Professional Documents
Culture Documents
DECEMBER 1980
THEARUP
Vol. 1 5 No. 4 December 1980 Cont ents
Published by
Ove Arup Partnership
13 Fitzroy Street. London W1 P 680
The spire of 6
Holy Trinity Church
Coventry,
by P. Beckmann and J. Blanchard
A computer system 17
for building services design,
by R. Aish
Ebury Street 24
Development,
by M. Smith
Structural Steel 26
Design Awards 1980
lions; and a new government project in sections are imported, the time to get the steel
The consulting Riyadh. The latter consists of three major to the site usually dictates that the design of
buildings, King's Office, Council of Ministers these buildings is part of a design-and-
engineer in and Majlis Al Shura, with an estimated construct package.
construction cost of £520m. The client is the
Saudi Arabia Minister of Finance and National Economy.
At present however the emphasis is swinging
back to reinforced concrete for two reasons.
Before discussing consulting engineering in Government clients are insisting that, where
Robert Pearson Saudi Arabia it is relevant to briefly outline
the present building developments in the
possible. indigenous materials and prod ucts
are to be used. This applies even if use of the
Kingdom. The Government has just entered local material or product has some cost
The scene in Saudi Arabia changes almost its third five-year plan. The previous five- penalty. Secondly, contractors are demon-
daily as a consequence of the unprecedented year plans were primarily directed towards strating that record construction schedules
building progress which is being maintained . improving all aspects of communication and acceptable to the client can be achieved
As an example of this progress, only four travel, education, hospitals and housing. The using conventional reinforced concrete build-
years ago an open storm drain coursed the present five-year plan gives much greater ings, where possible making use of precast
centre of Shawa Batha, the main street in emphasis to industrial developments, includ- concrete elements which are now readily
Riyadh ; the pavements and roads were poorly ing agriculture, so that in the future the available.
surfaced; car parking facilities were totally Kingdom will not rely primarily on oil exports When considering which materials. finishes,
inadequate; public transport was virtually for its income. This can be seen in the vast etc. to employ, the designer can assume that
non-existent ; there were few major buildings developments now proceeding in both Jubail almost everything is available in, or can be
of high quality, etc. Now a visitor to Riyadh and Yanbu . Therefore, for the consulting readily imported to, Saudi Arabia. There are
can travel via public transport along well- engineer there is a noticeable shift from the many precast concrete manufacturers and
developed streets, seeing many impressive design of separate buildings to the design of ready-mixed concrete plants ; mesh rein-
and well-designed commercial or government industrially-related projects. One could say forcement is assembled in Jeddah ; clay
buildings. that this presents a more challenging environ- hollow blocks can be obtained as against the
This article tries to give an insight into the ment for the consulting engineer because traditional dense hollow concrete block ; an
challenge facing the consulting engineer some of the Government projects now being increasing stock of rolled steel sections is
working in Saudi Arabia, and highlights some let consist of large community developments available in Jeddah; aluminium alloy window
of the differences in practising there and with a miscellany of different buildings. and door frames are made locally; air-
practising in the United Kingdom. Ove Arup The difference between Saudi and UK practice conditioning units are assembled in the
and Partners established a small local design can best be illustrated by looking at the Kingdom, etc.
office in Riyadh in 1975 shortly after the following aspects individually : The construction programme schedules
construction of their first two major structural (1) Construction achieved in Saudi Arabia are remarkable,
design projects in the Kingdom. These especially so because these construction
(2) Design programme schedules and fees
projects were the Riyadh Intercontinental schedules are, on the whole, being accom -
Hotel and King Faisal Conference Centre, for (3) Local design plished without a loss in the quality of the
which Arups were the structural engineers to (4) Examples of projects recently completed . project. Generally, the construction period is
the architect Trevor Dannatt ; and the Mecca about 60% of what it would be in England,
Hotel and Conference Centre for which the Const r u ction with the construction costs in the two
architects were Rolf Gutbrod and Frei Otto. Up to approximately five years ago, almost all countries now being virtually the same .
During the last few years the office has major buildings constructed in Saudi Arabia Contractors from the Far East still continue to
expanded significantly for structural work, had a reinforced concrete structural frame. produce tender prices 20% lower than other
multi-disciplinary work, and specifically for More recently, a significant number of steel - contractors. Hence the competition is very
the detailed design of two very large projects, framed buildings have been constructed, steel fierce .
namely ; 650 km of modern dual three - lane being used for the purpose of shortening the As examples of the speed of construction. the
2 expressway for the Ministry of Communica - construction period. Because all rolled steel Sitteen Street apartment and offices complex
in Riyadh for the General Organization of information to work with the contractor's should there be a structural failure because of
Social Insurance (37,000 m 2 gross area) tender can be more accurate. A recent example faulty consultant's design, the contractor,
was completed in 24 months. A comparable of this was a large prestigious Government as well as the consultant, is held accountable.
building in size and complexity, e.g. the project where contractors were asked to An unfortunate corollary of this is that,
Wolverhampton Civic Centre, took 34 months tender in an eight -week period and the because of the contractor's liability a less
to construct. Alternat ively, the new Lloyd 's consultants had not prepared a bill of scrupulous consultant could be tempted to
Redevelopment building in London is currently quantities. provide an inadequate level of design service.
estimated to take 5; years to construct ; in Therefore, what fees can one expect to As cl ients get to know one better, one is able
Saudi Arabia it would take 3 - 3! years. The receive ? to obta in better fees ; but an area of constant
climate in Saudi Arabia results in virtually no As Saudi Arabia develops, one would hope concern is the lack of site supervision. Ove
construction days being lost due to inclement for a quasi scale of professional fees. In the Arup & Partners are asked to supervise only
weather, but for three months of th e year site meantime, however, bearing in mind that the about one in four of the projects they design in
personnel have to work in shade temperatures Saud i Arabia even after trying to demonstrate
building costs in Saudi Arabia are almost the
which are in excess of 40 °C (104 ° F) . to clients the benefits of full site supervision.
same as in the UK, the maximum fee one can
To meet th e constru ction programmes many expect is about 5-8% of the bu ilding cost ; The worry is that, should structural failure
contractors work 16-18 hours per day, seven and to get th is fee one will be fortunate. occur in a building designed but not super -
days a week. Furthermore many of the labour Normally it w ill be between 2 - 5% and projects vised by a consultant, his reputation will
force from the Far East are on on e- year will be let for much less. The important aspect suffer even if the design is perfect.
ba chelor status contracts w ith no holiday is that the level of design service provided to In Saudi Arabia one has to obtain 'permission
allowance. As a consequen ce a percentage of the client, compared to the service provided to bu ild ' from th e local Municipality. There is
the labour force is always absent due to in the UK, is dramatically redu ced ; more is no separate planning and building regulation
exhaustion . sa id about this later. Not long ago the complete approval as in the UK. When commissioned
design for all disciplines of a university by a Government client, the client usually
Design programme schedules and fees project costing over 1 billion Saudi Riyals obtains the building permission approval, but
For the Saudi Government to achieve the was given to a consultant for a fee equal to when commissioned by a private client the
objectives of the current five - year plan, the 0.6% of the expected building cost. It is design team are responsible for getting the
construction programmes have to be very possible that, for this project, the consultant approval from the Municipality. This pro-
short. It follows that the time for the design was subsidized by his own government! In cedure is not straightforward. The Municipali-
must also be the min imum possible, parti - addition to competing with such low fees one ties do have some printed information giving
cularly as a design -and -constru ct package also has to absorb the rising value of sterling general plann ing and building regulation
can often produ ce a bu ilding qu icker than the against the Saudi Riya l. Four years ago conditions but the data is rather sparse ; and
more conventional appointment of consult ing £1 SR5.75, now £1 = SR8.0. the Mun ici pal ity will only give building
engineer separate from the appointment of the The toughest part of fee negotiations is the approval on the final detailed construction
contractor. Whether the design of a building is barga ining . Trading and therefore bargaining drawings. There is usually insufficient time to
as good using the design - and - construct is hereditary to Saudis and they are much complete all detailed drawings when the time
route is questionable. Certainly th is approach better at it than we are. They are also extremely arrives to submit for building approval.
gives the client less opportunity for con - shrewd in dealing with people. It seems that Moreover, if the Municipality request a few
tributing his own ideas and requirements one is not expected to ask for the minimum changes there is the risk of having to change
during the design development stages. design fee needed at the start of discussions - drawings. Therefore, the practice is to prepare
Typically, a 35,000 m2 commercial building bargaining is a time - honoured custom and the structural layout drawings, take copy
will be designed in a maximum of 9 - 10 one should be prepared to negotiate the negatives and produce typical reinforcement
months, this time including say two approval fee from the original proposal. The only details which are just enough for submitting
periods of two weeks each after the sketch strength a consultant has in such negotiations to the Municipality. When approval has been
design and design development stages is to be able to walk away from the project - granted the detailed reinforcement drawings
respectively . In addition, at the start of the but that is also the Achilles heel : if one does are prepared. This procedure wastes some
design programme the consultant has to carry walk away there is a queue of consultants copy negatives, and a few days only of
out a topographical site survey and geo - willing to do the project at lower fees. drawing . The Municipalities do not often ask
technical site investigation, as well as Obtaining payment of fees can be a problem. to see design calculations and they will
confirm all the services available around the In the UK when an invoice is submitted to a accept designs which are to any of the
site. Often no services drawings are availab le client, the fees are usually paid automatically internationally recognized codes and
from the local utility authorities and one has to after a relatively short period of time, whereas standards.
check with other cons ultants who, for in Saudi Arabia invoices are sometimes Rarely are reinforcement bending sc hedul es
example, may be designing new drainage for temporarily ignored. One has to be prepared prepared because the fee does not allow for
the area ; and then the local authorities have to make several personal visits to the clie nt th em. On several occasions, after a structural
to approve the services demands for the site. to obtain payment ; being sure to observe the design is finished , the contractor has
In a recent large project designed by Arup customs when meeting clients, i.e. not to separately appointed Ove Arup & Partners to
Associates, the sewage effluent has had to be walk in immediately asking for money but be prepare bending schedules. On any large
piped into a storage tank on the site and prepared to discuss the job and any other projects the reinforcement detailing is usually
pumped out at regular intervals until such matters until it is appropriate to mention fees. sent back to the Arups' London office. This
time that adequate new main drainage is happens on a regular basis and the London
constructed . Such aspects make it that much Local design reinforcement detailing group now have
more difficult to complete the design on The biggest impact on design is from the short considerable experience of the level of
time, and if one is late the client can impose design programme and the low fees . Although service to be provided for this type of work.
the standard penalty clause of 1, 2, 3 and 4% the design programmes are very short, the
(up to a cumulative maximum of 10%) With experience one soon learns the particular
final building can nevertheless be of high
deduction of the fee for the first, second, local conditions relevant to the design ; a few
quality, e.g. The Adil Khashoggi building in
third and fourth months delay respectively . examples are :
the photograph was designed in eight months
In calculating the fees required for a project and constructed in 30 months. (1) One is cautious about using load - bearing
many things need to be considered; the The other major difference from UK practice wall construction because of the risk of
cash flow , the type of job, the t imescale, the is that in Saudi Arabia the tender information removal of a wall at a later date.
client, etc. As in contracting, the competit ion is also the final construction documents. (2) Shops should usually be designed for
for design work is very fierce and there is Hence, the consultant does not prepare heavier loading than the UK codes
always another consu ltant will ing to take the tender documents as they are known in the recommend because of the souk ( bazaar)
job at a lower fee. The Saudi tender regulations UK. tradition of using the shop for the
require not less than five in number to be The number of drawings presented to the purpose of bulk storage as w ell as for
invited for Government projects and th is client is usually about 1 / 3 of that prepared in display.
applies to both consulting and contracting . England . The only way one can make a (3) Wind, temperature, rainfall and humidity
Many of our potential clients undertook their profit for the low fees ava ilable is to design the data have only been collected in the
tra ining in the United States where consultants project once only, unlike in the UK where the last 1 0 - 15 years. Originally th e airports
produce much less deta il than in the United design may be changed several times and the collected basic climatic data but now
Kingdom , and more of the 'shop -draw ing ' same drawing produ ced more than once. thorough records are being obtained by
(e .g. deta iled pipe - run layouts, detailed The rapid design process is a tremendous the Ministry of Agriculture. Due to the
reinforcement drawings, etc.) is left to the stimulus to the engineer. The whole design lack of rainfall records for a sufficient
contractor. It is difficult to convince such a team , particularly the architects, must be period of time it is accepted, for example
cl ient that by preparing more detailed dedicated to th is speed of work ing . by the Ministry of Communications, that
information (and therefore requiring a higher The Saudi tender regulat ions stipulate that one can apply rainfall pred iction data
fee) the contractor's tender price can be the contractor carr ies liabil ity for 10 years from Arizona because the two areas
reduced significantly, because with more after the project is comp leted . For example, have very similar climates. 3
The most stimulating aspect of the design The scope of work further increased when the Fig.1
work executed in Saudi Arabia is the speed Ministry of Communications asked Arups to Kocommas model
with which projects pass through the office. design a section of the Khurais road in the (Photo: Bi.ire Gutbrod)
The experience the engineer gains is excep- eastern outskirts of Riyadh , which involves
tional; he does the design quickly and sees the considerable lengths of viaduct and underpass
results equally as quickly. The hours may structures.
seem long (a standard working week is 45 Fig.2
The documentation for the 650 km has been
hours) but the pace of development is so Adil Khashoggi building
split into contract packages for which tenders
rapid that most engineers and contractors put (Photo: Robert Pearson)
have recently been received. Construction is
in more hours than this. Architects: Basem Shi ha bi
hoped to start as soon as possible. The
and Nabil Fanous, Riyadh
Khurais road project will be a negotiated
Examples of projects recently contract but again construction is expected to
completed commence very soon. 2
The following, together with the photographs,
The Government complex,
briefly covers four of Arups' projects in the
Riyadh
Kingdom.
Since late in 1975 Ove Arup & Partners have
Trans-Arabian expressway been working with Professor Rolf Gutbrod
and Professor Frei Otto upon the design of a
In early 1977 Ove Arup and Partners were
major government centre to be constructed on
appointed by the Ministry of Communications
a site just north of Riyadh. The project is
to undertake a reconnaissance study and
composed of H.M . The King's Office, The
prepare the design for the dualling of
Council of Ministers Building, The Majlis Al
approximately 250 km of existing road to the
Shura Assembly Hall and Representatives'
east and 250 km to the west of Riyadh. The
offices. Additional development on the site
road to the east commenced just outside the
includes a major mosque and the services
city and extended to Hofuf Junction.
accommodation required for such a centre.
Later the scope of work dramatically increased .
H.M. The King's Offices building comprises
The project became the design of approxi-
private offices and audience halls for His
mately 650 km of modern dual three-lane
Majesty The King and His Majesty The
highway with grade separation at all inter-
Crown Prince, and the supporting admini-
changes, numerous accommodation bridges
strative offices. The Council of Ministers
(or camel underpasses) wadi bridges and
building includes a council chamber for the
service areas, etc. Also required were by-
ministers and office suites for themselves and
passes at major villages along the route.
their staff. The Majlis Al Shura Building
The work entailed aerial surveys, detailed includes an assembly hall for 300 Repre-
ground surveys, soil sampling and testing sentatives and their associated offices. The
for the full length of the road and soft core total area of construction is approximately
and rotary boring for 64 bridge, 13 viaduct 250,000 m 2 • The office accommodation
and 4 underpass sites. comprises frame buildings clad with a marble
It was necessary to install a computer in fac;:ade which are arranged around the various
Arups' Riyadh office. The machine chosen was assembly halls in the project. These are set
a Prime 400, on which was mounted the within interior gardens which are covered by
MOSS design system, used extensively for shaded and glazed steel lattice compression
the highway design, many of the road draw- domes, the largest of which covers the
4 ings having been plotted entirely by computer. Majlis Al Shura, and is 92 m in diameter.
3 7
Figs . 7-8
GOSI Sitteen Street complex (Photos: Mike Head )
Figs. 3-6 thus min1m1ze temperature differentials . The would have been convenient to take full
Sequence of rock anchor installations result was satisfactory. The whole of the load factors with the water table at ground
on site for Ministry of PTT external structure was shot - blasted and the level but the construction cost would have
Headquarters building uniformity of concrete colour and absence of been prohibitive. To complicate the situation
( Photos : Robert Pearson) shrinkage cracks in the corbel speak highly there was no local data available on the
of the Korean contractor who carried out the seasonal variation of the water table. The
construction . design finally adopted gave reduced load
factors should the water table rise to ground
Headquarters building for the level; the design was evaluated and approved
Ministry of PTT by the French checking authority, Socotec.
Ove Arup & Partners were initially com- The photographs show the construction
missioned by the Joint Venture main sequence for the rock anchors.
The contract for the construction of the civil contractor Saudico / Wolff and Muller to GOSI Sitteen Street complex
engineering and ancillary accommodation has carry out a geotechnical site investigation for
recently been signed and work started on site. the new headquarters building for the The last project is the Sitteen Street office
Tenders for the construction of the major part Ministry of Posts, Telephones and Tele - and apartme nt comp lex for the General
of the works are to be sought in due course. communications in Riyadh. The building Organization of Social Insurance (GOSI).
comprises 115,000 m2 in area with 63,000 m2 The total gross area is 37,000 m 2 with one
The Adil Khashoggi building below ground level as a three level parking basement of car parking . The two identical
This building can be seen to dominate the zone. The commission was later extended to blocks are offices and the inclined · L' block
skyline as one approaches Dhahran airport. redesign the foundations , basement slab and contains apartments. The full detailed struc -
The view is particularly dramatic at night tural design was carried out in Arups'
retaining walls.
when the external structure is silhouetted by Riyadh office over a period of only 5 months.
The site investigation showed the water
the internal lighting . The building, with two The geometry of the ' L' block required special
table to be at - 8 m and piezometer tests
levels of basement car parking, is primarily provision to ensure lateral stability. Although
indicated a full hydrostatic head would result
office space with some levels for apartments. rock anchors were considered at the time as a
from the water table. The site environs are
From the design point of view there were two means of stabilizing the 'L' block. it was
served with main drainage but the building
unusual aspects. Firstly, the geotechnical decided instead to provide a continuous
is on the main wadi which passes through the
desk study indicated the possibility of solution counterweight reinforced concrete box (back -
centre of Riyadh . In the wadi catchment area
cavities in the underlying limestone. In the filled with sand) along the rear of the block at
domestic buildings are rapidly being con -
subsequent site investigation, cavities were foundation level. The complex was completed
structed with no drainage planned for about
found about 8 m below foundation level and in 24 months by a local Saudi contractor,
eight years, and the domestic effluent is
therefore beneath the foundations a regular Saudi Constructioneers, and the quality of
discharged into septic tanks with soakaways.
grid of drilling and grouting was carried out to work is excellent.
seal any cavities. The seco nd aspect was the Therefore, it was expected that a perched In the early construction stages the project
pouring of the large external concrete corbel 'sewage' water table could raise the existing was about four months in delay. As a result
above mezzanine level. This corbel is 2.7 m water table above the -8 m level. This has Arups' Project Planning and Site Services
deep and 2.3 m wide at the top. Guidance was happened in other parts of Riyadh . With the group was commissioned to prepare a
given by Arups' R & D Group regarding the basement foundation level at - 14m detailed work and manpower resource
possible problems from shrinkage cracking the building was subject to flotation over an programme using the original contractu al
due to the high differential temperature area of 2/ 3 of the site. To resist this flotation completion date. The programme showed it
gradient that can occur during the cooling the basement slab was rock -a nchored into was just possible to complete on time,
of such a massive concrete section. It was the limestone with 1450 anchors 9 m long . without lowering building standards. and
decided to insulate the member thoroughly The design posed conceptual stability prob- construction was finished just within schedule
with quilts for two weeks following the lems regarding the appropriate load factors - a tremendous achievement for both
concrete pour to decrease the cooling rate and for flotation as the water table varied. It contractor and supervising consultant's staff. 5
found , so it is also possible that it resulted worry about, but the slenderness of the
The spire of from an initial setting-out error, corrected at a masonry suggested that the wind stability
later stage of the work). needed great care in investigation.
Holy Trinity Church The spire is constructed as a single shell of The wind
Coventry sandstone masonry, and the few measure-
ments which, in the absence of scaffold or
This was in the halcyon days before Ronan
Point had collapsed and officialdom had tried
ladders, could be taken at the initial inspec-
Poul Beckmann tion, indicated an overall thickness of masonry
to bury the Art of Structural Engineering
under a mound of circulars and regulations.
of 0 .20 m, substantially reduced in places by
John Blanchard ornamental carving and weather erosion.
'The gospel according to Davenport ' of
predicting probable wind speeds by statistical
Introduction Apart from this, the masonry appeared to be ana lysi s of observations was being spread ,
in fair condition: there were only a few minor and results of wind-tunnel tests were being
The official guide states : 'The Parish Church
vertical cracks and there was no indication used to improve the translation of wind speeds
of The Holy Trinity was founded soon after
that the bed joints had opened due to uplift into wind loads, but the British Stand ards
the year 1043. In that year Earl Leofric and the
on the windward face. Institution, whilst admitting that their table
Lady Godiva , with the support of Edward the
Confessor, founded and endowed the new The most interesting features inside the spire of wind loads might be out of date, had not
Benedictine Priory in Coventry. The site of this were (a) the vane rod, a 32 mm square yet published their new code on how fast the
Priory and the early " Cathedral" of St. Mary wrought iron rod , which , as the name implies, wind was allowed to blow at a given point in
is only a few yards to the North of the church, connected the spindle of the weather vane Britain. We therefore wrote to the Meteoro -
on the other side of Pri ory Row'. with the central beam in the floor of the bell logical Office and received the following
chamber and (b) a number of 'stars' or reply:
It is a tradition that Holy Trinity was the Parish
'spiders' of tie rods which at several levels 'W e do not have wind observations at or near
Church for the northern half of Coventry,
connected the vane rod to the facets (or a height of 240 ft . for the Coventry area. Wind
which was owned by the Priory, whilst St.
'cants' in steeplejack jargon) of the masonry. speeds at the standard height of 33 ft. above
Mi chael's, adjacent, was the Parish Church
At the upper levels there were four rods in th e ground corresponding to 90, 95 and 100
for the southern half which came into the
each 'spider', each hooking round the vane m.p.h. at 240 ft. were obtained by assuming
ownership of the Earls of Chester. St.
rod ; lower down there were eight- legged a normal variation of speeds with height.
Michael's became the Cathedral wh ic h was
'spiders', the centra l connection being The adjusted speeds were analysed statis-
destroyed in enemy air-raids in 1940, whilst
through a split collar, bolted together. At the tic ally in rel ation to 40 years of records from
Holy Trinity w as saved by the efforts of
lowest level the spider rods were connected Birmingham (Edgbaston) from which it has
Canon Clitheroe who organized continuous
to a bracing ring of t i mber which in turn was been estimated that the probable return
firewatching on the roofs and is credited with
bolted through the masonry. Apart from, or periods of gust speeds (mean over 2-3
having personally shovelled several fire
perhaps because of, a liberal coating of seconds) for 90, 95 and 100 mph at 240 ft.
bombs off the roof.
pigeon droppings, the ironwork inside was in above th e ground are 35, 57 and 100 years
Like the majority of mediaeval churches, fairly good condition. respectivel y. The return periods for mean
Holy Trinity has features of several , successive,
On the outside, the tie rods terminated in iron 1 minute speeds of 90, 95 and 100 mph at
architectural styles: the North Porch is Early
anchor plates, bearing on the masonry. These 240 ft. above the ground are so great that for
English , the Chancel and Main N ave are
had original ly been shrouded in lead , but the practical purposes it can be assumed that
Decorated and the West Window is Per- these speeds will not occur.
anchor plates had nevertheless rusted badly
pendicular.
in many places and were pushing the lead I hope this information will serve your
The spire is the second highest of the famous covering off. Some small cracks were radiating purposes. An account for £1. 8s. 6d. is
'Three Spires of Coventry' the spire on the from some of the anchor plates. enclosed to cover the cost of answering your
tower of St. Michael 's reaches to 92 m, Holy Visually there did not appear to be much to enquiry'.
Trinity 72 m and Greyfriars' Church 58 m.
The original spire, which was slightly lower,
was blown down 'in a terrible gale of wind' Fig.1
on 24 January 1665. The roof of the church Holy Trinity
was badly damaged by the fall and a boy, and St . Michael's
passing by at the time , was killed. {Photo:
Poul Beckmann)
The spire was reconstructed in its present
shape in 1667.
The lantern of the tower was housing a peal of
bells until 1854 when Sir Giles Gilbert Scott,
who was restoring the church, had them
removed to an adjacent timber belfry. One
reason for doing so may have been a wish
to bring more light into the central crossing
by removing the ringing floor whi c h was
situated immediately above the crowns of the
tower arches, but an additional, if not the
prim e, motive may have been anxiety about the
integ rity of the masonry: the tower, as indeed
the whole church, was built of a local , very
soft sandstone, which weathers badly ; so
much so that a major restoration of the tower
was carried out about 1916.
Having survived the air raids of the Second
World War, largely intact, the church stood
without giving cause for concern until 1966,
when , prompted by widespread storm damage
to roofs in Sh effield , the vicar instructed the
architect, Mr C. F. Redgrave , to ask us to
examine the stability of the spire.
The spire
The spire rises 42 m from the top of the central
tow er. It is of octagonal section in plan and
about 6.5 m wide 'over the flats' at the base
where the transition to the square section of
the tower takes place through so-called
squint arc hes which are visible i n the top
corners of the one-time bell chamber. The
shape of the spire is not a perfect pyra mid
as the lowest 9 m of the facets taper less than
the remai nder; {this might indicate that a
more ambitious height was originally intended,
6 but no written evidence of th is has been
The first check on wind resistance
Our interpretation of the M eteorological
Office's letter was that the one minute mean
wind speed should be taken as 90 m.p.h .
(40.2 m/sec.) at 240 h . (73 m) height (since
!
+ 0.8p
Properties
But the calculation could not end here for
we ought not to have believed that we had 0.2
assessed the properties of the spire correctly.
Fig. 6 was prepared to see how sensitive
the response might be to changes in these.
This was derived analytically for a single
degree-of-freedom system and shows how
the persistent dynamic load factor PDLF 0 04 0.8 1.2 1.6 2.0 2.4
0.4
varies with the pulse - ratio ,: . The PD LF was
T im e in seconds si nce start of pul se (on e handstroke)
defined here as the ratio of the peak response
(persisting after the pulse) to the response if
Defl ection at point 8 (ti p of spire)
the maximum horizontal force were applied
Bend ing moment at point 7
as a static load. The pulse-ratio is the ratio of
the pulse duration ·p· to the natural period of
the structure. It is interesting to note that
the greatest response occurs when the pulse Fig. 7
length exceeds the natural period by 15% and Response of spire to swing of one bell
not, as might be expected , when they are
equal. (Fig. 6 also illustrates, if illustration
were needed, how dangerous dynamic
calculations can be if made blindly, especial ly consistently only 57% of its assumed value. Change ringing was then considered;
with the powerful computer programs now The program was therefore re -run with the although less damaging than firing we still
available. For suppose that, using the power structural model amended in this way. The needed an estimate of its effect so as to
of such a program, the force input had resulting responses were found , in fact, to be decide if and when it could be permitted.
represented the whole repeated sequence of multiplied as indicated by the above approxi- During change ringing the peaks from all
forces due to firing , and that the chosen mate approach. The bending moments strokes cannot coincide as they may with
model of the structure had had a natural caused by firing the bells were then taken to firing ; the contributions from earlier bells may
period equal to half the pulse length : Then be a weighted mean of those from the two be positive or negative by varying amounts.
the effect of one stroke would not, apart from analyses, with the higher value weighted by a (This would not be true, incidentally, for a
some stray harmonics, add anything to the factor of two. This presumed that we could high frequency structure with a gravest
next stroke ! ) not be quite so unlucky as to have the worst period of about .025 seconds ; but for such a
In our first analysis the value of ,: was .75/ properties of the spire combined with the structure the PDLF would be very small).
.45 = 1.72 giving a PDLF of 1.35. Had our worst timing by the ringers . Assuming the more critical natural period of
structure been modelled so as to give a Fig . 6 may also be used to show that our 0.625 seconds for Holy Trinity and, for
natural period of 0.625 seconds, with r= 1.2, argument was too facile when we found the simplicity, equal time intervals of 0.22
we should have expected to find basic effect of one stroke of all bells simply by seconds between each bell , it could be shown
responses 2.4 times those of the first analysis. summing their maximum horizontal thrusts. that the worst response occurred after a
And the longer period would have had Allowing for the d iffering values of T for series of changes culminating in 4 3 9 5 2 8
another unwelcome effect. For, with only the different bells and the resulting higher 1 7 6 1 0/ 3 4 9 2 5 8 1 6 7 1 0. The peak
3 ?, oscillations between each stroke (3-! x PDLFs for the lighter bells the multiplication bending moments were then 30% of those
.625 - 2.19) , the response would only decay factor of 5.1 used earlier becomes, for the that might occur during firing. If the intervals
to 76% of its initial value. It was not impossible first analysis, 8 .0 . With the higher period of between bells could vary by 25% of their
for the natural period to be 0.625 seconds ; the second analysis, the effect is very much nominal values and the ringers (obeying
it would only require that the mass was less significant and the facior 5.1 would be Murphy's First Law) would do this in the way
10 10% greater than assumed and the stiffness slightly reduced . most damaging for the structure, then the
resulting bending moments would be 37% of
the firing moments.
The calculated maximum sway of the top of
the spire during firing was 11 mm . 8
The calculated bending moments in the spire
Resistance moments shown thus •
during firing of the bells are plotted in Fig. 8
.;
together with the bending moments due to a "O
0
50 m.p.h. wind; a strong gale. The bending E
moments to cause failure, defined earlier as ,;
occurring when cracks penetrated half-way 1E 6 •
across the spire, are also indicated. Bending 0
u
moments causing a crack just to open may
"'"'
be taken as two-thirds of these. The graph ;s •
shows how bell-ringing effects are more "ii
significant than those of wind near the top of ·'"'=
c
2300
the spire but are relatively unimportant near
the base. They also show that the factors of
.g
·;;
4 •
Fig.8 0
safety under either bell - ringing or wind (l.
4100
loads are much more critical near the top of Bending
the spire. moments
0 400 800 1200
•
Following this work we reported that the caused by
Bending moments (kN - m)
bells could be re-hung provid ed they were firing
accompanied by an anemometer with its of bells
dial plainly visible in the ringing chamber.
' Firing' was to be discouraged and should be
prohibited in any wind stronger than a strong had been most serious on the lower slopes of but the depth of these cracks would exceed
breeze. Change ringing would be allowed for the spire. just above the transition between 10% of the width of the spire only near the
anyth ing less than a strong gale (50 m.p.h.) the very steep lower section and the more top and the bottom. The wind moments in
above which only a solitary bell might ring. pronounced upper taper. In other words. we Fig. 9 assumed that the wind was blowing
had lost most thickness where the girth was normal to one face of the octagon . With the
The steeplejacks' initial inspections greatest and it mattered most! wind blowing in a corner to corner direction
Lack of funds prevented the church from The quality of the stone turned out to be no the moments were increased by about 8% but
taking advantage of our (albeit qualified) more encouraging: a "fair sample' from the the safety factors and compressive stresses
approval of the re - hanging of the bells (they local quarry, judged by a mason to be ' better were in fact no worse ; cracks would , how-
were , in fact, subsequently sold) and we than some of the stone in the spire', was ever, have started earlier and would have
heard no more from Mr. Redgrave until early delivered to our Birmingham office with a penetrated deeper.
in 1972 when a further joint inspection of the request to pass it on by hand as 'the stone is
Further discoveries by the steeplejacks
spire was made. rather friable and will not stand much rough
handling' . While we were finalizing these calculations,
This time it was evident that rusting of the tie Furses' were inspecting the condition of the
bars was causing bursting stresses in the The laboratory managed nevertheless to cut
anchor plates for the tie rods and the sur-
masonry around the anchor plates and we prisms 76 mm long and 38 mm square, out of
rounding masonry and their findings indi -
recommended that the ends of the rods should the sample. These were weighed and tested
cated that the tie rods might have to be
be exposed by opening up the masonry, that for com pressive strength . Two prisms gave
replaced rather than repaired. In a letter
the rust should be cleaned off and the rods an average compressive strength, perpen-
advising that th eir latest report was coming
protected against rust prior to the masonry dicular to the bedding, of 12.7 N/m m 2 ,
they also wrote:
being reinstated. another two gave a strength parallel to the
bedding of 4.0 N/ mm 2 . The average density · ... We feel, however, that we should advise
As part of the preparations for this work, an of the four samples was 2030 kg / m 3 . you without delay that . . . the top 1 5 ft
inspection was carried out by W . J . Furse & (4.6 m) or so of the spire moves. The move-
Both strength and density were significantly
Company Ltd ., a firm of steeplejacks and ment appears to be from a bed joint which
less than expected and whilst the very low
stone masonry contractors. Their findings completely opens and closes (a width of i"
strength, parallel to the bedding, might have
caused us considerable concern : they (10 mm), when wind of this strength
been a function of the small size of the speci-
estimated that weathering had reduced the (approximately force 6) is blowing .. .'
thickness of the masonry to as little as men we once again went through the cal-
culations. This was the solid tip of the spire which,
0.08 m in places! although badly weathered, had not so far
We had made some allowance for weathering The final check on wind stability given us cause for concern, and in trying to
in our stability calculations but we had not find a reason why the solid tip of the spire
With better information on the density of the
imagined erosion on this scale, and whilst it should be rocking while the hollow part
masonry and the thickness of the walls as
was obvious that this was a local weak spot, remained steady we stumbled on an, up till
well as the general geometry of the spire, a new
calculations showed that a reduction of the then , unpublished principle which, whilst
and more detailed check on wind stability was
average thickness from the assumed 0.17 m perhaps not being the cause of the Pyramids
made with the wind loadings now calculated
to, say, 0.12 m would seriously diminish the having lost their tips, explains why so many
to CP3: Chapter V Part 2: 1972. This was
wind resistance of the spire, not only as a spires are blunt-ended .
interpreted in an orthodox way with a basic
consequence of the reduction in dead weight
wind speed of 44 m/ sec (98 m.p .h.) , a 50 year The inherent instability of solid
but also because the compressive stresses
return period, and, rather conservatively, pyramids
could no longer be considered insignificant.
ground roughness Category (3) and Size
We had so far ignored the vane rod in our Fig. 9 shows that the theoretical safety factor
Class C (15 second gusts) . The variation
calculations, but we thought at this stage that deduced from our calculations remained
down the spire of the resulting spire weight
it might for the time being, assist the stability nearly constant with height up to the level
and wind moment is shown by the full lines
a little by providing a tying down force to where the spire changes from hollow to solid
on Fig. 9. The dashed line on this figure
augment the stabilizing effect of the dead construction. However, within the solid
shows the nominal factor of safety against
weight (an optimistic assumption as it portion of the spire, the safety factor decreased
overturning . This safety factor fell below 1.8
turned out to be) , but we needed to assess so sharply with height that further study was
for the top 4 m and the lowest 18 m of the
the stability more accurately in order to obviously required .
spire.
decide on what needed to be done and we It was found by elementary statics that, for
If failure was defined, as in the earlier checks,
therefore requested 'further and better par- a uniform solid right cone of height 'x', den-
to occur when cracks penetrated half-way
ticulars' of the thickness and strength of the sity '9', and vertex semi-angle 'a.', the safety
across the spire, then the safety factor at the
stone. factor against overturning under a uniform
base was only 1.06. The dramatic reduction
effective wind pressure 'p', is given by
Furses' extended their ladders and, in order to from the corresponding previous value of 1.65
measure the thickness, drilled 16 mm holes can be attributed wholly to the 17% reduction n 9 tan a.
through each facet of the spire at 11 , 13.5, in weight and the 28% increase in wind load. x, if the cone is not anchored
p
19.5, 22, 30.5 and 33 m above the base. The Under the design wind the calculated com-
results were interesting but not entirely com- pressive stress in the stonework adjacent to down. A similar expression is found for a
forting: The average of the thicknesses the windows near the base was 2.3 M Pa but, pyramid. Thus for a given density, slenderness
measured at the upper two levels was 0 .20 m, this increased by 56% if the wind load and wind pressure, a value of ' x' can always be
at the middle two levels0.20 m and at the lower increased by 20%. Under the design wind , found for which the safety factor is less than
two levels 0.12 m with a confirmed individual tensile cracks could in theory (in the absence unity. It immediately follows that : ' If the
minimum of 0.076 m, indicating that erosion of any tensile strength) open up at any level masonry has negligible tensile strength then 11
a portion of t he soli d top of a pointed spire wi ll
always topple when the w ind blows, no
Nomina l safety factor against overturning
matter how gently it blows'. Th is 'Rule of
Spires' is obviously a specialized va riant of 0 1.0 2.0
Murphy's Law but is perhaps unique within 42
this codex in being capable of mathematical
rather than experimental proof.
That the Rule is not a mere academic cur- 36
iosity may be seen by considering a pointed
spire of the same slenderness as th at of Holy
~
Trinity. Assuming a fairly steady wind pressure ~
of 1.6 kPa and still negligible tensile strength, .; 30
then the top length of the spire up to 3.3 m E
long might be expected to fall. To see the ~
sig nificance of the tensile strength we sur-
'c. 24
mount the spire with a ball and cock, the cock 0"'
Q)
being rather negligently stuck cross-wind. "'
The calculated tensile stress at a level 3.3 m "'
.0
I
The remedial work s I I
The res ults of Furses' and our own investiga- I I
I
tions could be summarized thus: the wa lls of
l/
I - I J
- Bandsof50X12mm
flats with bolted joints
the spire were too light and too weak to give
adequate overall wind stability, the top was 'II 11
not adequately tied down and the rusting of I I
the tie bars was bursting the masonry which I I
I I
was also suffering from weather erosion.
I I
The rocking tip obviously called for the most I I
urgent action, but the choice of the most I I
appropriate remedy was dependent on what I I
was to be done about the overall stability of I I
the spire : I
Rebuilding was of course the best way of I I
dealing with the tip, but that would have
necessitated an amount of scaffolding not far
11 I
I
I I
short of what a complete reconstruction of I I
II
the entire spire would require , and wh ilst such I
a complete replacement would have been I I
nice, it was financially impractical and (as will
be seen) technically unnecessary.
Tak ing down the offending t ip and capping
of th e stump until better times were seen as a Fig.1 0
last resort, disliked by all, the more so as it The top cage: final design
12 did not help the overall stability significantly.
Reconnecting the vane rod at the top and
stressing it against the bell-chamber floor
beam would very elegantly have solved the
overall stability problem at the same time as
anchoring the wayward tip. Unfortunately,
it still meant dismantling the top with the
attendant high scaffolding cost and it was
also doubtful whether the bell chamber
floor could take the uplift without expensive
strengthening.
A suggestion of a glass-fibre-reinforced plastic
replica was briefly shuddered at, before being
dismissed as too difficult to hold down and,
more important, not having an adequate,
proven, lifespan.
In the end it was agreed to restrain the top of
the spire within a 'cage' of structural steelwork
extending far enough down to prevent the tip
from rocking relatively to the lower part of the
spire. It was considered by all concerned that,
if suitably rust-protected and painted, such
a cage would probably last 100 years and
could be made to be visually acceptable, at
the same time as allowing fairly quick
procurement and erection by Furses' steeple-
jacks.
Compromise solution
Our first proposal for this top cage was
substantially modified in the light of Furses'
very practical comments, and we finished up
with a compromise between the traditional
steeplejacks' circumferential strapping, which
mainly aims at limiting vertical cracks in
chimneys, and our requirement which was for
something to provide vertical tensile re-
straint (see Fig. 10). The steelwork was hot-
dip galvanized, etch primed and painted with Fig.11
a bitumen-based paint to match the brownish- Tower and spire
red stone. with inclined
The work of fabricating and erecting this hoist and top cage
strengthening was put in hand immediately (Photo:
and was carried out by Furses' in the early Paul Beckmann)
spring of 1977.
Fig.12
To improve the overall stability, we produced Vertical section through
a design which more than replaced, on the tower and brick lining
inside, the structural thickness which had
been eroded away on the outside. This Fig.13
replacement took the form of a lining of Horizontal sections through
brickwork, built hard up against the inside face tower and brick lining
of the masonry and tied to it with fish-tail
straps of stainless steel, fixed to the stone
with small expanding anchor bolts. The
brickwork was to be supported on encased
structural steel beams, the ends of which
penetrated the masonry shell of the spire and,
resting on plinths of engineering brickwork,
transferred the own weight of the brick
lining and the loads due to wind forces,
to the masonry of the tower below (see Fig .
13). The brick lining was to be 19.3 m high,
the thickness for the lower 10.0 m was to be
115 mm on the solid facets and 230 mm on
the facets with lights so as to compensate for
the extra weakening of the masonry section .
The top 9.3 m of the lining was to be 76 mm
brick-on-edge all the way round . The effect Horizontal
of this brick lining on the spire weights and on section Y-Y Z-Z
the safety factors is shown by the chain-
dotted lines in Fig. 9. z z
Vane rod renewal
The masonry under the anchor plates for the
tie rods was badly cracked in places; so much
so that it was doubtful whether effective
anchorages could be achieved for the replace-
ment rods . For this reason and also so as to
enable the new rods to be installed before the
old were removed, the new spiders were y y
designed to be at slightly different levels. To
allow renewal of the vane rod whilst preserv-
ing the bracing effect of the spiders the new
16 mm diameter stainless steel rods did not
hook round the vane rod, as the old ones had, x x
but radiated from split collars which were
bolted together around the vane rod, which
was to be renewed with 25 mm diameter Plan section X-X at base of spire
stainless steel after the tie rod spiders had been showing structural steel beams
replaced. The top of the new vane rod was to ~-s_u_p_po_r_ti_n_g_th_e_b_r_ic_k_li_n_in_g~~~~~~~~~13
14 15
Fig.14 16
Laying the brick lining
(Photo: Poul Beckmann)
Fig.15
View up the spire showing new spiders,
vane rod and completed brick lining
(Photo: Poul Beckmann)
Fig.16
Spire seen through Cathedral porch
(Photo: Pou I Beckmann)
References
(1) HEYWOOD , Sir A. P., editor. Bell
towers and bell hanging . Central Council of
Ringers, 1914. Chapter 4, pp. 54-60: 'A short
summary of a series of experiments and calcu-
lations mainly directed to expose the fallacy
of the theory that elasticity in a bell-frame
relieves the strain of the fabric of a bell-
tower', by E. H. Lewis.
(2) SAYERS, Dorothy L. The nine tailors,
Gollancz, 1934.
(3) JACKSON, Canon L. The Parish Church
of the Holy Trinity, Coventry: a guide written
by the Vicar. New edition, The Parish Church,
1971.
Credits
Architect
Claude F. Redgrave
Main contractor
J. W. Furse & Sons Ltd.
Quantity Surveyor
C. H. Osborne & Partners
Acknowledgement
Mr. Redgrave provided the major part of the
information on which the introduction is
based.
John Taylor & Co. of Loughborough provided
the information in Table 1 as well as Reference
14 1.
Scope o f t he study T h e tank
Study for It is envisaged that the provision and opera- Nine permutations of tank sizes were given
a deep water tion of such a facility would be of national
importance and should , therefore, meet the
varying from a maximum size of 1 OOm x 50m x
12m deep to a minimum of 50m x 25m x 8m
testing tank combined needs of industry, universities and
Government.
deep.
The method of circulating the water to produce
John Tyrrell The technical specification identified a
number of parameters to be considered for the
the required current and the wave generation
aspects were fundamental considerations in
proposed facility and these include the tank the design of the tank structure.
General plan area, water depth, wave generation, The proposed general arrangement of the
current, carriage, craneage and wind . Values tank is illustrated by the section in Fig. 1 and
As the exploration for oil and gas moves into for the maximum, basic and minimum
deeper waters, current offshore technology consists of a reinforced concrete box approx-
requirements were given for each parameter imately 7.5m wide around the perimeter of the
is being extrapolated beyond existing as well as stating further options to be con -
experience . The need for a new deep water building and forming access aprons at the top ,
sidered. together with a base slab to the tank.
testing facility to cater for the future demands
Engineering implications of the variable In order to reduce the energy losses in
of marine technology has been under review
by the Science Research Council Marine parameters were to be considered in terms pumping the water through the side channels
of design, manufacture and installation, and and improve the general flow characteristics,
Technology Directorate (SRC) and the
construction. allowance was made for shaping the concrete
National Maritime Institute (NMI) for some
time. Cost estimates were to be built up and in the form of a curved profile, particularly
presented to indicate the influence of the around the corners and at both ends,
A number of parallel studies have been com- relevant parametric variations.
missioned recently jointly by the SRC and W ave generati on
An unencumbered green field site was chosen
the NM I to assess the feasibil ity of a large - The specified wave requirements were as
as the basis for the study but the relative
sca le laboratory facility for hydrodynamic follows :
benefits of locating th e facility adjacent to
research and test ing . The main studies
existing facilities of the NM I at Feltham and
include : Max. Basic Min.
Glasgow University were also to be assessed.
(1) A technical study of the modelling and / Maximum height of
Current state of the art
or testing problems likely to be encountered regular waves (m) 2 1.5
There are a number of existing facilities both
(2) An engineering / economic study based in this co untry and abroa d where ship keeping
on an outline technical specification with the
Wavelength range (m) 1 to 30
and hydrodynamic testing are carried out.
main features varied parametrically Eight major facilities were ca refully c hosen to The wave maker was to be capable of
(3) A market research-type study to assess highlight the planning, design and operation producing:
the likely demand of such a facility. of particular relevance to the study and, (a) Uni - directional long crested waves
armed with a list of questions, we duly
Following an initial presentation Ove Arup & (b) Multi -directional irregu lar wave spectra
visited them. It soon became apparent that the
Partners were co mmissioned to carry out the technical specification far exceeded the (c) Irregular wave periodicity up to high
engineering/economic study in November capability of any existing laboratory and our return periods
1979. task amounted to a challenge. (d) Breaking waves in a control led manner.
1. Testing t ank
2. Trimdock
3. Moving carriage
4. Wave makers (two sides)
5. Beach under apron
6. Hinged access to dock
7. Monorail crane
8. Mobile craneage
9. Hydraulic working platform
1 0. Water cha nnels
T
11. Variable depth bottom
12. Current chamber
13. Plant
14. Loading dock
15. Workshop apron
16. Service co re
17. Workshops
18. Offices
Fig _1
Isometric view of tank
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~- 15
Plan at office level
1.5m 168m
EJ-:-i~
' ',,.-"r",,...,F,F~~'icSr~~....,.__,es,;""'rSo=a=arSF.,....SF"'~~~~~~~SF"'~~~~~~~~~ ~ ~ ~~ ~ ~~ ~ ~ ~~ _/
N
.,,"'°
"
"O
Hinged access
f
'°
0...
Offices, labs,
Max. tank size 100 x 50 x 12 m admi n.,
comp uter,
ameniti es
block
N lJ'~~~~1--~~~~~~~~~~~~~~~~~~~~~~~~~~~~-f-o~~~~~~~~~~~~-f-~~--, 44 m apron
\
1.5m 12m 100mtank
Longitudinal section
E
l!)
;;:;
Pit
30 m Current c hamber 8m 18 m
Fig.2
Plan and section of tank
Recent work at Edinburgh University, as part (2) A capability of complete variation of the containing a battery of axial flow fans. The
of the Department of Energy's wave energy current direction relative to the predominant capsule would be suspended from one of the
research programme has led to the develop- wave heading main tank carriages by means of a small
ment of a second generation of wavemakers (3) Variable vertical current velocity profile traversing carriage and a bogie unit to allow
which utilize advanced electronics to enable maintaining a limited flow capability over the the full 360° rotation.
an exacting specification for short crested whole depth range. Craneage and carriage
seas to be achieved . The wavemakers The combined requirements for wave , current Emphasis was placed on the flexibility of use
consist of narrow low - inertia paddles arranged and water depth variations led to the con- of the fa c ility and the arrangement was
vertically in a piano key lay-out and hinged at clusion that the recirculation of water for designed to provide a suitable system,
the bottom. The motion of each paddle is current generation should take place outside duplicated as necessary for maximum utiliz-
individually controlled to generate both the confines of the tank. The tank would ation during testing operations.
regular and irregular waves i n a predeter- therefore be surrounded by a water duct
mined manner. Different input signals and At roof level three separate cranes would allow
which would house all the current generation
phase shifts between adjacent paddles the interchange of bogies if required , thus
and profile control equipment.
enable short crested wavefronts to be permitting a model to be easily transferred
Two methods were studied for the generation between any location on the apron and tank.
generated in varying directions across the
of current; a number of large pumps in
tank. Wave absorption systems, based on A system of four half carriages, each canti-
parallel and high velocity water jets to induce
feedback from the hydrodynamic pressure on levering out from rails on the side aprons over
the total flow .
the water face of the paddle and its angular half the tank width was proposed. Ea c h half-
motion, enable any reflected waves to be Pumping the total water quantity was carriage could be rapidly locked and unlocked
absorbed and new waves to be generated proposed as the preferred solution in so far as with an opposite half carriage to form a very
simultaneously. This feature allows good it is more straightforward and the current flow rigid carriageway spanning the full tank
control and repeatability of wave conditions pattern is more predictable. To achieve the width if required.
without the pressure of unwanted reflected maximum current speed over the full width
A small ' delta carriage' could be suspend ed
waves and thus enables the plan area of the of the tank corresponding to a water flow
from sub-carriages to permit small immediate
tank to be significantly smaller than would rate of 300m 3 / sec., 10 of the largest pumps
movements i n any direction when required to
otherwise be the case. A similar arrangement available in this country would be required.
follow freely moving or self-propelled models.
was proposed for the new facility with wave- A louvre system installed at both ends of the
makers on two adjacent sides of the t ank but tank was devised to control the current flow Water depth
driven by a precision servo-hydraulic system. and achieve a variable veloc ity profile. Two methods of achieving a fully variable
In order to eliminate the effects of reflected depth of water were considered. The first was
Wind to adjust the quantity of water in the tank and
waves from the remaining two sides of the
tank, 'beaches ' would be provided under the A maximum mean wind speed of 12.5m / sec. the second was to install a movable floor
aprons. was specified over a limited area but over any which could be fixed at any depth below the
part of the tank in any direction . The wind surface of the water.
Current field should also be capable of being moved The preferred method was the movable floor
The requirements for current include: to follow a model. which could be controlled automatically and
(1) A maximum speed of 0.5m / sec. available It was envisaged that the wind requirement adjusted rapidly to limit disruptions to the
16 overthewholetankarea would be provided by means of a capsule testing operations.
The system comprises a vertically adjustable (2) Analyzing data from test runs It was envisaged that the facility would be
steel platform with small positive bouyancy, (3) Monitoring and displaying data during patronized by industrial organizations as well
held vertically in position by cables and the calibration of equipment as academic and government establishments.
horizontally by contact at several points with Close links would need to be maintained with
buffers around the sides of the tank. Depth (4) A word processing operation to produce universities and other research organizations
adjustments could be made by either tension - reports for the users to ensure that new developments in experi-
ing the cables to lower the floor, or easing the (5) Programme development. mental techniques and theoretical hydro-
cables off to allow the floor to rise. Steel dynamics would be incorporated in the
shafts. fastened to the underside of the The building testing procedures and interpretation of
platform, would pass into deep sockets in the results.
A single building envelope was proposed to
concrete floor of the tank. The shafts could be
house all functions and activities associated
rigidly locked at the required level by a Costs
with the tank facility. The envelope comprises
remotely operated hydraulic clamp system at An assessment of the capital costs for the
a clear span deep steel truss system with
the exit of each pocket. building and main equipment was based on
cladding of composite sandwich construction.
preliminary designs for the various para-
Data systems The principal concept of the building meters and from information obtained from
The proposed arrangement for data acquisition organization was to locate the workshops, specialist manufacturers.
and transmission consists of a central offices and general amenities at the end of
computing system located in a remote control the facility adjacent to the deep apron. A confidence band was applied to the costs
room and smaller computers mounted on ea c h and in the case of the primary equipment,
The workshops were located on two levels allowance was made to reflect the 'state of
of the four carriages as back-up to allow for within the concrete podium with the varied
maximum reliability. the art and the need for system development
functions planned to suit their sequence of and testing.
Each test, including the stages of instrument- activities and relationship to apron level.
ation and calibration, would be controlled Estimated running costs for the facility were
A zone for tank side workshops was located also provided .
from the carriages. Data could either be
on the end apron to provide a facility for
acqu ired and recorded direct on the local
instrumentation. fine engineering and adjust- Conclusion
minicomputer or transmitted to the central
ments. Above this area, a secondary structure
compiling installation by the acquisition The study has provided a stimulating insight
containing all offices, control room, computer
system on each carriage. of a relatively new sphere of interest to us.
complex. laboratories amenities and storage
The acquisition system would be requ ired to A number of people throughout the firm have
fac ilities was proposed .
accept and transmit for storage and sub- contributed in some way and our involvement
sequent analysis the data from a series of Natural daylight tends to stimulate algae with Arup Associates on the building
64 analogue transducers with the model growth in the water and although daylight organization and costing was, from our
under test. Data from the transducers would and outside awareness were considered for viewpoint, a fruitful one.
be read at 1 OOHz for a 10-minute test period . the elevations at all levels, no glazing was
Our report was well received by th e client but
provided over the tank area .
Three data transmission systems from the what happens next will, to a large extent,
carriage to the control computer were depend on the results of the other concurrent
investigated ; an umbilical cord , a radio The facility in operation studies. However, we are hopeful that with
telemetry link and an optical laser com - Part of the brief included an assessment of the whetted appetites, our study will lead to
munication system. type of organization and management struc- further work in these as yet uncharted
The central computer system was designed ture likely to be required to run a facility of waters.
for: this type.
Credit
(1) Receiving data during test runs and Information obtained from the various visits to
recording this data on a permanent storage existing establishments provided a rough Client
medium, in real time outline of the typical staffing levels. Department of Industry
all engineers and used predominantly for computing power available this has to be
A computer calculation tasks. distributed to a large and varied user com -
munity.
system for Arups employ about 150 Building Services
engineers which represents 18% of all Arups are in a unique position , being one of
building services engineering staff. We have a large time-
sharing and batch processing computer
the few engineering consultants that develop
their own computer programs. This develop-
design system ( D EC-10) located in London and desk
top computers (HP9845) in our regional
ment procedure involves co-operation bet-
ween client committee , The Mechanical and
offices. Thus although there is considerable Electrical Development Group (MEO) and
Robert Aish the Computer Group.
Introduction The way in which this co-operation functions
can best be described by comparing it with
There have been a number of highly successful
the normal design process used in the con-
demonstrations of complex computer-aided
struction industry.
design systems. Typically such systems have
attempted to integrate geometry modelling, The client committee represents the interest
graphic display and manipulation facilities of the end user, MEO operates effectively as
with complex multi-attribute evaluation of the consultant and the Computer Group
building performance. It would appear that fulfils the functions of the contractor.
it is not yet technically nor economically The dialogue between these groups continues
feasible to apply such an integrated CAD throughout the program development period
system in an organization such as ours. The since there is often interaction between cal-
technical limitations concern the inability of culation procedures and the effective use of
these systems to handle the complex geometry computing resources.
and the varied construction techniques which
An example of this is the recently developed
our architects and engineers wish to use . The
THERMAL program suite.
economic limitations concern the cost of
providing all design engineers with graphics
terminals, processing power and storage THE THERMAL PROGRAM SUITE
devices with reasonable access times. Thus This suite consists of the following programs:
the f irst aspect of this paper is to consider our HEAT : steady state heat loss calculations.
objective. The objective is to make a profitable
use of computers given the present and COOL : maximum instantaneous cooling
expected relative costs of computers and loads calculat ions using cyclic
design staff. If it is not possible to provide weather data .
sufficient computing resources so that every ENERGY : energy analysis using recorded
aspect of every engineer's work is done Fig.1 weather data and simulation tech -
within a fully automated CAD system, then Geographical distribution of Arup regional niques for both the performance of
there is an alternative task of designing a offices and computer network the building fabric and building
computing system which can be accessed by services. 17
COOL: Maximum instantaneous cooling
loads
OVE AR.UP PARTNERSHIP - PROGRAM HEAT PAGE
The COOL prog ram cal culates cooli ng loads
JOB TITLE : WORKED EXAMPLE FOR REA.TING PROGR "M M"DE BY RB and the steady state heat losses for :
JOB NO. , 5289 / 12 DATE l 7- De c- 79
(1) Up to 100 different room types
••ROOM I NFORMATI ON FOR THE HEAT ING PR OGRA,_. - ROOM NO. > 20
(2) Collections of an y number of particular
R00 '1 ROOM ROOM ROOM AIR AIR CHANG ES CONVECTIVE room types grouped into zones
NO . LENG WI DT HE IG TEMP PER HOUR OR RADIANT
( Ml ( Ml ( Ml (C) (C OR R ) (3) The collection of zones served by one
21 5 . 80 4.80 3.80 18.80 l.80 c central plant.
ROOM NO. OF NO. OF
The program ta kes into acc ount :
NO, SURFACES ROOMS OF
EXT INT THIS TYPE
(1) U -values and absorption and adm ittance
21 l l 1 coeffici ents of the walls
(2) The solar ga in fa ctors for glazing
EXTERNAL S URFACES FOR ROOM >
(3 ) Th e tilt and orientation of th e glazing
ROOM SURFACE LENGTH HEIGHT SURFACE WINDOW NO , OF (4) The geometry of shading devices (see
NO. REF. NO, ( M) ( M) TYPE T YPE WI NDOW S
21 7 80 4. ee 3. 80 11 39 l Fig . 3)
INTERNAL S URFACES F OR ROOM ) 21 (5) Simple occupancy, lighting and mach -
inery util ization profiles, and diversity factors
ROOM SURFAC E WIDTH HEIGHT SURFA C E TEMP. OT HER S I DE for these profiles.
NO. NO. (M) (M ) TYPE IN WINTE R (C)
21 819 s. ee J.ee 11 1 9. 00 The' program calculates the loads for a single
HE.\T LOSSES FRCJlt ROOM MODULE 21 typical day for each month . Climatic data used
by the program consist of :
LOSS THROUGH EXT. WALLS 299. 7 9 W
TOTAL GLAZING LOSS 324. 99 W (1) The design dry bulb temperature for each
LOSS THR OUGH !NT . WALLS 348.99 W
TOT.\L VENTILATION' LOSS 4 1 8.4 9 W month
TOT.\L HE.\T LOSS 13 82.99 W (2) Th e corresponding minimum dry bulb
VOLUKE OP ROOM 69.19 M3
temperature for each month
HEAT LOSS PER CUBIC METER 23.13 W/ M3
(3) The average da ily maximum wet bulb
temperature for each month .
ENVIR ONMENT.\L TEMPERATURE 18 . 99 DEG. C
INTERNAL AIR TEMPERATURE 2 9 . 14 DEG.C The program calculates for each hour of the
MEAN RADI.\NT TEMPERATURE 16 . 9 3 0 £ G.C
design day for each month the following
NUMBER OP ROOM S OP THIS TYPE sensible heat ga ins :
Fig.2
Output from the (a) Solar gains through windows
HEAT program (b) Gains due to periodi c flow through the
structure
(c) Gains due to steady flows through the
HEAT, COOL and ENERGY can each be used Although this program could equal ly well be
windows
with building data for up to 100 different implemented on a programmable cal culator
room types. The programs have a common file as on our DEC - 10 time - sharing system, there (d) Gains due to lights, occupants and
structure so that the same building data can are advantages in using this system . This is machinery
easily be used with any of the programs. particularly evident when large building (e) Ventilation loads caus ed by infiltration
refurbishing projects are being undertaken . and the following latent heat gains :
HEAT: Steady state heat loss calcula-
tions (a) Gains due to occupants and machinery
For example, if the user wishes to test alter -
This program calculates heat losses from native glazing and heating systems for a large (b) Ventil ation loads caused by infiltration .
rooms with either convective or radiant number of rooms , then he need only alter The user can select which output tables are
heating devices, following the method des- those data items under consideration without actually required to be printed . Alternatively
cribed in Book A of the Cl BS guide. Typical having to enter repetitively all the room data output can be obtained in graphical form
output for a single room is given in Fig . 2. for each new run of the program . (see Fig . 4) .
kW
7 C"T"T~,....,....-rir--r...,.,~rrr~rrr~..,,.~..,,.~-.::,:,...-,.-.,....,..,.,..,,..,......,.,..,,..,.....~
To ta l se nsi ble hea t gains ·
Right fin
distance
(DIS2)
-- -- 2
Infiltration
-1
2 4 6 8 10 12 14 16 18 20 22 24
H ours
Fig.3 Fig.4
Th e g eom etry of sh ading devi ces for windows Graphical output
wh ich ca n be sp ecifi ed for th e COOL and the ENERGY programs for the COOL program
18 ~~~~~~~~~~~~~~~~~~~~~~~~~
The building design team can use the COOL EN ER GV Energy analysis program (see Figs. 5, 6, 7). These different output
program to consider the effect on the size of tables can be combined into any energy flow
This program uses a more detailed model of
both cooling and heating plant of such factors diagram (Fig . 8) .
the energy transfers within the bu ilding, and a
as : The ENERGY program uses essential! y the
model of the air-conditioning or heating
(a) The overall form of the building , its system. together with hourly weather data, same description of the building, its zones.
aspect ratio and orientation to calculate the energy consumption of the room types, walls and windows that are used
building for each hour for a complete year. by the COOL program. However. much of the
(b) The design of windows. their material. energy consumption of a building is deter-
size and geometry of shading devices The sum of the energy suppli ed in the form of mined by the way it is used. Wh ile the COOL
(c) Alternative occupancy and utilization different utilities and used in various building program is only used to search for the maxi -
patterns. services is the final output of the program mum cooling load . only the maximum
5 7
JOB TITLE TEST FOR ENERGY PROGRAM JOB TITLE TEST FOR ENERGY PROGRAM
MONTH ELEC GAS OIL PEAK LOP MONTH ELEC GAS OIL PEAK LOP
------------------------------------------------- -------------------------------------------------
MONTHLY TOTALS (GIGAJOULES)
-------------------------------------------------
6
JOB NUMBER - 5289/02
1 252.3 14.. 0 26.2 2049.9 1. 2 1633.5 959.1 369.2 0.0 60.2 0.0 0.0 0.0
2 224.0 7.9 0.0 2166.5 1. 1 1485.0 871. 9 335.3 0.0 54.7 0.0 l'l. 0 0.0
3 259.3 9. 1 0.0 2383.5 1. 3 1707.8 1002.7 383.2 0.0 63.0 0.0 0.0 0.0
4 225.5 21. 0 72 .6 1780.8 1. 1 1485.0 871.9 339.2 0.0 54.7 0.0 0.0 0.0
5 263.1 54.5 2 77.5 1611.1 1. 3 1707.8 1002.7 383.2 0.0 63.0 0.0 0.0 0.0
6 248.8 61. 9 107.3 1359.3 1. 2 1633.5 959.1 367.3 0.0 60.2 0.0 0.0 0.0
7 247.8 65.9 554.3 1124.2 1. 2 1559.3 915.5 355.2 0.0 57.5 0.0 0.0 0.0
8 270. 2 72. 2 568.7 1324.0 1. 3 1707.8 1002.7 383.2 0.0 63.0 0.0 0.0 0.0
9 243.5 61. 7 458.5 1332.4 1. 2 1559.3 915 .5 353.2 0.0 57.5 0.0 0.0 0.0
10 249.9 58.9 362.7 1546.5 1. 2 1633 . 5 959.1 369.2 0.0 60.2 0 .0 0.0 0.0
11 249 .8 17.3 fil. 3 1993.5 1. 2 1633.5 959.1 367.3 0.0 60.2 0.0 0.0 0.0
12 237.3 8.3 0.0 20134.0 1. 2 1559 . 3 915.5 355.2 0.0 57.5 A.0 0 .0 "'. 0
QUARTERLY TOTALS (GIGAJOULES)
1 735.6 31. 0 26 . 2 6599.9 3. 6 4826.3 2833.7 1087. 7 0. 1 177.9 0.0 0.0 0.0
2 737.5 137 .4 757.4 4 751. 2 3. 6 4826.3 2833 . 7 1089.7 0.1 177.9 0.0 0.0 0.0
3 761.5 199.8 1581.5 3780.6 3. 6 4826.3 2833.7 1091.7 0.1 177.9 0.0 0.0 0.0
4 737.0 84.5 423.9 5624.1 3.6 4826.3 2813.7 1091. 7 0. 1 177.9 0.0 A. 0 0.0
-------------------------------------------------------------------------------------------------------------
2 971. 5 452.6 2789.1 20755.7 14.4 19305.0 11335 . 0 4360. 8 0. 3 711. 7 0.0 0.0 0.0
D D I Lighting 12% ID
~
.
:.
::c
< 3::
Electricity 24% '6"'"":8
D OI Power 10% ID ~~
m:i:
c
0 •
'i ~
It)
E
:, Cooling 2%
c:J Cl Cl
~::c
8;:
>-"
r~
c,...
w_
11 I I I .:.
c
c
<
I m 3::
~
::c
-.0 m
I-
D I :: N
:, .•
'6"'""~
m-
I I -,.e.
Cl)
•
I D II
Fig.8
Energy flows for a building complex derived from annual consumption data from the ENERGY program
occupancy and lighting usage need to be and then calculates the energy consumption conditions where the outside air temperature
considered. But for a full energy analysis a required by the central plant to produce and is greater than the return air temperature.
more detailed approach is required which can distribute hot or chilled water or air to satisfy Sixth, damper control for each zone can either
allow the user to describe precisely the these demands, giving the defined capacity be done by temperature or enthalpy.
utilization of the building. The ENERGY of the central plant and its efficiency/ Seventh, the user can select whether or not
program allows the user to specify utilization utilization characteristics. (This assumes that each zone will have winter humidification .
profiles for : the capacity of the cooling and heating
Eighth, frost protection can be specified for
(1) Central environmental conditioning plant system has been found using the COOL
the whole building together with the min-
program).
(2) Occupancy imum space temperature allowed .
The program allows the user to specify
(3) Lighting
different air-conditioning and heating systems Using the energy program
(4) Utilitylighting and to mix different systems within the same The computer program enables the engineer
(5) Hot water supply building. These systems are: to simulate the operation of the energy
(6) Machinery utilization (a) Compensated perimeter heating consuming building services systems. This
(7) Vertical transportation systems - with and without thermostatic radiator can be done prior to detail design of the
(8) Three different types of ancillary equp- valves building and its systems or after the building
ment. - with and without local time switching is completed and operating.
Up to seven different day profiles can be (b) Constant volume with terminal reheat The main applications of this program are the
defined for each type of activity or service. (c) Fourpipefancoilunits following:
Thus each type of day can have a utilization (d) Variable air volume (1) Energy conservation in design
profile for each activity or service. These day - with and without terminal reheat (2) Energy consumption reduction during
types can then be assigned by the user to days (e) Dual duct induction units. operation of the building
of the week to constitute a schedule for the (3) Feasibility studies for retrofitting/refur-
The program also allows the user to specify
central plant. For example a departmental bishing of buildings and services systems.
store might have four types of profiles: different control strategies for the central
plant and for each room. (1) Energy conservation in design
(1) A typical working day profile (assigned The program can be used to consider
from Monday to Thursday) First. if a constant volume system is used then
the user can specify the minimum and maxi- various possible alternative system solutions
(2) A late night shopping profile (assigned in the system design and/or preliminary design
mum air supply temperatures. The minimum
to Friday) phase of the building . The program can also be
air temperature must be capable of offsetting
(3) A half day profile (assigned to Saturday) the maximum heat gain, while the maximum used to determine the influence of the building
(4) A holiday profile (assigned to Sunday). air temperature must be capable of offsetting shape, facade, glass and shading, insulation,
the maximum heat loss for the air supply rate air tightness. Because of the effect on the
Each room type may have its own weekly
specified for the terminal unit for each room. energy consumption of the building of the
schedule of profile types so that the activity
type of HVAC system selected, the computer
and utilization pattern for services for any Second. a proportional band can be defined . program makes it possible to determine the
particular room can be different from that for For example, a proportional band of 4 ·c energy consumption for the alternative types
the building as a whole. allows the space temperature to vary 2 ·c of air-conditioning systems.
In addition up to 20 non-standard days may either side of the design temperature and
means that under full heating the temperature After selecting the type of HVAC system, the
be specified. These override the normal energy consumption and power demand
weekly cycles of day profiles. For example, if will be 2 ·c below the controlled temperature
program for the particular selected HVAC
day 120 is a public holiday it can be assigned and conversely, under full cooling, 2 ·c above
it. Selecting the proportional band enables a system, and therefore of the building, is also
to a holiday profile and this profile will be influenced by the size and routing of the
taken in preference to whatever profile is more economic use of energy to be achieved
if a precise space temperature is not required. main and sub-distribution system with its
normally assigned to the day of the week on various velocities, pressure drops, pressure
which the 120th day occurs. Third, the percentage saturation of air supplied balancing devices and equipment arrange -
The ENERGY program uses recorded weather in each room can be specified. ment in plant rooms .
data. A library of weather data files is available Fourth, for each zone the extract air as a Sometimes the design brief for the services
and new files can be added from weather percentage of supply air can be specified. systems limits the total allowable cost of
tapes written in a number of different This enables different zones or the whole energy consumption for the project. This has
nationally defined formats. building to have a positive or negative to be taken into consideration in the pre-
The ENERGY program calculates the hourly pressure. liminary design of the building and the
cooling or heating load required by each Fifth, for each zone the percentage minimum architect needs the various energy consump-
20 room type to maintain the design conditions, fresh air can be specified to be used under tion budgets to determine the optimum
combination of services and structural There are three further groups of programs surfaces at any latitude, tilt and azimuth (see
system during the design phase. associated with the THERMAL suite. These Fig.11).
The program enables the designer to under- are : (3) Distribution programs for pipes and
size the capacity of equipment and check (1) STEMP : Summer time temperatures ducts-
the resultant internal space conditions for the program which enables detailed examination PI PE 1 : pipe sizing for two pipe systems
various times of the day during the various of specific rooms in a building to determine PIPE 2: analysis of existing pipe systems and
seasons. whether air-conditioning is necessary. valve settings for two pipe systems
(2) Energy consumption reduction dur- (2) LIGHT : This program suite enables the DUCT1 :ductsizingusing:
ing operation of the building engineers to consider a number of design and -static regain
performance variables associated with a - constant pressure drop
Total cost of the energy consumption is
single room and its glazing. These factors are: - velocity reduction
determined by two factors:
(a) Daylight (see Fig . 10) . DUCT 2 : analysis of existing duct systems.
(a) Demand charges
(b) Use of artificial light (linear or point In most cases programs using the same cal-
These can be reduced by :
source on vertical or horizontal surfaces) culation procedure are available on the
(i) Power factor correction equipment (c) Sun paths on specified windows or HP9845.
(ii) Maximum demand control and / or limit-
ing devices
(iii) Optimum equipment stopping and I1Er1C111 ":> H11T 10 11 E . H/'IFLE PAGE
starting schedules. F U.-i~ l lVf.STJt~HT l 0 11
Jf1JI NO.
MADE
:'999
BY BF:'N
1,1 ,11H [ '. T v .-.F ,[rlO. ItlT ~H HI) GLH;s F[BF·E t1ATE 3 :"9
(b) Fuel / energy consumption PUii t-H_l'H; [f,-' 17 CHEC I ED
Energy consumption can be reduced through
optimum operation of the equipment. H ' l 11: THf PMRL f.· tr,;.FO~Ml"ll<(E UF [L[t1ENT S
The computer program can assist in: lH[F'MIL :;. vAfl'IJU P PPE SS•J PE GRADlEtlT S THi:-1)UGH ELEME1ll
(i) Determining the optimum stopping and L(t(AT I )fl [IF'( Bu u, S.AT rlCTUFIL • • .. V AP OU F' FL O~J • G M ;:. HP ' ""'""
starting schedule of the major pieces of TEMP V . P. \I . P. FP OH 10 (Vtllt EH$ltlC
r DEG C, \ l'\ ~ t1 --~, • II· M 2. I tlSI DE OUTSIDE
equipment
IW,IDI:. 2 1.00 l48'5 . 67 99 4. 27
(ii) The influence of varying control settings
~u n ·11 ,_:::: 1 18 .11 2076 . S':l 99 4 . l7 O . 1 1 ;- 0 . 000
of air and water supply by major equipment f'L'1'~· Tff.LOAPD
~U ~FA f £ L 15. 98 181 4. '57' 97'5 . 2~ o. 117 0. 11 7' 0 . 000
(iii) The influence of temperature variations c~ . .-n,
SU J.FH (:: 3 11, 0 7 11 17 . 85 95 4. 12 0. 117 0. 117 0.000
in the room Hrt;:tOH~ 1t
-;,JrF H,: : 4 827. 3 !5 S27 . 1 '5 o. I l ;- 0 . 006 0. 1 1 1
(iv) The influence of energy saving devices P O)F Fn T
such as evaporative cooling and economizer IJ ~ FH ( ~ '5 807 . 76 Bi , 69 o. 006 o. 00b 0 . M0
R (J) F FEL 1
cycle :,U Ff~ f i 6 3 . '5:- ?88 . !i9 652 . 0 3 0. 006 0. oe~ 1) . (100
F' (l) I" f[ll
(v) The influence of the increase in fan and ·;:.L1 f f HL :: 769.82 '56 4 . 39 (1, 006 o. 000
pump horsepower through inadequate main- :.t)O 705 . 4 7 !i6 4 . 38
2<I:
i0 00 >
and / or refurbishing of buildings service
systems
3000
The usage of the computer program is very
similar to the application described for energy
conservation in design . The only difference is
- .\..1
:I 2000
r
1000
building must be taken into consideration . '°·11·
Fig.9 SRT .
ACT. Y
VPP
>B
COOLI NG SYSTEM DETAILS
Note: If the respon se E is given to any further questi o ns in this routine
REFRIG COOL TCMERS CHLD WAT ER TrMER COND c. w WET REFRIG CON.WAT.
the user will be able to start the rout i ne again.
CA PAC CONS NO. FLOW RETURN DES LWT PUMP PU "IP BULB CONS COOL£[) ?
{K W) (KW) OF (Cl (Cl (Cl (KW ) (KW) (Cl (KW) ('i OR N )
1009 .e
• >WARNI NG
15. 0
• 6. 0 12.0 30 .0
REFRIG. CAPACITY OUT OF RANGE (0 T O 100 0 ) )
40.0 30 . 0 19. 0 1 780. 0
79 00 . 00
N
INPUT DATA FILE N1'ME> COOL2. T ST
• >WARN ING REPRIG . PLANT POWER OUT OF RANGE ( e TO 1000) ) 1700.90
' SYNOPSIS OF DATA FILE (Y OR N )? N
HOT WATER SU PPLY SYSTEM DETAILS DO YOU WI SH TO ALLOW VALUES OUTSIDE NORMAL RANGES (Y or N)? Y
H.w .s. IS H.W.S. 801 LEA PRIM,t,RY PUMP SECONDARY PUMP H. W. STORAGE DO YOU WI S H T O SU PPRE SS ERROR MESSAGES IN PRINT-OUT ( Y or N )? y
CAPACI TY ELECTRICAL EFFI C . POWER CONS POWER CONS CAPACITY
(KW) ( Y OR N ) (\ I (KW ) (KW) ( M)I DO YOU WANT A NIGHT-TIME RUN (Y OR N) > Y
1500. 00 N 80 .00 1.00 0.40 25 . 00
* >WARN INC : HOT WAT ER S YST. CAPCTY OUT OF RANGE ce T O U0B ) > 15B0. 00 WHERE WOULD YOU LI KE YOUR OUTPUT ?
ENTER L F OR LINE-PRINTER
ENTER D F OR DIS K
FAN S ENTER 8 FOR BOTH
>L
Z ONE FAN POWER FAN DAMPER EXTR. AS MINIMUM HUMIDITY CO IL OPP
NO . SUP. EXT. CNTRL. CNTRL. \ OF SUP. FRESH AIR CONTR OL DEW PT . NIGHT BATCH RUN OF PR OGRAM COOL SUB MITTED
(KW ) (KW) II ) (I I (DEG Cl INPUT DATA FI LE NAM E: COOL2 . TST
1 16 0.0 1 4'1.0 1 2 90 .00 30.H I 8.""
* >WARNINC : SU PPLY PAN POWER OUT OF RANGE ( B TO 100 ) > 160. 00 ENTRIES IN THE INPUT QUEUE UNDER YOUR PPN ARE AS F OL LOWS:
* >WARNING : EXTRACT FAN POWER OUT OF RANGE ( l!J TO 191!1 ) > 140.00
2 ee . e 1 e.e 1 2 90. ee 30.ee l e.""
3 129.018 5. 0 1 2 90.H 30.H l 8. 09 , I NPUT OUEUE:
• >WARNI NG : SU PPLY PAN POWER OUT OP RANGE ( 0 TO 108) > 120. 00
• >WARN ING : EXTR ACT PAN POWER OUT OF RANGE (0 TO 190 ) > 105. 011 PT Y PPN JOB S EO PRIO NAME TIME CORE AFTER
17210, 52 COO L2 1 4 3 62 C . G R, AI SH H :3 0:99 4 3 +97 : 49
4 160.9149,B 1 2 90.00 39 .00 l e.""
• >WARNINC : SU PPLY PAN POWER OUT OF RANGE (9 TO 100) > 1611.H
• >WARNING : EXTR ACT PAN POWER OUT OF RANGE ( 9 TO 190) > 140.H TOTAL (includes all jobs)
INP : 2 job s; 08:31:09 sec, ru n tlme
.MIC EXIT
Fig.14 Fig.15
Output of th e data vetting option of the Using the j ob control routine to submit a
ENERGY program night batch run of the COOL program
The program checks that there is 'logged 1n
Table1: Data modulesfortheTHERMALsuite capacity on the user's disk area for all inter-
mediate files and 'logged out' capacity for all
output files for the number of rooms and the
HEAT COOL ENERGY output options which the user has requested
in his input file.
Finally the job control routine shows the entry
General General General in the batch queue so that the user can check
Climatic Temperatures Non Standard Days that everything is correct.
Options Options
External Surfaces External Surfaces External Surfaces A typical application
Internal Surfaces Internal Surfaces Internal Surfaces The General Organization of Social Insurance
Glazing Types Glazing Types Glazing Types Saudi Arabia commissioned Ove Arup and
Room Room Room Partners Saudi Arabia Ltd. in October 1977
Zones Zones to design a building on Amir Nasir Street in
Systems Dammam.
The building consists of a basement car park,
two floors of shops, a restaurant and eight
@ (j)
floors of offices (See Fig. 16).
(!) @ © ©
The offices and restaurant are planned around
an internal naturally-lit courtyard with planting
at the lower level. The offices look into this
courtyard and the restaurant has direct access
to the planted area so that people can enjoy
the cool shaded environment as a contrast to
the hot dusty atmosphere of Dammam.
The building is air-conditioned and is shaded
on the outside by timber screens which echo
some of the indigenous forms of architecture
ofthe Middle East.
The THERMAL suite and other building
services programs were used in the design of
this building.
COOL was used to size the fan coil air-
conditioning units in each room and to size
the central refrigeration plant.
ENERGY was used to determine the total
annual energy consumption for the building.
To achieve this a weather tape for nearby
Dhahran was used and the data on the room
and window geometries was transferred from
the input data files used for the COOL
program,
The sun path program was used to design the
shading for the dome over the central court -
yard and the timber screens on the sides of
the building. The plotter generated the sun
path diagrams and a shading protractor. Using
Fig.16 the protractor the engineer established the
Office building, Dammam , Saudi Arabia abi lity of the shading devices to obscure the
direct sunlight.
PI PEI was used to design the water distri-
Fig. 13 shows how the user can progress are common to all DEC 10 Building Services bution system from the central plant to the
through the THERMAL suite using the UP - Programs. fan coil units in each room.
DATE program to move data from program CA DRAW, the computer-aided drawing pack-
Th e user types / COOL to initiate th e routin e
to program. This enables the user to desig n age, was used extensively to prepare the
the building geometry once and th en add the He selects the ' B' option to submit a batch run production drawings.
necessary extra data as he progresses to the of the programs.
more complex programs. Conclusions
The user identifies the input data file to be
Data vetting is an extremely important aspect This library of Building Services prog rams has
used .
of any program system which is to be used provided our building services engineers with
by a large group of users. Fig . 14 illustrates The program checks that this file exists and a range of powerful design and analysis aids.
the form of one of the input data modules for that it is an input file for COOL program . The user interface utilizes a simple interactive
the ENERGY program as it has been o utput qu estion naire technique and a very straight-
The user can select a synopsis of this input
to a user with the appropriate warning forward editor, with which most of our
data file, to allow values out of range or to
messages. engineers are familiar . After initial training we
suppress error messages in the printout.
Aft er vetting the input data, the user can have found that most users can prepare data
proceed, for example, to submit a batch job The user has the option of either a more and operate the programs with no supervision .
so that his input file can be run with the expensive but immediate day batch run or a The level of use of the programs is increasing
specified program. less expensive night batch run of the COOL
with, for example, three runs of the COOL
program.
Fig. 15 shows the dialogue between a user program and one run of the ENERGY program
and the interactive job control routine for the The user can select whether his output will be a week. Eight other organizations external to
COOL program. The facilities illustrated here printed or stored on disk or both. th e practice are also using these programs.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Ebury Street
Development
Maurice Smith
Arch it e c t:
T e d Le vy Be n jam in & P a rtners
The brief was to design a development which
could accommodate 96 luxury flats with shop
units at ground floor level and an under-
ground car park.
The planners stipulated that the height, scale
and module of the building should be in
keeping with the surrounding properties in
Ebury Street. To achieve the numbers of flats
and to stay within the height restriction , the
building was stepped above roof level. This
gave an elevation which blended with the
existing buildings which surround the
development.
The major structural problem was to ensure
that noise and vibration that was generated
from the London Transport Underground line
was not transmitted through the foundations
into the structure.
In order to overcome this problem the super-
structure is separated from the substructure
at first floor level. The transition slab at this
level , which carries the structure for the flats
above, is supported on bearings which sit on
column heads directly under the transition
slab. The structure is of reinforced concrete,
with piled foundations, and a mansard roof of
structural steel and timber.
The building contract commenced in February
1977 and was completed in mid - May 1979.
Credit s
Client:
MEPC
Architect:
Ted Levy Benjamin & Partners
Quantity surveyor:
Gardiner and Theobald
Main contractor:
Sir Robert McAlpine
EBURY STREET
----=
Figs.1 - 2 Figs. 3 -4
Cummins Engine Factory South Poplar Hea lth Centre
Client: Client:
Cummins Engine Company Ltd. City and East London Area Health Authority
Architects: Architects
Ahrends Burton & Koralek Derek Stow & Partners
Steelwork Contractor. Steelwork Contractor:
Redpath Engineering Ltd . J. H. Slade Ltd.
( Photos : Ove Arup & Partners) (Photos: Henk Snoek)
3
N
N
0
<D
(")
c:
x
Q
E
0
r
ctJ
c:
:,:
Q
E
0
.c:
r
>
.0
"'
.£"
n: