in air. In this case, the value is correct, and we do not need to apply correction
factors.
Page 6 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Table 4. Rated impulse voltage UNi for circuits powered by the contact line
| Page 7 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 8 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 9 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
5.7 Conclusions
Based on the insulation coordination study based on standard EN 50124-1, the following results have been
found for selecting Cantilever insulators:
• The nominal Voltage Un is: 750 Vdc, but the system is designed for 1500 Vdc.
• The minimum value for the rated insulation voltage UNm : is 1,8 kV
• Overvoltage category is: OV3
• The insulation type category is: basic insulation.
• The pollution degree should be categorized into: PD3.
• The rated impulse voltage for this equipment UNI: 10 kV
• The minimum clearance in air is: 14 mm.
• The minimum creepage distance is: 14 mm.
Page 10 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 7. Procedure of wire breakage caused by lightning in Vdc traction power system
| Page 11 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 12 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 10. Location of wires in conventional catenary system and “integrated catenary system”
A practice to avoid such troubles is to arranging surge arresters with an interval of 500 m along the catenaries
system. In addition, locating surge arresters at the feeder masts adjacent to each traction power substation or
at the d.c. output of the rectifiers in the substation transformer. Additionally, grounding wires (shielding wires)
are installed above the catenaries system in heavy lightning regions where the IKL (Isokeraunic Level) is greater
than 30 days. The evaluation of the effect of surge arresters during lightning stroke events and estimate
calculations of transient phenomena using in ATP-EMTP software; in order to estimate practical solutions for a
lightning protection design, it’s necessary to implement electromagnetic transient models of the system and
perform simulations of the transient process.
6.1.1 Surge Protective Device coordination
The Surge Protection Device (SPD) coordination has been used to provide proper installation of two or more
surge protective devices allocated at different points in the network. The full understanding of the right and
suitable position of surge protective devices must be gained as well as the variables affection on its function.
The successful coordination can be achieved taking into consideration the following items:
• Surge waveform and duration.
• The location of surge protective device with respect to the power system.
• Distance between the lightning strike and the protected equipment.
• The SPDs measured limiting voltage.
• The SPDs surge current capacity.
• The SPD aging.
• The earthing method.
• Suitable modes of protection for each SPD.
| Page 13 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 14 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
The 1620 kVA (2x840 kVA) delta-delta-star power transformer converts the 10,5 kV voltage of the primary
winding to 293 V. The secondary winding voltages of the transformer (with an angle difference of 30°) are
applied to a 12-pulse rectifier group 750 Vdc and 1500 kW, consisting of 2 diode bridges connected in series.
Each substation (except the substations located at the edge of the system) feeds the two adjacent sections of
the railway. Figure 14 represents the single line diagram of two adjacent substations where this configuration
is shown. The two sections of the contact line are electrically separated by an insulated overlap.
The positive DC busbar of each substation is connected to both sections of the Contact wire: 1x120 mm2 Cu
over each track (0,232 Ω/km at 75ºC and 20% wear has been considered).
Moreover, there are three single core parallel feeder cables of 1x185 mm2 Cu (0,115 Ω/km each feeder at 60ºC)
that run along both tracks in a duct below ground level at 1 m below the TOC. The outer insulation diameter is
25 mm. These three cables are connected to the contact line at some specific points (5 connections between
two substations) by one single core Cu 185 mm2 cable with approximately 25 m length.
The negative terminal of the rectifier of each substation is connected to all rails adjacent to the substations,
Figure 14, by 6 x 400 mm2 power cables with approximately 20 m length. The current returns to the substations
via 4 running rails (2 tracks), the ATP model rail is the reference with worst electrical resistance, 49E1 of 0,035
Ω/km.
| Page 15 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 16 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
In order to estimate the minimum rated impulse voltage, EN 50124 proposes a method in which by selecting
an overvoltage category and the corresponding rated insulation voltage, the rated impulse voltage is
determined accordingly in Section 5.2.
Finally, the environmental conditions shall also be taken into account and according to the macro-
environmental conditions in which the equipment is located. For indoor installations and outdoor equipment
protected from weather conditions, PD3 should be applied.
Section 5.7 summarizes the minimum ratings of the main electrical equipment of line system, applicable for
all the outdoor traction equipment like OCS insulators, parallel feeder cables and surge arresters as well as for
the majority of indoor equipment, such as rectifiers, DC busbar and feeder cables. The diodes installed at the
rectifiers have a maximum inverse voltage of 3600 V.
In terms of insulation coordination, although the system is designed for 1500 Vdc, the lightning overvoltage
study will be performed for the lowest operation voltage, 750 Vdc, according to the employer’s requirements.
The highest lightning overvoltages will be estimated and compared with the previous insulation levels in order
to conclude which is the adequate protection of the system against lightning discharges.
6.3 System modelling guidelines
The electrified railway traction power system is subject to a stroke of lighting. The lightning strike may generate
intense surge voltage overcurrent to the traction power system. Such transients can damage the electrical
insulation of connected equipment and cause railway operation problems. To ensure a reliable operation of
the railway, it is necessary to investigate lightning transients in the system, and design effective protection
against lightning.
For that reason, it’s very important to conduct an evaluation of the transient overvoltage environment of a dc
power distribution system. The application of properly rated surge arresters within a dc traction power system
cannot be overemphasized. Inadequate transient overvoltage protection has proven to be the cause of major
equipment damage.
In this case of study a traction dc power distribution system will be studied using a Metal Oxide Surge Arrester
(MOSA). The Metal-Oxide Varistor (MOV) Arresters are considered superior for dc power system protection
once their energy absorption capability is coordinated with the expected transient surge environment. Under
normal system operations, they will draw minimal current just in case such as ac circuits. They are, however,
designed to carry much greater current and suppress the voltage on occurrence of an overvoltage surge.
A simulation model for the rail power system including overhead wires, metallic mast, surge arresters,
insulators, mast surge impedance and mast footing resistance, and other components was developed in order
to reveal the surge voltage on these electric cables during a direct stroke of lighting
The simulations were performed with ATP-EMTP (Alternative transient Program / Electromagnetic Transients
Program) software. A complete simulation model is established on ATPDraw. ATP-EMTP is a powerful
professional and universal software for the simulation and analysis of transients of electromagnetic
phenomena. ATPDraw is a graphical, mouse-driven protocol of the ATP version of the Electromagnetic
Transients Program (EMTP); in ATPDraw generates the ATP input file by a user-friendly graphic interface using
the appropriate format in FORTRAN for the constructed electrical circuits.
The main emphasis of this section 6.3 is to identify the transient models of the railway power system
components to be used in digital lightning studies. The important model parameters for each component shall
be described below.
6.3.1 Lightning current source model
Lightning-induced surge intensity depends upon the isokeraunic level of the area. The IEC and IEEE standards
have developed different surge wave standards for testing suppressor devices. Both are recommended surge
waves that have been successfully tested for practical use of testing surge support devices for outdoor and
indoor applications.
For Application purposes, the standards and the industry have standardized voltage impulse waveforms 1.2/50
µs (Figure 20) indicating crest is reached in 1.2 µs and it decays to half the crest in 50 µs.
| Page 17 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Similarly, a current impulse wave of 8 x 20 µs (Figure 19) is used where the crews are reached in 8 µs and decays
to half the crest value in 20 µs. The 8/20 µs test wave shape is the most common current waveform used to
define ratings of surge protection devices. Under this test wave shape, the current rises from 10% of peak to
90% of peak in 8 microseconds and falls to 50% of peak in 20 microseconds.
A steep-fronted surge is one with a rise time of 0.1-0.5 µs and wave shape of 10/1000 µs (long wave) is more
representative of the high energy surges usually experienced from the inductive elements.
In general, the waveshape is denoted as tf / th impulse. th is the time-to half value or tail time. And tf is the front
time value. The Peak current magnitude and tail time are important when observing energy stres of the Surge
arrester (simplest representation is double ramp). Current wavefront is an important parameter with regard
to insulator flashover.
Page 18 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
• 8/20 µs wave: to characterize the current waves from an indirect stroke of lighting.
| Page 19 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
99.9
99.5
99 IEEE
98
Percent exceeding abscissa value
95
CIGRE
90
80
70
60
50
40
30
20
10
5
2
1
0.5
0.1
0.01
1 4 10 100 1000
Peak current, kA
Figure 21. Cumulative statistical distributions of peak currents for negative first strokes adopted by IEEE and
CIGRE (N = 408). Taken from CIGRE Report 63 (1991).
The lightning peak current value is a value that depends on probability of occurrence. For the CIGRE
distribution, 98% of peak currents exceed 4 kA, 80% exceed 20 kA, and 5% exceed 90 kA.
The values for peak current more provable to occur are from 5 to 20 kA to a direct stroke to a phase conductor,
while for above lightning currents to 200 kA are more probable to hit on shielding wire or at the top of the
structure of the tower, in consequence, the effect of flashover appears on insulators.
For this analysis purpose, the current surge wave of 8/20 µs is used according recommended for IEC and IEEE
practices to test surge suppror devices for outdoor and indoor applications. The time function of lightning
current can be defined at ATP Software that is known as “Type 15”. At ATP works with models TYPE 15 of surge
wave that are Cigré-Type, Heidler-Type and Standler-Type.
Page 20 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
where;
t90 and t10 are the times for 90 percent and 10 percent amplitude points on the leading edge of the waveform,
see Figure 23.
| Page 21 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
from the graph, t90 = 7,522 µs, t10 = 0,851 µs. Therefore front time is:
𝑇𝑓 = 1,25 ∙ (7,522 𝜇𝑠 − 0,851 𝜇𝑠) = 8,37 𝜇𝑠 ≈ 8 𝜇𝑠
Duration (Tail) is defined as the time between virtual origin and the time of the 50 percent amplitude point of
the tail. Here the virtual origin is obtained by a straight line between 10% and 90% amplitude points on the
leading edge of the waveform where intersects I = 0 line, see Figure 23. As for the tail time, it is the time
between virtual origin, t10 = 0,851 µs and time of 50% amplitude, t50 = 21,2 µs. Therefore:
𝑇ℎ = 21,2 𝜇𝑠 − 0,851 𝜇𝑠 = 20,3 𝜇𝑠 ≈ 20 𝜇𝑠
Page 22 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
𝐼𝑝 (𝑘𝑠 )𝑛 −𝑡
𝑖(𝑡) = × × 𝑒 𝜏2 (2)
𝜂 1 + (𝑘𝑠 )𝑛
where,
𝐼𝑝 : Peak current of lightning strike (Lightning current peak) [kA]
𝜂 : Peak current correction factor.
𝜏2 : Time constant for tail time (current decay-time), interval between t=0 and the tail time decreases at 37%
from peak value.
𝑛 : Decrement factor for current (current steepn factor).
and:
𝑡
𝑘𝑠 = (3)
𝜏1
𝜏1 : Time constant for front time (current rise-time), interval between t=0 and the peak value.
1⁄𝑛 ]
𝜂 = 𝑒 [−(𝜏1 ⁄𝜏2 )(𝑛𝜏2 ⁄𝜏1 ) (4)
where 𝜏1 is the wavefront time constant proportional to front duration, time interval between t = 0 and wave
peak; t is proportional to stroke duration, time interval between t = 0 and point on tail where amplitude falls
to 50 percent of the peak value; Ip is the peak value; and n is factor influencing rate of rise, typically n = 5 to 10.
For a 1.2/50 µs surge wave, amplitude 20 kA:
𝐼𝑝 = 20 𝑘𝐴 𝜏1 = 1,2𝐸 − 6 𝜏2 = 50𝐸 − 6
The waveshape shown in Figure 20 is a 1.2/50 µs surge wave, in other words; with a front time of 1.2 µs, and a
tail time of 50 µs. This waveshape is obtained at ATP software and represented in Figure 26, the peak current
value is 20 kA.
| Page 23 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 24 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 29. Dialog Box of the parallel resistance with the Heidler current source
6.3.2 Railway Transmission Line
Results derived from Electromagnetic Transients (EMT) simulations can be of vital importance for overhead
line designs. Although the selection of an adequate line model is required in many transient studies, it is
probably in overvoltage calculations where adequate and accurate line models are crucial, in this case, voltage
stress to be considered due fast front overvoltages, generally caused by lightning flashes. Overhead line
parameters are calculated using supporting routines available in most EMT programs. The parameters to be
calculated depend on the line and ground model to be applied, but they invariably involve the series impedance
(longitudinal field effects) and the shunt capacitance (transversal field effects) of the line.
Note that the length extent of an overhead line that must be included in a model depends on the type of
transient to be analysed, or, more specifically, on the range of frequencies involved in the transient proc. As a
rule of thumb, the lower the frequencies, the more length of line to be represented.
For low- and mid-frequency transients, the whole line length is included in the model. For fast and very fast
transients, a few line spans will usually suffice. These guidelines are illustrated in Figure 30 and summarized in
Table 8, which provide modelling guidelines for overhead lines proposed by CIGRE, IEEE, and IEC. Figure 30
| Page 25 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
shows the Line models for different ranges of frequency; (a) Steady-state and low-frequency transients, (b)
switching (slow-front) transients, and (c) lightning (fast-front) transients.
Page 26 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Two types of time-domain models have been developed for overhead lines: lumped- and distributed-
parameter models. The appropriate selection of a model depends on the line length and the highest frequency
involved in the phenomenon.
Lumped-parameter line models represent transmission systems by lumped R, L, G, and C elements whose
values are calculated at a single frequency. These models, known as pi-models, are adequate for steady-state
calculations, although they can also be used for transient simulations in the neighbourhood of the frequency
at which the parameters were evaluated. The most accurate models for transient calculations are those that
take into account the distributed nature of the line parameters. Two categories can be distinguished for these
models: constant parameters and frequency-dependent parameters.
The number of spans and the different hardware of a transmission line, as well as the models required to
represent each part (conductors and shield wires, towers, grounding, and insulation), depend on the voltage
stress cause.
For distribution overhead line design is based on lightning stres. By default, it is assumed that a distribution
line flashovers every time it is impacted by a lightning stroke. In addition, the selected distribution line
insulation level is usually the highest one of standardized levels. Except when calculating overvoltages caused
by nearby strokes to ground, there is little to do with EMT simulation of distribution lines in insulation
coordination studies, although those simulations can be very important in other studies.
A railway transmission line can be represented as an ordinary overhead power transmission line; the contact
wire aimed to transmit energy to the train and the rail ensure his return to the substation (Figure 31). Contact
line-wire can be modelled by several spans at each side of the point of impact. A rigorous representation of
each span should be based on a distributed-parameter line model. However, for lightning overvoltage
calculations, a constant-parameter line model can be accurate enough, and parameters are usually calculated
at 400-500 kHz or even 1 MHz.
ATP program offers several line models, like FD-line model (frequency dependent), which is known as JMARTI
are commonly used, but the model is based on the Bergeron’s traveling wave method used by the ATP.
There are other kind of models that can be used for overhead transmission line system in ATP-EMTP:
a) Bergeron: Constant-Parameter K.C. Lee or Clarke models. (Frequency-dependent models of
transmission lines are developed in mode domain using the transformation matrix). At this model
resistance and inductance are power system frequency dependents and is calculated at a fixed
frequency (Freq. init)
i. Clarke model: For transposed three-phase line analyses.
ii. K.C. Lee: For Non-transposed line analyses.
b) PI: nominal PI-Equivalent (for short lines)
c) J. Marti: Frequency-dependent model with constant transformation matrix.
d) Noda: Frequency-dependent model
e) Semlyen: Frequency-dependent simple fitted model.
Bergeron model, the PI model and the J. Marti model are two most usually used on transmission line and tower
models. J. Marti’s model is normally adopted for multi-conductor system because of its frequency-dependent
characteristic. However J. Marti’s model is unreliable for a short line span. As the present railway overhead line
system had a maximum span from 28 m in open track, Bergeron Model was selected for modelling the
overhead conductor system.
The Bergeron model is a very simple model. It is based on distributed LC-parameter travelling wave line model
with lumped resistance. This time-domain Bergeron Model is commonly used in power system transient fault
analyses. It represents in distributed manner, the L and the C elements of a PI section.
The Bergeron model has a lossl distributed parameters’ line describe the following values:
| Page 27 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
𝐿
Surge Impedance: 𝑍𝐶 = √ [Ω] (5)
𝐶
1
Phase propagation velocity: 𝑣= [𝑚/𝑠] (6)
√𝐿 ∙ 𝐶
where,
C: capacitance of the line, [m]
L: inductance of the line, [m]
The Bergeron Model accurately represents only fundamental frequency (i.e. 50 Hz) for inductance and
resistance, similar to PI section model; therefore, the surge impedance is constant.
The Technical characteristics of the overhead railway transmission line are show in table below; The railway
transmission line consists of 92 poles with 28 m spacing meaning total length of 2,6 km.
Parallel Feeder
Designation Contact wire Track Rail
Cables
material Hard Copper Fer 49E1 Copper
2
Section (mm ) 138 6951 3 x 1 x 185
Diameter (mm) 13,26 129 25
Resistivity
0,232 0,035 0,115
(Ω/km)
Table 9. Equivalent rays values of rails
Page 28 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 29 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 30 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Due to the fast-front times associated to lightning strike currents, most tower models assume that the tower
or pole response is dominated by the Transverse Electromagnetic Mode (TEM) wave and neglect other types
of radiations.
Several tower models have been developed over the years and can be categorized in several ways, using a
theoretical approach and models based on an experimental work. At Figure 33 are represented a summary of
the basic tower models for surge impedance measured in Ω. In this figure is not represented the
multiconductor vertical line tower model and the multi-story model of a transmission tower.
As seen in Figure 33, t = 𝜏; is travelling time along the tower or mast [µs]; c is the speed of light in free space =
3·108 m/s or 300 m/μs and h is the tower height [m]
As seen in Figure 33, The mast can be represented by simple geometric figures such as a cylinder. Surge
impedance of the cylindrical tower can be calculated with the formula (7):
2ℎ
𝑍𝑇 = 60 [ln (√2 ∙ ) − 1] (7)
𝑟
where,
h: height of the mast, [m]
r: radius of the mast, [m]
A loss distributed parameter transmission line (Bergeron's travelling wave model) characterized by impedance
and the propagation time is chosen to represent the mast.
From Figure 35 and Equation (7) we have:
2 ∙ 7,850 𝑚
𝑍𝑇 = 60 [ln (√2 ∙ ) − 1] = 258,724 Ω (8)
0,1095 𝑚
ℎ 7,850 𝑚
𝜏= = = 30,78 𝑛𝑠 = 0,03078 𝜇𝑠 (9)
0,85 ∙ 𝐶 0,85 × 3 ∙ 108
Where the wave propagation velocity at the structure is in order of 85% for the speed of light velocity.
| Page 31 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
d [mm]
Figure 35. Mast dimensions
2∙ℎ
𝑍𝐴𝐾 = 60 ∙ ln ( ) (10)
𝑟𝐴
where,
h: height of the cross-arm, [m]
rA: radius of the cross-arm, [m]
From Figure 35 and Equation (10) we have:
Page 32 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
2 ∙ 2,050 𝑚
𝑍𝐴𝐾 = 60 ∙ ln ( ) = 256,541 Ω (11)
0,057 𝑚
ℎ 2,050 𝑚
𝜏= = = 6,83 𝑛𝑠 = 0,00683 𝜇𝑠 (12)
𝐶 3 ∙ 108
𝑅0
𝑅𝑇 =
𝐼 (13)
√1 + 𝐼
𝑔
where,
𝑅𝑇 : Earth resistance, [Ω].
𝑅0 : is the footing resistance measured with low Current and low frequency (i.e. 50-60 Hz), [Ω].
𝐼𝑔 : is the current required to produce a voltage Gradient, Eo , at which soil breakdown occurs or it’s sufficient
to initiate soil ionization, [A]
𝐼 : is the lightning current through the footing resistance [A].
The constant resistance 𝑅0 of the model is estimated in ohm based on the vertical ground rod dimensions
connected at mast and the soil parameters with equation (17); but there is no dedicated earthing for every
mast, the mast footing resistance was assumed to be closed to value of 25 Ω.
| Page 33 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
The exprion of Ig , the limiting current to initiate sufficient soil ionization is given by equation (14):
1 𝐸0 ∙ 𝜌
𝐼𝑔 = ∙ [𝑘𝐴] (14)
2 ∙ 𝜋 𝑅02
where,
𝜌 : soil or ground resistivity, [Ω∙m]; 100 Ω∙m.
𝐸0 : soil ionization gradient, [about 400 kV/m].
To obtain 𝐼 from past equation, Mast foot resistance is represented in ATP by a non-linear resistance R(TACTS)
type 91 controlled through MODELS in which the equations (13) and (14) are implanted. The current signal is
passed from control section in EMTP MODELS to calculate ground resistance value. The model was submitted
to a lightning wave form of 8 / 20 µs and 10 kA amplitude (Figure 48), the result is shown in Figure 37 that
illustrates the response of current in ohms of the earth resistance program.
The earth resistance program is as shown below:
MODEL earth2
INPUT I2
OUTPUT Rg2
DATA Rho {DFLT:100}, EO {DFLT:400E3}, R50 {DFLT:25}
VAR Ibrk, Rg2
INIT
Rg2:=50
ENDINIT
EXEC
Ibrk:=Rho*EO/(2*pi*R50*R50)
Rg2:=R50/(SQRT(1+(ABS(I2)/Ibrk)))
ENDEXEC
ENDMODEL
Where variables in the routine are:
Rho = 𝜌 = 100 Ω
E0 = 𝐸0 = 400 000 𝑉/𝑚
R50 = 𝑅0 = 25 Ω
It has been known that in general the footing impedance tends to be capacitive in the case of high resistivity
earth, and inductive in the low resistivity earth case. A problem of representation is the following: The footing
impedance can be resistive, inductive and capacitive depending on the season and the weather when a
measurement is made, i.e. the impedance is temperature- and soil moisture-dependent. Therefore, it is not
easy to select a model of the footing impedance and this is the reason why resistance model is adopted in this
case. Another consideration is that the mast is erected on the concrete foundation; in most cases there is no
dedicated earthling for all mast.
Page 34 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
𝜌 4∙𝐿 2∙ℎ+𝐿
𝑅0 = × ln × (17)
2∙𝜋∙𝐿 1,3 ∙ 𝑑 4 ∙ ℎ + 𝐿
where,
𝜌 : is the soil resistivity, [Ωm]
𝐿: is the length of earthing electrode, [m], 3 m.
| Page 35 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
ℎ: distance from the top of the electrode to the surface [m], 0,5 m.
𝑑: is the electrode diameter, [m], 0,0254 m.
Assuming that the spacing between these rods depends on mast spacing, is large and enough to neglect the
interaction between them. The soil parameters are: 𝜌 = 100 Ω𝑚, 𝜀𝑟 = 8, and 𝜇𝑟 = 8
At common practice for railway power systems, the earth resistance 𝑅0 of an arrester must be l than 3 Ω,
preferred value is 1 Ω by employers requirement.
𝑅0
𝑅𝑇 =
2 ∙ 𝜋 ∙ 𝑅02 ∙ 𝐼 (18)
√1 +
𝐸0 ∙ 𝜌
Page 36 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
It allows for the accurate computation of the fast-front surges arising at overhead lines and impinging on
substations due to either backflashover or shielding failure of the lines.
Line outages occurred when insulation flashover. There are two kinds of flashover, direct stroke flashover and
indirect stroke or induced voltage flashover. The direct stroke occurs when lightning hits a shield wire or
structure (pole/tower/mast) or phase conductors which can leads ton backflashover and shielding failure
flashover respectively. The indirect stroke occurs when lightning hits the ground on nearby objects leading to
induced voltage flashovers. Flashover occurs when the voltage induced across the insulator is equal to or
exceeds the CFO (Critical Flashover) voltage. For traction power systems; the lightning current flows into the
earth via mast if a flashover by insulators is caused by lightning overvoltage. Overvoltage relays at substation
detect mast potential raised by fault current on shielding wires and open circuit breakers immediately. The
term “flashover” is described as an electrical discharge completed from an energized conductor to a grounded
support structure, which will be the overhead contact system at masts in case of an light trail transit dc traction
power system.
| Page 37 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
𝑡𝑐 = 𝑡𝑖 + 𝑡𝑠 + 𝑡𝑙 (19)
where,
𝑡𝑖 : Corona inception time, assumed zero or is neglected as it is very short compared with the another two
times (ti = 0), [µs]
𝑡𝑠 : Streamer propagation time, [µs]
𝑡𝑙 : Leader propagation time, [µs]
1 𝑡𝑠
𝑎 = ∫ 𝑢(𝑡)𝑑𝑡 (20)
𝑡𝑠 0
a = 400 g + 50 [kV] | For positive polarity voltage,
a = 450 g + 150 [kV] | For negative polarity voltage,
1 𝐸
= 1,25 ∙ ( ) − 0,95 (21)
𝑡𝑠 𝐸50
𝐸50
𝑡𝑠 = (22)
1,25 ∙ 𝐸 − 0,9 ∙ 𝐸50
E: Maximum gradient in gap before breakdown, [kV/m]
E50: Average gradient at (CFO) Critical Flashover-voltage, [kV/m]
For tl leader propagation time can be obtained from the following equation:
𝑑𝑙𝑖 𝑢(𝑡)
= 𝑘 ∙ 𝑢(𝑡) [ − 𝐸0 ] (23)
𝑑𝑡 𝑔 − 𝑙𝑖
𝐸0 : Minimum leader progrion electric field strength, critical leader-inception gradient, [V m-1]
𝑙𝑖 : leader length, [m]
𝑘 : Leader Coefficient, [m2 /kV2 s-1]
𝑢(𝑡) : Voltage across gap or insulator, [kV]
𝑔: gap length, [m]
and,
Page 38 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
number. The insulator may withstand a high magnitude impulse voltage with longer duration. The start-up
time (i.e., zero time) for the volt-time characteristics must be synchronized to the instant that a stroke of
lighting hits the shielding wire or the tower top. If the insulator voltage exceeds this voltage, a flashover occurs
across the insulator. The front time for the arcing can be quite steep, (around 20 ns) and is determined by the
physics of air gap breakdown. For a simplified analysis, a detailed arcing model for flashover is not necessary,
and a short-circuit (ideal switch) representation will be adequate.
𝐾2
𝑉𝑉−𝑡 = 𝐾1 + (24)
𝑡 0,75
where,
𝐾1 = 400 x L
𝐾2 = 710 x L
𝑉𝑉−𝑡 = Flashover voltage, [kV]
L = Insulator Length, [m]
t = Elapsed time after lightning stroke, [µs]
The breakdown occurs when the leader length “Li” is equal to gap length “g” and the corresponding time
specifies the tl
To determine the CFO (Critical flashover) voltage that has the insulation strength of an insulator for a negative
lightning strike the following equation is given:
710 710
𝐶𝐹𝑂 = (400 + 0,75
) × 𝑑 = (400 + 0,75 ) × 0,140 𝑚 = 82 𝑘𝑉 (25)
𝑡 6
where,
𝐶𝐹𝑂 is the Critical Flashover-voltage, [kV]
𝑑 is the length of an insulator, [m]
| Page 39 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
was prepared in the interface MODELS which is an internal routine of the Electromagnetic Transients Program
– Alternative Transients program. The flashover model consists of a (three-phase) TACS switch controlled by a
MODELS component with a time–voltage characteristic.
The MODELS code is given below and it calculates a time–voltage characteristic (FLASH) as exponential
decaying starting from U0 (100 kV) and ending at UINF (82 kV) with a time constant of TAU (2 ms). UINI (3 kV)
is the rated insulation voltage.
The flashover proc is initiated when the voltage goes above UINF. The values in this characteristic can certainly
be discussed, but the value of UINF should be well above the switching insulation level of typically 10 kV; value
of Rated Lightning impulse withstand (1.2/50 μs).
MODEL flash3
comment--------------------------------------
| Front of wave flashover characteristic |
| of the HV insulator. |
| Input: Voltage accross the insulator. |
| Output: Close command for the TACS switch |
-----------------------------------endcomment
INPUT UP, UN
OUTPUT CLOSE
DATA UO {DFLT: 100E3}, UINF {DFLT:82E3}, TAU {DFLT:8.e-7}, UINI {DFLT:3E3}
VAR CLOSE, TT, U, FLASH
INIT
CLOSE:=0
TT:=0
FLASH:=INF
ENDINIT
EXEC
U:= ABS(UP-UN)
IF (U>UINI) THEN
TT:=TT+timestep
FLASH:=(UINF + (UO-UINF)*(EXP(-TT/TAU)))
IF (U>FLASH) THEN CLOSE:=1 ENDIF
ENDIF
ENDEXEC
ENDMODEL
For convenience the MODEL-SWITCH components is compred into a group with a readable vector icon and
with the data U0, UINF, TAU and nodes; UPA-B-C and UN surfaced.
6.3.6 Surge Arrester Model
If a stroke of lighting hits a power line, the only way to protect it is by using a lightning arrester. The lightning
arrester is a non-linear device that acts as an open circuit to low potentials (or conducts a very small current in
order of µA), but conducts electrical current at very high potentials, when operating limits the voltage by
diverting the overvoltage charge on the line to the earth. The surge arrester handles its operation under both
normal and abnormal (overvoltage) conditions based on its nonlinearity (V-I characteristics). The metal oxide
varistor, which is nonlinearly characterized, is the vital element of the surge arrester. When lightning strikes a
line protected with a lightning arrester, the non-lineal resistance draws the current to ground. The surge
Page 40 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
arrester is installed where a cable-wire junction is provided. The arrester is intended to limit the surge voltages
exerted on the cables, and this dispositive is earthed locally via a dedicated down leader. Once the overvoltage
is passed out, the surge arrester returns to its normal state, but the surge arrester can be damaged when it is
subjected to overvoltage of too high energy.
The surge arresters used for protection of exterior electrical distribution lines will be either of Metal-Oxide
Surge Arrester (MOSA), with resistors made of Zinc-Oxide (ZnO) blocks, or gapped type with resistors made of
Silicon-Carbide (SiC). Expulsion types are no longer used. Metal-Oxide (MO) surge arresters are widely used as
protective devices against switching and lightning over-voltages in power systems. The distinctive features of
the MO arresters are their extremely non-linear voltage-current Characteristic, ignorable power losses, high
level reliability and speed.
MOSA cannot only be modelled by a non-linear resistance, since its response depends on the magnitude and
the rate of rise (slope) of the surge pulse. MOSA behave differently for various surge waveforms, depending
each time on magnitude and rate of rise of the surge. Several frequency dependent models of MOSA have been
proposed in a way that the model simulation results corresponds to the actual behaviour of the arrester. The
difficulties for each model arise in the estimation of its parameters, since there is demanded manufacturers’
data on datasheets and apply iterative procedure.
Table illustrates different kinds of models proposed for transient simulation; those are frequency-dependent
models. At first column is represented the IEEE model of Workgroup 3.4.11. This model includes the nonlinear
resistors, designated by A0 and A1, separated by RL low pass filter, where their parameters are calculated from
the estimated height of the arrester, the number of columns of MO disks and the curves shown in Figure 45.
The model in Table 11 second column, (Pinceti model) has been proposed by Pinceti-Gianettoni. This model is
based on IEEE model with some differences. The capacitance is eliminated, since its effect on model behaviour
is negligible. Resistance R (about 1 MΩ) replaced between the input terminals, only to avoid numerical troubles.
Resistance R0 stabilizes or avoid the numerical oscillations and the nonlinear resistors A0 and A1 can be
estimated by using the curves shown in Figure 45. The model proposed by Fernandez-Diaz, shown in Table 11,
third column, (Fernandez-Diaz model), has recently been developed which is recommended by IEEE W.G.
3.4.11 and Pinceti model. The nonlinear resistors A0 and A1 are connected in parallel and separated by
inductance L1. Capacitance C is the value of terminal to terminal of capacitor (C value depends of capacitance
for the arrester height), and the resistor represents of arrester which has the value of the whole resistance of
1 MΩ (used to avoid numerical oscillations, for higher voltages can be assumed to 10 MΩ).
| Page 41 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 42 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 43 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
𝑉10
𝐷𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑘𝑉 = [𝑅𝑒𝑙𝑎𝑡𝑖𝑣𝑒 𝐼 ∙ 𝑅 𝑖𝑛 𝑝. 𝑢. 𝑓𝑜𝑟 𝐴0 (𝑖)] × [ ] (26)
1,6
For A1,
𝑉10
𝐷𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑘𝑉 = [𝑅𝑒𝑙𝑎𝑡𝑖𝑣𝑒 𝐼 ∙ 𝑅 𝑖𝑛 𝑝. 𝑢. 𝑓𝑜𝑟 𝐴1 (𝑖)] × [ ] (27)
1,6
In order to determine nonlinear resistors for nonlinear resistors A0 and A1 using equations (26), (27) and Table
12 we have:
Page 44 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 46. Slow-front A0 curve and fast-front A1 curve for nonlinear components of the MOV
| Page 45 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 46 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 49. Residual voltage of IEEE model with a 8/20-µs Test wave 10 kA
At Figure 49 is represented the residual voltage of the surge arrester modelled with the IEEE method, implying
a test wave of 10 kA and a 8/20-µs impulse current. in this case a peak rise is observed at 7,6 µs, the value of
this peak is 3,914 kV, and this introduce error to the model.
Figure 50. Residual voltage of IEEE model with a 8/20-µs Test wave 10 kA for modelling testing
| Page 47 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
𝑅 = 1 𝑀Ω (35)
Values for A0 and A1 are the same for IEEE model that are in Table 13.
Figure 52. Residual voltage of Pinceti model with a 8/20-µs Test wave 10 kA
Page 48 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
𝑞
𝑉
𝑖 = 𝑝×( ) (36)
𝑉𝑟𝑒𝑓
Where p and q are the characteristics of the arrester and Vref is arbitrary. (Typical values for q = 14 to 30). i and
v are Arrester current and voltage.
Station class metal-Oxide Arrester could be modelled by:
1,0 𝑞
𝑝 = 1000 × [ ] (40)
𝑐
Using equations (37) to (40) can be obtained Voltage-current (V-I) values for non-linear resistor, and are shown
in Table 14:
| Page 49 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
I V
0,00001 238,1
0,00003 1190,5
0,0001 1666,7
0,0005 1845,2
0,01 1904,8
1 2000,0
10 2113,1
125 2345,2
250 2416,7
500 2500,0
1000 2642,9
1500 2738,1
3000 2881,0
5000 3023,8
10000 3238,1
20000 3559,5
40000 4000,0
100000 5000,0
Table 14. V-I curve parameters for non-linear resistor
Figure 55. Residual voltage of Non-Linear Resistance model with a 8/20-µs Test wave 10 kA
Figure 55 is represents the residual voltage of the surge arrester modelled with the as non-linear resistance
with a test wave of 10 kA and a 8/20-µs. in this case a peak rise is observed at 8,5 µs, the value of this peak is
3,241 kV. No oscillations at the peak are observed at this model (Figure 57), the desired residual voltage of 3,65
kV is not reached with this model.
Figure 56 and Figure 57 represent the behaviour of the tree models for their residual voltage at a response of
a 8/20-µs Test wave 10 kA. IEEE model is preferred for this case study.
Page 50 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 56. Residual voltage for IEEE, Pinceti and MOV NLR model (st = 1 ms)
Figure 57. Residual voltage for IEEE, Pinceti and MOV NLR model (st = 0,16 ms)
The surge arrester components of the ATPDraw electromagnetic model allows the compression and grouping
of all of them as a single block called GROUP (see Figure 58) which schematises the whole group of components
in a single software block making clearer the system representation.
Figure 58. Representation of Surge Arrester model at ATP-EMTP using GROUP routine
| Page 51 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
In order to model the power grid in ATP-Draw, the parameters of the network are: V = 10,5 kV, and Icc = 59,489
kA; then the MVASC is:
𝑀𝑉𝐴𝑠𝑐
𝐼𝑠𝑐 = → 𝑀𝑉𝐴𝑠𝑐 = 𝐼𝑠𝑐 × √3 × 𝑉𝐹−𝐹 (41)
√3 × 𝑉𝐹−𝐹
In addition, taking an assumed value of X/R =10 from Table 15, we have:
The X/R value of the network represents the magnitude of reactance ratio over resistance from the utility
connection point to above. If X/R ratio is equal to zero, means that the network only has a resistive portion and
reactance is negligible. For a value of X/R ratio equal to one, it means that the relationship of reactance and
resistance are equal. When the value of X/R becomes larger it means that inductive values of the network are
more representative, i.e. when are connected large generators, or large groups of generators to the network
these make higher the X/R ratio of the network. Bigger X/R ratio value means the longer d.c. component will
take to decay (longer time constant) for the asymmetric short-circuit component. Another example is large
lengths and/or high voltage rated transmission lines connected to the power grid, these make the X/R ratio
value larger. Values of X/R ratios go from 1 to 40. For distribution lines at utility source point, the values of X/R
typically used are from 2 to 10.
tan 𝜃 = 10 (44)
𝑋𝐿 𝑆𝐶 0,101 Ω
𝐿𝑆𝐶 = = = 324,4 𝜇𝐻 (48)
2 × 𝜋 × 𝑓 2 × 𝜋 × 50 𝐻𝑧
Page 52 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
6.3.8 Transformers
In the electrical railway network there is a transformer that has three-phase windings, one in its primary side
and the secondary side with two windings. Therefore, this transformer has a twelve-phase output to supply a
twelve-phase substation rectifier. Substation transformer and rectifier are responsible for transforming the
voltage of the energy network coming from feeders 10,5 kV level to the catenary voltage. Transformer reduces
the tension of the catenary 10,5 kV, 50 Hz to suitable level for traction motors operation 750 V, and rectifier
changes the Vac into a Vdc.
The EMTP has several models of transformers. BCTRAN: is a subprogram support or routine integrated in ATP-
EMTP, which can be used to derive the linear matrix representation [R], [wL] or [A], [R] for single and three
phase transformers using the resulting data of the excitation tests and short-circuit in nominal frequency.
The parameters for the rectifier transformer are listed in section 6.2.1
| Page 53 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
The substation rectifier is a twelve-phase model and it has two rectifier diode bridges. Figure 60 illustrates the
typical elementary diagram for a front end 12-pulse converter. The DC sides of both 6-pulse bridge rectifiers
are connected in parallel for higher current and connected in series for higher voltage.
Figure 61 illustrates the model of the substation at ATP-EMTP software. At the instant of 0 ms the system is
initialized and it is necessary to wait for the system to reach its steady-state condition before applying the
lightning discharge. As can be seen in Figure, the dc operating voltage is reached in l than 5 ms approx. Figure
61 represents a controlled switch voltage (D_FOV), it closes to ground when the Flashover voltage is reached,
the switch represents an insulation failure to ground at the Rectifier Bridge. The Diodes presented at the
rectifiers have a maximum inverse voltage of 3 600 V, a voltage limit that if exceeded will lead to fail of the
diodes. Diodes will breakdown and a large current in the reverse direction will pass. Therefore, it is important
to guarantee that this voltage is not exceeded.
Page 54 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 64. Overvoltage measured at output of rectifier bridge, protected with SPF
In the next case, the surge arrester is removed and the overvoltage is measured with the same conditions of
last case of study. Rectifier Bridge is not protected of atmospheric overvoltages (Figure 65). At 1 ms is applied
the same lightning discharge and the voltage rises over the insulation critical flashover voltage of the rectifier,
3,6 kV and a fault to earth is represented when D_FOV Closes to ground and voltage decreases to a value very
close to 0 V (Figure 66).
Figure 65. Lightning discharge of 1 kA applied to rectifier bridge, not protected by SPD
| Page 55 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 66. Overvoltage measured at output of rectifier bridge, not protected with SPF
6.3.10 Modelling the railway power system
The calculation of lightning-caused overvoltages requires a detailed model as was introduced in section 6.3.2,
in which structures, footing impedances, insulators, surge arresters and mast clearances, in addition to active
conductor and shield wires, need to be represented; (Those elements where modelled in section 6.3 at
previous sections of present document). However, only a few spans at both sides of the point of impact of
lightning must be considered in the line model. Since lightning is a fast-front transient phenomenon, a
multiphase model with distributed parameters, including conductor asymmetry is required for the
representation of each span.
Page 56 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 57 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 70. Simplified scheme for the system configuration of the one line diagram
The system is subdivided into different sections:
• At both opposite sides there are two substations composed of a 3-winding transformer, a rectifier
bridge, and a surge arrester.
• The Overhead line for the OCS is divided in 6 sections; each section is divided by the junction of the
parallel feeder cables to the OCS wire. There are 5 connection points of the OCS to the parallel feeder
cables.
Page 58 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 59 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Page 60 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 61 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
same time would increase the number of discharging paths to the lightning current that flows through the
contact line. The present work aims to simulate only the worst-case conditions in order to guarantee that, apart
from the simulated conditions, the majority of the system conditions will be contemplated, therefore, between
the two simulated substations no moving trains (or stopped trains connected to the contact line) will be
considered.
At the instant 0 ms the system is initialized, and it’s necessary to wait for the system to reach a steady-state
condition before Appling the lighting discharge. The lighting discharge is applied at 0,5 ms in all simulations
and plotted until the overvoltage disappears.
In this work, simulations were performed by Simulation time Tmax = 0.0003 s to Tmax = 0.0006 s and Simulation
step ∆t = 1E-8 s.
6.4 Computation of specific lightning events
In order to execute different kinds of simulations it is necessary to establish a well -defined methodology of
realistic scenarios and considerations that may guide decision-making for the implementation of preventive
actions and taking criteria in at designing stage.
Three system variations were established to evaluate the behaviour of the railway power system and
determine the best configuration that ensures the protection of the system equipment. By changes in the
topology of the network is established a variation, for example changing the position surge arrester and later
is prepared various study cases and scenarios (system stages or operation scenarios).
In spite of the fact that on the contractor’s requirements at the work site it is referred that surge arresters
should be earthed via 1 Ω impedance maximum, simulations are performed for a sensitive analysis of 0 Ω, 1 Ω,
5 Ω and 10 Ω, in order to compare the results. In addition, the characteristics of lightning currents have a
fundamental importance on insulation coordination and on the design of distribution lines equipment; a
sensitive analysis of these characteristic parameters of the lightning discharge is also performed, in order to
evaluate the real impact on the system. For each case of surge arresters, earthing resistance value is applied
for different lightning of peak current of 4 kA, 10 kA and 20 kA. Those values were taken from Figure 21, taking
in account that the probability of occurrence of a 4 kA peak current of stroke exceed 98%, for 10 kA exceed
90%, and for 20 kA exceed 80%.
The overvoltages that arise at the terminals of the rectifier of the diode bridge and at the connection point of
the cables and the contact line are analysed. The overvoltages are then compared with the withstand voltages
of the equipments and their adequate lightning protection are concluded.
It should be noted that the situation of the surge arresters positioned only at the connection points between
the contact line and the cables is not considered, once it would leave all the substation equipment unprotected
against overvoltages originated from lightning discharges that occur in the substation and between the
substation and the first connection point of the cables to the contact line.
6.4.1 System Variation 1. No Surge Arresters
Case of Study 1:
In order to show evidence of the importance of the installation of surge arresters at the system, a lightning
discharge is applied at zone A, i.e., near the substation and without any kind of overvoltage protection. Voltage
curves are represented for a 4 kA and 20 kA lightning discharge at the terminals of the rectifier of the diode
bridge and at the connection point of the cables and the contact line system, and are compared with the rated
impulse overvoltage of the equipment of the substation, Uni = 10 kV (Section 5.5). The discharge is made on
the contact line at the first mast near the substation.
6.4.2 System Variation 2. Surge arresters at dc substations only
In this variation of the topology of the network, surge arresters positioned at the DC busbar of the substations
and various cases of study are recreated by simulations. Surge arresters are connected between the positive
rectifier poles and the substation earth mat and between the negative pole of the rectifier output and the
substation earth mat (Figure 75).
Page 62 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
The path to earth for a surge reaching the positive pole of a rectifier is thus achieved through the surge arresters
installed at the positive terminal. A surge coming from the running rails is also effectively limited by the
installation of surge arresters at the negative terminal.
Figure 75. Positioning of surge arresters at the substation positive and negative terminals
Case of Study 1:
Discharge current is applied at zone A. Various scenarios are created changing parameters of different
components:
• Surge arrester earth resistance varies to 0 Ω, 1 Ω, 5 Ω and 10 Ω,
• Lightning discharge current peak varies to 4 kA, 10 kA and 20 kA.
• Lightning overvoltage effects are observed at the discharge point, at the end of substation of zone A,
connection point with the parallel feeder cable.
Case of Study 2:
Discharge current is applied at zone B. Various scenarios are created changing parameters of different
components:
• Surge arrester earth resistance varies to 0 Ω, 1 Ω, 5 Ω and 10 Ω,
• Lightning discharge current peak varies to 4 kA, 10 kA and 20 kA.
• Lightning overvoltage effects are observed at the discharge point, at the end of substation of other
zone (Not A), connection point with the parallel feeder cable.
6.4.3 System Variation 3. Surge arresters at dc substations and connection points between the contact line
system and the parallel feeder cables.
In this system variation the surge arresters are located not only in the substations, but also in the interface
between the cables and the contact line, as shown in Figure 76. Apart from this change to the system, all other
parameters are kept constant. The same kind of simulations are performed and the results are then compared
with the previous system variation.
It is also important to locate the surge arresters close to the point of connection between overhead conductor
and cable at mast. Failure to do this may result in voltage build up at the cable connection which could exceed
the insulation level of the cable, resulting in insulation breakdown. In Figure 27, the adequate positioning of
surge arresters along the contact line is shown.
| Page 63 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 76. Simplified model for the system configuration for system variation 3
Figure 77. Positioning of the surge arresters at the interface feeder cable-contact line
Case of Study 1:
Discharge current is applied at zone A. Various scenarios are created changing parameters of different
components:
• Surge arrester earth resistance varies to 0 Ω, 1 Ω, 5 Ω and 10 Ω,
• Lightning discharge current peak varies to 4 kA, 10 kA and 20 kA.
• Lightning overvoltage effects are observed at the discharge point, at the end of substation of zone A,
connection point with the parallel feeder cable.
Case of Study 2:
Page 64 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Discharge current is applied at zone B. Varied scenarios are created changing parameters of different
components:
• Surge arrester earth resistance varies to 0 Ω, 1 Ω, 5 Ω and 10 Ω,
• Lightning discharge current peak varies to 4 kA, 10 kA and 20 kA.
• Lightning overvoltage effects are observed at the discharge point, at the end of substation of other
zone (Not A), connection point with the parallel feeder cable.
6.5 Results of simulations
6.5.1 System Variation 1. No Surge Arresters
As mentioned in section 6.4.1, no surge arresters will be used in this system variation.
| Page 65 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
a) b)
Figure 79. a) Voltage on OCS wire at first tower near substation, b) CFO Voltage at insulator on mast
Figure 80-a) represents the voltage at most excited diode of the rectifier bridge when overvoltage occurs, the
voltage on the most exited diode is over 20 kV. Figure 80-a) illustrates that the insulation is damaged at 3,6 kV
(red line at figure) leading to a fault to earth at 0,05 ms when lightning discharge is introduced to railway power
system. Figure 80-b) illustrates an overvoltage at DC busbar were the connected the parallel feeder cable and
OCS is. It allow us to conclude that, if nothing’s done to protect the system against lightning discharges, the
overvoltages that arise to the nearest substation is much above the rated impulse overvoltage of the
equipment, Uni = 10 kV (red line BIL). There is an overvoltage peak of 57 kV at nearest substation on the DC
busbar. This amplitude represents a danger for the correct operation of the equipment in it. If the discharge
current has an amplitude greater than 5 kA, the overvoltages are even worst.
a) b)
Figure 80. a) CFO voltage at most exited diode, b) voltage at DC busbar on nearest substation
a) b)
Figure 81. a) voltage at most exited diode on near substation, b) Voltage at DC busbar on S/E
This scenario has the same parameter condition as the last one, only that the lightning discharge changes to
20 kA value. Results for 10 kA lightning discharge were not presented in this work because results are quite
similar, but magnitudes change in the same rate for 4 kA magnitude.
Figure 81-a) shows the overvoltage on the most exited diode (blue line) that is higher than the CFO voltage that
diode can withstand (red line). Figure 81-b) illustrates how a peak voltage of 100 kV (green line) is transferred
to the nearest substation. In this case, the peak voltage at the nearest substation is lower (in comparison with
Page 66 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Figure 80-a), scenario 5 kA) due to the flashover condition at the cantilever and the insulator on the first mast,
there is a path to the ground that uses a voltage traveling wave that is the mast. In this scenario, the cantilever
and/or the insulator could be damaged or destroyed due to this transient overvoltage.
Figure 82-a) illustrates the potential difference on insulation at cantilever when a flashover occurs. The red line
is the CFOV for cantilever, and the green line is the voltage on insulation on cantilever. In that the green line
touches and is over red line, there is Flashover effect on it. Figure 82-b) shows the voltage on insulator when a
flashover occurs on the cantilever as well. Blue line represents the voltage on the insulator; red line represents
the critical flashover voltage from 6.3.5 and Figure 42.
a) b) z
Figure 82. a) CFO voltage at cantilever, b) CFO voltage at insulator
6.5.2 System Variation 2. Surge arresters at dc substations only
As was introduced in section 6.4.1 in this system variation, surge arresters are positioned only at the DC busbar
of the substations (Figure 75).
6.5.2.1.1 Scenario 1: Lightning discharge current peak 4 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 83. a) Voltage at DC busbar on S/E, b) a) CFO voltage at most exited diode
By applying a discharge current of 4 kA at zone A, at the DC busbar of the substation the transient overvoltage
is measured, where it is connected the rectifier bridge and the parallel feeder cable and even the overhead
contact wire. Overvoltages are plotted in Figure 83. Red lines are critical flashover voltage, blue lines are
transient overvoltage for each case. There is no insulation troubles.
The results were achieved based on the usage of surge arresters located at the DC busbar of substations, using
an earth resistance of 1 Ω for surge arrester grounding.
Figure 84-a) illustrates the resulting overvoltage on the OCW, and into the insulation of cantilever. No critical
Flashover voltage is presented. Figure 84-b) illustrates the voltage at the insulator; voltage is not transferred
to mast or to the insulator.
| Page 67 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
a) b)
Figure 84. a) Voltage on Cantilever, b) CFO voltage at insulator
As shown in this scenario, there are no insulation coordination troubles, once the observed overvoltage is well
below of rated impulse overvoltage of the equipment, (Uni = 10 kV). But in this case, for the rectifier bridge, the
peak value of the observed overvoltage exceed the maximum voltage of the equipment.
6.5.2.1.2 Scenario 2: Lightning discharge current peak 10 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 85. a) Voltage at DC busbar on S/E, b) a) CFO voltage at most exited diode
In this scenario there is neither a problem with the insulation of the equipment connected to de DC busbar or
with the diodes of the rectifier.Figure 85. The cantiveler and their insulator could suffer damage due to
flashover because voltage at cantiveler is 1,3 MV and voltage at insulator is 0,9 MV, Figure 86.
a) b)
Figure 86. a) CFO voltage on Cantilever, b) CFO voltage at insulator
Page 68 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
6.5.2.1.3 Scenario 3: Lightning discharge current peak 20 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 87. a) Voltage at DC busbar on S/E, b) a) CFO voltage at most exited diode
In this scenario there is no trouble with the insulation coordination of the equipment connected to de DC
busbar (transient overvoltage is under the BIL), but the diodes of the rectifier bridge could suffer damage due
flashover, as shown in Figure 87 and Figure 88.
a) b)
Figure 88. a) Voltage on OCS wire at third mast near to substation, b) Voltage at insulator
The cantiveler and their insulator could suffer damage due to flashover because voltage at cantiveler is 2,4 MV
and voltage at insulator is 1,1 MV, Figure 88. At Figure 88-a There is CFOV, and current goes to the insulator
after CFOV is reached, andit drops because of the insulation failure and insulation beacomes a conductor.
Voltage drops almost to zero because it’s a ground fault trough the mast structure.
| Page 69 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Overvoltage peak
Earth Maximum [kV]
resistance peak discharge
[Ω] current [kA] At DC substation
busbar
4 6,123
0 10 7,685
20 8,712
4 7,313
1 10 8,330
20 13,61
4 8,375
5 10 21,88
20 50,20
4 9,614
10 10 45,01
20 76,67
Table 16. Maximum overvoltage at the nearest substation for study case 1, system variation 2
Figure 89. Representation of simplified model at the centre of OCW system with SPD at both S/E
6.5.2.2.1 Scenario 1: Lightning discharge current peak 4 kA, and surge arrester earth resistance of 1Ω
By applying a discharge current of 4 kA at zone B, at the DC busbar of the substation, the transient overvoltage
is measured. Overvoltages are plotted in Figure 90. The red line represents the BIL and critical voltage for
diodes, transient overvoltage curves are under these curves and there are no insulation troubles. The blue line
represents substation in zone A, and the pink line represents the other substation. At both substations, once
the observed overvoltage is well below the rated impulse overvoltage of the equipment, (Uni = 10 kV).
Page 70 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
a) b)
Figure 90. a) Voltage at DC busbar on S/E on 1 & 2, b) a) CFO voltage at most exited diode on SSEE 1 & 2
The results were achieved based on the usage of surge arresters located at the DC busbar of substations, using
an earth resistance of 1 Ω for surge arrester grounding.
Figure 91-a) illustrates the resulting voltage on the cantilever. Figure 91-b) illustrates the voltage at the
insulator. No CFO voltage is presented on it.
a) b)
Figure 91. a) Voltage on Cantilever, b) voltage at insulator
As shown in this scenario, there are no insulation coordination troubles at cantilever, and overvoltage is not
transferred to the insulator. At both substations, once the observed overvoltage is well below rated impulse
overvoltage of the equipment, (Uni = 10 kV). But in this case for the rectifier bridge, the peak value of the
observed overvoltage exceed the maximum voltage of the equipment.
6.5.2.2.2 Scenario 2: Lightning discharge current peak 10 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 92. a) Voltage at DC busbar on S/E, b) a) CFO voltage at most exited diode
In this scenario there is no problem with the insulation of the equipment connected to de DC busbar for both
substations. Figure 92-a) red line represents the BIL or Uni , the blue line represents the transient overvoltage
for substation at zone A and the pink line represents the other substation. At both substations, once the
observed overvoltage is well below of rated impulse overvoltage of the equipment, (Uni = 10 kV).
The diodes of the rectifier bridge of both substations could suffer damage due to flashover, Figure 92-b) red
line representsthe critical overvoltage that diodes can withstand, the blue linerepresents the transient
overvoltage peak for the most exited diode at zone A, and the pink line represents the transient overvoltage
| Page 71 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
at most exited diode at other substation. For the rectifier bridge in both substations, the amplitude of peak
value of the observed transient overvoltage exceeds the maximum voltage of the equipment.
As shown in this scenario, there are no insulation coordination troubles at cantilever; the overvoltage is not
transferred to mast by the double protection of insulator, Figure 93.
a) b)
Figure 93. a) voltage on Cantilever, b) voltage at insulator
6.5.2.2.3 Scenario 3: Lightning discharge current peak 20 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 94. a) Voltage at DC busbar on S/E, b) b) CFO voltage at most exited diode
In this scenario there is no trouble with the insulation coordination of the equipment connected to de DC
busbar for both substations. The red line at Figure 94-a) ilustrates the BIL of the equipment., the blue
linerepresents the transient overvoltage on DC bubsar at substation at zone A, and the pink line ilustrates the
transient overvoltage at DC busbar at the other substation. The diodes of the rectifier bridge of both
substations could not suffer damage due to flashover, as shown in Figure 94-b) the blue line ilustrates the
overvoltage at substation in zone A, the pink line ilustrates the transient overvoltage at diodes at other
substation.
a) b)
Figure 95. a) CFO voltage on Cantilever, b) CFO voltage at insulator
As shown in this scenario, there are insulation coordination troubles at cantilever, and the overvoltage is
transferred to mast by the critical flashover at insulator. Insulator could suffer damage because overvoltage
amplitude is over the red line, which is the critical flashover voltage for the insulator. In this scenario
overvoltage doesn´t reach to both substations, but overvoltage transient is transferred to mast and ground
due insulation failure.
Page 72 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Table 17. Maximum overvoltage at both substations for study case 2, system variation 2
6.5.3 System Variation 3. Surge arresters at dc substations and connection points between the contact line
system and the parallel feeder cables.
As was introduced in section 6.4.3 in this system variation, the surge arresters are located not only in the
substations, but also in the interface between the cables and the contact line, as shown in Figure 76.
6.5.3.1.1 Scenario 1: Lightning discharge current peak 4 kA, and surge arrester earth resistance of 1Ω
By applying a discharge current of 4 kA at zone A, at the DC busbar of the substation the transient overvoltage
is measured, where the rectifier bridge and the parallel feeder cable and even the overhead contact wire are
connected. Transient Overvoltages are plotted in Figure 96. The transient overvoltage will not damage the
equipment on substation, the amplitude for overvoltage is under the red line, BIL.
The results were achieved based on the usage of surge arresters located at the DC busbar of substations, and
in connection points of the OCW to the parallel feeder cables, this using an earth resistance of 1 Ω for surge
arrester grounding.
| Page 73 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
a) b)
Figure 96. a) Voltage at DC busbar on S/E, b) a) CFO voltage at most exited diode
Figure 97-a) illustrates the resulting overvoltage on the OCW, and into the insulation of cantilever. Figure 97-
b) illustrates the voltage at the insulation; voltage is not transferred to mast or to the insulator.
a) b)
Figure 97. a) Voltage on Cantilever, b) Voltage at insulator
As shown in this scenario, there are no insulation coordination troubles, once the observed overvoltage is well
below the rated impulse overvoltage of the equipment, (Uni = 10 kV). But in this case, for the rectifier bridge,
the peak value of the observed overvoltage exceeds the maximum voltage of the equipment.
6.5.3.1.2 Scenario 2: Lightning discharge current peak 10 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 98. a) Voltage at DC busbar on S/E, b) a) Voltage at most exited diode
In this scenario there is no problem with the insulation of the equipment connected to de DC busbar, and the
diodes of the rectifier bridge could not suffer damage due to flashover, Figure 98-b. But the cantiveler and
their insulator could suffer damage due to flashover because voltage at cantiveler is 1,3 MV and voltage at
insulator is 0,9 MV,Figure 99. The red line represents the insulation critical voltage limits, the blue curve
represents the transient overvoltage ampitude. Due to the fact that the overvoltage flows by mast while the
flashover effect occurs, there’s no overvoltage transferred to substation, but equimpment at the caternary
transmision line could suffer damage and/or failure.
Page 74 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
a) b)
Figure 99. a) CFO voltage on Cantilever, b) CFO voltage at insulator
6.5.3.1.3 Scenario 3: Lightning discharge current peak 20 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 100. a) Voltage at DC busbar on S/E, b) a) CFO voltage at most exited diode
In this scenario there is no trouble with the insulation coordination of the equipment connected to de DC
busbar, but the diodes of the rectifier bridge could suffer damage due to overvoltage, as shown in Figure 100
and Figure 101.
a) b)
Figure 101. a) Voltage on OCS wire at third mast near to substation, b) Voltage at insulator
The cantiveler and their insulator could suffer damage due to flashover because voltage at cantiveler is 2,4 MV
and voltage at insulator is 1,1 MV, Figure 101. In both figures overvoltage is over the Critical flashover voltage
(red line).
| Page 75 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
Overvoltage peak
Earth Maximum [kV]
resistance peak discharge
[Ω] current [kA] At DC substation
busbar
4 2,845
0 10 3,169
20 3,349
4 4,903
1 10 9,407
20 13,170
4 7,824
5 10 18,300
20 27,570
4 8,813
10 10 29,020
20 48,510
Table 18. Maximum overvoltage at the nearest substation for study case 1, system variation 3
Figure 102. Representation of simplified model at the centre of OCW system with SPD at both S/E
6.5.3.2.1 Scenario 1: Lightning discharge current peak 4 kA, and surge arrester earth resistance of 1Ω
By applying a discharge current of 4 kA at zone B, at the DC busbar of the substation the transient overvoltage
is measured. Overvoltages are plotted in the Figure 103.
Page 76 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
a) b)
Figure 103. a) Voltage at DC busbar on S/E on 1 & 2, b) a) CFO voltage at most exited diode on 1 & 2
The results were achieved based on the usage of surge arresters located at the DC busbar of substations, using
an earth resistance of 1 Ω for surge arrester grounding.
Figure 104-a) illustrates the voltage on insulator at the cantilever. Figure 104-b) illustrates the voltage at the
insulator, no CFO voltages is presented in both cases.
a) b)
Figure 104. a) Voltage at Cantilever, b) voltage at insulator
As shown in this scenario, there is no insulation coordination trouble at cantilever, and there is no tension
transferred to mast by the cantilever and by the insulator. At both substations, once the observed overvoltage
is well below of rated impulse overvoltage of the equipment, (Uni = 10 kV). Diodes don’t suffer any damage
due to transient overvoltage.
6.5.3.2.2 Scenario 2: Lightning discharge current peak 10 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 105. a) Voltage at DC busbar on S/E, b) a) voltage at most exited diode
In this scenario there is no problem with the insulation of the equipment connected to de DC busbar for both
substations, at Figure 92-a) and Figure 92-b) the blue curve represents substation of zone A located at left on
the schemes, and the pink line represents substation at the other side. At both substations, once the observed
overvoltage is well below of rated impulse overvoltage of the equipment, (Uni = 10 kV,) red line for both figures
represents the critical overvoltage limit for insulation.
As shown in this scenario, there are insulation coordination troubles at cantilever, but they are not transferred
to mast by the double protection of insulator, Figure 93.
| Page 77 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
a) b)
Figure 106. a) Voltage on Cantilever, b) voltage at insulator
6.5.3.2.3 Scenario 3: Lightning discharge current peak 20 kA, and surge arrester earth resistance of 1Ω
a) b)
Figure 107. a) Voltage at DC busbar on S/E, b) a) CFO voltage at most exited diode
In this scenario there are no troubles with the insulation coordination of the equipment connected to de DC
busbar for both substations. The red line at Figure 107-a) ilustrates the BIL and blue and pink curves ilustrate
the transient overvoltages on both DC bubsar at substations. Even the diodes of the rectifier bridge of
substations could not suffer damage, as shown in Figure 107-b..
a) b)
Figure 108. a) CFO Voltage on Cantilever, b) voltage at insulator
As shown in this scenario, there are insulation coordination troubles with cantilever, and with insulation at the
insulator due lightning transient overvoltages.
Page 78 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
Table 19. Maximum overvoltage at both substations for study case 2, system variation 3
6.6 Conclusions
Since it is more difficult to guarantee the earth resistance of the surge arresters along the contact line below
the 1 Ω or even 5 Ω, the 10 Ω case is also considered. As results show, even for the worst case conditions of
earth resistance of the surge arresters located at the substation and along the contact line, maximum
overvoltages at the DC busbar of the substation are never above the insulation level of the substation
equipment.
Therefore, the introduction of surge arresters along the contact line, not only protect the cables (as will be
seen shortly), but also contribute to better protect the substation equipment – the comparison of Table 16 to
Table 19 confirm this fact.
Regarding cables that supply power to the contact line, the installation of surge arresters along the interface
cable-contact line and along the track also contribute to reduce maximum transient overvoltages expected to
arise at these system assets.
If the lightning discharge occurs in zone B, and considering an earth surge resistance varying from 0 Ω to 10 Ω,
maximum overvoltages at the parallel power cables connection points vary from 2.11 kV to 5.17 kV
respectively, i.e., the introduction of surge arresters effectively limit maximum overvoltages below the
lightning withstand voltage of the equipment. As was already mentioned above, the same conclusion is valid
for the remaining equipment.
If the discharge occurs right next to the interface between the cable and the contact line, zone A, the surge
arresters are effective if the surge arresters earth resistance does not exceed 1 Ω.
Above this value, the current that reaches the cable runs through the earth resistance of the surge arrester
causing a voltage drop that is unavoidably added to the arrester residual voltage, originating overvoltages that
surpass the UNi cable rated impulse voltage. This situation can occur especially at high current discharge values,
10 kA or above. The existence of reflected overvoltages increases the deterioration of the voltage behaviour.
However, it is important to stress that this case is very pimistic, so that, in general, it can be said that, by the
installation of surge arresters in the substations and also along the line, all the system equipment (inside and
outside equipment) is fully protected against lightning overvoltages.
| Page 79 of 81
Insulation Coordination Study - Analysis of Lightning Overvoltages
It’s recommended to use the Elektroline surge arrester at connection points of the rails with rectifiers, at the
DC busbar of substation and in mast where OCW and parallel feeder cables are joined.
It is recommended to add another reference of surge arrester into the substation only for protecting the
rectifier bridge at substations, ie HE60MC07 - Raychem Surge Arresters Type HE 60 for D.C. Railway
Applications. When lightning impacts at the first structure at the substation, the overvoltage is close to or
almost over to 3,6 kV (Figure 109). In addition, 3,6 kV is the breakover voltage for a rectifier diode as indicated
in section 6.3.9, and the residual overvoltage of the surge arrester is 3,6 kV as indicated in the catalogue (Figure
44) that is the same breakover voltage for exited diodes. Those values are almost at the limit. If another surge
arrester is selected with lower residual voltage for substations, it will protect the rectifier diodes in case of a
transient due a lightning discharge. A 3,6 kV residual voltage for surge arrester is an ideal condition, using a
earth resistance of 0 Ω, as can be seen in previous tables, the residual voltage of surge arrester varies upon
their earth resistance, it must be taken account that earthing resistance for surge arrester can vary from 1 Ω,
3 Ω, 5 Ω or even 10 Ω, that’s unfavourable for diodes. In that case, the residual voltage for surge arrester must
be as low as possible, and/ or earth resistance for surge arrester must be as low as possible.
Figure 109. Transient overvoltage at substation zone A, due a 20 kA lightning impulse impacts on first mast at
OCW and Surge arrester earth resistance is 0 Ω
Page 80 of 81 |
Insulation Coordination Study - Analysis of Lightning Overvoltages
| Page 81 of 81